1 EXHIBIT “A”
Change Order Form
EXHIBIT “A”

CHANGE ORDER FORM
City of Milpitas
455 E. Calveras Boulevard
Milpitas, California 93035
CONTRACT CHANGE ORDER NO. __
Date: [INSERT]
To: [CONTRACTOR NAME]
[ADDRESS]
[ADDRESS]
Attn: [CONTRACTOR REP]
Project: [INSERT]
This Change Order covers changes to the contract as described herein. The Contractor shall construct, furnish equipment and materials, and perform all work as necessary or required to complete the Change Order items for the amount agreed upon between the Contractor and City of Milpitas and set forth herein.

Item
No. Description of Changes
Increase/
(Decrease)
in Contract
Amount
Contract
Time
Extension,
Days
1 2
Totals $
Original Contract Amount: $XX.00
Change by Previous Change Order(s): $XX.00
Contract Price Prior to this Change Order: $XX.00
Current Change Order Amount: $XX.00
Revised Contract Amount including this Change Order: $XX.00 38077.00180\29080232.10

Page 2 of 2 ends

2 EXHIBIT “A”
Change Order Form
The Contract Price and Contract Time shall be adjusted as set forth above. The undersigned Contractor approves the foregoing Change Order as to the changes, if any, in the contract price specified for each item including any and all supervision costs and other miscellaneous costs relating to the change in work, and as to the extension of time allowed, if any, for completion of the entire work on account of said Change Order. The Contractor agrees to furnish all labor and materials and perform all other necessary work, inclusive of the directly or indirectly related to the approved time extension, required to complete the Change order items. This document will become a supplement of the contract and all provisions will apply hereto. It is understood that the Change Order shall be effective when approved by the City.

Contractor accepts the terms and conditions stated above as full and final settlement of any and all claims arising out of or related to the subject of this Change Order and acknowledges that the compensation (time and cost) set forth herein comprises the total compensation due for the work or change defined in the Change Order, including all impact on any unchanged work. By signing this Change Order, the Contractor acknowledges and agrees that the stipulated compensation includes payment for all Work contained in the Change Order, plus all payment for any acceleration or interruption of schedules, extended overhead costs, delay, and all impact or cumulative impact on all Work under this Contract. The signing of this Change Order acknowledges full mutual accord and satisfaction for the change and that the stated time and/or cost constitute the total equitable adjustment owed the Contractor as a result of the change. The Contractor hereby releases and agrees to waive all rights, without exception or reservation of any kind whatsoever, to file any further claim or request for equitable adjustment of any type, for any reasonably foreseeable cause that shall arise out of, or as a result of, this Change Order and/or its impact on the remainder of the Work under the Contract.

Accepted:
(Signature) Contractor’s Authorized Representative Date Recommended:
(Signature) [**INSERT NAME, TITLE**] Date
Approved:
(Signature) Steven G. McHarris, City Manager Date
This Contract Change Order consists of XX pages and any exhibits attached to this Contract Change Order shall not be part of the Contract Change Order unless specifically initialed by or on behalf of both the Contractor and the City of Milpitas.

Contract Change Order
#1

EXHIBIT B - TECHNICAL SPECIFICATION

PLAYGROUND EQUIPMENT
PART 1 – GENERAL

1.01 RELATED SECTIONS

1. Poured-in-Place

2. Engineered Wood Fiber

1.02 DESCRIPTION OF WORK
Provide all necessary materials, labor, tools and equipment to perform the work included in this section for the installation of freestanding and composite playground equipment.

1.03 SUBMITTALS
A. Contractor shall submit a minimum of two (2) sets of submittal drawings and (2) sets of structural calculations signed and sealed by a Professional Engineer licensed in the state of California for City’s review and approval.

These submittals shall be the 1st order of work.

B. Product Data: Submit manufacturer's “cut-sheets,” technical data, installation instructions, warranties, and finish/color samples for all play equipment listed.

C. Qualification Data: For the qualified installer and Play Equipment shall be of IPEMA certification.

D. Product Certificates: For each type of playground equipment, from the manufacturer.

E. Warranty: Sample product warranty.

F. Material Certificates: For the following items, from the manufacturer:

Shop finishes.

Recycled plastic.
1 PLAYGROUND EQUIPMENT
(11/20/2019)
2 PLAYGROUND EQUIPMENT
(11/20/2019)

G. Qualification data for the Certified Playground Safety Inspector (CPSI) such as a resume and list of references.

1.04 JOB CONDITIONS
Contractor is solely responsible to protect all play equipment from any damage or vandalism until acceptance of project, or written acceptance of individual play equipment.

1.05 QUALITY ASSURANCE
A. Installer Qualifications: Installation must be completed by a manufacturer approved installer.

B. Inspector Qualifications: Installation must be inspected by a Certified Playground Safety Inspector.

C. Safety Standards: Provide playground equipment complying with or exceeding the requirements in ASTM F 1487.

D. Manufacturer Qualifications: A firm whose playground equipment components have been certified by IPEMA’s third-party product certification service.

Playground equipment and play structure components shall have the IPEMA Certification Seal.

1.06 WARRANTY
A. Special Warranty: Manufacturer’s standard form in which manufacturer agrees to repair or replace components of playground equipment that fails in materials or workmanship within the specified warranty period.

Failures include, but are not limited to, the following:
3 PLAYGROUND EQUIPMENT
(11/20/2019)

a. Structural failures
b. Deterioration of metals, metal finishes, and other materials beyond normal weathering.

B. Warranty period:

Swing seats – 3 years
Play structure posts, clamps, fasteners, beams – 100 year PART 2 – PRODUCTS

2.01 PLAY EQUIPMENT
Basis of Design product is by Landscape Structures Inc., Models as indicated in the specification.

1. Or Approved Equal. (Contractor must submit an or equal product a minimum of 4 days prior to the Bid Date)
A. Colors: TBD through submittal process.

B. Play equipment items shall be as specified on these documents.

2.02 PAINT
Paint shall meet the following requirements:

Primer shall be a quality two-part epoxy primer with good hiding power and formulated specifically for the purpose of covering graffiti if graffiti removal is the aim.

It shall be compatible with the surface it is used on as per the manufacturer's data sheet and must adhere well to the substrate and resist fading and chalking.
4 PLAYGROUND EQUIPMENT
(11/20/2019)

The paint shall comply with the volatile organic compound (VOC) requirements of California Environmental Protection Agency Air Resources Board, Architectural Surface Program
The Paint shall be exterior gloss enamel, mixed to match the color and finish of the adjacent surface to the satisfaction of the City’s representative, unless otherwise directed.

PART 3 – EXECUTION

3.01 EXAMINATION
A. Each play area and its condition shall be examined with the Installer for compliance with requirements for site clearing, earthwork, site surface and subgrade drainage, and other conditions affecting performance of the Work.

Begin installation of the playground equipment only after the final grading and completion of the protective surface or as permitted by the City.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.02 PREPARATION
Verify locations of playground perimeter and pathways. Verify that playground layout and equipment locations and fall zones comply with requirements for each type and component of equipment.
5 PLAYGROUND EQUIPMENT
(11/20/2019)

3.03 EQUIPMENT INSTALLATION
A. All play equipment shall be installed per the manufacturer’s specifications.

B. To guide installation, each structure shall be accompanied by bills of materials, written instructions, an erection plan view drawing, and a footing plan location drawing to be furnished prior to or with the delivery of the play structure. To facilitate assembly, each part shall be indelibly stenciled with an easily-read identification number keyed to the bills of materials and erection drawings. All components shall be shipped unitized, protectively wrapped, banded for mechanical handling and ready for assembly.

Maximum Equipment Height: Coordinate installed heights of equipment and components with finished elevations of protective surfacing. Set equipment so fall heights and elevation requirements for age group use and accessibility are within required limits. Verify that playground equipment elevations comply with requirements for each type and component of equipment.

C. Install all play equipment per respective manufacturer’s instructions in conjunction with all Contract Documents. Immediately notify the City Representative of any conflicting information or discrepancies.

D. Immediately after installation of adjacent paving, plantings, or other fixtures, Contractor shall completely wash down play equipment contained within the area until clean and free of debris.
6 PLAYGROUND EQUIPMENT
(11/20/2019)

E. Post and Footing Excavation: Excavate holes for posts and footings as indicated in firm, undisturbed or compacted subgrade soil.

F. Retain first paragraph below for playground equipment set without concrete or delete if playground equipment is attached to a supporting structure that does not require support by concrete footings. Post Set on Subgrade: Level bearing surfaces with drainage fill to required elevation.

G. Retain paragraph below if playground equipment is set with concrete footings. Most playground equipment requires concrete footings. Post Set with Concrete Footing: Comply with ACI 301 for measuring, batching, mixing, transporting, forming, and placing concrete.

Set equipment posts in concrete footing. Protect portion of posts above footing from concrete splatter. Verify that posts are set plumb or at the correct angle, alignment, height, and spacing. Retain first subparagraph below for posts set in concrete.

Place concrete around posts and vibrate or tamp for consolidation. Hold posts in position during placement and finishing operations until concrete is sufficiently cured.

Embedded Items: Use setting drawings and manufacturer's written instructions to ensure correct installation of anchorages for equipment.

Concrete Footings: Cast-In-Place Concrete. Smooth top, and shape to shed water.

3.04 QUALITY CONTROL
A. Upon completion of the installation of playground equipment products/parts, the playground shall be inspected and certified compliant by:
7 PLAYGROUND EQUIPMENT
(11/20/2019)

A Certified Playground Safety Inspector (CPSI) hired and paid for by the Contractor for playground safety compliance with ASTM F 1487-11 and ASTM F2373 (Equipment for children as 6 months -23 months) CPSI shall provide written report of findings to Contractor. Should the report identify deficiencies, these should be corrected at Contractor’ expense.

B. Notify the City’s representative 48 hours in advance of date and time of final inspection.

C. Contractor to provide final playground safety audit report to City noting full compliance.

D. Painted surfaces shall be free of streaks and bubbling and be consistent in color. The City’s representative shall inspect workmanship for approval.

3.05 MAINTENANCE
A. Contractor shall maintain all play equipment in a first-class, new condition until project final acceptance, or written acceptance of individual play equipment.

3.06 CLOSEOUT
A. Furnish to the City’s Representative, all manufacturer warranties, manuals, product maintenance training, and as-built drawings.

PART 4 – MEASUREMENT AND PAYMENT
The contract bid price paid for the items, playground equipment, shall include full compensation for furnishing all playground equipment, materials, labor, tools, equipment and incidentals including the hiring of a Certified Playground Safety Inspector; and for doing all work involved in the assembly, placement, footings, hardware, accessories, and all other elements for a complete functional playground equipment; submittal of full plans, specifications and structural calculations for the playground equipment and structures to the City for its review 8 PLAYGROUND EQUIPMENT
(11/20/2019)

and approval, as shown on the plans, or as per the specifications and as directed by the City.

END OF SECTION
[Type here] [Type here] [Type here]
1 PIP Specs ( Rev.11/20/2019)

TECHNICAL SPECIFICATION

POURED-IN-PLACE PLAYGROUND PROTECTIVE SURFACING
PART 1 – GENERAL
The new Poured-in-Place (PIP) surface for playgrounds shall be installed at the same location and cover the same area as the existing PIP surface which is to be replaced. The new PIP surface shall match the color of the existing PIP surface (dark colors shall not be permitted) and meet or exceed the performance requirements of the CPSC, ADA and Fall Height Test ASTM F1292-18. The surface must yield both a peak deceleration of no more than 200 G-max and a Head Injury Criteria (HIC) value of no more than 1,000 for a head-first fall from the highest accessible portion of play equipment being installed.

1.1 SCOPE
A. Furnish labor, material, and equipment necessary to install the new Poured-inPlace (PIP), resilient surfacing system to replace the existing PIP surface at the playground.
a. Work shall include, but not be limited to the following: removal and disposal of the existing PIP surface: layout, excavation, backfill, and furnishing and installing of base material where required; furnishing and installing of pouredin-place, resilient surfacing and all other incidental work to provide a complete resilient surfacing system.
b. Poured-in-Place playground surfacing shall consist of a polyurethane binder mixed with 100% recycled, shredded tire material which will make up the Cushion Layer. The Cushion Layer is capped with EPDM, TPV or Treated SBR rubber granules mixed with a polyurethane binder creating the Wear Course. [Type here] [Type here] [Type here]
2 PIP Specs ( Rev.11/20/2019)
Surfaces shall comply with ADA and CPSC guidelines as well as ASTM Standards. Manufacture is to be certified by IPEMA, and a third-party testing organization for playground surfaces and equipment.

1.2 PERFORMANCE REQUIREMENTS
A. Area Safety:

Poured-in-Place surface within playground use zones shall meet or exceed the performance requirements of the CPSC, ADA and Fall Height Test ASTM F1292-

18. The surface must yield both a peak deceleration of no more than 200 G-max and a Head Injury Criteria (HIC) value of no more than 1,000 for a head-first fall from the highest accessible portion of play equipment being installed as shown on drawings. IPEMA certification is required. (ASTM F1292-18 section 4.3.3; the laboratory test used to determine critical fall height shall have been conducted on surfacing material samples identical in design, materials, components, and thickness and manufactured as the installed playground surface).

B. Accessibility: NOTE: Children's outdoor play areas shall be in compliance with the Uniform Federal Accessibility Standards (UFAS) FED-STD-795 and the Architectural and Engineer Instructions (9AEI) Design Criteria.

C. The requirements of the Americans with Disabilities Act. Accessibility Guidelines (ADAAG) 28 CFR Part 36 that provide equal or greater accessibility than the requirements of UFAS must also be met in children's outdoor play areas.

D. Poured-in-Place surfaces intended to serve as accessible paths of travel for persons with disabilities shall be firm, stable and slip resistant, and shall meet the requirements of ASTM F 1951-14 and ASTM F1292-18.
[Type here] [Type here] [Type here]
3 PIP Specs ( Rev.11/20/2019)

1.3 APPLICABLE STANDARDS
A. ASTM International
B. ASTM C1028 - Standard test method for Determining the Static coefficient of friction of Ceramic Tile and Other Like Surfaces by the Horizontal Dynamometer Pull Meter Method.

C. ASTM D412 - Standard Test Methods for Vulcanized Rubber and Thermoplastic Rubbers and Thermoplastic Elastomers-Tension.

D. ASTM D624 - Standard Test Method for Tear Strength of Conventional Vulcanized Rubber and Thermoplastic Elastomers.

E. ASTM D2859 - Standard Test Method for Flammability of Finished Textile Floor Covering Materials.

F. ASTM E303 - Standard Test Method for Measuring Surfacing Frictional Properties using the British Pendulum tester.

G. ASTM F1292-18 - Standard Specification for Impact Attenuation of Surfacing Materials within the Use Zone of the Playground Equipment.

H. ASTM F1951 - Standard Specification for Determination of Accessibility of Surface Systems under and around Playground Equipment.

1.4 Poured-in-Place surfaces shall be installed by experienced personnel trained, certified and by the Manufacturer for PIP installation.

1.5 Submittals: The following shall be submitted:

A. The Contractor shall submit, two (2) complete sets of the material submittals, including manufacturer's name and address, specific trade names, catalog and model numbers, illustrations and descriptive material, and samples of the proposed material for this project for approval by the City’s representative.

B. Products submitted as equal must include hard copies of manufacture’s written specifications and warranty.
[Type here] [Type here] [Type here]
4 PIP Specs ( Rev.11/20/2019)
C. Manufacturer's descriptive data and installation instructions.

D. Manufacturer's details showing depths of Wear Course and sub-base materials, anchoring systems and edge details.

E. Upon request, a listing of at least five installations where products similar to these proposed for use have been installed and have been in service for a minimum period of 3 years. The list shall include owner or purchaser, address of installation, date of installation, contact person, and phone number.

F. A signed statement by the Manufacturer’s authorized official certifying that the surfacing system meets the requirements of ASTM F1292-18 for a head-first fall from the highest accessible portion of the specified playground equipment.

G. A signed statement from the Manufacturer of the poured in place surfacing attesting that all materials under this section shall be installed only by personnel trained and certified by the Manufacturer.

H. IPEMA Certification is mandatory

1.6 Delivery, Storage and Handling:

Materials and equipment shall be delivered and stored in accordance with the manufacturer's recommendations.

1.7 Project Site Conditions:

Poured-in-Place surfacing must be installed on a dry sub-surface, with no prospect of rain within the initial drying period, and within the recommend temperature range of the manufacturer. Installation in weather condition of extreme heat, cold (less than 55 degrees F), and/or high humidity may affect cure time, and the structural integrity of the final product. Immediate surrounding sites must be reasonably free of dust conditions or this could affect the final surface look. [Type here] [Type here] [Type here]
5 PIP Specs ( Rev.11/20/2019)

1.8 Sequencing and Scheduling:

Poured-in-Place surfacing shall be installed only after all playground equipment, shade structures, signs and any other items that will be within the surfacing area have been installed. Poured in Place surface installation shall be coordinate with installation of playground equipment when required.

1.9 Poured in Place surface installation shall also be coordinated with the manufacturer representative.

1.10 Warranty:

Poured-in-Place surface shall maintain required impact attenuation characteristics and be guaranteed against defects in workmanship and material for a five (5) year period. Warranty will be specific to maintenance requirements and performance standards of the completed product.

PART 2 – PRODUCTS

2.1 Poured-in-Place Safety surfacing shall consist of both recycled and synthetic materials meeting the requirements of this specification.

2.2 PRODUCT SCOPE
A. Poured-in-Place Surface: The poured-in-place surface shall consist of 100 percent recycled granulated and or shredded tire material mixed with a polyurethane binder, then capped with either an EPDM, TPV and aliphatic binder or aromatic binder.

B. It shall consist of a uniform material manufactured in such a way that the top portion meets the requirements specified herein for wear surface.

C. The type of safety surfacing shall be a poured-in-place system and shall be as indicated on the plans.
[Type here] [Type here] [Type here]
6 PIP Specs ( Rev.11/20/2019)

2.3 CUSHION LAYER SECTION
A. Impact Attenuating Cushion Layer:

Cushion Layer consists of recycled styrene butadiene rubber (SBR) adhered with a 100 percent solids polyurethane binder to form a resilient porous material.

B. Strands of SBR may vary from 0.5 mm - 2.0 mm in thickness by 3.0 mm - 20 mm in length.

C. SBR Crumb Rubber (5-9 Mesh) using sieve analysis ASTM D5644 with a fiber content of .1% or less mixed in.

D. Foam or standard rubber granules are not permitted in Cushion Layer.

E. Binder shall be between 10 – 14 % of the total weight of the material and shall provide 100 percent coating of the particles.

F. The Cushion Layer shall be compatible with the Wear Course and must meet requirements herein for impact attenuation.

2.4 WEAR COURSE
A. Wear Course shall consist of Ethylene Propylene Diene Monomer (EPDM), Thermal Plastic Vulcanized (TPV) granules with polyurethane binder formulated to produce an even, uniform, seamless surface.

Installation of surfacing shall be seamless and completely bonded to concrete of asphalt subsurface. Material shall cover all foundations and fill around all elements penetrating the surface.
[Type here] [Type here] [Type here]
7 PIP Specs ( Rev.11/20/2019)
B. EPDM shall be peroxide cured with an EPDM content of 26 percent and shall include a processing aid to prevent hardness with 26% poly content to maintain dynamic testing characteristics, weatherization and UV stability.

C. ASTM D2240 (Shore A) hardness of 55-65, not less than 26 percent rubber hydrocarbons.

D. Size of EPDM granules shall be 1.5-4 mm across. Binder shall be not less than 20 percent of total weight of rubber used in the wear surface and shall provide 100 percent coating of the particles.

E. TPV shall be angular granules with a (Shore A) hardness of 65°A ±5 and particle size between 1-4mm. Binder shall be not less than 20 percent of total weight of rubber used in the wear surface and shall provide 100 percent coating of the particles.

F. Thickness of Wear Course shall be a minimum 1/2 inch (12.7 mm).

G. The Wear Course shall be porous.

2.5 BINDER
A. No Toluene Diphenyl Isocyanate (TDI) shall be used.

B. No filler materials shall be used in urethane such as plasticizers and the catalyzing agent shall contain no heavy metals.

