Cities Index.
Mead and Hunt Letter.pdf

City Council/Public Finance and Economic Development Authority/Parking Authority
August 7, 2023

Document
Mead and Hunt Letter.pdf
Meeting
August 7, 2023
Body
City Council/Public Finance and Economic Development Authority/Parking Authority
Pages
2
Original file
286 KB
Text extracted from the city's file for reading and search. Open the original on cityofmerced.legistar1.com. That file is the official record.

Mead & Hunt | 1360 19 th Hole Drive, Suite 200, Windsor, CA, 95492-7717 | 707-526-5010 | meadhunt.com

July 13, 2023

Michael Wegley
Interim City Engineer
City of Merced
678 W. 18
th Street
Merced, CA 95340

Project: Merced Yosemite Regional Airport Terminal Replacement Project 2023, Re-bid FAA AIP No. 3-06-152-030-2023
Subject: Analysis of Bid Results

Dear Mr. Wegley:

The bid opening for the above-referenced Project wa s held July 6, 2023, at 2:00 p.m., with a total of three bids received. The basis of award for the Project w as the combination of Bid Schedules A, B and C for the Base Bid only.

We have reviewed the proposal package submitted by Thompson Builders Corporation and have the following comments:

1. Math error for Bid Schedule A Item #8 and summat ion error for Bid Schedule A as noted on the attached bid tabulation.

We have reviewed the proposal package submitted by Bobo Construction, Inc. and have the following comments:

1. Unit price “in words” reflects total price figur es instead of unit price “in figures.

2. Proposal package was incomplete.
a. Missing SOV for building.

We have reviewed the proposal package submitted by Diede Construction, Inc. And have the following comments:

1. Proposal package was incomplete.
a. Missing signed Addendum 01.
b. Missing SOV for building.

2. Numerous math errors in bid tabs A through C as noted on the attached bid tabulation.

Upon review of the bid package submitted for this P roject and pending receipt of the Buy American waiver information and documentation, we recommend obtaining concurrence with the FAA for the District to award the Contract for the subject Proj ect to Thompson Builders Corporation in the amount of $15,419,685.63 (with correction) for the combined B ase Bid totals for Bid Schedules A, B, and C, Our recommendation is based on our analysis of Thompson Builders Corporation being the only responsive Michael Wegley
July 10, 2023

Page 2 of 2 ends

Mead & Hunt | 1360 19 th Hole Drive, Suite 200, Windsor, CA, 95492-7717 | 707-526-5010 | meadhunt.com bidder. As part of the award, Thompson Builders Cor poration is required to provide detailed Good Faith Effort Documentation for Disadvantaged Business Ent erprise (DBE) participation within 2 working days o f notification that they are the lowest responsive bidder.

Please feel free to contact me if you have any questions.

Sincerely,
MEAD & HUNT, Inc.

Joe Cruz
Project Manager

Attachments:

Bid Tabulation

Merced Yosemite Regional Airport, City of Merced
Terminal Replacement Project 2023 Math Error on Bid Schedule Form AIP: 3-06-0152-030-2023 Amount not shown on Bid Schedule Form Bid Abstract - Re-Bid Summary
Item Spec No. Description Unit Qty Unit Cost Total Unit Cost Total Unit Cost Tota l Unit Cost Total 1 SP 100-3.1 Airfield Safety and Traffic Control LS 1 $32,400.00 $32,400.00 $30,000.00 $30,000.00 $34,000.00 $34,000.00 $218,025.00 $218,025.00 2 SP 100-3.2 Construction Staking and Survey Layout LS 1 $21,000.00 $21,000.00 $9,600.00 $9,600.00 $9,700.00 $ 9,700.00 $21,830.00 $21,830.00 3 C-100-14 Contractor Quality Control Program (CQCP) L S 1 $42,000.00 $42,000.00 $121,000.00 $121,000.00 $121,41 1.63 $121,411.63 $225,720.00 $225,720.00 4 C-102a Prepare Storm Water Pollution Prevention Pl an (SWPPP) LS 1 $7,500.00 $7,500.00 $1,400.00 $1,400.00 $1 ,400.00 $1,400.00 $21,600.00 $21,600.00 5 C-102b Water Pollution Control LS 1 $51,000.00 $51,000.00 $7,400.00 $7,400.00 $7,400.00 $ 7,400.00 $137,295.00 $137,295.00 6 C-105-5a Mobilization (Limited to 10% of Total Bid Schedule Cost) LS 1 $209,927.25 $209,927.25 $200,000.00 $ 200,000.00 $200,000.00 $200,000.00 $270,000.00 $270,000 .00 7 C-105-5b Engineer/RPR Field Office LS 1 $50,400.00 $50,400.00 $15,000.00 $15,000.00 $15,000. 00 $15,000.00 $141,075.00 $141,075.00 8 P-101-5.1a Asphalt Pavement Removal SY 8,880 $8.00 $71,040.00 $75.00 $666,000.00 $5.00 $44,400 .00 $5.00 $44,400.00 9 P-101-5.1b Portland Cement Pavement Removal SY 830 $40.00 $33,200.00 $7.00 $5,810.00 $7.00 $5,810.00 $3 8.00 $31,540.00 10 P-101-5.2 Removal of Foreign Substances/contaminat es SF 480 $2.50 $1,200.00 $25.00 $12,000.00 $25.00 $12,000. 00 $27.00 $12,960.00 11 P-101-5.3 Storm Drain Pipe Removal LF 330 $35.00 $11,550.00 $18.00 $5,940.00 $18.00 $5,940.00 $20.00 $6,600.00 12 P-101-5.4 Storm Drain Structure Removal EA 2 $1,800.00 $3,600.00 $1,100.00 $2,200.00 $1,100.00 $2, 200.00 $810.00 $1,620.00 13 P-101-5.6 Removal of Existing Chain Link Fence, Ga tes, and Foundations LF 620 $20.00 $12,400.00 $5.00 $3,1 00.00 $5.00 $3,100.00 $4.00 $2,480.00 14 P-101-5.7 Miscellaneous Demolition and Removals LS 1 $16,000.00 $16,000.00 $6,800.00 $6,800.00 $6,800.00 $ 6,800.00 $4,050.00 $4,050.00 15 P-152-4.1 Unclassified Excavation CY 900 $20.00 $18,000.00 $53.00 $47,700.00 $53.00 $47,700. 00 $122.00 $109,800.00 16 P-152-4.2 Subgrade Preparation SY 9,670 $4.25 $41,097.50 $8.00 $77,360.00 $8.00 $77,360.0 0 $9.00 $87,030.00 17 P-156-8.1 Cement-Treated Subgrade, 12-Inch Depth SY 9,670 $18.00 $174,060.00 $20.00 $193,400.00 $19.00 $183 ,730.00 $24.00 $232,080.00 18 P-209-5.1 Crushed Aggregate Base Course, P-209 CY 1,620 $85.00 $137,700.00 $137.00 $221,940.00 $170.00 $2 75,400.00 $200.00 $324,000.00 19 SP 100-3.6 Sand (for Bond Breaker) CY 3 $70.00 $210.00 $1,200.00 $3,600.00 $1,200.00 $3,600.0 0 $1,418.00 $4,254.00 20 P-401-8.1 Asphalt Surface Course, P-401 TON 1,740 $180.00 $313,200.00 $220.00 $382,800.00 $250.00 $435,000.00 $320.00 $556,800.00 21 P-501-8.1a Portland Cement Concrete Pavement, P-50 1 SY 2,610 $200.00 $522,000.00 $193.00 $503,730.00 $210.00 $548,100.00 $182.00 $475,020.00 22 P-501-8.1b Portland Cement Concrete Pavement, P-50 1, Reinforced SY 320 $210.00 $67,200.00 $372.00 $119,040. 