Text extracted from the city's file for reading and search. Open the original on cityofmerced.legistar1.com. That file is the official record.

North Ptax
Engineering Group, Inc.

Response to City of Merced
Request for Proposal
Canal Street Water Main
Replacement
Project No. 121055
620 12th Street, Modesto, CA 95354
P: (209) 524-3525 / F: (209) 524-3526
Nowth Stax
Engineering Group, Inc. PROPOSAL

CANAL STREET WATER MAIN REPLACEMENT
14T# STREET TO 15TH STREET
PROJECT NO. 121055
OCTOBER 1, 2021

1. PROJECT MANAGEMENT, MEETINGS, COORDINATION, PROCESSING, AND PERMITTING A. Attend project kick-off with City Staff to discuss the project intent, scope, approach, project limits, chedule, budget, regulatory items, project requ
equirerents, and record any feedback that wond requins adilan processing, entilements, environmental B. Review applicable Agency Guidelines, Requirements, Design Standards, Utility Master Plans, Record Improvement Plans, Final Maps, and other supporting documentation. Identify existing utilities to be impacted by the project.

C. Prepare a bar chart project schedule itemizing all activities and subtasks to successfully meet project milestones. Provide monthly updates of the project schedule to the City Project Manager.

D. Perform high level quality control and project oversite throughout the development of the design, plans, and overall project.

E. Coordinate with City Staff during review and approval process.

F. Attend meetings for coordination during the design and Improvement Plan process, as necessary.

G. Attend meetings as outlined in the RFP for the submittal documents.

H. Prepare Civil submittal packages for submission. Revise Improvement Plans in accordance with the Agency review comments. This Task estimates four submittal reviews prior to approval. Additionally, an AutoCAD version 2020 compatible drawing file and Microsoft Word Specifications will be provided with the final submittal.

2. TOPOGRAPHIC AND PROPERTY BOUNDARY SURVEY
A. Record Research - Perform record research at Merced County to locate Recorded Control Maps, Right-of- Way Maps, Records of Survey, Corner Records, and other official maps of records.

B. Right-of-Way and Control Field Survey - Perform a Topographic and Right-of-Way Survey to provide design control and right-of-way mapping for the project. Set horizontal and vertical control points for project mapping in accordance with City of Merced horizontal and vertical control requirements. All Surveying and Mapping shall be in compliance with the provisions of the Professional Land Surveyors Act, Sections 8700 to 8805 Business and Professions Code; the provisions of the California Coordinate System, Sections 8801 to 8819 of the Public Resources Code; and any other applicable code in the State of California. The horizontal datum will be based on the North American Datum 1983 (NAD 83). The vertical datum shall be based on the North American Vertical Datum of 1988 (NAVD 88) and closed network bench loops will be run through the control monuments. Perform a Field Survey to search and locate existing survey monuments and physical evidence required to establish existing rights-of-way and property lines at those locations where any portion of the project infringes upon the required setback limits of the project improvements, work areas, storage, and staging areas. Perform calculations for the right-of-ways based on the found monumentation and lines of occupation located with the field survey. 620 12'h Street Modesto, CA 95354
P: (209) 524-3525 / F: (209) 524-3526
North Stax
Engineering Group, Inc.

C. Land Net Surveys - Calculate record right-of-way lines and property lines located within the project limits in accordance with record maps, record deeds, and documents as required to calculate field search positions for existing Right-of-Way Monuments, Street Survey Monuments, and Parcel Corner Monuments.

D. Topographic Survey - Perform a detailed Field Survey of existing Canal Street including physical improvements, driveways, structures, visible utilities, and drainage features. All work and files will be based on project coordinate control in accordance with the City of Merced requirements for the preparation of documents and maps. Topographic Field Survey will locate existing site improvements and gutter, handicap ramps, striping, signs, fences, driveways, pavement elevations, existing ground elevations, visible utilities, structures, utility poles, trees, planters, and other miscellaneous visible features. Cross-sections will be taken at 50-foot intervals along Canal Street except in areas of vertical curves where cross-sections will be taken on 25-foot intervals and extend 50-feet along 14th Street and 15" Street. Measure the existing invert and pipe sizes for the accessible utility structures. Consultant will coordinate with property owners to gain "right of entry" during the Field Survey where needed. The Survey data will be processed and rendered into a Digital Terrain Model (DTM) and CAD base map. The CAD map shall exhibit 1-foot contours, spot elevations, all pertinent surface features, tree measurements, and utilities.