C. Weight of polyurethane shall be no less than 8.5 lbs. /gal (1.02 Kg/l) and [Type here] [Type here] [Type here]
8 PIP Specs ( Rev.11/20/2019)
no more than 9.5 lbs. /gal (1.14 Kg/1).

D. Manufacturer is permitted to modify the type of urethane required to match extreme weather conditions. Substitutions must be equal to or exceed original quality.

2.6 INSERTS
A. Insert shall be Thermal Plastic Vulcanized (TPV) angular granules with a (Shore A) hardness of 65° A ± 5 and particle size between 0.5-1.5 mm.

B. Thickness of the TPV Insert shall be 1/2" - 5/8" inch.

C. TPV Insert shall be porous.

D. Aromatic or Aliphatic urethane shall be used as a binder.

E. Location - TPV Insert to be installed under swings, swing bays, slide exits.

Location of wear mat inserts shall be approved by the Owner.

F. Standard Color TPV 0.5-1.5mm shall be used. Colors shall include four standard colors: Terra Cotta Red, Blue, Green, and Beige.

G. Size: Swing bay use locations shall have TPV Inserts inclusive of all outside bay structure poles. Singular swings and slide exits shall be 4'x4'x1/2" in thickness.
[Type here] [Type here] [Type here]
9 PIP Specs ( Rev.11/20/2019)

2.7 MATERIALS
A. Wear Course - EPDM Granules and/or TPV Granules
Manufacturer: NH Rubber Products and Rosehill Polymers, or equal As Distributed by: Robertson Industries Inc. (800) 858-0519, or equal Location Used: Playground Area
B. Cushion Layer - Shredded SBR
As Distributed by: Robertson Industries Inc. (800) 858-0519, or equal Location Used: Playground Area
C. Binder – Aromatic VORAMER MR Products
Manufacturer: DOW Chemical, or equal
As Distributed by: Robertson Industries Inc. (800) 858-0519, or equal Location Used: Playground Area
D. Binder – Aliphatic Urethane Premium, Non-Ambering
Manufacturer: Accella Polyurethane Systems, or equal,
As Distributed by: Robertson Industries Inc. (800) 858-0519, or equal Location Used: Playground Area
PART 3 – EXECUTION

3.1 SITE PREPARATION
A. Finished Grade/Slope:

Verify that finished elevations or adjacent areas are as indicated on the architectural or site plans, that the appropriate sub-grade elevation has been established for the particular safety surface to be installed, and that the subsurface has been installed per architectural, site or equipment plans while meeting accessibility and use zones requirements. [Type here] [Type here] [Type here]
10 PIP Specs ( Rev.11/20/2019)
B. Aggregate Sub Base:

Tolerance of aggregate sub base, where required, shall be with 3/8" inch (10mm) in 10' ft. (3050 mm). Verify that aggregate sub base has been fully compacted. Per ADA Guidelines: compacted Aggregate sub base - 4" inches of ¾” inch minus irregular stone with fines compacted to 95% percent in 2”-inch watered lifts.

C. Drainage:

Verify that sub-surfacing drainage, if required, has been installed to provide positive drainage.

3.2 INSTALLATION
A. Poured in Place Surfacing:

Components of the poured in place surfacing shall be mixed on site in a rotating tumbler to ensure components are thoroughly mixed and are in accordance with manufactures recommendations. Installation of surfacing shall be seamless up to 2,000 square feet per day and completely bonded to sub base. Material shall cover all foundations and fill around all elements penetrating the surface.

B. Cushion Layer:

Whenever practical, cushion layer of surfacing material shall be installed in one continuous pour on the same day of up to 2,000 square feet. When a second pour is required, stop the seam and fully coat the step of the previous work with polyurethane binder to ensure 100% bond with new work. Apply adhesive in small quantities so that new cushion layer can be placed before the adhesive dries.
[Type here] [Type here] [Type here]
11 PIP Specs ( Rev.11/20/2019)
C. Wear Course:

Wear Course must be either quality peroxide cured EPDM, TPV or Treated SBR granules. Wear surface shall be bonded to Cushion Layer. If necessary, additional primer shall be used between the cushion layer and Wear Course. Apply adhesive to Cushion Layer in small quantities allowing the Wear Course to be applied before adhesive dries. Surface shall be hand troweled to a smooth, even finish. Except where the Wear Course is composed of differing color patterns, pour shall be
continuous and seamless up to 2,000 square feet per day. Manufacturer’s sales representative shall be contacted for seamless in excess of 2,000 square feet. Where seams are required due to color change, size or adverse weather, a step configuration will be constructed to maintain Wear Course integrity. The edge of initial pour shall be coated with adhesive and wearing surface mixture shall be immediately applied. Pads with multiple seams shall include a top coat of urethane before being placed into use.

Butt joint seams shall not be acceptable except for repairs. Under special conditions and with Owners written approval seams may be permitted in same color pad. Manufacturer shall be consulted for specific applications.

D. Perimeter:

For installations over Existing Concrete, the perimeter must be saw cut to provide a keyway 1 inch deep x 1 inch wide, or formed during the pour, with surfacing rolled down into the void. Primer adhesive must be applied to all sides of the void. When connecting to a concrete curb or border, the inside vertical edge shall be primed with adhesive and the final 2 inches of the cushion layer shall be tapered to allow the wear surface material to be 1.5 - 2 thick where it joins the concrete.

E. Asphalt:

When installing over New Asphalt, a curb or other type of border is [Type here] [Type here] [Type here]
12 PIP Specs ( Rev.11/20/2019)
recommended around the entire pad to separate the new surface from other ground materials. Primer adhesive must be applied to the inside vertical edge of the border before poured in place surface installation.

F. Asphalt:

When installing over Existing Asphalt, a key way cut of 1”-inch-deep by 1" inch wide for the poured in place to taper into and terminate with required ADA slope.

G. Thickness: Construction methods such as the use of measured screeds or guides shall be employed to ensure that the full depth of specified surfacing material is installed. Surfacing system thickness throughout the playground equipment use zone shall be as required to meet the impact attenuation requirements specified herein.

H. Clean Up:

Manufacturer’s installers shall work to minimize excessive adhesive on adjacent surfaces or play equipment. Spills of excess adhesive shall be promptly cleaned.

I. Protection:

The safety surface shall be allowed to fully cure in accordance with Manufacturer's instructions. The surface shall be protected from all traffic during the curing period of 48 hours or as instructed by the Manufacturer.

J. Manufacturer Services:

A representative of the manufacturer experienced in installation of Pouredin-Place playground safety surfacing shall be provided to supervise the installation to ensure that the system meets the impact attenuation requirements as specified herein.
[Type here] [Type here] [Type here]
13 PIP Specs ( Rev.11/20/2019)

3.3 SITE AREA CLEAN UP
The site shall be kept clean and free of tools, trash, and debris and installation materials on a daily basis. Products may be stored on site during installation with appropriate protective measures and approval by the City’s representative.

4.0 TESTING AND INSPECTION
Upon completion of installation of safety surface material and play equipment:

1. Contractor shall contract an independent ASTM certified testing company for conducting the Impact Attenuation tests on the newly installed playground protective surfaces. Number of tests required per playground shall be dependent on the fall heights of the number of playground equipment installed. All test certificates shall be submitted to the City.

2. Contractor shall contract a Certified Playground Inspector (CPSI) to assess safety compliance of the playground. The written report of the findings by CPSI shall be submitted to the City.

3. The cost for conducting the Impact Attenuation tests, and the CPSI inspections shall be included within the bid price for various items.

4. Any and all defects or deficiencies identified by the Impact Attenuation tests, and the CPSI inspection reports shall be rectified by the Contractor at his own expense.
[Type here] [Type here] [Type here]
14 PIP Specs ( Rev.11/20/2019)

5.0 PAYMENT
The payment for Poured-in-Place (PIP) surface shall be per square foot of the actual area of the Poured-in-Place (PIP) surface installed at the play area to the required depth as specified. The unit rate shall include removing and disposal of the existing Poured-in-Place surface material, surface preparation required for installing the new PIP surface, and the costs of inspection by a CPSI and the associated reports.

END OF SECTION
1 EWF (Rev.11/20/2019)

TECHNICAL SPECIFICATION

ENGINEERED WOOD FIBER (EWF) PROTECTIVE SURFACE
PART 1 - GENERAL
Work Details
The work specified in this section consists of installation of Engineered Wood Fiber in accordance with these specifications, and in conformity with the dimensions and notes shown on the plans.

Quality Assurance and Compliance Details
Accessibility of Surface Systems - ASTM F1951-08: Determination of accessibility of surface systems under and around playground equipment.

Impact Attenuation - ASTM F1292-04: Impact attenuation of surface systems under and around playground equipment.

Standard for Engineered Wood Fiber - ASTM F2075-04: Minimum characteristics for those factors that determine particle size, consistency, purity and ability to drain.

IPEMA Certification: Manufacturer shall provide proof of certification. "In the interest of public playground safety, IPEMA provides an independent laboratory which validates a manufacturer's certification of conformance to ASTM F1292-04 and ASTM F2075-04. A list of current validated products, their thickness and critical heights may be viewed at
www.ipema.org."
PART 2 - MATERIAL DATA
Product shall be manufactured of ground wood fiber comprised of softwoods and/or hardwoods, consisting of randomly sized wood fibers the majority of which shall not exceed 2" in length and no more than 15% fines to aid in compaction.

Product shall have minimal bark and be free of twigs, leaf debris and other organic material, and be non-flammable.
2 EWF (Rev.11/20/2019)
Product depth, after installation, shall be in accordance with the procedure described in ASTM F1292 and shall meet guidelines for critical height as set forth by the Consumer Product Safety Commission for use of wood products for protective surfacing.

PART 3 - SUB-BASE TYPES & DETAILS
Engineered Wood Fiber may be installed over compacted earth. When required, a layer of gravel shall be installed to facilitate drainage.

PART 4 - SITE PREPARATION AND REQUIREMENTS
For in-ground (i.e. on grade) installations, the area shall be excavated to the depth required for the system (12 in. for 12 in. system, and 8 in. for 8 in. system). Both in-ground and above-ground systems shall be properly graded to not less than 1% (one percent) grade. The engineered wood fiber systems shall not be installed on grades exceeding 10 percent. Substrate (for both inground and above-ground systems) shall be firmly compacted, especially when additional fill material is to be provided. The substrate shall be free of stones, roots and other vegetation.

PART 5 - INSTALLATION
Appropriate depths of Engineered Wood Fiber shall be installed to comply with fall heights and equipment use zones as required by the Consumer Product Safety Commission's Handbook for Playground Public Safety, and applicable ASTM standards, and state and local codes and regulations.

Installation Instructions

1. Install playground equipment.

2. For above-ground systems, install retaining wall.

3. Install applicable drainage system. If manufactured drainage is being 3 EWF (Rev.11/20/2019)
used, follow instructions for the proper installation of the product.

4. If gravel drainage is used, place 3 inches of drainage gravel on a layer of geotextile fabric. The lower end of the site should be connected to a drain to channel collected water away from the site. Overlap all seams of the geotextile fabric a minimum of 3 in. Slit fabric to fit around equipment uprights. Where possible, overlap all slit fabric with next piece of fabric.

5. Cover drainage system (either manufactured drainage or gravel) or earth substrate with geotextile fabric. Overlap all seams a minimum of 3 in. Slit fabric to fit around equipment uprights. Where possible, overlap at slit fabric with next piece of fabric.

6. With permanent marker or warning label, mark uprights of equipment with compacted system depth 12 in.

7. Install the engineered wood fiber to a compacted depth of 12-inches, with mounding in the center of the play areas of the playground. Extra materials shall be provided to allow for compaction. Small front-end loader may be used to spread EWF. Care shall be provide that the front-end loader will not travel on the fabric or turn sharply on the EWF.

Manual spreading of the EWF may also be necessary. All EWF material delivered to the site must be installed which will result in level of the surfacing several inches above grade until it compacts. EWF needs to be compacted in order to be considered handicapped accessible. This can be achieved over time and usage, or with a mechanical compactor.

Saturating the initial load with water will help with compaction.

8. Wear mats shall be installed in excessive wear areas, such as slide exits, under swings, and sliding poles.

9. For a smooth finished surface, EWF shall be hand raked. After two weeks of active use, surface should be raked again.

Periodical adjustments of engineered wood fiber are required under slides, swings and other concentrated use zones. Installing wear mats in these areas will help control displacement in these high use zones.

PART 6 – WARRANTY
Engineered Wood Fiber shall have a 15 year performance warranty. 4 EWF (Rev.11/20/2019)
PART 7 – MAINTENANCE
A copy of the manual for maintenance of Engineered Wood Fiber shall be submitted to the City.

PART 8.- TESTING AND INSPECTION
Upon completion of installation of safety surface material and play equipment:

1. Contractor shall contract an independent ASTM certified testing company for conducting the Impact Attenuation tests on the newly installed playground protective surfaces. Number of tests required per playground shall be dependent on the fall heights of the number of playground equipment installed. All test certificates shall be submitted to the City.

2. Contractor shall contract a Certified Playground Inspector (CPSI) to assess safety compliance of the playground. The written report of the findings by CPSI shall be submitted to the City.

3. The cost for conducting the Impact Attenuation tests, and the CPSI inspections shall be included within the bid price for various items.

4. Any and all defects or deficiencies identified by the Impact Attenuation tests, and the CPSI inspection reports shall be rectified by the Contractor at his own expense.

PART 9 – PAYMENT
The payment for Engineered Wood Fiber (EWF) surface shall be in square foot of the actual area of the Engineered Wood Fiber surface installed at the play area to the required depth as specified. The unit rate shall include removing and disposal of the existing EWF surface and surface preparation if and when required for installing the new EWF surface, and the costs of inspection by a CPSI and the associated reports.

END OF SECTION
1 PATHWAY SPECIFICATION
(11/20/2019)

TECHNICAL SPECIFICATION

PATHWAY REPAIRS
PART 1 – GENERAL

1.1 RELATED SECTIONS

3. Pathway Rehabilitation

1.2 DESCRIPTION OF WORK
Provide all necessary materials, labor, tools and equipment to perform the work included in this section for the rehabilitation of the pathway located at Big Basin Drive and Clear Lake Avenue.

PART 2 – SITE PREPERATION

2.1 GENERAL EXCAVATION
A. Excavation shall be made to such widths as will give safe room for construction including bracing, supporting, and draining.

B. When performing excavation, the Contractor shall take all reasonable care to protect free from damage any foundations, walls, projecting reinforcement, pipes, utilities, and any other items encountered. The Contractor shall promptly draw to the notice of the Project Manager any conditions that may prevent him/her from providing such protection.

2.2 PREPARATION OF GRADE
A. Loose materials shall be removed from all cut surfaces. Exposed soils shall be scarified to a minimum depth of 6 inches and moistened (dried) to 2 to 3 percent above optimum moisture content, and re-compacted to a minimum of 95 percent relative compaction based on ASTM D1557 prior to placing any required backfill or base course.

B. The bottom of all excavations shall be rendered firm and dry (except as noted).

C. Any visible cracks in the bottom of the footing excavations shall be closed by wetting prior to construction of the foundation.

2.3 COMPACTION – GENERAL
A. Compaction of backfills, subgrade soils, aggregate base, aggregate subbase, and other soil materials shall be accomplished to the following density criteria or in horizontal lifts of thicknesses noted, or if not noted, as compatible with the compaction equipment used.

Material
Minimum Percent
Relative
Maximum
Uncompacted Lift
2 PATHWAY SPECIFICATION
(11/20/2019)

Compaction
(ASTM D1557)
Thickness
(Inches)
Subgrade soil (minimum of 12-inch
depth) below roads, parking lots,
sidewalks, foundation and slabs
95 8
Base and subbase fill for pavement
support:

Less than 3 feet below finish grade 95 8
Base course below asphalt or
concrete pavement
95 8
B. Fill and backfill soils shall be aerated and placed at moisture contents of 2 to 3 percent over optimum. Flooding or ponding of any fill or backfill materials and jetting of materials will not be permitted.

C. No placement or compacting shall be done when either the previously placed or the new materials are too wet from rain or excess application of water to obtain the compaction specified. At such time, work shall be suspended until the previously placed and/or new materials have dried sufficiently to permit proper compacting.

2.4 EXCAVATION BELOW GRADE
A. If the Contractor excavates below grade through error or for its own convenience, the Contractor may be directed by the Project Manager to replace the overǦexcavated material with structural fill/backfill or lean concrete as acceptable to the Project Manager.

The work of excavating below grade and furnishing and placing the acceptable material shall be performed at no additional cost to the City.

2.5 DISPOSAL OF MATERIALS
A. Excavated material shall not be stacked on any excavation or over buried pipes or structures. Inconvenience to traffic and work by others shall be avoided as much as possible. Excavated material shall be segregated for use in backfilling as structural fill/backfill, nonǦstructural (fill/backfill, trench backfill material, or for offǦsite disposal).

B. Surplus excavated material shall be disposed of by the Contractor off the work site. Any costs associated with the hauling and disposal of this surplus material shall be borne by the Contractor. If too much suitable fill material is removed from the site, the cost of bringing it back will be the responsibility of the Contractor.

C. Material which is unsuitable for fill, including rock, cemented materials, boulders, broken concrete, asphalt and other materials, shall be removed and disposed of at the Contractor's expense at a waste disposal or landfill site conforming to all local, State, and Federal regulations.

2.6 FINISH GRADING
A. Finish grading in preparation for placing of paving, walks, slabs, and appurtenances shall be performed at all places that are indicated on the Drawings, to the lines, grades, and elevations shown and otherwise as acceptable to the Project Manager. During the process of grading, the subgrade shall be maintained in a wellǦdrained condition. Finish grading for areas underlying paving, walks, structures, and slabs on grade shall be to plus or minus 0.04 feet of the designated grade.
3 PATHWAY SPECIFICATION
(11/20/2019)

B. If at the time of grading it is not possible to place any material in its proper section of the permanent embankment, fill, or excavation, such material shall be stockpiled for later use in designated staging areas. No extra payment will be made for the stockpiling or double handling of excavated material.

C. Stones or rock fragments larger than 3 inches in their greatest dimensions will not be permitted in the top 6 inches of the finished subgrade of fills or embankments.

D. In cuts, all loose or protruding rocks or boulders on the back slopes shall be barred loose or otherwise removed to line or finished grade of slope. All cut and fill slopes shall be uniformly dressed to the slope, crossǦsection and alignment shown on the Drawings.

2.7 SOIL TESTING/QUALITY ASSURANCE
A. Where referred to in the specifications, "compaction" or "relative compaction" shall refer to inǦplace dry density of soil expressed as a percentage of the maximum dry density of the same material as determined by ASTM D1557.

B. The percent relative compaction shall be determined and controlled in accordance with the requirements of either ASTM Standard Test Method D1557 or Caltrans California Test 216, as determined by the Project Manager. The field density shall be determined in accordance with the requirements of either ASTM Standard Test Method D1556 or Caltrans California Test 231, as determined by the Project Manager. Individual test results shall be used to determine whether compaction of an area meets minimum requirements in lieu of an averaging method as stated in Caltrans Test Method No. 231 (Part II). The Contractor shall have tests performed by a third-party consultant as required to determine compliance with the compaction requirements specified in these specifications.

C. Prior to the general placement of any materials and during such placement, the Project Manager will select areas within the limits of any work for testing the degree of compaction obtained. The Contractor shall arrange and pay for soil tests to be made by an independent testing laboratory acceptable to the City. The Contractor shall cooperate fully in obtaining the information desired. The frequency of testing shall be as determined and signed by the Project Manager. Testing shall be in accordance with the ASTM references listed above.

D. If test results are unsatisfactory, all costs involved in correcting the deficiencies in compacted materials shall be borne by the Contractor without additional cost to the City.

Costs of retesting and reinspection required as the result of inadequate, insufficient, or incomplete work by the Contractor shall be borne by the Contractor without additional cost to the City.

PART 3- AGGREGATE BASE COURSE

3.1 GENERAL

A. Section Includes: Aggregate base course for use under roadways, pavements, concrete slabs-on-grade, concrete structures, under drainage and electrical structures, and others as specified in these specifications or shown on the Drawings.

