CITY OF MERCED PROJECT NO. CP230035
CHANGE ORDER NO. 4
DATE: October 4, 2024
PROJECT NAME: WWTF Phase VI Project - Headworks Improvements PROJECT LOCATION: Merced, California
CONTRACTOR: GSE Construction Company Inc
ADDRESS: 7633 Southfront Road, Ste 160, Livermore, CA 94551 REASON FOR CHANGE ORDER:
SaveCo additional startup trip to replace second bar screen THE NUMBER OF WORKING DAYS WILL BE ADJUSTED AS FOLLOWS: 0 SKETCH ATTACHED: No
DESCRIPTION OF CHANGE: Unit Quantity Unit Price Amount
1. 1 day of travel and 2 days on site LS 1 $ 9,789.15 $ 9,789.15 Total for Change Order: $ 9,789.15
ORIGINAL CONTRACT AMOUNT: 3,152,700.00
CHANGE ORDER #1 AMOUNT: $ 9,443.00
CHANGE ORDER #2 AMOUNT: 4,442.00
CHANGE ORDER #3 AMOUNT: $ 1,252.36
CHANGE ORDER #4 AMOUNT: $ 2,789.15
TOTAL PROJECT COST TO DATE: 3,177,626.51
FUNDS/ACCOUNTS VERIFIED:
CP230035-WWSTP-CON-CIPINFR $ 2,936.75
CP230035-WWTP-CON-CIPINFR S 6,852.41
FINANCE OFFICE DATE -
ACCEPTED DATE: 10/8/24
(CONTRACTOR)
RECOMMENDED DATE: 10/8/24
-
(CITY ENGINEER)
Sill Osu 10-1024
RECOMMENDED DATE:
-
(PROJECT CHAMPION)
APPROVED comerwell DATE: 10-18-24
As To Form
AUTHORIZED DATE:
(INTERIM CITY MANAGER)
ATTESTED DATE:
(ASSISTANT/DEPUTY CITY CLERK)
(SEAL)
1 GISE PCO #005
CONSTRUCTION
GSE Construction Co. Inc. Project: 876 - Merced WWTF Phase VI Project Improvement 7633 Southfront Road, Suite 160 1961 Gove Road
Livermore, California 94551 Merced, California 95341
Phone: (925) 447-0292
Fax: (925) 447-0962
Prime Contract Potential Change Order #005: CE #011 - SaveCo Additional Startup
TO: City of Merced FROM: GSE Construction Co.
678 West 18th Street 7633 Southfront Rd. Suite 160
Merced, California 95340 Livermore, California 94551
PCO NUMBER/REVISION: 005 / 0 CONTRACT:
REQUEST RECEIVED FROM: CREATED BY: Marc Saar (GSE Construction Co.) STATUS: Pending - In Review CREATED DATE: 9/25/2024
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
SCHEDULE IMPACT: O days PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $9,789.15
POTENTIAL CHANGE ORDER TITLE: CE #011 - SaveCo Additional Startup CHANGE REASON: Allowance
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows) CE #011 - SaveCo Additional Startup
SaveCo bar screen additional startup trip.
ATTACHMENTS:
Start Up #2 Change Order Request 2024 .docx
City of Merced GSE Construction Co.
678 West 18th Street 7633 Southfront Rd. Suite 160
Merced, California 95340 Livermore, California 94551
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
GSE Construction Co. Inc. Page 1 of 1 Printed On: 9/25/2024 12:06 PM PDT SAVECO® North America, Inc.
1570 St. Paul Ave.
SAVÉCO® Gurnee, IL 60031
P: 815.636.8306 • F: 847.672.7968
Member of WAMGROUP* www.savecowaterna.com • [email protected]
CHANGE ORDER REQUEST
Project: WEC222051AB Merced WWTF
Change Order REQUEST Date: 09/20/2024
Marc Saar
GSE Construction
Reference: Purchase Order 876-001
Signed September 25, 2023
Description Cost
Startup #2: 1 day of travel and 2 days on site to startup the second bar screen. $7,778.00
Total $ 7,778.00
Please issue a Contract Change Order for the sum of: $ 7,778.00 The Contract time will be increased by the following number of days: (0) Days SAVÉCO North America, Inc.
1570 St Paul Avenue
Gurnee, IL 60031
GSE CONSTRUCTION INC. DATE: 9/25/2024
PROJECT: City of Merced Phase VI Project Headworks Improvements CE# CEN 11 PROJECT No. : 876
PROPOSAL CALCULATION
DESCRIPTION OF PROPOSAL: Additional Startup trip for the second bar screen. The original proposal provided by the owner only included one trip.
BRIEF DESCRIPTION OF WORK
UNIT PRICES LABOR DIRECT COSTS TOTAL
DIRECT
DESCRIPTION QTY UNIT EQUIP. MATERIAL LABOR SUB EQUIP. MATERIAL LABOR S/CONTRACT COST Material
SaveCo Additional Startup Trip 1 LS SO $7.778.00 0 $ 0.0 0.00 $0.00 $7,778.00 $0.00 $0.00 $7.778.00 Sales tax 8.25% S641.69 $641.69
TOTALS 0.0 #DIV/O! $0.00 $8.419.69 $0.00 $0.00 $8.419.69 MARKUP EQUIPMENT 15% $0.00 $0.00
MARKUP MATERIALS 15 % $1,262.95 $1,262.95
MARKUP LABOR 25 % $0.00 $0.00
MARKUP SUBCONTRACTS 5 % $0.00 $0.00
BOND and INSURANCE (all risk) 1.1% $106.51
TOTAL CHANGE COST $9,789.15