00 $370.00 $118,400.00 $530.00 $169,600.00 23 P-610-5.1a Marking, Initial and Final Application, Yellow with Reflective Media SF 960 $10.50 $10,080.00 $ 11.00 $10,560.00 $11.00 $10,560.00 $11.00 $10,560.00 24 P-610-5.1b Marking, Initial and Final Application, Red with Reflective Media SF 900 $11.25 $10,125.00 $11. 00 $9,900.00 $11.00 $9,900.00 $11.00 $9,900.00 25 P-610-5.1c Marking, Single Application, Black SF 4,410 $4.00 $17,640.00 $3.00 $13,230.00 $3.00 $13,230.0 0 $3.00 $13,230.00 26 P-610-5.1d Marking, Temporary, Yellow with Reflect ive Media SF 340 $8.00 $2,720.00 $11.00 $3,740.00 $11.00 $3 ,740.00 $11.00 $3,740.00 27 P-610-5.1e Marking, Temporary, Black (Cover Existi ng markings) SF 480 $5.00 $2,400.00 $11.00 $5,280.00 $11.0 0 $5,280.00 $11.00 $5,280.00 28 D-701-5.1a Storm Drain Pipe, 12-Inch, PVC C900 wit h Jet Fuel Resistant Seals LF 90 $120.00 $10,800.00 $227 .00 $20,430.00 $230.00 $20,700.00 $247.00 $22,230.00 29 D-701-5.1b Storm Drain Pipe, 12-Inch, HDPE LF 60 $160.00 $9,600.00 $194.00 $11,640.00 $190.00 $11,400 .00 $135.00 $8,100.00 30 D-701-5.1d Storm Drain Pipe, 24-Inch, HDPE LF 230 $215.00 $49,450.00 $210.00 $48,300.00 $210.00 $48,3 00.00 $228.00 $52,440.00 31 D-701-5.1e Storm Drain Pipe, 30-Inch, HDPE LF 300 $290.00 $87,000.00 $21.00 $6,300.00 $210.00 $63,000 .00 $297.00 $89,100.00 32 D-701-5.1f Storm Drain Pipe, 30-Inch, RCP Class V LF 50 $310.00 $15,500.00 $227.00 $11,350.00 $230.00 $11,50 0.00 $486.00 $24,300.00 33 D-751-5.1b Catch Basin, Type 3, HS-20 Rated EA 4 $9,500.00 $38,000.00 $7,036.00 $28,144.00 $7,000.00 $ 28,000.00 $11,482.00 $45,928.00 34 D-751-5.1c Catch Basin, Type 4, HS-20 Rated EA 2 $12,500.00 $25,000.00 $7,036.00 $14,072.00 $7,000.00 $14,000.00 $31,406.00 $62,812.00 35 D-752-5.1 Oil Water Separator EA 1 $105,000.00 $105,000.00 $57,000.00 $57,000.00 $57,00 0.00 $57,000.00 $392,567.00 $392,567.00 36 SP 100-3.9 Chain Link Fence, Including Gates, Temp orary LS 1 $25,000.00 $25,000.00 $11,400.00 $11,400.00 $11 ,000.00 $11,000.00 $2,228.00 $2,228.00 37 F-162-5.1 Chain Link Fence with Privacy Slats, 8-F oot LF 410 $90.00 $36,900.00 $155.00 $63,550.00 $160.00 $65 ,600.00 $203.00 $83,230.00 38 F-162-5.2a Pedestrian Access Gate with Privacy Sla ts, 8-Foot EA 3 $2,500.00 $7,500.00 $5,700.00 $17,100.00 $ 5,700.00 $17,100.00 $7,830.00 $23,490.00 39 SP 100-3.10 Pedestrian Hand Rail LF 180 $110.00 $19,800.00 $407.00 $73,260.00 $410.00 $73,800 .00 $533.00 $95,940.00 BID SCHEDULE A TOTAL $2,309,199.75 TOTAL $3,041,076.00 TOTAL $2,622,561.63 TOTAL $4,042,854.00 Item Spec No. Description Unit Qty Unit Cost Total Unit Cost Total Unit Cost Tota l Unit Cost Total 1 SP 100-3.1 Airfield Safety and Traffic Control LS 1 $21,600.00 $21,600.00 $11,000.00 $11,000.00 $11,000.00 $11,000.00 $162,675.00 $162,675.00 2 SP 100-3.2 Construction Staking and Survey Layout LS 1 $14,000.00 $14,000.00 $9,700.00 $9,700.00 $9,700.00 $ 9,700.00 $21,830.00 $21,830.00 3 C-100-14 Contractor Quality Control Program (CQCP) L S 1 $28,000.00 $28,000.00 $54,000.00 $54,000.00 $53,000.0 0 $53,000.00 $225,720.00 $225,720.00 4 C-102a Prepare Storm Water Pollution Prevention Pl an (SWPPP) LS 1 $5,000.00 $5,000.00 $1,500.00 $1,500.00 $1 ,400.00 $1,400.00 $82,688.00 $82,688.00 5 C-102b Water Pollution Control LS 1 $34,000.00 $34,000.00 $12,000.00 $12,000.00 $12,000. 