Timeline of Development
Initial ARPA allocation-5 million
• Base bid awarded- 5.8 million
• 2 fields, tennis/pickleball
courts, volleyball court, futsal
court, park lighting, some
parking and pathways
Additional ARPA allocation-3.3 million
• Change order 1 awarded- 1.3
million
• Added pathways in central
area, concession/restroom
infrastructure, playground
site prep, large picnic shelter
• Change Order 2 prepared- 1.5
million
• Adds scope that was not part
of initial bid but required to
carry out work authorized for
Phase 2
ALPINE SKI HOUSE
REQUESTING
AUTHORIZATION FOR SINGLE
SOURCING OF ADDITIONAL
WORK REQUESTED BY CITY
COUNCIL
Change Order 2- funded by City Council but not
part of the initial bid
• 2 additional soccer/football fields
• Soil import & site grading
• Additional electrical controls
• 2 basketball courts
• Concrete
• Backboards, striping, surfacing
Requesting to wave competitive bidding process
and award additional work to Single Source
• Single source purchases are allowed for
standardization of specific equipment,
supplies, or for reasons of compatibility
• Authorization provided in City Charter
section 3.04.210