Attachment 2
AMENDMENT MODIFICATION SUMMARY - (E-76)

FEDERAL AID PROGRAM CALIFORNIA DEPARTMENT OF TRANSPORTATION DLA LOCATOR: 10-MER-0-MER PROJECT LOCATION:

PREFIX: CML NORTH SIDE OF CHILDS AVE (FROM GOLDEN VALLEY HIGH SCHOOL TO COFFEE ST. (WEAVER MIDDLE SCHOOL)).

PROJECT NO: 5085(061) TYPE OF WORK:

SEQ NO: CONSTRUCT A CLASS I (FULLY-SEPARATED). "SAFE ROUTES TO SCHOOL" PREVAUTH/ AGREE DATES:

STATE PROJ NO: 10200247LN FED RR NO'S:

ALT. PROJ NO: PUC CODES: RV:

AGENCY: MERCED PROJ OVERSIGHT: ASSUMED/LOCAL ADMIN CON:

ROUTE: ENV STATUS / EIS 05/10/2023 SPR:

DISASTER NO: RW STATUS / DT: 1 08/10/2023 MCS:

TIP DATA INV RTE: OTH:

MCAG BEG MP:

FSTIP YR: 22/23 END MP: PROJECT END DATE (PED): 03/30/2025 STIP REF: 205-0000-0319 BRIDGE NO:

FSTIP ID CMAQ21-05

PROG CODE LINE NO IMPV TYPE FUNG SYS URBAN AREA URB/RURAL DEMO ID Y003 30 28
Y003 31 17
Y400 10 15

FUNDING SUMMARY

PHASE PROJECT COST FEDERAL COST AC COST
PE PREV. OBLIGATION $98,741.00 $87,415.00 $0.00
PE PE THIS $0.00 $0.00 $0.00
PE SUBTOTAL $98,741.00 $87,415.00 $0.00
RW PREV. OBLIGATION $0.00 $0.00 50.00
RW THIS REQUEST $0.00 $0.00 $0.00
RW SUBTOTAL $0.00 $0.00 $0.00
CON PREV. OBLIGATION $1,135,509.00 $1,005,266.00 $0.00
CON CON THIS REQUEST $520,262.00 $201,000.00 $0.00
CON SUBTOTAL $1,655,771.00 $1,206,266.00 $0.00
OTH PREV. OBLIGATION $0.00 $0.00 $0.00
OTH OTH THIS REQUEST $0.00 $0.00 $0.00
OTH SUBTOTAL $0.00 $0.00 $0.00
TOTAL: $1,754,512.00 $1,293,681.00 50.00

STATE REMARKS
05/16/2022 * SEQ 1: Initial authorization of the PE phase. * Proiect End Date (PED) established as 08/01/2023 effective SEO 1 approval. * Final design shall not start until NEPA is approved.

Ster aton regreest to xiend the project end date (PED) from 81012310 813124. Project progres has been slowed by negotiations with the ulies of the eventual relocation of their facilitie. There are no 09/01/2023
* SEQ 3: Initial authorization of the CON/CE phase. * CMAQ Emission Reduction (Ib/yr): ROG - 0.03; NOx - 0.02; PM2.5 - 0.00; PM10 - 0.02. * Project End Date (PED) established as 03/30/2025 effective SEQ SEat: AN Pist Program sing done Aard. aMd A alter gig 221,000 to CON is attached.

SEQ 4: CON adjustment at award. Obligating additional $201,000 YO03 funds at award as post programming change. No change to PED of 03/30/25.

FEDERAL REMARKS

AUTHORIZATION
AUTHORIZATION TO PROCEED WITH REQUEST: CON PREPARED IN FADS BY: NORIEGA, JASMINE ON 2024-07-02 948-3755 FOR: CON POST PROGRAMMING REVIEWED IN FADS BY: LIMA, WISHING ON 2024-07-16 599-4988 DOCUMENT TYPE: AMOD SUBMITTED IN FADS BY: LIMA, WISHING ON 2024-07-16 FOR CALTRANS PROCESSED IN FADS BY: SIGNATURE, NOT_REQUIRED ON 2024-07-16 FOR WA E-76 AUTHORIZED DATE IN FMIS GRACE REGIDOR ON 2024-07-24 10:45:44.0 SIGNATURE HISTORY FOR PROJECT NUMBER 5085(061) AS OF 07/30/2024

FHWA FMIS SIGNATURE HISTORY
MOD # SIGNED BY SIGNED ON
WAII HAYS 07/23/2024
WAIl HAYS 07/23/2024
GRACE REGIDOR 07/24/2024
WAIl HAYS 11/14/2023
WAII HAYS 11/14/2023
GRACE REGIDOR 11/15/2023
WAIl HAYS 06/05/2023
WAIl HAYS 06/05/2023
GRACE REGIDOR 06/12/2023
SHUN HUEY 06/01/2022
SHUN HUEY 06/01/2022
GRACE REGIDOR 06/02/2022
FHWA FMIS 3.0 SIGNATURE HISTORY

CALTRANS SIGNATURE HISTORY

DOCUMENT TYPE SIGNED BY SIGNED ON
AMEND/MOD LIMA, WISHING 07/16/2024