00 $12,000.00 $137,295.00 $137,295.00 6 C-105-5a Mobilization (Limited to 10% of Total Bid Schedule Cost) LS 1 $113,889.66 $113,889.66 $130,000.00 $ 130,000.00 $130,000.00 $130,000.00 $135,000.00 $135,000 .00 7 C-105-5b Engineer/RPR Field Office LS 1 $33,600.00 $33,600.00 $15,000.00 $15,000.00 $15,000. 00 $15,000.00 $91,260.00 $91,260.00 8 P-101-5.1a Asphalt Pavement Removal SY 7,110 $8.00 $56,880.00 $6.00 $42,660.00 $5.00 $35,550.0 0 $6.00 $42,660.00 9 P-101-5.1b Portland Cement Pavement Removal SY 200 $40.00 $8,000.00 $48.00 $9,600.00 $48.00 $9,600.00 $ 70.00 $14,000.00 10 P-101-5.3 Storm Drain Pipe Removal LF 280 $35.00 $9,800.00 $18.00 $5,040.00 $18.00 $5,040.00 $ 20.00 $5,600.00 11 P-101-5.4 Storm Drain Structure Removal EA 3 $1,800.00 $5,400.00 $1,100.00 $3,300.00 $1,100.00 $3, 300.00 $810.00 $2,430.00 12 P-101-5.5 Curb and Gutter Removal LF 510 $9.00 $4,590.00 $5.00 $2,550.00 $5.00 $2,550.00 $17. 00 $8,670.00 13 P-101-5.7 Miscellaneous Demolition and Removals LS 1 $24,000.00 $24,000.00 $6,800.00 $6,800.00 $6,800.00 $ 6,800.00 $4,050.00 $4,050.00 14 P-152-4.2 Embankment In-Place CY 800 $24.00 $19,200.00 $66.00 $52,800.00 $67.00 $53,600. 00 $82.00 $65,600.00 15 P-152-4.2 Subgrade Preparation SY 7,230 $4.25 $30,727.50 $10.00 $72,300.00 $10.00 $72,300 .00 $11.00 $79,530.00 16 P-156-8.1 Cement-Treated Subgrade, 12-Inch Depth SY 7,230 $18.00 $130,140.00 $22.00 $159,060.00 $22.00 $159 ,060.00 $27.00 $195,210.00 17 P-209-5.1 Crushed Aggregate Base Course, P-209 CY 30 $85.00 $2,550.00 $168.00 $5,040.00 $170.00 $5,100.00 $198.00 $5,940.00 18 SP 100-3.6 Sand (for Bond Breaker) CY 32 $70.00 $2,240.00 $1,200.00 $38,400.00 $1,200.00 $38, 400.00 $1,418.00 $45,376.00 19 P-401-8.1 Asphalt Surface Course, P-401 TON 1,470 $180.00 $264,600.00 $243.00 $357,210.00 $270.00 $396,900.00 $320.00 $470,400.00 20 P-501-8.1b Portland Cement Concrete Pavement, P-50 1, Reinforced SY 300 $210.00 $63,000.00 $117.00 $35,100.0 0 $120.00 $36,000.00 $170.00 $51,000.00 21 SP 100-3.7 Portland Cement Concrete, 3,000 PSI, Re inforced CY 80 $975.00 $78,000.00 $1,300.00 $104,000.00 $1 ,300.00 $104,000.00 $980.00 $78,400.00 22 SP 100-3.3 Curb and Gutter LF 860 $48.00 $41,280.00 $56.00 $48,160.00 $56.00 $48,160. 00 $94.00 $80,840.00 23 SP 100-3.5 Thermoplastic Markings (Landside) SF 1,720 $7.50 $12,900.00 $29.00 $49,880.00 $29.00 $49,880 .00 $30.00 $51,600.00 24 D-701-5.1b Storm Drain Pipe, 12-Inch, HDPE LF 240 $160.00 $38,400.00 $136.00 $32,640.00 $140.00 $33,6 00.00 $154.00 $36,960.00 25 D-701-5.1c Storm Drain Pipe, 18-Inch, HDPE LF 250 $190.00 $47,500.00 $194.00 $48,500.00 $190.00 $47,5 00.00 $217.00 $54,250.00 26 D-751-5.1a Catch Basin, Type 2, HS-20 Rated EA 6 $7,500.00 $45,000.00 $7,035.00 $42,210.00 $7,000.00 $ 42,000.00 $7,557.00 $45,342.00 27 D-751-5.1d Catch Basin (Curb Inlet), Type C EA 1 $8,000.00 $8,000.00 $1,700.00 $1,700.00 $17,000.00 $1 7,000.00 $11,503.00 $11,503.00 28 SP 100-3.8 Refuse (Trash) Enclosure EA 1 $55,000.00 $55,000.00 $37,000.00 $37,000.00 $37,000. 00 $37,000.00 $42,907.00 $42,907.00 29 SP 100-3.4 Traffic Signs LS 1 $15,000.00 $15,000.00 $15,600.00 $15,600.00 $16,000. 