E. Monument Preservation - Research existing records for horizontal and vertical control monuments and property corners that might be compromised by project activities. Show existing monuments on the project survey to be incorporated into the construction documents, perform a Field Survey to set reference ties for any monument with the potential of disturbance during project construction activities. Based on the found monuments and reference ties, prepare pre-construction corner records for the found monuments in accordance with Section 8771 of the Professional Land Surveyors Act in the Business and Professional Code of the State of California. Process and file the pre-construction corner records with the County Surveyor.

3. CIVIL ENGINEERING CONSTRUCTION DOCUMENTS AND SPECIFCATIONS A. Prepare an off-site base plan for the project site which includes improvements for Canal Street between 14th Street and 15" Street for the replacement of sidewalks, curb, gutter, and accessible ramps along with the removal and replacement of the existing 16 inch water main. Canal Street shall have a structural section of 3 inches of asphalt over 11 inches of aggregate base over 12 inches of compacted subgrade.

Additionally, a bid alternative for Canal Street will be provided for a full depth reclamation (FDR) using 12 inches of cement under 3 inches of asphalt. If off-site improvements extend beyond the limits described in this project, additional fees will be required. Any modifications to the approved off-site public base plan will require additional fees.

B. Identify demolition requirements and prepare a Demolition Plan with notes, call-outs, and specifications.

C. Design Grading and Drainage Plans for off-site public improvements utilizing the approved base plan described in item A above including the design of accessible ramps.

D. Design and replace the existing 16 inch water main in Canal Street between 14" Street and 15" Street. All existing services and devices such as fire hydrants, meters, etc. will need to be relocated to connected to the new 16 inch water main. The off-site water system will include water valves, fire hydrants, and water service piping from the new public water main in the existing street.

E. Coordinate with the Dry Utility Consultant and show (for reference only) the location of dry utilities.

C'anal Street Water Main Replacement Scope of Work
Merced, CA Page 2
North Stax
Engineering Group, Inc.

F. Prepare 65%, 90%, and 100% Off-Site Public Improvement Plans per City of Merced Standards that will include a Cover Sheet, Notes-Specification Sheet, Construction Detail Sheets), Topography Plan(s), Demolition Plan(s), Dimension Plan(s), Signage and Striping Plan(s), Grading and Drainage Plan(s), Water Plan(s), Profile(s), and Erosion Control Plan(s). Submit an electronic copy and a minimum of 3 sets of 11x17 plans, specifications, and estimated of the Off-Site Public Improvement Plans to the City of Merced for review and comment. Make requested City of Merced corrections to the Off-Site Public Improvement Plans.

G. Provide Project Specifications for the 90% and 100% submittal packages in Microsoft Word. Project Specifications will be related to the Civil Engineering improvements and provided to the City of Merced to include in the overall project documents. The City of Merced will provide the front end boiler plate specification templates for the Civil Engineer to utilize and modify for the project.

H. Prepare an Engineer's Estimate and Bid Quantity for bidding purposes for the 90% and 100% submittal packages only. One Engineer's Estimates and one Bid Quantity Sheet will be provided for the project at the 90% and 100% phase of the project.

4. BIDDING ASSISTANCE, CONSTRUCTION ADMINISTRATION AND RECORD DRAWINGS A. Attend one pre-construction/field project kick-off meeting.

B. Provide supplemental instructions and clarifications to bidders, as necessary.

C. Produce addendums to modify the bid documents (plans and specifications), as required.

D. Respond to Contractor's Requests for Information (RFI) during the bidding process.

E. Respond to Contractor's Requests for Information (RFI) during the course of construction.

F. Produce addendums to modify the construction documents (plans and specifications), as required to address unforeseen conditions that arise during construction.

G. Review and process submittals and shop drawings from Contractor.

H. Assist in determining and processing request for information and change orders.

I. Perform periodic field visits at the major construction stages of the project to answer construction questions.

EXCLUSIONS, NEXT PAGE
Canal Street Water Main Replacement Scope of Work
Merced, CA Page 3
North Stax
Engineering Group, Inc.

