CITY OF MERCED PROJECT CP220013/CP240043
CHANGE ORDER NO. 1
DATE: August 3, 2023
PROJECT NAME: Regional Park Restrooms
PROJECT LOCATION: Merced, California
CONTRACTOR: T&S Intermodal Maintenance, Inc DBA T & S West, a Stock Corporation - CA-General ADDRESS: 6540 S. Austin Road, Stockton, CA 95215
REASON FOR CHANGE ORDER:
Additional work to award Bid Alternate # 1 Applegate
THE NUMBER OF WORKING DAYS WILL BE ADJUSTED AS FOLLOWS 20 SKETCH ATTACHED: No
DESCRIPTION OF CHANGE: Unit Quantity Unit Price Amount
Permits, Bonds, Licenses & Insurance LS $ 35,000.00 $ 35,000.00 2 Public convenience and Safety LS 1 $ 3,000.00 $ 3,000.00 3 Water Pollution Control LS 1,000.00 1,000.00
Demolition of Restrooms EA 5,000.00 $ 10,000.00
Remove Existing Drain and Piping EA 3,000.00 3,000.00
Abandon Lateral Utilities LS $ 5,000.00 $ 5,000.00
Prepare Subbase/base for restroom slab EA 1.00 $ 1.00
New Connection to Existing Utilities IS $ 5,000.00 $ 5,000.00 Prepare Subbase/base for restroom slab EA 1 20,000.00 20,000.00 10 CTX Precast Santiago (Dakota) S-349 EA $ 220,000.00 $ 220,000.00 11 Remove Existing Concrete SF 1100 10.00 11,000.00
12 Install Concrete SF 1291 $ 30.00 38,730.00
13 Electrical System EA 1 $ 10,000.00 $ 10,000.00
14 Landscaping SF 1100 5.00 $ 5,500.00
15 Native Fill Material for Slopes CY 150 $ 50.00 $ 7,500.00 16 Restoration of Site LS 1 $ 3,000.00 3,000.00
Total for Change Order: $ 377.731.00
ORIGINAL CONTRACT AMOUNT: 458,350.00 CP220013
CHANGE ORDER #1 AMOUNT: $ 377,731.00 CP240043
TOTAL PROJECT COST TO DATE: $ 836,081.00
FUNDS ACCOUNTS VERIFIED:
20114010 - CP240043 S 377,731.00
FINANCE OFFICE DATE
ACCEPTED DATE: 8/04/2073
-
RECOMMENDED DATE: 8/14/23
(INTERIM CITY ENGINEER)
1 ATTACHMENT NO. 1
8/4/25
RECOMMENDED DATE:
8/16/2023
APPROVED DATE:
(INTERIM CITY ATTORNEY)
AUTHORIZED DATE:
(CITY MANAGER)
ATTESTED DATE:
(ASSISTANT/DEPUTY CITY CLERK)
(SEAL)
2