00 $16,000.00 $15,728.00 $15,728.00 30 F-162-5.1 Chain Link Fence with Privacy Slats, 8-F oot LF 60 $90.00 $5,400.00 $155.00 $9,300.00 $160.00 $9,600 .00 $203.00 $12,180.00 31 F-162-5.2b Manual Swing Gate, 8 Foot Total Opening , with Privacy Slats, 8-Foot EA 1 $4,500.00 $4,500.00 $4 ,000.00 $4,000.00 $4,000.00 $4,000.00 $5,265.00 $5,265.0 0 32 SP 100-3.11 Square Bollards Stainless Steel Finish EA 26 $400.00 $10,400.00 $2,300.00 $59,800.00 $2,300.00 $5 9,800.00 $3,953.00 $102,778.00 33 SP 100-3.12 Rubber Parking Bumper EA 19 $200.00 $3,800.00 $300.00 $5,700.00 $300.00 $5,700.0 0 $304.00 $5,776.00 34 SP 100-3.13 Decomposed Granite LS 1 $8,500.00 $8,500.00 $14,000.00 $14,000.00 $15,000.00 $15,000.00 $18,900.00 $18,900.00 35 SP 100-3.14 Bike Rack LS 1 $3,500.00 $3,500.00 $2,800.00 $2,800.00 $2,800.00 $2, 800.00 $9,430.00 $9,430.00 36 T-901-5.1 Seeding LS 1 $3,500.00 $3,500.00 $17,000.00 $17,000.00 $17,000.00 $1 7,000.00 $19,508.00 $19,508.00 BID SCHEDULE B TOTAL $1,251,897.16 TOTAL $1,515,350.00 TOTAL $1,565,340.00 TOTAL $2,438,301.00 Item Spec No. Description Unit Qty Unit Cost Total Unit Cost Total Unit Cost Tota l Unit Cost Total 1 A-300-5.1 6-inch Sanitary Sewer Lateral LS 1 $9,000.00 $9,000.00 $14,500.00 $14,500.00 $15,000.00 $15,000.00 $20,633.00 $20,633.00 2 A-321-5.1 8-inch Fire Service Lateral with Double Check Valve Backflow Preventer and Fire Department Connection Assemblies LS 1 $25,000.00 $25,000.00 $45,000.00 $45,000.00 $45,000. 00 $45,000.00 $102,854.00 $102,854.00 3 A-321-5.1 2-inch Domestic Water Service Connection Lateral with Backflow Preventer Assembly LS 1 $12,000.00 $12,000.00 $31,000.00 $31,000.00 $31,000. 00 $31,000.00 $52,951.00 $52,951.00 4 A-321-5.1 6-inch Fire Hydrant and Valve Assembly LS 1 $8,000.00 $8,000.00 $32,000.00 $32,000.00 $32,000.00 $32,000.00 $36,954.00 $36,954.00 5 Division 02 Demolish Existing GA Terminal building, Restroom building, and Restaurant building LS 1 $138,896.00 $138,896.00 $35,000.00 $35,000.00 $35,00 0.00 $35,000.00 $50,505.00 $50,505.00 6 Division 02 -
Division 34 Construct new terminal building and mechanical yard LS 1 $9,689,601.00 $9,689,601.00 $10,555,844.00 $10,555, 844.00 $11,073,784.00 $11,073,784.00 $10,192,500.00 $10 ,192,500.00 BID SCHEDULE C TOTAL $9,882,497.00 TOTAL $10,713,344.0 0 TOTAL $11,231,784.00 TOTAL $10,456,397.00 Item Spec No. Description Unit Qty Unit Cost Total Unit Cost Total Unit Cost Tota l Unit Cost Total 1 Division 02 -
Division 26 Shade structure at new parking lot LS 1 $1,468,903.00 $1,468,903.00 $1,300,000.00 $1,300,00 0.00 $454,635.00 $454,635.00 $893,161.00 $893,161.00 BID ALTERNATE TOTAL $1,468,903.00 TOTAL $1,300,000.00 T OTAL $454,635.00 TOTAL $893,161.00 Engineer's Estimate Thompson Builders Diede Construction, Inc ALTERNATE BID - BID SCHEDULE C TOTAL BASE BID - SCHEDULES A, B, C AND ALTERNATE BID 1 - SCHEDULE C $14,912,496.91 $15,874,320.63 $17,830,713.00

BID SCHEDULE C
TOTAL BASE BID SCHEDULES A, B, C $13,443,593.91 $16,937,552.00 $15,419,685.63 Engineer's Estimate Diede Construction, Inc

BID SCHEDULE B
BID SCHEDULE A Thompson Builders
Bobo Construction, Inc
$16,569,770.00
Bobo Construction, Inc
$15,269,770.00

← All documents from this meeting