3.2 REFERENCES

4 PATHWAY SPECIFICATION
(11/20/2019)

A. State of California Department of Transportation (Caltrans):

1. Standard Specifications.

B. American Society of Testing and Materials (ASTM):

1. C 117 – Test Method for Material Finer than 75 mM (Number 200) Sieve in Mineral Aggregate by Washing.

2. C 136 – Method for Sieve Analysis of fine and Coarse Aggregates.

3. D 4318 – Test Method for Liquid Limit, Plastic Limit, and Plasticity Index of Soils.

3.2 SUBMITTALS

A. Product Data:

1. Source, gradation, and testing data for aggregate base course.

1. MATERIALS
A. Aggregate Base Course:

1. Caltrans Standard Specification Section 26 Class 2, 3/4- inch maximum aggregate size free from vegetable matter and other deleterious substances, and of such nature that aggregate can be compacted readily under watering and rolling to form a firm, stable base.

2. Materials derived from processing demolished or removed asphalt concrete are not acceptable.

3. Coarse aggregate material retained in Number 4 sieve shall consist of material of which at least 25 percent by weight shall be crushed particles when tested in accordance with California Test 205.

4. Aggregate shall not be treated with lime, cement, or other chemical material before the Durability Index test is performed.

5. Aggregate grading and sand equivalent tests shall be performed to represent not more than 500 cubic yards or one day’s production of material, whichever is smaller.

6. Grade within the limits and conform to quality requirements as follows when tested in accordance with California Test 202:

Sieve Sizes
(Square Openings)
Percent by Weight
Passing Sieve
1 inch 100
3/4 inch 90-100
Number 4 35-60
Number 30 10-30
Number 200 2-9
Quality Requirements
Description California Test Minimum Test Result
5 PATHWAY SPECIFICATION
(11/20/2019)

Resistance ( R
Value) 301 78
Sand Equivalent 217 22
Durability Index 229 35

2. PART 3 EXECUTION

1. EXAMINATION
A. Verification of Conditions: Examine conditions upon which the work specified in this Article depends for defects that may influence installation and performance.

B. Do not proceed with installation until unsatisfactory conditions have been corrected.

2. PREPARATION
A. Subgrade Preparation: Prepare as specified in Article 4.8 - Excavation and Backfill.

3. INSTALLATION
A. Furnish, spread, and compact aggregate base course material to the lines, grades, and dimensions indicated on the Drawings.

4. Spreading: The aggregate base material shall be delivered to the project site as a uniform mixture. It shall be deposited in place and spread in a manner that will maintain the uniformity of the material. Each layer shall be free from pockets of coarse or fine material. Where the required compacted thickness is 0.50 feet or less, the aggregate base may be spread and compacted in one layer. Where the required compacted thickness is more than 0.50 feet, the aggregate base material shall be spread in 2 or more layers so that each uncompacted layer thickness does not exceed

0.50 feet.

5. Compacting: Compact in accordance with the requirements of Article 4.8 - Excavation and Backfill.

PART 4 - ASPHALT PAVING

4.1 GENERAL

4. SUMMARY

A. Section Includes:

1. Removal, preparation, and replacement of existing asphaltic concrete pavement required as shown on the Drawings and as specified in these specifications.

2. Asphaltic concrete (AC) pavement for roadway, and grade adjustments, on prepared aggregate base course as shown on the Drawings.

5. REFERENCES
A. State of California, Department of Transportation (Caltrans):

6. Standard Specifications
B. American Society for Testing and Materials (ASTM):
6 PATHWAY SPECIFICATION
(11/20/2019)

1. D1557 Test Methods for Moisture-Density Relations of Soils and SoilǦAggregate Mixtures Using 10-lb Rammer and 18-in Drop.

2. D5581 Test Method for Resistance to Plastic Flow of Bituminous Mixtures Using Marshall Apparatus.

6. SUBMITTALS
A. Product information for aggregate materials, asphaltic concrete mix design, and prime and tack coats.

3. PART 2 PRODUCTS

1. MATERIALS
A. Prime (tack) coat shall be Type SCǦ70 liquid asphalt conforming to the requirements of the Caltrans Standard Specifications Section 39-4.02 and 93.

C. Asphaltic concrete surfacing shall conform to Caltrans Standard Specifications Section 39. Mineral aggregate shall be Type B, 3/4Ǧinch maximum gradation, medium class.

D. Asphalt to be mixed with the aggregate shall meet the requirements of Caltrans Standard Specifications Section 92, AR 4000, steam-refined paving asphalt.

4. PART 3 EXECUTION

1. PAVEMENT REMOVAL
A. Existing asphaltic pavements to be removed shall be saw cut without damaging adjacent pavement that is not to be removed.

E. The trimmed edges shall be painted with a coating of prime coat immediately prior to constructing the new abutting asphaltic pavements.

F. All removed aggregate and asphaltic pavement material is the property and disposal responsibility of the Contractor.

2. PROTECTION
A. No traffic shall be allowed until surface of paving has cooled sufficiently to prevent damage.

G. Barricades shall be erected if required to protect paving from traffic.

3. PAVEMENT INSTALLATION
A. The construction of AC pavements shall conform to the requirements of the Caltrans Standard Specifications and upon completion, the pavement shall be true to grade and cross sections.

H. The Contractor shall not pass equipment over any pipe, drain, utility line, duct or structure before it is protected by ample fill material, properly compacted. Any damage to such facilities shall be promptly repaired by the Contractor at his/her own expense.

I. Base and subbase materials shall be bladed to a smooth surface and shall be compacted to 95 percent relative compaction as determined by ASTM D1557. Subgrade for pavement shall not vary more than 0.05 feet (1.5 cm) from the specified road grade.
7 PATHWAY SPECIFICATION
(11/20/2019)

J. Asphaltic concrete shall have a minimum overall thickness of 4 inches.

Asphaltic concrete shall be compacted at least two layers if total thickness is more than 3 inches; at least three layers shall be placed if total thickness is more than 5.4 inches. Compact the asphaltic concrete to at least 95 percent of the relative compaction achieved by a specimen of the same mix design subjected to 75 blows per ASTM D5581.

K. All existing asphaltic pavement to be paved over or against shall receive a tack coat at a rate of 0.1 gallons per square yard (0.46 liters per square meter).

L. The total width of the accepted aggregate base material shall receive a bituminous prime coat at the rate of 0.25 gallons per square yard (1.14 liters per square meter).

M. When asphaltic concrete is to be applied over existing pavement and local irregularities (with only very minor damage) in the existing surface would result in a course of more than 1” thickness, the surface of the existing pavement shall be brought to uniform contour by patching with asphaltic concrete, thoroughly tamped or rolled until it conforms with the surrounding surface, and a prime coat applied.

N. When asphaltic concrete is to be applied over existing pavement, existing surfaces adjoining gutters and other permanent features shall be ground to create smooth transitions and to maintain surface water flow lines.

O. Potholes and depressed areas in existing pavements to be overlaid with new asphaltic concrete shall be saw cut and completely removed, subgrade and aggregate base course prepared, and patched with new asphaltic concrete before the installation of new pavement overlays.

P. Spreading shall be as nearly continuous as possible. When asphaltic concrete is laid against vertical surfaces such as gutters, the face of the vertical surface shall be roughened for proper bonding, cleaned, and then painted with a light coating of asphalt cement or emulsified asphalt.

Q. At terminations of new surface course, the asphaltic concrete shall be feathered into the existing surface over such a distance as may be required to produce a smooth riding transition. Existing pavements to be over-laid shall be ground or removed as required to avoid feather edges less than 1 inch in depth.

4. RESURFACING
A. In all existing pavement areas where the surface is removed, broken or damaged by Contractor's equipment or in which the ground has caved in or settled due to the installation of the improvements, or areas designated to be repaved, resurfaced, or modified, the surface shall be restored to the original grade by the Contractor.

R. Restoration of asphaltic concrete pavement shall be to the same section as the existing roadway/paved area or a minimum thickness of 2- inches, whichever is greater.

S. Wherever asphaltic concrete pavement does not terminate against a curb, gutter, or another pavement, the Contractor shall provide and 8 PATHWAY SPECIFICATION
(11/20/2019)

install a ground contact rated, pressure treated hem-fir, No. 2 or better, 2 by 6 header board, securely staked and fastened in place.

5. PAVEMENT MARKING REPAIR
A. All traffic markings and signs painted on areas which are covered with new or repair pavement shall be replaced in kind.

6. SPECIAL REQUIREMENTS
A. The restoration of all surfaces, as described herein, disturbed by the installation or repair to underground facilities shall be completed as soon as is reasonable and practical.

T. Areas trenched by the Contractor and designated to be resurfaced shall be temporarily paved with 1-inch thick (minimum) layer of cold asphalt mix within 3 working days after they are backfilled. After all major work that might damage pavement is completed, complete resurfacing of the entire specified area shall be performed.

7. CLEAN-UP
A. After all installation, repair and restoration of paving has been completed, all excess asphalt, dirt, rock and other debris shall be removed from the roadways. Adjoining curbs, gutters, structures, and other surfaces over-sprayed or splattered shall be cleaned of all asphalt concrete products.

8. REPAIR OF PAVEMENT SURFACE
A. Following final completion, the Contractor shall repair settled pavement over trenches, excavation, or backfill placed as part of this work during the period of the warranty of the work.

U. All materials and labor required for the repair of paving shall be supplied by the Contractor and the work shall be done in a manner satisfactory to the Project Manager.

2.1 TRAFFIC CONTROL
A. The Contractor shall submit a traffic control plan for approval by the City prior to the commencement of work. The contractor shall provide all necessary signs, advance warning signs, barricades, caution tape, guards, flagmen, arrow boards and other safety devices as may be required by the City Supervisor to give advised and reasonable protection, safety, and warning to persons and vehicular traffic in the area. All traffic control devices and methods shall conform to the applicable sections of the current State Specifications and the “Manual of Traffic Controls for Construction and Maintenance Work Zones”, except as specified herein.

The costs of providing traffic control, including all necessary personnel, directional and safety equipment, and all work involved in traffic control, shall be included in the various bid items for this contract end no additional payment will be allowed.

2.2 DUST CONTROL
A. The provisions of Section 10 of the State Specifications shall govern, except that the water is not a pay item, and the entire cost of preventing dust nuisance shall be at the expense of the Contractor.
9 PATHWAY SPECIFICATION
(11/20/2019)

2.3 SAFETY COMPLIANCE
A. Contractor accepts responsibility for determining that all necessary safeguards and PPE for protection of contractor’s employees are available or will be furnished to employees. All work performed must conform to CAL-OSHA standards. If the Contractor is observed failing to meet these requirements, the City reserves the right to issue a “Stop Work’ notice at which point the Contractor will cease operations at the work site until safety compliance is implemented and formal notice to resume operations by the City Supervisor has been issued. The Contractor is responsible for any cost(s) associated with the disruption of operations as a result safety noncompliance delay.

The Contractor shall inform the City Supervisor immediately if a safety hazard is discovered within a City public right of way.

2.4 CLOSEOUT
A. All services provided shall be subject to inspection and shall meet the approval of the City.

If they not approved, the City shall have the right to reject them or to require correction.

B. Acceptance or rejection of the work shall be made as promptly as practical, but failure to accept or reject the work shall not relieve the Contractor from responsibility for services provided not in accordance with the contract.

C. The City will not be deemed to have accepted the services by virtue of a partial or full payment for it.

D. The City shall be the final judge of all services and its decisions of all questions in dispute will be final.

PART 3 – MEASUREMENT AND PAYMENT
The contract bid price paid for pathway repair shall include full compensation for furnishing all materials, labor, tools, equipment and incidentals as per the specifications and as directed by the City.

END OF SECTION
1 Augistine Park Tech Specs
11/20/2019
Park: AUGUSTINE MEMORIAL PARK PLAYGROUND
Location: Cortez St. & Coelho St., Milpitas, CA 95035
Scope of Service:
2-5 Years Old Play Area:

1. Engineered Wood Fiber (EWF)
Remove and dispose the existing sand from the 2-5 yr. old play area and replace it with Engineered Wood Fiber min. 12 inches, meeting ASTM F1292 Impact Attenuation of Surface Systems Under and Around Playground Equipment.

2. Poured-in-Place (PIP) Surface
Remove and dispose of the existing Poured-in-Place (PIP) Surface and replace it with new Poured-in-Place (PIP) Surface meeting the requirements of ASTM F1292 Impact Attenuation of Surface Systems Under and Around Playground Equipment. Color and pattern to be determined via submittal review.

3. Fence
Remove and dispose of the existing 160 LF Of GI chain-link fence and replace it with a new vinyl coated steel chain-link fence compliant with ASTM 2049-11 (2017).
5-12 Years Old Play Area:

1. Poured-in-Place (PIP) Surface
Remove and dispose of the existing Poured-in-Place (PIP) Surface and replace it with new Poured-in-Place (PIP) Surface meeting the requirements of ASTM F1292 Impact Attenuation of Surface Systems Under and Around Playground Equipment. Color and pattern to match the existing.

2. Ground Elements (Free Standing) Equipment
Remove and dispose the existing Free Standing Slide and the Sliding Pole and replace it with a new Free Standing Slide with similar agility asset that is nonmetallic and has hand support. Sliding pole need not be replaced. New slide shall have max. fall height of 72 inches, min. area required shall be 6 ft.

The new slide shall be Rushwinder Slide Model No. 189314A by Landscape Structures or equal. Color shall be blue, gold and green in theme.

Exhibit C - 23-035 Technical Specifications by Park
2 Augistine Park Tech Specs
11/20/2019

3. Composite Structure Equipment
Chin Up Bar
Remove and dispose of the existing Chin Up Bar from the Composite Structure area. Install a new Chin Up Bar to another location of the play area, where this equipment will not interfere with other equipment, or a location designated by the City.

The new equipment shall be Freestanding Chin Up Station Model # 137958A by Landscape Structures or equal.

4. Site Restoration and Clean-up
Clean up the site and restore the play area to the pre-construction condition.

5. Attached Technical Specifications for EWF and PIP and Playground Equipment shall be followed.

6. Conformance to Standards and Submission of Certificates a) All play equipment and the play area surfaces to be provided by the Contractor shall meet USCPSC, IPEMA, and ASTM standards. b) Where play area surfaces have been replaced, the Contractor shall contract an independent ASTM certified testing company for conducting the Impact Attenuation tests on the newly installed playground protective surfaces. Test certificates shall be submitted to the City.
c) After installation of the play equipment, the play equipment and the installation shall be certified by a Certified Playground Safety Inspector (CPSI) and the certification submitted.
1 Augustine Park
11/20/2019
Augustine Memorial Park Photos
2 Augustine Park
11/20/2019
3 Augustine Park
11/20/2019
4 Augustine Park
11/20/2019
5 Augustine Park
11/20/2019
6 Augustine Park
11/20/2019
"VHVTUJOF.FNPSJBM Park – Qty. Sheet
Item Description
Unit Quantity Unit
Rate
$
Amount
$
2-5 yrs. Play Area

1. Remove and dispose the
existing sand and replace it with
Engineered Wood Fiber (EWF). SF 400

2. Remove and dispose the
existing Poured-in-Place (PIP),
Synthetic Safety Surface from
and install new PIP Surface as
described in the specifications
and shown on the plans
SF
2,600

3. Remove and dispose the
existing fence in 2-5 yr. play
area, and replace it with a new
fence compliant with ASTM
2046
LF
160
5-12 yrs. Play Area

4. Remove and dispose the
existing Poured-in-Place (PIP),
Synthetic Safety Surface and
install new PIP Surface as
described in the specifications
and shown on the plans
SF 8,000

5. Remove and dispose the
existing Free-Standing Slide
and Sliding Pole and replace it
with a new Free-Standing Slide
only.

Each 1
Augustine Memorial Park Playground
Quantity Sheet
NOTE: This sheet is to be completed and uploaded as part of Bidder’s response. Please upload this completed page in response to Question No. 9 "VHVTUJOF.FNPSJBM Park – Qty. Sheet

6. Remove and dispose the
existing Chin Up Bar from the
Composite Structure area and
replace it with a new free
standing Chin Up Bar in another
location of the play area that
does not interfere with other fall
zones.

Each 1

7. Site restoration and clean-up LS LS
TOTAL
Total Amount in Words____________________________________________

Cerano Park – Tech. Specs
11/20/2019

TECHNICAL SPECIFICATION
Park: CERANO PARK PLAYGROUND
Location: Murphy Ranch Rd., Milpitas, CA 95035
Scope of Service:

1. Poured-in-Place (PIP) Surface
Remove and dispose the existing Poured-in-Place (PIP) Surface from the 5-12 yr. and 2-5 yr. old play areas and replace it with new Poured-in-Place (PIP) Surface meeting the requirements of ASTM F1292 Impact Attenuation of Surface Systems Under and Around Playground Equipment. Color and pattern to be determined via submittal review.

2. Composite Structure Equipment:
a) Remove and dispose the existing Net Climber from the 2-5 yr. old play area and replace it with a new Sway Net from Kompan or equal. Color shall match the existing equipment.
b) Remove and dispose the existing Double Slide from the 2-5 yr. old play area and replace it with a new Double Plastic Slide from Kompan or equal. Color shall match the existing equipment.

3. Site Restoration and Clean-up
Clean up the site and restore the Play area to the pre-construction condition.

4. Attached Technical Specifications for PIP, and Playground Equipment shall be followed.

5. Conformance to Standards and Submission of Certificates a) All play equipment and the play area surfaces to be provided by the Contractor shall meet USCPSC, IPEMA, and ASTM standards. b) Where play area surfaces have been replaced, the Contractor shall contract an independent ASTM certified testing company for conducting the Impact Attenuation tests on the newly installed playground protective surfaces. Test certificates shall be submitted to the City.
c) After installation of the play equipment, the play equipment and the installation shall be certified by a Certified Playground Safety Inspector (CPSI) and the certification submitted.

Cerano Park – Tech. Specs
11/20/2019
Cerano Park Photos

Cerano Park – Tech. Specs
11/20/2019

Cerano Park – Tech. Specs
11/20/2019

Cerano Park – Tech. Specs
11/20/2019

Cerano Park – Tech. Specs
11/20/2019

Cerano Park – Tech. Specs
11/20/2019

Cerano Park – Tech. Specs
11/20/2019

Cerano Park – Tech. Specs
11/20/2019
Item Description
Unit Quantity Unit
Rate
$
Amount
$

1. Remove and dispose the
existing PIP, Poured-in-Place
Synthetic Safety Surface and
install new PIP as described in
the specifications and shown on
the plans
SF 2100

2. Remove and dispose the
existing Net Climber from the 2-
5 yr. old Composite Structure
Equipment, and replace it with
new sway net by Kompan
Each 1

3. Remove and dispose the
existing Double Slide from the
2-5 yr. old Composite Structure
Equipment, and replace it with
new Double Plastic Slide by
Kompan
Each 1

4. Site restoration and clean-up LS LS
TOTAL

Total Amount in Words ……………………………………………………………..

Cerano Park Playground
Quantity Sheet
NOTE: This sheet is to be completed and uploaded as part of Bidder’s response. Please upload this completed page in response to Question No. 10 1 John McDermott Park – Tech. Specs
11/20/2019

TECHNICAL SPECIFICATION
Park: JOHN MCDERMOTT PARK PLAYGROUND
Location: Alverez Ct., Milpitas, CA 95035
Scope of Service:

1. Engineered Wood Fiber (EWF) Surface
Remove and dispose the existing Engineered Wood Fiber (EWF) from the 2-5 yr. and 5-12 yr. old play areas and replace it with new Engineered Wood Fiber min. 12 inches, meeting ASTM F1292 Impact Attenuation of Surface Systems Under and Around Playground Equipment.

2. Repair of Existing Poured-in-Place (PIP) Surface
a) Repair the damaged sections of the surface and the edges of the existing PIP surface. Color and pattern to be determined via submittal review. b) Roll coat the entire repaired PIP surface with an aliphatic binder. Color of roll coat to match the existing PIP color.
c) After the surface and the edges of the PIP surface repaired and cured per the manufacturer’s instructions, the PIP surface shall be pressure washed to remove all the loose material. The surface shall be allowed to dry for a minimum of two days. Prior to application of roll coat, the surface shall be cleaned with an air blower.
d) The PIP surface shall be allowed to cure for a period of minimum 7 days prior to opening the park for use.