EXCLUSIONS:

1. Any task not listed in the above Scope of Work

2. Preliminary Title Reports for any property within the project limits. City of Merced will be responsible for acquiring and payment of all associated fees.

3. Agency Fees, Applications, and Permits.

4. This Scope of Work excludes any time required to identify, discuss, present, or represent any occupational discrepancies, boundary disputes, gaps, overlaps, or title discrepancies. Client will be advised should our survey find conflicts with title or occupation evidence. Services shall be billed on a Time and Materials basis shown on our current Rate Schedule at the time the services are rendered.

Record of Survey, Lot Line Adjustment, Certificate of Compliance, Acquisitions, Parcel Map, Final Map, Easements, Plats, Legal Descriptions, Special Mapping Services not specifically identified in this scope.

6. ALTA/NSPS Survey or Easement Abandonment.

7. Construction Staking.

8. Specific Plan, General Plan, EIR and CEQA Amendment, Assessment Districts, Annexations, Reimbursement Agreements, Sound Studies, and Archeological Mitigation Program.

9. Any coordination or processing with State or Federal Agencies.

10. Arborist Report, Landscaping, and Irrigation Plans.

11. Any applicable RWQCB Application and/or Annual Fees, Annual Compliance Report, NOI Submittal Fees.

12. Public Agency Engineering or Analysis not specifically listed in the above Scope of Work.

13. Dry Utility Design (lighting, electrical, undergrounding overhead lines, gas, CATV, joint trench, etc.).

14. Traffic Control Plan, Traffic Engineering, Additional Lanes, Signage, Striping, and Traffic Signal Design.

15. Decorative Wall, Gate, Fencing, and Structural Retaining Wall Design and Specifications.

16. SWPPP, Monitoring and Inspections (QSP/BMP and others), Annual Reports, Notice of Termination (NOT), REAP, Lab Fees, Testing, etc.

17. ISR, Air Board Permitting, and Dust Control Plans.

18. Geotechnical Engineering (Structural Sections), Dewatering Design, Blasting Recommendations/Design, Trenching/Excavation analysis relating to the site, Hydrologic Engineering, Environmental Engineering.

19. Any work related to Plans or Specifications for a pump station not specifically identified above.

20. Fire Water Design, Plans, and Calculations. Fire Flow Test, Fire Sprinkler Design/Well, Tank, and Booster Pump Design, Calculations, Plans, and Specifications.

21. Sewer System Design, Calculations, Plans, Septic System, Grease Traps, Sewer Lift Stations, etc.

22. Storm Drainage System Design, Calculations, Plans, Retention System, Lift Stations, etc. Project assumes existing storm water conveyance system already exists and no improvements will be required.

23. Storm Water Quality Analysis, Design, Calculations and Report. Hydromodification, Volume Reduction and Treatment.

24. Cathodic Protection Design.

25. Processing and plan preparation not specifically identified in the above Scope of Work.

Canal Street Water Main Replacement Scope of Work
Merced, CA Page 4
North Stax Canal Street Water Main Replacement - Project No. 121055 Engineering Group, Inc. 14th Street to 15th Street
Estimated Level of Effort
1-Oct-21
PRIMARY SCOPE TASKS Project Manager or Land Surveyar Field Survey Principal In Charge Civil Designer CAD Drafter Land Surveyor Total Hours Total Cost Civil Engineer Assistant

ITEM TASK ACTIVITY
$173.07 $162.27 $162.27 $118.13 $135.23 $118.13 $209.91 TASK 1
Project Management, Meetings, Coordination, Processing and Permitting 16 $10,471.68 Sub-Total $10,471.68
TASK 2 - Topographic and Property Boundary Survey
$443.53
Record Research
Right-of-Way and Control Field Survey $1,616.82
Land Net Surveys $1,651.02
$6,649.94
Topographic Survey
Moment Presention $2,296.61
Sub-Total $12,657.92
TASK 3
152 $21,220.24
A-H Civil Engineering Construction Documents and Specifications Sub-Total $21,220.24
TASK 4
Bidding Assistance, Construction Administration and Record Drawings 40 $11,416.72 Sub-Total $11,416.72
TOTAL 104 72 104 20 366 $55,766.56