CITY OF MERCED
Project #123035 - WWTF Phase VI ASD Supplemental Heating and Headworks
UNIT OF ESTIMATED UNIT ITEM UNIT ITEM UNIT ITEM UNIT ITEM UNIT ITEM UNIT ITEM UNIT ITEM NO. ITEM MEASURE QUANTITY PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE TOTAL PRICE TOTAL 1 Construction of all work associated with the Merced WWTF Phase VI Project - ASD Supplemental Heating System and
Headworks Improvements, excluding work listed in other bid items in the base bid schedule LS 1 11,068,000.00 $ 11,068,000.00 $ 13,383,324.00 $ 13,383,324.00 $ 13,086,924.00 $ 13,086,924.00 $ 13,495,000.00 $ 13,495,000.00 $ 11,693,550.00 $ 11,693,550.00 $ 10,992,000.00 $ 10,992,000.00 $ 11,801,620.00 $ 11,801,620.00 $ 2 Sheeting, shoring and bracing, or equivalent method for the protection of life and limb in trenches and open excavations in conformance with all applicable safety orders LS 1 25,000.00 $ 25,000.00 $ 20,000.00 $ 20,000.00 $ 110,000.00 $ 110,000.00 $ 25,924.00 $ 25,924.00 $ 30,000.00 $ 30,000.00 $ 111,000.00 $ 111,000.00 $ 5,000.00 $ 5,000.00 $ 3 Active Solar Dryer (ASD) Supplemental Heating System: For Thermal Process Systems (TPS) ASD Supplemental Heating
System equipment and services in accordance with
Specification Section 11387. Note: the amount written into this bid item includes freight and sales tax. LS 1 3,283,315.00 $ 3,283,315.00 $ 3,283,315.00 $ 3,283,315.00 $ 3,283,315.00 $ 3,283,315.00 $ 3,283,315.00 $ 3,283,315.00 $ 3,283,315.00 $ 3,283,315.00 $ 3,283,315.00 $ 3,283,315.00 $ 3,283,315.00 $ 3,283,315.00 $ 4 Perforated Plate Screens and Washer Compactors: For
SAVECO North America, Inc. perforated plate screens and washer compactors in accordance with Specification Section 11334. Note: the amount written into this bid item includes freight and sales tax. LS 1 900,761.00 $ 900,761.00 $ 900,761.00 $ 900,761.00 $ 900,761.00 $ 900,761.00 $ 900,761.00 $ 900,761.00 $ 900,761.00 $ 900,761.00 $ 900,761.00 $ 900,761.00 $ 900,761.00 $ 900,761.00 $ TOTAL BASE BID AMOUNT 15,277,076.00$ 17,587,400.00 $ 17,381,000.00 $ 17,705,000.00 $ 15,907,626.00 $ 15,287,076.00 $ 15,990,696.00 $ 5 Headworks Improvements: Provide deductive amount to
construct the work identified on the headworks area A
drawings as "Deductive Bid Work". LS 1 (1,632,400.00) $ (1,632,400.00) $ (2,800,000.00) $ (2,800,000.00) $ (3,230,000.00) $ (3,230,000.00) $ (3,898,200.00) $ (3,898,200.00) $ (2,756,550.00) $ (2,756,550.00) $ (2,489,000.00) $ (2,489,000.00) $ (1,640,149.62) $ (1,640,149.62) $ 7 TOTAL BID WITH BID DEDUCTIVE ITEM "A" 13,644,676.00$ 14,787,400.00 $ 14,151,000.00 $ 13,806,800.00 $ 13,151,076.00 $ 12,798,076.00 $ 14,350,546.38 $ Did not write in the 13,644,676. Was calculated by us with the deductive. Discrepancy in bid. They wrote in 15,287,000 and 12,798,000 Mountain Cascade., Inc
(Livermore, CA)
Clark Bros., Inc
(Fresno, CA)
Garney Pacific., Inc
(Tracy, CA)
Bid Opening: Thompson Builders Corp.
(Novato, CA)
GSE Construction Company Inc.
(Lathrop, CA)
C. Overaa & Co.
(Richmond, CA)
W.M. Lyles Co.
(Fresno, CA)
ATTACHMENT # 1