3. Composite Structure Equipment:

The existing Gametime slide in the 5-12 yr. old play area has neck entrapment issue, so it shall be removed and replaced with a new Gametime Swerve Slide or equal. Color shall be blue, grey, or cranberry in theme.

4. Site Restoration and Clean-up
Clean up the site and restore the Play area to the pre-construction condition.

5. Attached Technical Specifications for EWF and PIP Repair, and Playground Equipment shall be followed.

6. Conformance to Standards and Submission of Certificates a) All play equipment and the play area surfaces to be provided by the Contractor shall meet USCPSC, IPEMA, and ASTM standards. 2 John McDermott Park – Tech. Specs
11/20/2019
b) Where play area surfaces have been replaced, the Contractor shall contract an independent ASTM certified testing company for conducting the Impact Attenuation tests on the newly installed playground protective surfaces. Test certificates shall be submitted to the City.
c) After installation of the play equipment, the play equipment and the installation shall be certified by a Certified Playground Safety Inspector (CPSI) and the certification submitted.

3 John McDermott Park – Tech. Specs
11/20/2019
John McDermott Park Photos
4 John McDermott Park – Tech. Specs
11/20/2019
5 John McDermott Park – Tech. Specs
11/20/2019
6 John McDermott Park – Tech. Specs
11/20/2019
7 John McDermott Park – Tech. Specs
11/20/2019

8 John McDermott Park – Tech. Specs
11/20/2019
Item Description
Unit Quantity
Unit
Rate
$
Amount
$

1. Remove and dispose the
existing Engineered Wood Fiber
(EWF) from 5-12 yrs.(1160 SF),
and 2-5 yrs. (500 SF) play areas
and install new EWF as
described in the specifications
and shown on the plans
SF 1,700

2. Repair the damaged sections of
the existing PIP surface and
edges. Color of repaired surface
to match the existing color.

SF 100

3. Roll coat the entire existing PIP
surface. Color of surface to
match the existing color SF 400

4. Remove and dispose the
existing Gametime Slide from
the Composite Structure
Equipment 5-12 yrs. play area,
and replace it with a new
Gametime Swerve Slide, or
equal.

Each 1

5. Site restoration and clean-up LS LS

TOTAL

Total Amount in Words ……………………………………………………………..

JOHN McDERMOTT PARK PLAYGROUND

QUANTITY SHEET
NOTE: This sheet is to be completed and uploaded as part of Bidder’s response. Please upload this completed page in response to Question No.11 1 O’Toole Elms Park – Tech Specs
11/20/2019

TECHNICAL SPECIFICATION
Park: O’TOOLE ELMS PARK PLAYGROUND
Location: 700 South Abel St., Milpitas, CA 95035
Scope of Service:

1. Repair of Existing Poured-in-Place (PIP) Surface
5-12 yr. Old Play Area
Roll coat the entire PIP surface with an aliphatic binder. Color of roll coat to match the existing PIP color. Color and pattern to be determined via submittal review.

Prior to roll coat, the surface shall be pressure washed to remove all the loose material. The surface shall be allowed to dry for a minimum of two days. Prior to application of roll coat, the surface shall be cleaned with an air blower.

2. Repair of Existing Poured-in-Place (PIP) Surface
2-5 yr. Old Play Area
a) Repair the damaged sections of the surface at slide exits, swing posts, and the edges of the existing PIP surface.
b) Roll coat the entire repaired PIP surface with an aliphatic binder. Color of roll coat to match the existing PIP color. Color and pattern to be determined via submittal review.

After the surface and the edges of the PIP surface repaired and cured per the manufacturer’s instructions, the PIP surface shall be pressure washed to remove all the loose material. The surface shall be allowed to dry for a minimum of two days. Prior to application of roll coat, the surface shall be cleaned with an air blower.

The PIP surface shall be allowed to cure for a period of minimum 7 days prior After the surface and the edges of the PIP surface repaired and cured per the manufacturer’s instructions, the PIP surface shall be pressure washed to remove all the loose material. The surface shall be allowed to dry for a minimum of two days. Prior to application of roll coat, the surface shall be cleaned with an air blower.
2 O’Toole Elms Park – Tech Specs
11/20/2019
The PIP surface shall be allowed to cure for a period of minimum 7 days prior to opening the park for use.

3. Site Restoration and Clean-up
Clean up the site and restore the Play area to the pre-construction condition.

4. Attached Technical Specifications for PIP repair shall be followed.

5. Conformance to Standards and Submission of Certificates a) All play equipment and the play area surfaces to be provided by the Contractor shall meet USCPSC, IPEMA, and ASTM standards. b) Where play area surfaces have been replaced, the Contractor shall contract an independent ASTM certified testing company for conducting the Impact Attenuation tests on the newly installed playground protective surfaces. Test certificates shall be submitted to the City.
c) After installation of the play equipment, the play equipment and the installation shall be certified by a Certified Playground Safety Inspector (CPSI) and the certification submitted.

3 O’Toole Elms Park – Tech Specs
11/20/2019
O’Toole Elms Park Photos
4 O’Toole Elms Park – Tech Specs
11/20/2019
5 O’Toole Elms Park – Tech Specs
11/20/2019
3FQBJSUIFEBNBHFETFDUJPOTPGUIFFYJTUJOH1*1BOE
SPMMDPBUUIFFOUJSF1*1TVSGBDFXJUIBOBMJQIBUJD
CJOEFS
6 O’Toole Elms Park – Tech Specs
11/20/2019
3FQBJSFYJTUJOH1*1TVSGBDFJOZSPMEQMBZBSFB
7 O’Toole Elms Park – Tech Specs
11/20/2019
3FQBJSFYJTUJOH1*1TVSGBDFJOZSPMEQMBZBSFB
8 O’Toole Elms Park – Tech Specs
11/20/2019
Item Description
Unit Quantity
Unit
Rate
$
Amount
$

1. 2-5 yr. old play area:

Repair the damaged sections of
the existing Poured-in Place
(PIP) Surface and the edges.
and roll coat per specification.

Color of repaired PIP to match
the existing PIP.

SF 100

2 Roll coat the existing Poured-in
Place (PIP) surface for the 2-5
yr. old and 5-12 yr. old play
areas. Color to match the
existing PIP surface
SF 2,300

3 Site restoration and clean-up LS LS

TOTAL

Total Amount in Words ……………………………………………………………..

O’TOOLE ELMS PARK PLAYGROUND

QUANTITY SHEET
NOTE: This sheet is to be completed and uploaded as part of Bidder’s response. Please upload this completed page in response to Question No. 12 1 Pinewood Park- Tech. Specs
11/20/2019

TECHNICAL SPECIFICATION
Park: PINEWOOD PARK PLAYGROUND
Location: Starlite Dr. & Lonetree Ct., Milpitas, CA 95035 Scope of Service:

1. Engineered Wood Fiber (EWF)
Remove and dispose the existing sand from the 2-5 yr. old and 5-12 yr. play areas and replace it with Engineered Wood Fiber min. 12 inches, meeting ASTM F1292 Impact Attenuation of Surface Systems Under and Around Playground Equipment.

2. Poured-in-Place (PIP) Surface
Remove and dispose the existing Poured-in-Place (PIP) Surface from the 2-5 yr. old and 5-12 yr. play areas and replace it with new Poured-in-Place (PIP) Surface meeting the requirements of ASTM F1292 Impact Attenuation of Surface Systems Under and Around Playground Equipment. Color and pattern to be determined via submittal review.

3. Composite Structure Equipment - Equipment Replacement 5-12 yr. Old Play Area
a) Spiral Slide (Duraglide Slide)
The slide is composed of segments that connect to make one continuous slide and some segments are warping and separating.

The existing slide is to be demolished and disposed and replaced with a new spiral slide with similar agility asset to be installed. b) Curved Slide (sectional Snake Slide)
The slide is composed of segments that connect to make one continuous slide and there are gaps between the segments.

The existing slide is to be demolished and disposed and replaced with a new curved slide with similar agility asset to be installed. c) Colors shall match existing equipment.

4. Site Restoration and Clean-up
Clean up the site and restore the Play area to the pre-construction condition. 2 Pinewood Park- Tech. Specs
11/20/2019

5. Attached Technical Specifications for EWF, PIP, and Playground Equipment shall be followed.

6. Conformance to Standards and Submission of Certificates a) All play equipment and the play area surfaces to be provided by the Contractor shall meet USCPSC, IPEMA, and ASTM standards. b) Where play area surfaces have been replaced, the Contractor shall contract an independent ASTM certified testing company for conducting the Impact Attenuation tests on the newly installed playground protective surfaces. Test certificates shall be submitted to the City.
c) After installation of the play equipment, the play equipment and the installation shall be certified by a Certified Playground Safety Inspector (CPSI) and the certification submitted.

3 Pinewood Park- Tech. Specs
11/20/2019
Pinewood Park Photos
4 Pinewood Park- Tech. Specs
11/20/2019
5 Pinewood Park- Tech. Specs
11/20/2019
6 Pinewood Park- Tech. Specs
11/20/2019
7 Pinewood Park- Tech. Specs
11/20/2019
Pinewood Park Playground Quantity Sheet
NOTE: This sheet is to be completed and uploaded as part of Bidder’s response. Please upload this completed page in response to Question No. 13 8 Pinewood Park- Tech. Specs
11/20/2019
Item Description Unit Quantity
Unit
Rate
$
Amount
$

1. Remove and dispose the existing
Poured-in-Place (PIP) Surface
from 2–5 yrs. old play area, and
install new PIP, as described in the
specifications and shown on the
plans SF 1,400

2. Remove and dispose the existing
PIP, Poured-in-Place Synthetic
Safety Surface from 5-12 yr. old
play area and install new PIP, as
described in the specifications and
shown on the plans
SF 1,600

3. Remove and dispose the existing
EWF from 2-5 yr. old play area
and install new EWF, as described
in the specifications and shown on
the plans SF 3,300

4. Remove and dispose the existing
EWF from 5-12 yr. old play area
and install new EWF, as described
in the specifications and shown on
the plans
SF 6400

5. Remove and dispose the following
existing Composite Structure
Equipment from 5-12 old play area,
and replace and install new
structures from All About Play

5a. Spiral Slide ( Duraglide Slide) Ea 1
9 Pinewood Park- Tech. Specs
11/20/2019

Total Amount in Words ……………………………………………………………..
5b. Curved Slide (Sectional Snake
Slide) Ea 1

6. Site restoration and clean-up LS LS
TOTAL
1 Selwyn Park – Tech Specs
11/20/2019

TECHNICAL SPECIFICATION
Park: SELWYN PARK PLAYGROUND
Location: 228 Selwyn Dr., Milpitas, CA 95035
Scope of Service:

1. Engineered Wood Fiber (EWF)
Remove and dispose the existing sand from the play area and replace it with Engineered Wood Fiber min. 12 inches, meeting ASTM F1292 Impact Attenuation of Surface Systems Under and Around Playground Equipment .

2. Repair of Poured-in-Place (PIP) Surface
a) Repair the damaged sections and the edges of the existing PIP surface and edges. Color and pattern to be determined via submittal review. b) Roll coat the entire repaired PIP surface with an aliphatic binder. Color of roll coat to match the existing PIP color.

After the surface and the edges of the PIP surface repaired and cured per the manufacturer’s instructions, the PIP surface shall be pressure washed to remove all the loose material. The surface shall be allowed to dry for a minimum of two days. Prior to application of roll coat, the surface shall be cleaned with an air blower.

The PIP surface shall be allowed to cure for a period of minimum 7 days prior After the surface and the edges of the PIP surface repaired and cured per the manufacturer’s instructions, the PIP surface shall be pressure washed to remove all the loose material. The surface shall be allowed to dry for a minimum of two days. Prior to application of roll coat, the surface shall be cleaned with an air blower.

The PIP surface shall be allowed to cure for a period of minimum 7 days prior to opening the park for use.

3. Composite Structure Equipment
a) Remove and dispose the existing Barrier along the stairs and replace it with a new barrier from Landscape Structures or equal.
b) Remove and dispose the existing Tower Climber (Chimney Climber) from the 2 Selwyn Park – Tech Specs
11/20/2019
existing Composite Structure Equipment and replace and install a new Tower Climber from Ross Recreation or equal.
c) Color shall be teal, lime, and orange in theme.

4. Site Restoration and Clean-up
Clean up the site and restore the Play area to the pre-construction condition.

5. Attached Technical Specifications for EWF, PIP Repair, and Playground Equipment shall be followed.

6. Conformance to Standards and Submission of Certificates a) All play equipment and the play area surfaces to be provided by the Contractor shall meet USCPSC, IPEMA, and ASTM standards. b) Where play area surfaces have been replaced, the Contractor shall contract an independent ASTM certified testing company for conducting the Impact Attenuation tests on the newly installed playground protective surfaces. Test certificates shall be submitted to the City.
c) After installation of the play equipment, the play equipment and the installation shall be certified by a Certified Playground Safety Inspector (CPSI) and the certification submitted.

3 Selwyn Park – Tech Specs
11/20/2019
Selwyn Park Photos

4 Selwyn Park – Tech Specs
11/20/2019
5 Selwyn Park – Tech Specs
11/20/2019
6 Selwyn Park – Tech Specs
11/20/2019
7 Selwyn Park – Tech Specs
11/20/2019
8 Selwyn Park – Tech Specs
11/20/2019

9 Selwyn Park – Tech Specs
11/20/2019

Total Amount in Words …………………………………………………………..

Item Description
Unit Quantity
Unit
Rate
$
Amount
$

1. Remove and dispose a)
Barriers and b) Tower Climber
(Chimney Climber) from the
existing Composite Structure
Equipment and replace and
install a new Barrier and a
Tower Climber:

1a. Barrier Each 1
1b. Tower Climber Each 1

2. Repair the damaged sections of
the existing PIP surface and
edges. Color of repaired
surface to match the existing
color.

SF 400

3. Roll coat the entire existing PIP
surface. Color of surface to
match the existing color. SF 1,000

4. Remove and dispose the
existing sand and replace it with
Engineered Wood Fiber as
described in the specifications
and shown on the plans
SF 2,800

5. Site restoration and clean-up LS LS
TOTAL
Selwyn Park Playground Quantity Sheet
NOTE: This sheet is to be completed and uploaded as part of Bidder’s response. Please upload this completed page in response to Question No. 14 Tom Evatt Park- Tech Specs
11/20/2019

TECHNICAL SPECIFICATION
Park: TOM EVATT PARK PLAYGROUND
Location: Machado Ave., Milpitas, CA 95035
Scope of Service:

1. Poured-in-Place (PIP) Surface
Remove and dispose of the existing Poured-in-Place (PIP) Surface and the edges in the 2-5 yr. old play area and replace it with new Poured-in-Place (PIP) Surface meeting the requirements of ASTM F1292 Impact Attenuation of Surface Systems Under and Around Playground Equipment. Color and pattern to be determined via submittal review.
 Play Structure – Removal of Equipment
B
Diagonal Saucer Rope Climber
This equipment is to be remove including the attachment at overhead bar, since the equipment interferes with the circulation around play area C
Rocking Seat West
This equipment is to be remove including all attachments, since the equipment creates conflict due proximity of adjacent components.  Site Restoration and Clean-up
Clean up the site and restore the Play area to the pre-construction condition.

4. Attached Technical Specifications for PIP shall be followed.

5. Conformance to Standards and Submission of Certificates a) All play equipment and the play area surfaces to be provided by the Contractor shall meet USCPSC, IPEMA, and ASTM standards. b) Where play area surfaces have been replaced, the Contractor shall contract an independent ASTM certified testing company for conducting the Impact Attenuation tests on the newly installed playground protective surfaces. Test certificates shall be submitted to the City.
c) After installation of the play equipment, the play equipment and the installation shall be certified by a Certified Playground Safety Inspector (CPSI) and the certification submitted.

Tom Evatt Park- Tech Specs
11/20/2019
Tom Evatt Park Photos
Tom Evatt Park- Tech Specs
11/20/2019
d)
Tom Evatt Park- Tech Specs
11/20/2019
Tom Evatt Park- Tech Specs
11/20/2019
Tom Evatt Park- Tech Specs
11/20/2019
Tom Evatt Park- Tech Specs
11/20/2019

Tom Evatt Park- Tech Specs
11/20/2019
Item Description
Unit Quantity
Unit
Rate
$
Amount
$
1 Remove and dispose the
existing, Poured-in-Place (PIP)
Synthetic Safety Surface and
install new Poured-in-Place
Synthetic Safety Surface as
described in the specifications
and shown on the plans
SF 2800

2 Remove and dispose the
following play equipment from
the Play Structure:
a) Diagonal Saucer Rope
Climber
b) Rocking Seat West
No replacements necessary
LS LS

3 Site restoration and clean-up LS LS
TOTAL

Total Amount in Words ……………………………………………………………..

Tom Evatt Park Playground Quantity Sheet
NOTE: This sheet is to be completed and uploaded as part of Bidder’s response. Please upload this completed page in response to Question No. 15 [Type here] [Type here] [Type here]
1 TECHNICAL SPECIFICATION
Park: PARC METRO (CENTRAL) PLAYGROUND
Location: Comet Drive, Milpitas, CA 95035
Scope of Service:

1. Poured-in-Place (PIP) Surface
Remove and dispose the existing river sand playground surface and replace it with new Poured-in-Place (PIP) Surface meeting the requirements of ASTM F1292 Impact Attenuation of Surface Systems Under and Around Playground Equipment. Color and pattern to be determined via submittal review.

2. Play Structure – Removal and Installation of Equipment a) Remove and dispose of three existing play structures and associated appurtenances.
b) Furnish and install one playground structures for ages 2 – 5 from Ross Recreation PlaySense Series or equal.
c) Furnish and install one playground structures for ages 2 – 5 from Ross Recreation PlaySense Series or equal.
d) Colors shall be green, blue, orange, and copper in theme.

3. Site Restoration and Clean-up
Clean up the site and restore the Play area to the pre-construction condition.

4. Attached Technical Specifications for PIP shall be followed.

5. Conformance to Standards and Submission of Certificates a) All play equipment and the play area surfacing to be provided by the Contractor shall meet USCPSC, IPEMA, and ASTM standards. b) Where play area surfaces have been replaced, the Contractor shall contract an independent ASTM certified testing company for conducting the Impact Attenuation tests on the newly installed playground protective surfaces. Test certificates shall be submitted to the City.
c) After installation of the play equipment, the play equipment and the [Type here] [Type here] [Type here]
2 installation shall be certified by a Certified Playground Safety Inspector (CPSI) and the certification submitted
Park Metro (Central) Photos
REMOVE SAND AND REPLACE WITH PIP.

REMOVE TWO EXISTING PLAY STRUCTURES

AND ASSOCIATED APPURTENANCES AND

REPLACE WITH ONE PLAYGROUND STRUCTURE
FOR AGES 2-5 FROM ROSS RECREATION
PLAYSENSE SERIES.

REMOVE EXISTING PLAY STRUCTURES AND

ASSOCIATED APPURTENANCES AND REPLACE WITH
ONE PLAYGROUND STRUCTURE FOR AGES 2-5
FROM ROSS RECREATION PLAYSENSE SERIES.

REMOVE SAND AND REPLACE WITH PIP.

PARK METRO (CENTRAL) PLAYGROUND

QUANTITY SHEET
NOTE: This sheet is to be completed and uploaded as part of Bidder’s response.

Please upload this completed page in response to Question No. 16 Item Description
Unit Quantity Unit
Rate
$
Amount
$

1. Remove and dispose of three
existing play structure. Each
3 Remove and dispose the
existing river sand playground
surface and replace it with new
Poured-in-Place (PIP),
Synthetic Safety Surface as
described in the specifications
and shown on the plans
SF 700

2. Remove and dispose of three
existing play structures and
associated appurtenance and
furnish and install two
playground structure for ages 2-
5 from Ross Recreation
PlaySense Series or equal.

