CITY OF MERCED PROJECT NO. 117039
CHANGE ORDER NO. 3
DATE: 10/03/2022
PROJECT NAME: G Street Improvements Childs Ave to 13th St PROJECT LOCATION: Merced, California
CONTRACTOR: Rolfe Construction
ADDRESS: 3573 Southern Pacific Ave, Atwater, CA 95301
REASON FOR CHANGE ORDER:
Additional scope of work being added to project. Extra work includes curb and gutter replacement, 10” water main replacement on G St, and extension of storm sewer on intersection of G St and W. Childs Ave to remove “bubble up” curb and gutter inlets.
THE NUMBER OF WORKING DAYS WILL BE ADJUSTED AS FOLLOWS: None SKETCH / BACKUP ATTACHED: Yes
DESCRIPTION OF CHANGE:
No. Description Unit Unit Price Qty. Total
1. Credit for Bid Item 26 Concrete C&G Install LF $225.00 50 ($11,250.00)
2. Credit for Bid Item 41 Install New Tree Wells EA $4,169.00 14 ($58,366.00)
3. Additional LF for Bid Item 26 Concrete C&G Install LF $123.70 154 $19,049.80
4. Additional LF for Bid Item 13 Remove C&G EA $34.00 104 $3,536.00
5. Addition of Storm Drain LS LS $237,877.00 1 $237,877.00
6. Addition of replacement of 10” Water main LS $275,880.00 1 $275,880.00
Total added cost for Schedule “A” on change order 3: $466,726.80
ORIGINAL CONTRACT AMOUNT: $ 2,531,371.00
CHANGE ORDER #1 AMOUNT: $ -(98,500.00) CHANGE ORDER #2 AMOUNT: $ 8,392.00 CHANGE ORDER #3 AMOUNT: $ 466,726.80 FUNDS/ACCOUNTS VERIFIED:
TOTAL PROJECT COST TO DATE: $ 2,907,989.80 450-1104-637.65-00-117039 (100%) $ 466,726.80 Total: $ 466,726.80
_______________________________
FINANCE OFFICE DATE
ACCEPTED_____________________________________________________DATE_______________________ (CONTRACTOR)
RECOMMENDED________________________________________________DATE_______________________ (CITY ENGINEER)
RECOMMENDED________________________________________________DATE_______________________ (PROJECT CHAMPION)
APPROVED_____________________________________________________DATE_______________________ (CITY ATTORNEY)
AUTHORIZED___________________________________________________DATE_______________________ (CITY MANAGER)
ATTESTED______________________________________________________DATE_______________________ (ASSISTANT/DEPUTY CITY CLERK) (SEAL)