DA TE: October 3, 2023
CITY OF MERCED PROJECT NO. CP220061
CHANGE ORDER NO. 2
PROJECT NAME: Community Park 42
PROJECT LOCATION: Merced, California
CONTRACTOR: American Paving Company
ADDRESS: P.O. Box 27587, Fresno CA 93729
REASON FOR CHANGE ORDER:
Additional work to add underground electrical, water. Quantity adjustment for additional asphalt per the contract unit price.
THE NUMBER OF WORKING DAYS WILL BE ADJUSTED AS FOLLOWS: 40 SKETCH ATTACHED: Yes
DESCRIPTION OF CHANGE:
Quantity Adjustments
Item No Item Unit Quantity Unit Price
I Portable Changeable Message Siirns (base bid Item 7) LS -1 $ 2 Storm Drain Manholes (base bit Item 18) EA 2 $
3 6" Sewer (Additional Sewer lines) (base bid Item 23) LF 1391 $ 4 Sewer Manhole (base bid Item 24) EA 3 $
5 10" Water Line (Offsite) (base bid Item 33) LF -499 s 6 Credit for deletion of Polyolefin under concrete (base bid & CCO# I) LS -1 $ 7 Credit for Storm Drain Pipe Substituion of ADS (12" & Above) LS -I $ 15,000.00
3,500.00
167.00
5,000.00
90.00 41,900.00
47,000.00
Amount
$ (15,000.00)
$ 7,000.00
$ 232,297.00
$ 15,000.00
$ (44,910.00)
$ (41,900.00)
$ (47,000.00)
Total for Quanity Adjustments: $ 105,487.00
Extra Work
Item No Item Unit Quantity Unit Price Amount
I Surveying Services LS I $ 9,200.00 $ 9,200.00
2 Soil Import LS I $ 112,200.00 $ I 12,200.00
3 Site Grading (Rough/ Fine) SF 259,710 $ 1.55 $ 402,550.50 4 12" Storm Drain LF 38 $ 80.00 s 3,040.00
5 Storm Drain Area Drains EA I s 2,400.00 $ 2,400.00
6 Connect to Existing Storm Drain LS I $ 3,200.00 $ 3,200.00 7 Electrical LS 1 $ 401,500.00 $ 401,500.00
8 Concrete Flatwork (Site Finish 'A') SF 23,666 $ 9.50 $ 224,827.00 9 Plexipave Surfacing Basketball Court (Site Finish 'J') SF 9,400 $ 2.00 $ 18,800.00 10 Plexipave Surfacing Basketball Court Striping (Site Finish 'K ') LF 1,100 $ 2.00 $ 2,200.00 11 Plexipave Surfacing Basketball Court Perimeter (Site Finish 'L'} SF 4,625 $ 2.00 $ 9,250.00 12 2x4 Header at Limit of Phase I (Site Feature • 50') LF 1,477 $ 15.00 $ 22,155.00 13 Basketball Poles, Backboard, and Rim (Site Feature '59') EA 4 $ 9,000.00 $ 36,000.00 14 Irrigation System SF 226,609 $ 0.60 $ 135,965.40
15 Extra Work to Connect to MID transformer LS 1 $ 18,300.00 $ 18,300.00 16 Extra Work to relocate 6" & 12" force main LS I $ 12,250.00 $ 12,250.00 17 Extra Work to remove & replace crushed rock for underground LS I $ 1,414.10 $ 1,414.10 18 Extra Work to relocated storm drain@ Well Site 20 LS I $ 11,800.00 $ 11,800.00 Total for Extra Work $ 1,427,052.00
Total for Change Order No. 2 S 1,532,539.00
1 Attachment 2