Each 3
Remove and dispose the
existing river sand playground
surface and replace it with new
Poured-in-Place (PIP),
Synthetic Safety Surface as
described in the specifications
and shown on the plans
SF 600

3. Site restoration and clean-up LS LS
TOTAL

Total Amount in Words ……………………………………………………………..

TECHNICAL SPECIFICATION
Park: PARC METRO (EAST) PLAYGROUND
Location: 398 Curtis Avenue, Milpitas, CA. 95035
Scope of Service:

1. Poured-in-Place (PIP) Surface
Remove and dispose the existing river sand playground surface and replace it with new Poured-in-Place (PIP) Surface meeting the requirements of ASTM F1292 Impact Attenuation of Surface Systems Under and Around Playground Equipment. Color and pattern to be determined via submittal review.

2. Play Structure – Removal and Installation of Equipment a) Remove and dispose of one existing play structures and associated appurtenances.
b) Furnish and install one playground structures for ages 2 – 5 from Ross Recreation PlaySense Series or equal.
c) Colors shall be green, blue, orange, and copper in theme.

3. Site Restoration and Clean-up
Clean up the site and restore the Play area to the pre-construction condition.

4. Attached Technical Specifications for PIP shall be followed.

5. Conformance to Standards and Submission of Certificates a) All play equipment and the play area surfacing to be provided by the Contractor shall meet USCPSC, IPEMA, and ASTM standards. b) Where play area surfaces have been replaced, the Contractor shall contract an independent ASTM certified testing company for conducting the Impact Attenuation tests on the newly installed playground protective surfaces. Test certificates shall be submitted to the City.
c) After installation of the play equipment, the play equipment and the installation shall be certified by a Certified Playground Safety Inspector (CPSI) and the certification submitted.

Park Metro (East) Photos

REPLACE THE EXISTING SAND

WITH PIP SURFACE

REPLACE EXISTING PLAY STRUCTURE AND

APPURTENANCES WITH NEW PLAYGROUND
FOR AGES 2-5 FROM RECREATION
PLAYSENSE.

PARK METRO (EAST) PLAYGROUND

QUANTITY SHEET
NOTE: This sheet is to be completed and uploaded as part of Bidder’s response.

Please upload this completed page in response to Question No. 17 Item Description
Unit Quantity Unit
Rate
$
Amount
$

1. Remove and dispose the
existing river sand playground
surface and replace it with new
Poured-in-Place (PIP),
Synthetic Safety Surface as
described in the specifications
and shown on the plans
SF
850

2. Remove and dispose of one
existing play structures and
associated appurtenance and
furnish and install one
playground structure for ages 2-
5 from Ross Recreation
PlaySense Series or equal.

Each 1

3. Site restoration and clean-up LS LS
TOTAL

Total Amount in Words ……………………………………………………………..
[Type here] [Type here] [Type here]
1 TECHNICAL SPECIFICATION
Park: PARC METRO (WEST) PLAYGROUND
Location: 32 Curtis Avenue, Milpitas, CA. 95035
Scope of Service:

1. Poured-in-Place (PIP) Surface
Remove and dispose the existing river sand playground surface and replace it with new Poured-in-Place (PIP) Surface meeting the requirements of ASTM F1292 Impact Attenuation of Surface Systems Under and Around Playground Equipment. Color and pattern to be determined via submittal review.

2. Play Structure – Removal and Installation of Equipment a) Remove and dispose of two existing play structures and associated appurtenances.
b) Furnish and install one playground structures for ages 2 – 5 from Ross Recreation PlaySense Series or equal.
c) Furnish and install one playground structures for ages 5 – 12 from Ross Recreation PlaySense Series or equal.
d) Colors shall be green, blue, orange, and copper in theme.

3. Site Restoration and Clean-up
Clean up the site and restore the Play area to the pre-construction condition.

4. Attached Technical Specifications for PIP shall be followed.

5. Conformance to Standards and Submission of Certificates a) All play equipment and the play area surfacing to be provided by the Contractor shall meet USCPSC, IPEMA, and ASTM standards. b) Where play area surfaces have been replaced, the Contractor shall contract an independent ASTM certified testing company for conducting the Impact Attenuation tests on the newly installed playground protective surfaces. Test certificates shall be submitted to the City.
[Type here] [Type here] [Type here]
2 c) After installation of the play equipment, the play equipment and the installation shall be certified by a Certified Playground Safety Inspector (CPSI) and the certification submitted.

Parc Metro (West) Photos

REPLACE SAND WITH NEW PIP

REMOVE AND INSTALL ONE

PLAYGROUND STRUCTURES FOR AGES
2-5 FROM ROSS RECREATION

PLAYSENSE SERIES

REMOVE AND INSTALL ONE

PLAYGROUND STRUCTURES FOR AGES
5-12 FROM ROSS RECREATION

PLAYSENSE SERIES

PARK METRO (EAST) PLAYGROUND

QUANTITY SHEET
NOTE: This sheet is to be completed and uploaded as part of Bidder’s response.

Please upload this completed page in response to Question No. 18 Item Description
Unit Quantity Unit
Rate
$
Amount
$

1. Remove and dispose the
existing river sand playground
surface and replace it with new
Poured-in-Place (PIP),
Synthetic Safety Surface as
described in the specifications
and shown on the plans
SF
3,500

2. Remove and dispose of one
existing play structures and
associated appurtenance and
furnish and install one
playground structure for ages 2-
5 from Ross Recreation
PlaySense Series or equal.

Each 1

3. Remove and dispose of one
existing play structures and
associated appurtenance and
furnish and install one
playground structure for ages 5-
12 from Ross Recreation
PlaySense Series or equal.

Each 1

3. Site restoration and clean-up LS LS
TOTAL

Total Amount in Words ……………………………………………………………..
[Type here] [Type here] [Type here]
1 pe e 11 2 2 1

TECHNICAL SPECIFICATION
Park: SINNOTT PARK PLAYGROUND
Location: Clear Lake Avenue, Milpitas, CA. 95035
Scope of Service:

1. Poured-in-Place (PIP) Surface
Remove and dispose the existing river sand playground surface and replace it with new Poured-in-Place (PIP) Surface meeting the requirements of ASTM F1292 Impact Attenuation of Surface Systems Under and Around Playground Equipment. Color and pattern to be determined via submittal review. PIP shall only be installed for the fall protection area surrounding the play structures.

The remaining area shall be replaced with Engineered Wood Fiber (EWF).

2. Engineered Wood Fiber (EWF)
The remaining area surrounding the PIP surface shall be replaced with Engineered Wood Fiber (EWF), min. 12 inches, meeting ASTM F1292 Impact Attenuation of Surface Systems Under and Around Playground Equipment.

3. Play Structure – Removal and Installation of Equipment a) Remove and dispose of two existing play structures and associated appurtenances.
b) Furnish and install one playground structures for ages 2 – 5 from Ross Recreation PlaySense Series or equal.
c) Furnish and install one playground structures for ages 5 – 12 from Ross Recreation PlaySense Series or equal.
d) Colors shall be blue, green, gold, and grey/silver in theme.

4. Pathway Rehabilitation
a) Rehabilitation of the pathway located at Big Basin Drive and Clear Lake Avenue and perform pathway rehabilitation per attached technical specifications.

5. Site Restoration and Clean-up
[Type here] [Type here] [Type here]
2 pe e 11 2 2 1
Clean up the site and restore the Play area to the pre-construction condition.

6. Attached Technical Specifications for PIP shall be followed.

7. Conformance to Standards and Submission of Certificates a) All play equipment and the play area surfacing to be provided by the Contractor shall meet USCPSC, IPEMA, and ASTM standards. b) Where play area surfaces have been replaced, the Contractor shall contract an independent ASTM certified testing company for conducting the Impact Attenuation tests on the newly installed playground protective surfaces. Test certificates shall be submitted to the City.
c) After installation of the play equipment, the play equipment and the installation shall be certified by a Certified Playground Safety Inspector (CPSI) and the certification submitted.

Sinnott Park Photos
REMOVE SAND AND REPLACE WITH PIP.

REMOVE AND DISPOSE OF TWO EXISTING PLAY STRUCTURES AND

APPURTENANCES AND REPLACE WITH ONE PLAYGROUND
STRUCTURES FOR AGES 2-5 AND ONE PLAYGROUND STRUCTURES
FOR AGES 5-12 FROM ROSS RECREATION PLAYSENSE SERIES.

REMOVE AND REPLACE WITH ONE PLAYGROUND
STRUCTURES FOR AGES 5-12 FROM ROSS
RECREATION PLAYSENSE SERIES.

REMOVE AND REPLACE WITH ONE PLAYGROUND
STRUCTURES FOR AGES 2-5 FROM ROSS
RECREATION PLAYSENSE SERIES.

SINNOTT PARK PLAYGROUND

QUANTITY SHEET
NOTE: This sheet is to be completed and uploaded as part of Bidder’s response.

Please upload this completed page in response to Question No. 19 Item Description
Unit Quantity Unit
Rate
$
Amount
$

1. Remove and dispose the
existing river sand playground
surface and replace it with new
Engineered Wood Fiber (EWF)
and Poured-in-Place (PIP),
Synthetic Safety Surface as
described in the specifications
and shown on the plans.

SF 3,500
1a. Poured-in-Place (PIP),
Synthetic Safety Surface as
described in the specifications
and shown on the plans.

SF 6,500
1b. Replace remaining playground
area with Engineered Wood
Fiber (EWF).

SF

3. Remove and dispose of one
existing play structures and
associated appurtenance and
furnish and install one
playground structure for ages 2-
5 from Ross Recreation
PlaySense Series or equal.

Each 1

4. Remove and dispose of one
existing play structures and
associated appurtenance and
furnish and install one
playground structure for ages 5-
12 from Ross Recreation
PlaySense Series or equal.

Each 1

5. Site restoration and clean-up LS LS
TOTAL

Total Amount in Words ……………………………………………………………..
38077.00180\34438574.1
-1 SLFRF FEDERAL CONTRACT PROVISIONS

EXHIBIT D

SLFRF FEDERAL CONTRACT PROVISIONS
During the performance of this contract, _________________________________________ (the “Contractor” or “Vendor”) shall comply with all applicable federal laws and regulations including but not limited to the federal contract provisions in this Exhibit. In this Exhibit, the term “Agency” shall mean the local agency entering into this contract with the Vendor.

1. REQUIRED CONTRACT PROVISIONS IN ACCORDANCE WITH APPENDIX II TO PART 200 – CONTRACT PROVISIONS FOR NON-FEDERAL ENTITY CONTRACTS UNDER FEDERAL AWARDS (2 C.F.R. § 200.327)
(a) Appendix II to Part 200 (A); Appendix II to Part 200 (B): Remedies for Breach; Termination for Cause/Convenience. If the contract does not include provisions for termination for cause and termination for convenience by the Agency, including the manner by which it will be effected and the basis for settlement, then the following termination clauses shall apply. If the contract does not provide for administrative, contractual, or legal remedies in instances where Vendor violates or breaches the terms of the contract, then the following provisions shall apply. (i) Termination for Convenience. The Agency may, by written notice to Vendor, terminate this contract for convenience, in whole or in part, at any time by giving written notice to Vendor of such termination, and specifying the effective date thereof (“Notice of Termination for Convenience”). If the termination is for the convenience of the Agency, the Agency shall compensate Vendor for work fully and adequately provided through the effective date of termination. No amount shall be paid for unperformed work including anticipated profit.

Vendor shall provide documentation deemed adequate by the Agency to show the work actually completed by Vendor prior to the effective date of termination. This contract shall terminate on the effective date of the Notice of Termination for Convenience. (ii) Termination for Cause. If Vendor fails to perform pursuant to the terms of this contract, the Agency shall provide written notice to Vendor specifying the default (“Notice of Default”). If Vendor does not cure such default within ten (10) calendar days of receipt of Notice of Default, the Agency may terminate this contract for cause, or may, in its sole discretion, make a demand on Vendor’s performance bond surety. If Vendor fails to cure a default as set forth above, the Agency may, by written notice to Vendor, terminate this contract for cause, in whole or in part, and specifying the effective date thereof (“Notice of Termination for Cause”). If the termination is for cause, Vendor shall be compensated for that portion of the work which has been fully and adequately completed and accepted by the Agency as of the date the Agency provides the Notice of Termination. In such case, the Agency shall have the right to take whatever steps it deems necessary to complete the project and correct Vendor's deficiencies and charge the cost thereof to Vendor, who shall be liable for the full cost of the Agency's corrective action, including reasonable overhead, profit and attorneys' fees.
(iii) Reimbursement; Damages. The Agency shall be entitled to reimbursement for any compensation paid in excess of work rendered and shall be entitled to withhold compensation for defective work or other damages caused by Vendor’s performance of the work. (iv) Additional Termination Provisions. Upon receipt of a Notice of Termination for Convenience or Notice of Termination for Cause, Vendor shall promptly discontinue the work unless the Notice directs to the contrary. Vendor shall deliver to the Agency and transfer title (if necessary) to all completed work, and work in progress including drafts, documents, plans, forms, 38077.00180\34438574.1
-2 SLFRF FEDERAL CONTRACT PROVISIONS
maps, products, graphics, computer programs and reports. Vendor acknowledges the Agency’s right to terminate this contract with or without cause as provided in this Section, and hereby waives any and all claims for damages that might arise from the Agency’s termination of this contract.

The Agency shall not be liable for any costs other than the charges or portions thereof which are specified herein. Vendor shall not be entitled to payment for unperformed work, and shall not be entitled to damages or compensation for termination of work. If Agency terminates this contract for cause, and it is later determined that the termination for cause was wrongful, the termination shall automatically be converted to and treated as a termination for convenience. In such event, Vendor shall be entitled to receive only the amounts payable under this Section, and Vendor specifically waives any claim for any other amounts or damages, including, but not limited to, any claim for consequential damages or lost profits. The rights and remedies of the Agency provided in this Section shall not be exclusive and are in addition to any other rights and remedies provided by law, equity or under this contract including, but not limited to, the right to specific performance. (b) Appendix II to Part 200 (C) – Equal Employment Opportunity: Except as otherwise provided under 41 C.F.R. Part 60, if this contract meets the definition of a “federally assisted construction contract” in 41 C.F.R. § 60-1.3, then Vendor shall comply with the following equal opportunity clause, in accordance with Executive Order 11246 of September 24, 1965 entitled “Equal Employment Opportunity,” as amended by Executive Order 11375 of October 13, 1967 and implementation regulations at 41 C.F.R. Chapter 60:
(i) The Vendor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, sexual orientation, gender identity, or national origin. The Vendor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment without regard to their race, color, religion, sex, sexual orientation, gender identity, or national origin. Such action shall include, but not be limited to the following: Employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. The Vendor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided setting forth the provisions of this nondiscrimination clause.
(ii) The Vendor will, in all solicitations or advertisements for employees placed by or on behalf of the Vendor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, sexual orientation, gender identity, or national origin.
(iii) The Vendor will not discharge or in any other manner discriminate against any employee or applicant for employment because such employee or applicant has inquired about, discussed, or disclosed the compensation of the employee or applicant or another employee or applicant. This provision shall not apply to instances in which an employee who has access to the compensation information of other employees or applicants as a part of such employee's essential job functions discloses the compensation of such other employees or applicants to individuals who do not otherwise have access to such information, unless such disclosure is in response to a formal complaint or charge, in furtherance of an investigation, proceeding, hearing, or action, including an investigation conducted by the employer, or is consistent with the Vendor's legal duty to furnish information. (iv) The Vendor will send to each labor union or representative of workers with which he has a collective bargaining agreement or other contract or understanding, a notice to be provided advising the said labor union or workers' representatives of the Vendor's commitments 38077.00180\34438574.1
-3 SLFRF FEDERAL CONTRACT PROVISIONS
under this section, and shall post copies of the notice in conspicuous places available to employees and applicants for employment.
(v) The Vendor will comply with all provisions of Executive Order 11246 of September 24, 1965, and of the rules, regulations, and relevant orders of the Secretary of Labor. (vi) The Vendor will furnish all information and reports required by Executive Order 11246 of September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to his books, records, and accounts by the administering agency and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.
(vii) In the event of the Vendor's noncompliance with the nondiscrimination clauses of this contract or with any of the said rules, regulations, or orders, this contract may be canceled, terminated, or suspended in whole or in part and the Vendor may be declared ineligible for further Government contracts or federally assisted construction contracts in accordance with procedures authorized in Executive Order 11246 of September 24, 1965, and such other sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of September 24, 1965, or by rule, regulation, or order of the Secretary of Labor, or as otherwise provided by law.
(viii) The Vendor will include the portion of the sentence immediately preceding paragraph (i) and the provisions of paragraphs (i) through (vii) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to section 204 of Executive Order 11246 of September 24, 1965, so that such provisions will be binding upon each subcontractor or vendor. The Vendor will take such action with respect to any subcontract or purchase order as the administering agency may direct as a means of enforcing such provisions, including sanctions for noncompliance:

Provided, however, that in the event a Vendor becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of such direction by the administering agency, the Vendor may request the United States to enter into such litigation to protect the interests of the United States.

The applicant further agrees that it will be bound by the above equal opportunity clause with respect to its own employment practices when it participates in federally assisted construction work: Provided, That if the applicant so participating is a State or local government, the above equal opportunity clause is not applicable to any agency, instrumentality or subdivision of such government which does not participate in work on or under the contract.

The applicant agrees that it will assist and cooperate actively with the administering agency and the Secretary of Labor in obtaining the compliance of contractors and subcontractors with the equal opportunity clause and the rules, regulations, and relevant orders of the Secretary of Labor, that it will furnish the administering agency and the Secretary of Labor such information as they may require for the supervision of such compliance, and that it will otherwise assist the administering agency in the discharge of the agency's primary responsibility for securing compliance.

The applicant further agrees that it will refrain from entering into any contract or contract modification subject to Executive Order 11246 of September 24, 1965, with a contractor debarred from, or who has not demonstrated eligibility for, Government contracts and federally assisted 38077.00180\34438574.1
-4 SLFRF FEDERAL CONTRACT PROVISIONS
construction contracts pursuant to the Executive Order and will carry out such sanctions and penalties for violation of the equal opportunity clause as may be imposed upon contractors and subcontractors by the administering agency or the Secretary of Labor pursuant to Part II, Subpart D of the Executive Order. In addition, the applicant agrees that if it fails or refuses to comply with these undertakings, the administering agency may take any or all of the following actions: Cancel, terminate, or suspend in whole or in part this grant (contract, loan, insurance, guarantee); refrain from extending any further assistance to the applicant under the program with respect to which the failure or refund occurred until satisfactory assurance of future compliance has been received from such applicant; and refer the case to the Department of Justice for appropriate legal proceedings.
(c) Appendix II to Part 200 (D) – Davis-Bacon Act: Not applicable to this contract since it is funded by the SLFRF.
(d) Appendix II to Part 200 (D) – Copeland “Antti-Kickback” Act: Not applicable to this contract since it is funded by the SLFRF.
(e) Appendix II to Part 200 (E) – Contract Work Hours and Safety Standards Act:
(i) If this contract is in excess of $100,000 and involves the employment of mechanics or laborers, Vendor shall comply with 40 U.S.C. 3702 and 3704, as supplemented by Department of Labor regulations (29 C.F.R. Part 5). Under 40 U.S.C. 3702, each contractor must be required to compute the wages of every mechanic and laborer on the basis of a standard work week of 40 hours. Work in excess of the standard work week is permissible provided that the worker is compensated at a rate of not less than one and a half times the basic rate of pay for all hours worked in excess of 40 hours in the work week. The requirements of 40 U.S.C. 3704 are applicable to construction work and provide that no laborer or mechanic must be required to work in surroundings or under working conditions which are unsanitary, hazardous or dangerous.

These requirements do not apply to the purchases of supplies or materials or articles ordinarily available on the open market, or contracts for transportation or transmission of intelligence. (ii) Overtime Requirements. No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which he or she is employed on such work to work in excess of forty hours in such workweek unless such laborer or mechanic receives compensation at a rate not less than one and one-half times the basic rate of pay for all hours worked in excess of forty hours in such workweek. (iii) Violation; liability for unpaid wages; liquidated damages. In the event of any violation of the clause set forth in paragraph (ii) of this section the contractor and any subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such contractor and subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in paragraph (ii) of this section, in the sum of $10 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of forty hours without payment of the overtime wages required by the clause set forth in paragraph (ii) of this section. (iv) Withholding for unpaid wages and liquidated damages. The Agency shall upon its own action or upon written request of an authorized representative of the Department of 38077.00180\34438574.1
-5 SLFRF FEDERAL CONTRACT PROVISIONS
Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the Vendor or subcontractor under any such contract or any other Federal contract with the same prime contractor, or any other federally-assisted contract subject to the Contract Work Hours and Safety Standards Act, which is held by the same prime contractor, such sums as may be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in paragraph (iii) of this section.
(v) Subcontracts. The Vendor or subcontractor shall insert in any subcontracts the clauses set forth in paragraph (ii) through (v) of this Section and also a clause requiring the subcontractors to include these clauses in any lower tier subcontracts. The Vendor shall be responsible for compliance by any subcontractor or lower tier subcontractor with the clauses set forth in paragraphs (ii) through (v) of this Section.
(f) Appendix II to Part 200 (F) – Rights to Inventions Made Under a Contract or Agreement:
(i) If the Federal award meets the definition of “funding agreement” under 37 C.F.R. § 401.2(a) and the non-Federal entity wishes to enter into a contract with a small business firm or nonprofit organization regarding the substitution of parties, assignment or performance of experimental, developmental, or research work under that “funding agreement,” the non-Federal entity must comply with the requirements of 37 C.F.R. Part 401 (Rights to Inventions Made by Nonprofit Organizations and Small Business Firms Under Government Grants, Contracts and Cooperative Agreements), and any implementing regulations issued by the Federal awarding agency.
(ii) The regulation at 37 C.F.R. § 401.2(a) currently defines “funding agreement” as any contract, grant, or cooperative agreement entered into between any Federal agency, other than the Tennessee Valley Authority, and any contractor for the performance of experimental, developmental, or research work funded in whole or in part by the Federal government. This term also includes any assignment, substitution of parties, or subcontract of any type entered into for the performance of experimental, developmental, or research work under a funding agreement as defined in the first sentence of this paragraph. (g) Appendix II to Part 200 (G) – Clean Air Act and Federal Water Pollution Control Act: If this contract is in excess of $150,000, Vendor shall comply with all applicable standards, orders, or requirements issued pursuant to the Clean Air Act (42 U.S.C. 7401-7671q) and the Federal Water Pollution Control Act as amended (33 U.S.C. 1251-1387). (i) Pursuant to the Clean Air Act, (1) Vendor agrees to comply with all applicable standards, orders or regulations issued pursuant to the Clean Air Act, as amended, 42 U.S.C. § 7401 et seq., (2) Vendor agrees to report each violation to the Agency and understands and agrees that the Agency will, in turn, report each violation as required to assure notification to the Federal awarding agency and the appropriate Environmental Protection Agency Regional Office, and (3) Vendor agrees to include these requirements in each subcontract exceeding $150,000.
(ii) Pursuant to the Federal Water Pollution Control Act, (1) Vendor agrees to comply with all applicable standards, orders or regulations issued pursuant to the Federal Water Pollution Control Act, as amended, 33 U.S.C. 1251 et seq., (2) Vendor agrees to report each violation to the Agency and understands and agrees that the Agency will, in turn, report each 38077.00180\34438574.1
-6 SLFRF FEDERAL CONTRACT PROVISIONS
violation as required to assure notification to the Federal awarding agency and the appropriate Environmental Protection Agency Regional Office, and (3) Vendor agrees to include these requirements in each subcontract exceeding $150,000.
(h) Appendix II to Part 200 (H) – Debarment and Suspension: A contract award (see 2 C.F.R. § 180.220) must not be made to parties listed on the government wide exclusions in the System for Award Management (SAM), in accordance with the OMB guidelines at 2 CFR 180 that implement Executive Orders 12549 (3 C.F.R. part 1986 Comp., p. 189) and 12689 (3 C.F.R. part 1989 Comp., p. 235), “Debarment and Suspension.” SAM Exclusions contains the names of parties debarred, suspended, or otherwise excluded by agencies, as well as parties declared ineligible under statutory or regulatory authority other than Executive Order 12549. (i) This contract is a covered transaction for purposes of 2 C.F.R. pt. 180 and 2 C.F.R. pt. 3000. As such Vendor is required to verify that none of the Vendor, its principals (defined at 2 C.F.R. § 180.995), or its affiliates (defined at 2 C.F.R. § 180.905) are excluded (defined at 2 C.F.R. § 180.940) or disqualified (defined at 2 C.F.R. § 180.935). (ii) Vendor must comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C and must include a requirement to comply with these regulations in any lower tier covered transaction it enters into.
(iii) This certification is a material representation of fact relied upon by Agency.

If it is later determined that Vendor did not comply with 2 C.F.R. pt. 180, subpart C and 2 C.F.R. pt. 3000, subpart C, in addition to remedies available to the Agency, the Federal Government may pursue available remedies, including but not limited to suspension and/or debarment. (iv) Vendor warrants that it is not debarred, suspended, or otherwise excluded from or ineligible for participation in any federal programs. Vendor also agrees to verify that all subcontractors performing work under this contract are not debarred, disqualified, or otherwise prohibited from participation in accordance with the requirements above. Vendor further agrees to notify the Agency in writing immediately if Vendor or its subcontractors are not in compliance during the term of this contract.
(i) Appendix II to Part 200 (I) – Byrd Anti-Lobbying Act: If this contract is in excess of $100,000, Vendor shall have submitted and filed the required certification pursuant to the Byrd Anti-Lobbying Amendment (31 U.S.C. § 1353). If at any time during the contract term funding exceeds $100,000.00, Vendor shall file with the Agency the Federal Standard Form LLL titled “Disclosure Form to Report Lobbying.” Contractors that apply or bid for an award exceeding $100,000 must file the required certification. Each tier certifies to the tier above that it will not and has not used Federal appropriated funds to pay any person or organization for influencing or attempting to influence an officer or employee of any agency, a member of Congress, officer or employee of Congress, or an employee of a member of Congress in connection with obtaining any Federal contract, grant or any other award covered by 31 U.S.C. 1352. Each tier must also disclose any lobbying with non-Federal funds that takes place in connection with obtaining any Federal award. Such disclosures are forwarded from tier to tier up to the recipient who in turn will forward the certification(s) to the awarding agency.
(j) Appendix II to Part 200 (J) – §200.323 Procurement of Recovered Materials:
(i) Vendor shall comply with section 6002 of the Solid Waste Disposal Act, as amended by the Resource Conservation and Recovery Act. The requirements of Section 6002 38077.00180\34438574.1
-7 SLFRF FEDERAL CONTRACT PROVISIONS
include procuring only items designated in guidelines of the Environmental Protection Agency (EPA) at 40 C.F.R. part 247 that contain the highest percentage of recovered materials practicable, consistent with maintaining a satisfactory level of competition, where the purchase price of the item exceeds $10,000 or the value of the quantity acquired during the preceding fiscal year exceeded $10,000; procuring solid waste management services in a manner that maximizes energy and resource recovery; and establishing an affirmative procurement. (ii) In the performance of this contract, the Vendor shall make maximum use of products containing recovered materials that are EPA-designated items unless the product cannot be acquired: Competitively within a timeframe providing for compliance with the contract performance schedule; Meeting contract performance requirements; or At a reasonable price. (iii) Information about this requirement, along with the list of EPA-designate items, is available at EPA’s Comprehensive Procurement Guidelines web site, https://www.epa.gov/smm/comprehensive-procurement-guideline-cpg-program. (iv) The Vendor also agrees to comply with all other applicable requirements of Section 6002 of the Solid Waste Disposal Act.”
(k) Appendix II to Part 200 (K) – §200.216 Prohibition on Certain Telecommunications and Video Surveillance Services or Equipment:
(i) Vendor shall not contract (or extend or renew a contract) to procure or obtain equipment, services, or systems that uses covered telecommunications equipment or services as a substantial or essential component of any system, or as critical technology as part of any system funded under this Contract. As described in Public Law 115–232, section 889, covered telecommunications equipment is telecommunications equipment produced by Huawei Technologies Company or ZTE Corporation (or any subsidiary or affiliate of such entities). (1) For the purpose of public safety, security of government facilities, physical security surveillance of critical infrastructure, and other national security purposes, video surveillance and telecommunications equipment produced by Hytera Communications Corporation, Hangzhou Hikvision Digital Technology Company, or Dahua Technology Company (or any subsidiary or affiliate of such entities).
(2) Telecommunications or video surveillance services provided by such entities or using such equipment.
(3) Telecommunications or video surveillance equipment or services produced or provided by an entity that the Secretary of Defense, in consultation with the Director of the National Intelligence or the Director of the Federal Bureau of Investigation, reasonably believes to be an entity owned or controlled by, or otherwise connected to, the government of a covered foreign country.
(ii) See Public Law 115-232, section 889 for additional information. (l) Appendix II to Part 200 (L) – §200.322 Domestic Preferences for Procurement:
(i) Vendor shall, to the greatest extent practicable, purchase, acquire, or use goods, products, or materials produced in the United States (including but not limited to iron, 38077.00180\34438574.1
-8 SLFRF FEDERAL CONTRACT PROVISIONS
aluminum, steel, cement, and other manufactured products). The requirements of this section must be included in all subcontracts
(ii) For purposes of this section:
(1) “Produced in the United States’’ means, for iron and steel products, that all manufacturing processes, from the initial melting stage through the application of coatings, occurred in the United States.
(2) ‘‘Manufactured products’’ means items and construction materials composed in whole or in part of nonferrous metals such as aluminum; plastics and polymer-based products such as polyvinyl chloride pipe; aggregates such as concrete; glass, including optical fiber; and lumber.

2. CONTRACTING WITH SMALL AND MINORITY FIRMS, WOMEN’S BUSINESS ENTERPRISE AND LABOR SURPLUS AREA FIRMS (2 C.F.R. § 200.321) (a) Vendor shall be subject to 2 C.F.R. § 200.321 and will take affirmative steps to assure that minority firms, women’s business enterprises, and labor surplus area firms are used when possible and will not be discriminated against on the grounds of race, color, religious creed, sex, or national origin in consideration for an award.
(b) Affirmative steps shall include:
(i) Placing qualified small and minority businesses and women's business enterprises on solicitation lists;
(ii) Assuring that small and minority businesses, and women's business enterprises are solicited whenever they are potential sources; (iii) Dividing total requirements, when economically feasible, into smaller tasks or quantities to permit maximum participation by small and minority business, and women's business enterprises;
(iv) Establishing delivery schedules, where the requirement permits, which encourage participation by small and minority business, and women's business enterprises; and (v) Using the services/assistance of the Small Business Administration (SBA), and the Minority Business Development Agency (MBDA) of the Department of Commerce.

Vendor shall submit evidence of compliance with the foregoing affirmative steps when requested by the Agency.
2-1421
2-1421
2-1421
2-1421
2-1421
2-1421
2-1421
2-1421
2-1421
2-1421
2-1421
2-1421
2-1421
2-1421
2-1422
2-1422
2-1422
2-1422
2-1422
2-1422
2-1422
2-1421
2-1421
2-1421
2-1422
2-1422
2-1422
2-1422
2-1422
2-1422

38077.00180\29080232.10 C2

CITY OF MILPITAS

MILPITAS, CALIFORNIA

CONTRACT DOCUMENTS AND SPECIFICATIONS FOR

REHABILITATION OF ELEVEN CITY
PARKS
IFB NO. 23-035
38077.00180\29080232.10 C2
-i- 00 11 16 – NOTICE INVITING BIDS

TABLE OF CONTENTS
Page
00 11 16 – NOTICE INVITING BIDS ......................................................................................... 1 00 21 13 – INSTRUCTIONS TO BIDDERS ............................................................................... 3 00 41 43 – BID FORMS ...........................................................................................................12 00 52 13 – CONTRACT ...........................................................................................................35 00 61 13 – BOND FORMS .......................................................................................................40 00 72 13 – GENERAL CONDITIONS .......................................................................................52 00 73 13 – SPECIAL CONDITIONS ....................................................................................... 109 01 00 00 – GENERAL REQUIREMENTS ............................................................................... 112 EXHIBIT “A” CHANGE ORDER FORM .................................................................................. A-1 EXHIBIT "B" PROJECT SPECIFICATIONS………………………………………………………..B-1 EXHIBIT "C" TECHNICAL SPECIFICATIONS BY PARK………………………………………...C-1 EXHIBIT “D” SLFRF CONTRACT PROVISIONS………………………………………………….D-1 EXHIBIT “E” PARK DRAWINGS…………………………………………….................................E-1 38077.00180\29080232.10 C2
-1- 00 11 16 – NOTICE INVITING BIDS
00 11 16 – NOTICE INVITING BIDS
NOTICE IS HEREBY GIVEN that the City Council of the City of Milpitas (“City”) invites and will receive electronic Bids up to but not later than 2:00 p.m. on Thursday, November 10, 2022 via ProcureNow.com, the City’s eProcurement website, for the furnishing to City of all labor, equipment, materials, tools, services, transportation, permits, utilities, and all other items necessary for Rehabilitation of Eleven City Parks (the “Project”). At said time, Bids will be electronically opened and read aloud at the City Office. Bids received after said time shall not be accepted. Bids shall be valid for a period of 90 calendar days after the Bid opening date.

Bids must be submitted on the City’s Bid Forms. Bidders may obtain a copy of the Contract Documents from ProcureNow.com and no other method of obtaining documents may be accepted. To the extent required by section 20103.7 of the Public Contract Code, upon request from a contractor plan room service, the City shall provide an electronic copy of the Contract Documents at no charge to the contractor plan room.

It is the responsibility of each prospective bidder to download and print all Bid Documents for review and to verify the completeness of Bid Documents before submitting a bid. Any Addenda will be posted ProcureNow.com. It is the responsibility of each prospective bidder to check ProcureNow.com on a daily basis through the close of bids for any applicable addenda or updates. The City does not assume any liability or responsibility based on any defective or incomplete copying, excerpting, scanning, faxing, downloading or printing of the Bid Documents.

Information on ProcureNow.com may change without notice to prospective bidders. The Contract Documents shall supersede any information posted or transmitted by ProcureNow.com.

Each Bid shall be accompanied by cash, a certified or cashier’s check, or Bid Bond secured from a surety company satisfactory to the City Council, the amount of which shall not be less than ten percent (10%) of the submitted Total Bid Price, made payable to City of Milpitas as bid security. The bid security shall be provided as a guarantee that within five (5) working days after the City provides the successful bidder the Notice of Award, the successful Bidder will enter into a contract and provide the necessary bonds and certificates of insurance. The bid security will be declared forfeited if the successful Bidder fails to comply within said time. No interest will be paid on funds deposited with City.

A non-mandatory Pre-Bid Conference is scheduled for 18 October 2022 at 10:30 a.m. PDT to review the Project's existing conditions via Zoom teleconference call. Representatives of the City and consulting engineers, if any, will be present. Bidders need only to attend one Pre-Bid Conference. Questions asked by Bidders at the Pre-Bid Conference not specifically addressed within the Contract Documents shall be answered in writing, and issued as an Addendum.

The successful Bidder will be required to furnish a Faithful Performance Bond and a Labor and Material Payment Bond each in an amount equal to one hundred percent (100%) of the Contract Price. Each bond shall be in the forms set forth herein, shall be secured from a surety company that meets all State of California bonding requirements, as defined in California Code of Civil Procedure Section 995.120, and that is a California admitted surety insurer.

Pursuant to Section 22300 of the Public Contract Code of the State of California, the successful Bidder may substitute certain securities for funds withheld by City to ensure its performance under the contract.
38077.00180\29080232.10 C2
-2- 00 11 16 – NOTICE INVITING BIDS
Pursuant to Labor Code Section 1773, City has obtained the prevailing rate of per diem wages and the prevailing wage rate for holiday and overtime work applicable in Santa Clara County from the Director of the Department of Industrial Relations for each craft, classification, or type of worker needed to execute this contract. A copy of these prevailing wage rates may be obtained via the internet at: www.dir.ca.gov/dlsr/
In addition, a copy of the prevailing rate of per diem wages is available at the City’s Department of Public Works and shall be made available to interested parties upon request. The successful bidder shall post a copy of the prevailing wage rates at each job site. It shall be mandatory upon the Bidder to whom the Contract is awarded, and upon any subcontractors, to comply with all Labor Code provisions, which include but are not limited to the payment of not less than the said specified prevailing wage rates to all workers employed by them in the execution of the Contract, employment of apprentices, hours of labor and debarment of contractors and subcontractors.

Pursuant to Labor Code sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. No Bid will be accepted nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. If awarded a contract, the Bidder and its subcontractors, of any tier, shall maintain active registration with the Department of Industrial Relations for the duration of the Project. Notwithstanding the foregoing, the contractor registration requirements mandated by Labor Code Sections 1725.5 and 1771.1 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Sections 1725.5 and 1771.1.

This Project is subject to compliance monitoring and enforcement by the Department of Industrial Relations. In bidding on this Project, it shall be the Bidder’s sole responsibility to evaluate and include the cost of complying with all labor compliance requirements under this contract and applicable law in its Bid.

Unless otherwise provided in the Instructions for Bidders, each Bidder shall be a licensed contractor pursuant to sections 7000 et seq. of the Business and Professions Code in the following classification(s) throughout the time it submits its Bid and for the duration of the contract: General A or General B.

Substitution requests shall be made within 35 calendar days after the award of the contract.

Pursuant to Public Contract Code Section 3400(b), the City may make findings designating that certain additional materials, methods or services by specific brand or trade name other than those listed in the Standard Specifications be used for the Project. Such findings, if any, as well as the materials, methods or services and their specific brand or trade names that must be used for the Project may be found in the Special Conditions.

City shall award the contract for the Project to the lowest responsive, responsible Bidder as determined by the City from the BASE BID ALONE. City reserves the right to reject any or all bids or to waive any irregularities or informalities in any bids or in the bidding process.

For further information, contact Zachary DeVine, Senior Buyer at [email protected] or (408) 586-3163.

END OF NOTICE INVITING BIDS
38077.00180\29080232.10 C2
-3- 00 21 13 – INSTRUCTIONS TO BIDDERS
00 21 13 – INSTRUCTIONS TO BIDDERS

1. SECURING DOCUMENTS
Bids must be submitted to the City on the Bid Forms which are a part of the Bid Package for the Project. Bid and Contract Documents may be obtained from the City as specified in the Notice Inviting Bids. Prospective bidders are encouraged to telephone in advance to determine the availability of Contract Documents. Any charge for the Contract Documents is stated in the Notice Inviting Bids.

The City may also make the Contract Documents available for review at one or more plan rooms, as indicated in the Notice Inviting Bids.

Addenda, if any, issued during the bid period will be posted on www.ProcureNow.com. Failure to acknowledge addenda may make a bid nonresponsive and not eligible for award of the contract.

2. EXAMINATION OF SITE AND CONTRACT DOCUMENTS
At its own expense and prior to submitting its Bid, each Bidder shall visit the site of the proposed work and fully acquaint itself with the conditions relating to the construction and labor required so that the Bidder may fully understand the work, including but not limited to difficulties and restrictions attending the execution of the work under the contract. Each Bidder shall carefully examine the Drawings, and shall read the Specifications, Contract, and all other documents referenced herein. Each Bidder shall also determine the local conditions which may in any way affect the performance of the work, including local tax structure, contractors’ licensing requirements, availability of required insurance, the prevailing wages and other relevant cost factors, shall familiarize itself with all federal, state and local laws, ordinances, rules, regulations and codes affecting the performance of the work, including the cost of permits and licenses required for the work, and shall make such surveys and investigations, including investigations of subsurface or latent physical conditions at the site or where work is to be performed as may be required. Bidders are responsible for consulting the standards referenced in the Contract.

The failure or omission of any Bidder to receive or examine any contract documents, forms, instruments, addenda, or other documents, or to visit the site and acquaint itself with conditions there existing shall in no way relieve any Bidder from any obligation with respect to its Bid or to the contract and no relief for error or omission will be given except as required under State law.

The submission of a Bid shall be taken as conclusive evidence of compliance with this Article.

Storm, surface, nuisance, or other waters may be encountered at various times during construction of the Project. Federal and State laws require the City and its contractors to appropriately manage such waters pursuant to the requirements of California State Water Resources Control Board Order Number 2009-0009-DWQ and any amendment or renewal thereof, the Federal Clean Water Act, and the California Porter Cologne Water Quality Control Act. By submitting a Bid, each Bidder acknowledges that it has investigated the risk arising from such waters, has prepared its Bid accordingly, and assumes any and all risks and liabilities arising therefrom.

3. INTERPRETATION OF DRAWINGS AND DOCUMENTS
Prospective Bidders unclear as to the true meaning of any part of the Drawings, Specifications or other proposed contract documents may submit to the Engineer of the City a written request 38077.00180\29080232.10 C2
-4- 00 21 13 – INSTRUCTIONS TO BIDDERS
for interpretation. The prospective Bidder submitting the request is responsible for prompt delivery. Interpretation of the Drawings, Specifications or other proposed contract documents will be made only by a written addendum duly issued and a copy of such addenda will be mailed or delivered to each prospective Bidder who has purchased a set of Drawings and Specifications. The City will not be responsible for any other explanation or interpretations of the proposed documents. If a Prospective Bidders becomes aware of any errors or omissions in any part of the Contract Documents, it is the obligation of the Prospective Bidder to promptly bring it to the attention of the City.

4. INSPECTION OF SITE; PRE-BID CONFERENCE
Each prospective bidder is responsible for fully acquainting itself with the conditions of the Project Site (which may include more than one site), as well as those relating to the construction and labor of the Project, to fully understand the facilities, difficulties and restrictions which may impact the cost or effort required to complete the Project. To this end, a Pre-Bid Meeting and Site Walk will be held on the date(s) and time(s) indicated in the Notice Inviting Bids.

5. ADDENDA
The City reserves the right to revise the Contract Documents prior to the Bid opening date.

Revisions, if any, shall be made by written Addenda. All Addenda issued by the City shall be included in the Bid and made part of the Contract Documents. Pursuant to Public Contract Code Section 4104.5, if the City issues an Addendum which includes material changes to the Project less than 72 hours prior to the deadline for submission of Bids, the City will extend the deadline for submission of Bids. The City may determine, in its sole discretion, whether an Addendum warrants postponement of the Bid submission date. Any Addenda will be posted on www.ProcureNow.com. Please Note: Bidders are responsible for ensuring that they have received any and all Addenda. To this end, each Bidder should contact Zachary DeVine, Senior Buyer at City of Milpitas City Hall, 455 E. Calaveras Bouelvard, Milpitas, CA 95035 or (408) 586- 3163 or [email protected] to verify that it has received all Addenda issued, if any, prior to the Bid opening. The Bidder shall indicate the Addenda received prior to bidding in the space provided in the Bid Form. Failure to indicate all Addenda may be sufficient cause for rejecting the Bid.

6. ALTERNATE BIDS
If alternate bid items are called for in the Contract Documents, the time required for completion of the alternate bid items has already been factored into the Contract duration and no additional Contract time will be awarded for any of the alternate bid items. The City may elect to include one or more of the alternate bid items, or to otherwise remove certain work from the Project scope of work. Accordingly, each bidder must ensure that each bid item contains a proportionate share of profit, overhead, and other costs or expenses which will be incurred by the bidder.

7. COMPLETION OF BID FORMS
Bids shall only be prepared using copies of the Bid Forms which are included in the Contract Documents. The use of substitute Bid Forms other than clear and correct photocopies of those provided by the City will not be permitted. Bids shall be executed by an authorized signatory as described in these Instructions to Bidders. In addition, Bidders shall fill in all blank spaces (including inserting “N/A” where applicable), and initial all interlineations, alterations, or erasures 38077.00180\29080232.10 C2
-5- 00 21 13 – INSTRUCTIONS TO BIDDERS
to the Bid Forms. Bidders shall neither delete, modify, nor supplement the printed matter on the Bid Forms nor make substitutions thereon. USE OF BLACK OR BLUE INK, INDELIBLE PENCIL, OR A TYPEWRITER IS REQUIRED. Deviations in the Bid Forms may result in the Bid being deemed non-responsive.

8. MODIFICATIONS OF BIDS
Each Bidder shall submit its Bid in strict conformity with the requirements of the Contract Documents. Unauthorized additions, modifications, revisions, conditions, limitations, exclusions or provisions attached to a Bid may render it non-responsive and may cause its rejection.

Bidders shall not delete, modify, or supplement the printed matter on the Bid Forms, or make substitutions thereon. Oral, telephonic and electronic modifications will not be considered.

9. SUBCONTRACTORS
Bidder shall set forth the name, address of the place of business, and contractor license number of each subcontractor who will perform work, labor, furnish materials or render services to the bidder on said contract and each subcontractor licensed by the State of California who, under subcontract to bidder, specially fabricates and installs a portion of the Work described in the Drawings and Specifications in an amount in excess of one half of one percent (0.5%) of the total bid price, and shall indicate the portion of the work to be done by such subcontractor in accordance with Public Contract Code Section 4104.

The successful bidder will be required to self-perform at least 60% of the work.

10. LICENSING REQUIREMENTS
Pursuant to Business and Professions Code Section 7028.15 and Public Contract Code Section 3300, all bidders must possess proper licenses for performance of this Contract.

Subcontractors must possess the appropriate licenses for each specialty subcontracted.

Pursuant to Business and Professions Code Section 7028.5, the City shall consider any bid submitted by a contractor not currently licensed in accordance with state law and pursuant to the requirements found in the Contract Documents to be nonresponsive, and the City shall reject the Bid. The City shall have the right to request, and Bidders shall provide within ten (10) calendar days, evidence satisfactory to the City of all valid license(s) currently held by that Bidder and each of the Bidder’s subcontractors, before awarding the Contract.

Notwithstanding anything contained herein, if the Work involves federal funds, the Contractor shall be properly licensed by the time the Contract is awarded, pursuant to the provisions of Public Contract Code section 20103.5.

11. BID GUARANTEE (BOND)
Each bid shall be accompanied by: (a) cash; (b) a certified or cashier’s check made payable to City of Milpitas; or (c) a Bid Bond secured from a surety company satisfactory to the City Council, the amount of which shall not be less than ten percent (10%) of the Total Bid Price, made payable to City of Milpitas as bid security. Personal sureties and unregistered surety companies are unacceptable. The surety insurer shall be California admitted surety insurer, as defined in Code of Civil Procedure Section 995.120. The bid security shall be provided as a guarantee that within ten (10) working days after the City provides the successful bidder the Notice of Award, the successful bidder will enter into a contract and provide the necessary 38077.00180\29080232.10 C2
-6- 00 21 13 – INSTRUCTIONS TO BIDDERS
bonds and certificates of insurance. The bid security will be declared forfeited if the successful bidder fails to comply within said time, and City may enter into a contract with the next lowest responsive responsible bidder, or may call for new bids. No interest shall be paid on funds deposited with the City. City will return the security accompanying the bids of all unsuccessful bidders no later than 60 calendar days after award of the contract.

12. IRAN CONTRACTING ACT OF 2010
In accordance with Public Contract Code Section 2200 et seq., the City requires that any person that submits a bid or proposal or otherwise proposes to enter into or renew a contract with the City with respect to goods or services of one million dollars ($1,000,000) or more, certify at the time the bid is submitted or the contract is renewed, that the person is not identified on a list created pursuant to subdivision (b) of Public Contract Code Section 2203 as a person engaging in investment activities in Iran described in subdivision (a) of Public Contract Code Section 2202.5, or as a person described in subdivision (b) of Public Contract Code Section 2202.5, as applicable.

The form of such Iran Contracting Certificate is included with the bid package and must be signed and dated under penalty of perjury.

13. NONCOLLUSION DECLARATION
Bidders on all public works contracts are required to submit a declaration of noncollusion with their bid. This form is included with the bid package and must be signed and dated under penalty of perjury.

14. PUBLIC WORKS CONTRACTOR REGISTRATION CERTIFICATION
Pursuant to Labor Code sections 1725.5 and 1771.1, all contractors and subcontractors that wish to bid on, be listed in a bid proposal, or enter into a contract to perform public work must be registered with the Department of Industrial Relations. No bid will be accepted nor any contract entered into without proof of the contractor’s and subcontractors’ current registration with the Department of Industrial Relations to perform public work. If awarded a contract, the bidder and its subcontractors, of any tier, shall maintain active registration with the Department of Industrial Relations for the duration of the Project. To this end, Bidder shall sign and submit with its Bid the Public Works Contractor Registration Certification on the form provided, attesting to the facts contained therein. Failure to submit this form may render the bid non-responsive. In addition, each Bidder shall provide the registration number for each listed subcontractor in the space provided in the Designation of Subcontractors form.

15. WAGE THEFT CERTIFICATION
Bidders on public works contracts are required to submit a certification disclosing whether the Bidder or any of its proposed subcontractors has been found by a final court order or administrative action of an investigatory government agency to have violated federal, state or local wage and hour laws, including but not limited to the federal Fair Labor Standards Act, the California Labor Code and the Milpitas Minimum Wage Ordinance, within the past five (5) years from the bid submission deadline.
38077.00180\29080232.10 C2
-7- 00 21 13 – INSTRUCTIONS TO BIDDERS

16. BIDDER INFORMATION AND EXPERIENCE FORM
Each Bidder shall complete the questionnaire provided herein and shall submit the questionnaire along with its Bid. Failure to provide all information requested within the questionnaire along with the Bid may cause the bid to be rejected as non-responsive. The City reserves the right to reject any Bid if an investigation of the information submitted does not satisfy the Engineer that the Bidder is qualified to properly carry out the terms of the contract.

17. WORKERS' COMPENSATION CERTIFICATION
In accordance with the provisions of Labor Code Section 3700, Contractor shall secure the payment of compensation to its employees. Contractor shall sign and file with the City the following certificate prior to performing the work under this Contract:

I am aware of the provisions of Section 3700 of the Labor Code, which require every employer to be insured against liability for workers’ compensation or to undertake self-insurance in accordance with the provisions of that code, and I will comply with such provisions before commencing the performance of the work of this contract.

The form of such Workers' Compensation Certificate is included as part of this document.

18. SIGNING OF BIDS
All Bids submitted shall be executed by the Bidder or its authorized representative. Bidders may be asked to provide evidence in the form of an authenticated resolution of its Board of Directors or a Power of Attorney evidencing the capacity of the person signing the Bid to bind the Bidder to each Bid and to any Contract arising therefrom.

If a Bidder is a joint venture or partnership, it may be asked to submit an authenticated Power of Attorney executed by each joint venturer or partner appointing and designating one of the joint venturers or partners as a management sponsor to execute the Bid on behalf of Bidder. Only that joint venturer or partner shall execute the Bid. The Power of Attorney shall also: (1) authorize that particular joint venturer or partner to act for and bind Bidder in all matters relating to the Bid; and (2) provide that each venturer or partner shall be jointly and severally liable for any and all of the duties and obligations of Bidder assumed under the Bid and under any Contract arising therefrom. The Bid shall be executed by the designated joint venturer or partner on behalf of the joint venture or partnership in its legal name.

19. SUBMISSION OF SEALED BIDS
Once the Bid and supporting documents have been completed and signed as set forth herein, they shall be electronically uploaded, along with the Bid Guarantee and other required materials, to ProcureNow.com before the time and day set for the receipt of bids. No oral, paper, or telephonic bids will be considered. No forms transmitted via e-mail, facsimile, or any other non-approved electronic means will be considered unless specifically authorized by the City as provided herein. Bids received after the time and day set for the receipt of bids shall be returned to the bidder unopened.

Only where expressly permitted in the Notice Inviting Bids may bidders submit their bids via electronic transmission pursuant to Public Contract Code sections 1600 and 1601. Any 38077.00180\29080232.10 C2
-8- 00 21 13 – INSTRUCTIONS TO BIDDERS
acceptable method(s) of electronic transmission shall be stated in the Notice Inviting Bids. City may reject any bid not strictly complying with City’s designated methods for delivery.

20. OPENING OF BIDS
At the time and place set for the opening and reading of bids, or any time thereafter, each and every bid received prior to the time and day set for the receipt of bids will be publicly opened and read. The City will leave unopened any Bid received after the specified date and time, and any such unopened Bid will be returned to the bidder. It is the bidder’s sole responsibility to ensure that its Bid is received as specified. Bids may be submitted earlier than the date(s) and time(s) indicated.

The public reading of each bid will include the following information:

A. The name and business location of the bidder.

B. The nature and amount of the bid security furnished by bidder.

C. The bid amount.

Bidders or their representatives and other interested persons may be present at the opening of the bids. The City may, in its sole discretion, elect to postpone the opening of the submitted Bids. The City reserves the right to reject any or all Bids and to waive any informality or irregularity in any Bid.

21. WITHDRAWAL OF BID
Any bid may be withdrawn either personally or by written request, incurring no penalty, at any time prior to the scheduled closing time for receipt of bids. Requests to withdraw bids shall be worded so as not to reveal the amount of the original bid. Withdrawn bids may be resubmitted until the time and day set for the receipt of bids, provided that resubmitted bids are in conformance with the instructions herein.

Bids may be withdrawn after bid opening only by providing written notice to City within five (5) working days of the bid opening and in compliance with Public Contract Code Section 5100 et seq., or as otherwise may be allowed with the consent of the City.

22. BIDDERS INTERESTED IN MORE THAN ONE BID
No Bidder shall be allowed to make, file or be interested in more than one bid for the same work unless alternate bids are specifically called for. A person, firm or corporation that has submitted a sub-proposal to a Bidder, or that has quoted prices of materials to a Bidder, is not thereby disqualified from submitting a sub-proposal or quoting prices to other bidders. No person, firm, corporation, or other entity may submit a sub-proposal to a Bidder, or quote prices of materials to a Bidder, when also submitting a prime Bid on the same Project.

23. SUBSTITUTION OF SECURITY
The Contract Documents call for monthly progress payments based upon the percentage of the Work completed. The City will retain a percentage of each progress payment as provided by the Contract Documents. At the request and expense of the successful Bidder, the City will 38077.00180\29080232.10 C2
-9- 00 21 13 – INSTRUCTIONS TO BIDDERS
substitute securities for the amount so retained in accordance with Public Contract Code Section 22300.

24. PREVAILING WAGES
The City has obtained from the Director of the Department of Industrial Relations the general prevailing rate of per diem wages in the locality in which this work is to be performed for each craft or type of worker needed to execute the Contract. These rates are available at the City or may be obtained online at http://www.dir.ca.gov. Bidders are advised that a copy of these rates must be posted by the successful Bidder at the job site(s).

25. DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS
In accordance with the provisions of the Labor Code, contractors or subcontractors may not perform work on a public works project with a subcontractor who is ineligible to perform work on a public project pursuant to Labor Code Sections 1777.1 or 1777.7. Any contract on a public works project entered into between a contractor and a debarred subcontractor is void as a matter of law. A debarred subcontractor may not receive any public money for performing work as a subcontractor on a public works contract. Any public money that is paid to a debarred subcontractor by the Contractor for the Project shall be returned to the City. The Contractor shall be responsible for the payment of wages to workers of a debarred subcontractor who has been allowed to work on the Project.

26. INSURANCE REQUIREMENTS
Prior to commencing work, the successful bidder shall purchase and maintain insurance as set forth in the General Conditions.

27. PERFORMANCE BOND AND PAYMENT BOND REQUIREMENTS
The successful bidder will be required to furnish a Labor and Material Payment Bond and a Faithful Performance Bond each in an amount equal to one hundred percent (100%) of the contract price. Each bond shall be secured from a surety company that meets all State of California bonding requirements, as defined in California Code of Civil Procedure Section 995.120 and is admitted by the State of California. Each bond shall be accompanied, upon the request of City, with all documents required by California Code of Civil Procedure Section 995.660 to the extent required by law. All bonding and insurance requirements shall be completed and submitted to City within ten (10) working days from the date the City provides the successful bidder with the Notice of Award.

28. SALES AND OTHER APPLICABLE TAXES, PERMITS, LICENSES AND FEES Contractor and its subcontractors performing work under this Contract will be required to pay California sales tax and other applicable taxes, and to pay for permits, licenses and fees required by the agencies with authority in the jurisdiction in which the Work will be located, unless otherwise expressly provided by the Contract Documents.

29. FILING OF BID PROTESTS
Bidders may file a “protest” of a Bid with the City of Milpitas City Engineer. In order for a Bidder’s protest to be considered valid, the protest must:
38077.00180\29080232.10 C2
-10- 00 21 13 – INSTRUCTIONS TO BIDDERS
A. Be filed in writing within five (5) calendar days after the bid opening date; B. Clearly identify the specific irregularity or accusation; C. Specify in detail the grounds for protest and the facts supporting the protest; and D. Include all relevant, supporting documentation with the protest at time of filing.

If the protest does not comply with each of these requirements, the City may reject the protest without further review.

If the protest is timely and complies with the above requirements, the City Engineer, or other designated City staff member, shall review the protest, any response from the challenged Bidder(s), and all other relevant information. The City Engineer will provide a written decision to the protestor.

The procedure and time limits set forth in this Article are mandatory and are the sole and exclusive remedy in the event of a Bid protest. Failure to comply with these procedures shall constitute a failure to exhaust administrative remedies and a waiver of any right to further pursue the Bid protest, including filing a Government Code Claim or legal proceedings.

30. BASIS OF AWARD; BALANCED BID
The City shall award the Contract to the lowest responsible Bidder submitting a responsive Bid.

The lowest Bid will be determined on the basis of the Total Base Bid alone unless otherwise set forth in the Notice Inviting Bids.

The City may reject any Bid which, in its opinion when compared to other Bids received or to the City’s internal estimates, does not accurately reflect the cost to perform the Work. The City may reject as non-responsive any Bid which unevenly weights or allocates costs, including but not limited to overhead and profit to one or more particular bid items.

31. AWARD PROCESS
Once all Bids are opened and reviewed to determine the lowest responsive and responsible Bidder, the City Council may award the contract. The apparent successful Bidder should begin to prepare the following documents: (1) the Performance Bond; (2) the Payment Bond; and (3) the required insurance certificates and endorsements. Once the City notifies the Bidder of the award, the Bidder will have fourteen (14) calendar days from the date of this notification to execute the Contract and supply the City with all of the required documents and certifications.

Regardless of whether the Bidder supplies the required documents and certifications in a timely manner, the Contract time will begin to run twenty-one (21) calendar days from the date of the Notice of Award. Once the City receives all of the properly drafted and executed documents, certifications from the Bidder, and any other documents as maybe specified in the Contract Documents, the City shall issue a Notice to Proceed to that Bidder.

32. EXECUTION OF CONTRACT
As required herein the Bidder to whom an award is made shall execute the Contract in the amount determined by the Contract Documents. The City may require appropriate evidence that the persons executing the Contract are duly empowered to do so. The Contract and bond 38077.00180\29080232.10 C2
-11- 00 21 13 – INSTRUCTIONS TO BIDDERS
forms to be executed by the successful Bidder are included within these Specifications and shall not be detached.

38077.00180\29080232.10
-35- 00 52 13 – CONTRACT

00 52 13 – CONTRACT
This CONTRACT, No. 23-035 is made and entered into this _______________________, by and between City of Milpitas, sometimes hereinafter called “City,” and G&G Builders Inc. sometimes hereinafter called “Contractor.” WITNESSETH: That the parties hereto have mutually covenanted and agreed, and by these presents do covenant and agree with each other as follows:
a. SCOPE OF WORK. The Contractor shall perform all Work within the time stipulated in the Contract, and shall provide all labor, materials, equipment, tools, utility services, and transportation to complete all of the Work required in strict compliance with the Contract Documents as specified in Article 5, below, for the following Project:

REHABILITATION OF ELEVEN CITY PARKS
The Contractor and its surety shall be liable to the City for any damages arising as a result of the Contractor’s failure to comply with this obligation. b. TIME FOR COMPLETION. Time is of the essence in the performance of the Work. The Work shall be commenced on the date stated in the City’s Notice to Proceed. The Contractor shall complete all Work required by the Contract Documents WITHIN ONE HUNDRED EIGHTY (180) CALENDAR DAYS from the commencement date stated in the Notice to Proceed. By its signature hereunder, Contractor agrees the time for completion set forth above is adequate and reasonable to complete the Work.
c. CONTRACT PRICE. The City shall pay to the Contractor as full compensation for the performance of the Contract, subject to any additions or deductions as provided in the Contract Documents, and including all applicable taxes and costs, the sum of Eight Hundred Seventy-Two Thousand Fifty-Nine Dollars and Zero Cents ($872,059.00).

Payment shall be made as set forth in the General Conditions. d. LIQUIDATED DAMAGES.In accordance with Government Code section 53069.85, it is agreed that the Contractor will pay the City the sum set forth in Section 00 73 13, Article 1.11 for each and every calendar day of delay beyond the time prescribed in the Contract Documents for finishing the Work, as Liquidated Damages and not as a penalty or forfeiture. In the event this is not paid, the Contractor agrees the City may deduct that amount from any money due or that may become due the Contractor under the Contract. This Article does not exclude recovery of other damages specified in the Contract Documents.
e. COMPONENT PARTS OF THE CONTRACT. The “Contract Documents” include the following:

Notice Inviting Bids
Instructions to Bidders
Bid Form
Bid Bond
Designation of Subcontractors
Information Required of Bidders
38077.00180\29080232.10
-36- 00 52 13 – CONTRACT
Non-Collusion Declaration Form
Iran Contracting Act Certification
Public Works Contractor Registration Certification
Wage Theft Certification
Performance Bond
Payment (Labor and Materials) Bond
General Conditions
Special Conditions
Technical Specifications
Addenda
Plans and Drawings
Caltrans Standard Specifications, except Division 1
Caltrans Standard Plans
Applicable Local Agency Standards and Specifications, as last revised Approved and fully executed change orders
Any other documents contained in or incorporated into the Contract The Contractor shall complete the Work in strict accordance with all of the Contract Documents.

All of the Contract Documents are intended to be complementary. Work required by one of the Contract Documents and not by others shall be done as if required by all. This Contract shall supersede any prior agreement of the parties.
f. PROVISIONS REQUIRED BY LAW AND CONTRACTOR COMPLIANCE. Each and every provision of law required to be included in these Contract Documents shall be deemed to be included in these Contract Documents. The Contractor shall comply with all requirements of applicable federal, state and local laws, rules and regulations, including, but not limited to, the provisions of the California Labor Code and California Public Contract Code which are applicable to this Work.
g. INDEMNIFICATION. Contractor shall provide indemnification and defense as set forth in the General Conditions.
h. PREVAILING WAGES. Contractor shall be required to pay the prevailing rate of wages in accordance with the Labor Code which such rates shall be made available at the City’s Administrative Office or may be obtained online at http://www.dir.ca.gov and which must be posted at the job site.
i. WAGE THEFT PREVENTION.
(a) Contractor, and any subcontractor it employs to complete work under this Contract, shall comply with all applicable federal, state and local wage and hour laws.

Applicable laws may include, but are not limited to, the Federal Fair Labor Standards Act, the California Labor Code and the Milpitas Minimum Wage Ordinance. (b) BY SIGNING THIS CONTRACT, CONTRACTOR AFFIRMS THAT IT HAS

DISCLOSED ANY FINAL JUDGMENTS, DECISIONS OR ORDERS FROM A COURT OR INVESTIGATORY GOVERNMENT AGENCY, FINDING IN THE FIVE (5) YEARS PRIOR TO

EXECUTING THIS CONTRACT THAT CONTRACTOR OR ITS SUBCONTRACTORS HAS VIOLATED ANY APPLICABLE WAGE AND HOUR LAWS. CONTRACTOR FURTHER

AFFIRMS THAT IT OR ITS SUBCONTRACTOR(S) HAS EITHER FULLY SATISFIED EACH 38077.00180\29080232.10
-37- 00 52 13 – CONTRACT

JUDGMENT, DECISION OR ORDER, OR, IF ANY JUDGMENT, DECISION OR ORDER HAS

NOT BEEN FULLY SATISFIED, CONTRACTOR AFFIRMS THAT IT OR ITS

SUBCONTRACTOR(S) IS CURRENTLY SATISFYING SAID JUDGMENT, DECISION OR

ORDER THROUGH A PAYMENT OR ALTERNATIVE PLAN APPROVED BY THE

APPLICABLE COURT/GOVERNMENT AGENCY AND THAT CONTRACTOR OR ITS

SUBCONTRACTOR(S) ARE IN COMPLIANCE WITH SAID PLAN AS OF THE DATE OF EXECUTING THIS CONTRACT.
(c) If at any time during the term of this Contract, a court or investigatory government agency issues a final judgment, decision or order finding that Contractor or a subcontractor it employs to perform work under this Contract has violated any applicable wage and hour law, or Contractor learns of such a judgment, decision, or order that was not previously disclosed in its bid/proposal, Contractor shall inform the City no more than fifteen (15) calendar days after the judgment, decision or order becomes final or from the date of learning of the final judgment, decision or order. Contractor or its subcontractor(s) shall, within thirty (30) calendar days after notifying the City, either (i) fully satisfy any such judgment, decision, or order and provide the City with documentary evidence of satisfying said judgment, decision or order; or (ii) provide the City documentary evidence of a payment or other alternative plan approved by the court/government agency to satisfy the judgment, decision or order. If the Contractor or its subcontractor is subject to a payment or other alternative plan, the Contractor or its subcontractor shall continue to submit documentary evidence every thirty (30) calendar days during the term of the Contract demonstrating continued compliance with the plan until the judgment, decision or order has been fully satisfied.
(d) For purposes of this Section, a "final judgment, decision, or order" refers to one for which all appeals have been exhausted or the time period to appeal has expired. Relevant investigatory government agencies include: the United States Department of Labor, the California Division of Labor Standards Enforcement, the City, or any other governmental entity or division tasked with the investigation and enforcement of wage and hour laws. (e) Failure to comply with any part of this Section constitutes a material breach of this Contract. Such breach may serve as a basis for immediate termination of this Contract and/or any other remedies available under this Contract and/or law. (f) Notice provided to the City shall be addressed to: Attention: Finance Director, 455 E. Calaveras Blvd. Milpitas, CA 95035. The Notice provisions of this Section are separate from any other notice provisions in this Contract and, accordingly, only notice provided to the above address satisfies the notice requirements in this Section. [REMAINDER OF PAGE LEFT INTENTIONALLY BLANK]

38077.00180\29080232.10
-38- 00 52 13 – CONTRACT
IN WITNESS WHEREOF, this Contract has been duly executed by the above-named parties, on the day and year above written.

CITY OF MILIPITAS [INSERT NAME OF CONTRACTOR]
By By:

Steven G. McHarris
City Manager Its:

Printed
Name:

(CONTRACTOR’S SIGNATURE MUST BE

NOTARIZED AND CORPORATE

SEAL AFFIXED, IF APPLICABLE)
APPROVED AS TO FORM:

By:

City Attorney

END OF CONTRACT
38077.00180\29080232.10
-39- 00 52 13 – CONTRACT
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.

STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WITNESS my hand and official seal.

Signature of Notary Public

OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.

CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT  Individual
 Corporate Officer
Title(s) Title or Type of Document
 Partner(s)  Limited
 General Number of Pages
 Attorney-In-Fact
 Trustee(s)
 Guardian/Conservator Date of Document
 Other:

Signer is representing:

Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
38077.00180\29080232.10
-40- 00 61 13 – BOND FORMS
00 61 13 – BOND FORMS

1.1 Performance Bond.

KNOW ALL PERSONS BY THESE PRESENTS:

THAT WHEREAS, the City of Milpitas, (hereinafter referred to as “City”) has awarded to _________________________, (hereinafter referred to as the “Contractor”) an agreement for ____________________________________, (hereinafter referred to as the “Project”).

WHEREAS, the work to be performed by the Contractor is more particularly set forth in the Contract Documents for the Project dated ________________, (hereinafter referred to as “Contract Documents”), the terms and conditions of which are expressly incorporated herein by reference; and
WHEREAS, the Contractor is required by said Contract Documents to perform the terms thereof and to furnish a bond for the faithful performance of said Contract Documents.

NOW, THEREFORE, we, ______________________, the undersigned Contractor and ________________________________________________ as Surety, a corporation organized and duly authorized to transact business under the laws of the State of California, are held and firmly bound unto the City in the sum of ___________________________ DOLLARS, ($____________), said sum being not less than one hundred percent (100%) of the total amount of the Contract, for which amount well and truly to be made, we bind ourselves, our heirs, executors and administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH, that, if the Contractor, his or its heirs, executors, administrators, successors or assigns, shall in all things stand to and abide by, and well and truly keep and perform the covenants, conditions and agreements in the Contract Documents and any alteration thereof made as therein provided, on its part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their intent and meaning; and shall faithfully fulfill all obligations including the one (1) year guarantee of all materials and workmanship; and shall indemnify and save harmless the City, its officials, officers, employees, and authorized volunteers, as stipulated in said Contract Documents, then this obligation shall become null and void; otherwise it shall be and remain in full force and effect.

As a part of the obligation secured hereby and in addition to the face amount specified therefore, there shall be included costs and reasonable expenses and fees including reasonable attorney’s fees, incurred by City in enforcing such obligation.

As a condition precedent to the satisfactory completion of the Contract Documents, unless otherwise provided for in the Contract Documents, the above obligation shall hold good for a period of one (1) year after the acceptance of the work by City, during which time if Contractor shall fail to make full, complete, and satisfactory repair and replacements and totally protect the City from loss or damage resulting from or caused by defective materials or faulty workmanship.

The obligations of Surety hereunder shall continue so long as any obligation of Contractor remains. Nothing herein shall limit the City’s rights or the Contractor or Surety’s obligations under the Contract, law or equity, including, but not limited to, California Code of Civil Procedure Section 337.15.
38077.00180\29080232.10
-41- 00 61 13 – BOND FORMS
Whenever Contractor shall be, and is declared by the City to be, in default under the Contract Documents, the Surety shall remedy the default pursuant to the Contract Documents, or shall promptly, at the City’s option:
i Take over and complete the Project in accordance with all terms and conditions in the Contract Documents; or
ii Obtain a bid or bids for completing the Project in accordance with all terms and conditions in the Contract Documents and upon determination by Surety of the lowest responsive and responsible bidder, arrange for a Contract between such bidder, the Surety and the City, and make available as work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the contract price, including other costs and damages for which Surety may be liable.

The term “balance of the contract price” as used in this paragraph shall mean the total amount payable to Contractor by the City under the Contract and any modification thereto, less any amount previously paid by the City to the Contractor and any other set offs pursuant to the Contract Documents. iii Permit the City to complete the Project in any manner consistent with California law and make available as work progresses sufficient funds to pay the cost of completion of the Project, less the balance of the contract price, including other costs and damages for which Surety may be liable. The term “balance of the contract price” as used in this paragraph shall mean the total amount payable to Contractor by the City under the Contract and any modification thereto, less any amount previously paid by the City to the Contractor and any other set offs pursuant to the Contract Documents.

Surety expressly agrees that the City may reject any contractor or subcontractor which may be proposed by Surety in fulfillment of its obligations in the event of default by the Contractor.

Surety shall not utilize Contractor in completing the Project nor shall Surety accept a bid from Contractor for completion of the Project if the City, when declaring the Contractor in default, notifies Surety of the City’s objection to Contractor’s further participation in the completion of the Project.

The Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project to be performed thereunder shall in any way affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration or addition to the terms of the Contract Documents or to the Project.
[REMAINDER OF PAGE LEFT INTENTIONALLY BLANK]

38077.00180\29080232.10
-42- 00 61 13 – BOND FORMS
IN WITNESS WHEREOF, we have hereunto set our hands and seals this _______ day of ______________, 20___.
(Corporate Seal)
Contractor/Principal

By

Title
(Corporate Seal)
Surety

By
Attorney-in-Fact

(Attach Attorney-in-Fact Certificate) Title
(The rate of premium on this bond is ____________ per thousand. The total amount of premium charges is $_______________________________.
(The above must be filled in by corporate attorney.)

THIS IS A REQUIRED FORM
Any claims under this bond may be addressed to:
(Name and Address of Surety)

(Name and Address of Agent or
Representative for service of
process in California, if different
from above)
(Telephone number of Surety
and Agent or Representative for
service of process in California)

38077.00180\29080232.10
-43- 00 61 13 – BOND FORMS
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.

STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WITNESS my hand and official seal.

Signature of Notary Public

OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.

CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT  Individual
 Corporate Officer
Title(s) Title or Type of Document
 Partner(s)  Limited
 General Number of Pages
 Attorney-In-Fact
 Trustee(s)
 Guardian/Conservator Date of Document
 Other:

Signer is representing:

Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for Contractor/Principal. 38077.00180\29080232.10
-44- 00 61 13 – BOND FORMS
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.

STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WITNESS my hand and official seal.

Signature of Notary Public

OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.

CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT  Individual
 Corporate Officer
Title(s) Title or Type of Document
 Partner(s)  Limited
 General Number of Pages
 Attorney-In-Fact
 Trustee(s)
 Guardian/Conservator Date of Document
 Other:

Signer is representing:

Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for the Attorney-in-Fact. The Power-of Attorney to local representatives of the bonding company must also be attached.

END OF PERFORMANCE BOND
38077.00180\29080232.10
-45- 00 61 13 – BOND FORMS

1.2 Payment Bond (Labor and Materials).

KNOW ALL MEN BY THESE PRESENTS That
WHEREAS, the City of Milpitas (hereinafter designated as the “City”), by action taken or a resolution passed _______________ , 20_____, has awarded to ________________________ hereinafter designated as the “Principal,” a contract for the work described as follows:
__________________________________ (the “Project”); and WHEREAS, said Principal is required to furnish a bond in connection with said contract; providing that if said Principal or any of its Subcontractors shall fail to pay for any materials, provisions, provender, equipment, or other supplies used in, upon, for or about the performance of the work contracted to be done, or for any work or labor done thereon of any kind, or for amounts due under the Unemployment Insurance Code or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees of said Principal and its Subcontractors with respect to such work or labor the Surety on this bond will pay for the same to the extent hereinafter set forth.

NOW THEREFORE, we, the Principal and __________________________ as Surety, are held and firmly bound unto the City in the penal sum of ______________ Dollars ($___________) lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH that if said Principal, his or its subcontractors, heirs, executors, administrators, successors or assigns, shall fail to pay any of the persons named in Civil Code Section 9100, fail to pay for any materials, provisions or other supplies, used in, upon, for or about the performance of the work contracted to be done, or for any work or labor thereon of any kind, or amounts due under the Unemployment Insurance Code with respect to work or labor performed under the contract, or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department or Franchise Tax Board from the wages of employees of the contractor and his subcontractors pursuant to Revenue and Taxation Code Section 18663, with respect to such work and labor the Surety or Sureties will pay for the same, in an amount not exceeding the sum herein above specified, and also, in case suit is brought upon this bond, all litigation expenses incurred by the City in such suit, including reasonable attorneys’ fees, court costs, expert witness fees and investigation expenses.

This bond shall inure to the benefit of any of the persons named in Civil Code Section 9100 so as to give a right of action to such persons or their assigns in any suit brought upon this bond.

It is further stipulated and agreed that the Surety on this bond shall not be exonerated or released from the obligation of this bond by any change, extension of time for performance, addition, alteration or modification in, to, or of any contract, plans, specifications, or agreement pertaining or relating to any scheme or work of improvement herein above described, or pertaining or relating to the furnishing of labor, materials, or equipment therefore, nor by any change or modification of any terms of payment or extension of the time for any payment pertaining or relating to any scheme or work of improvement herein above described, nor by any rescission or attempted rescission or attempted rescission of the contract, agreement or bond, nor by any conditions precedent or subsequent in the bond attempting to limit the right of recovery of claimants otherwise entitled to recover under any such contract or agreement or 38077.00180\29080232.10
-46- 00 61 13 – BOND FORMS
under the bond, nor by any fraud practiced by any person other than the claimant seeking to recover on the bond and that this bond be construed most strongly against the Surety and in favor of all persons for whose benefit such bond is given, and under no circumstances shall Surety be released from liability to those for whose benefit such bond has been given, by reason of any breach of contract between the owner or City and original contractor or on the part of any obligee named in such bond, but the sole conditions of recovery shall be that claimant is a person described in Civil Code Section 9100, and has not been paid the full amount of his claim and that Surety does hereby waive notice of any such change, extension of time, addition, alteration or modification herein mentioned, including but not limited to the provisions of sections 2819 and 2845 of the California Civil Code.

IN WITNESS WHEREOF, we have hereunto set our hands and seals this _______ day of ______________, 20__.
(Corporate Seal)
Contractor/Principal

By

Title
(Corporate Seal)
Surety

By
Attorney-in-Fact

(Attach Attorney-in-Fact Certificate) Title

38077.00180\29080232.10
-47- 00 61 13 – BOND FORMS
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.

STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WITNESS my hand and official seal.

Signature of Notary Public

OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.

CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT  Individual
 Corporate Officer
Title(s) Title or Type of Document
 Partner(s)  Limited
 General Number of Pages
 Attorney-In-Fact
 Trustee(s)
 Guardian/Conservator Date of Document
 Other:

Signer is representing:

Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for Contractor/Principal. 38077.00180\29080232.10
-48- 00 61 13 – BOND FORMS
Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.

STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally appeared , who proved to me on the basis of satisfactory evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/their authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WITNESS my hand and official seal.

Signature of Notary Public

OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.

CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT  Individual
 Corporate Officer
Title(s) Title or Type of Document
 Partner(s)  Limited
 General Number of Pages
 Attorney-In-Fact
 Trustee(s)
 Guardian/Conservator Date of Document
 Other:

Signer is representing:

Name Of Person(s) Or Entity(ies)
Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for the Attorney-in-Fact. The Power-of-Attorney to local representatives of the bonding company must also be attached.

END OF PAYMENT BOND
38077.00180\29080232.10

GENERAL CONDITIONS

TABLE OF CONTENTS
Page
-49- 00 72 13 – GENERAL CONDITIONS

TABLE OF CONTENTS
00 72 13 – GENERAL CONDITIONS .......................................................................................52 ARTICLE 1 DEFINED TERMS .............................................................................................52 ARTICLE 2 CONTRACT DOCUMENTS ..............................................................................56 ARTICLE 3 PRECONSTRUCTION AND CONSTRUCTION COMMUNICATION ................57 ARTICLE 4 CONTRACT DOCUMENTS: COPIES & MAINTENANCE ................................57 ARTICLE 5 EXAMINATION OF DRAWINGS, SPECIFICATIONS AND SITE OF WORK ..............................................................................................................57 ARTICLE 6 EXISTENCE OF UTILITIES AT THE WORK SITE ............................................58 ARTICLE 7 SOILS INVESTIGATIONS ................................................................................59 ARTICLE 8 ARTICLE 8. CONTRACTOR’S SUPERVISION ................................................59 ARTICLE 9 WORKERS .......................................................................................................60 ARTICLE 10 INDEPENDENT CONTRACTORS ....................................................................60 ARTICLE 11 SUBCONTRACTS ............................................................................................60 ARTICLE 12 VERIFICATION OF EMPLOYMENT ELIGIBILITY ............................................60 ARTICLE 13 REQUESTS FOR SUBSTITUTION ...................................................................61 ARTICLE 14 SHOP DRAWINGS ...........................................................................................62 ARTICLE 15 SUBMITTALS ...................................................................................................62 ARTICLE 16 MATERIALS .....................................................................................................63 ARTICLE 17 PERMITS AND LICENSES ...............................................................................64 ARTICLE 18 TRENCHES ......................................................................................................64 ARTICLE 19 DIVERSION OF RECYCLABLE WASTE MATERIALS .....................................65 ARTICLE 20 REMOVAL OF HAZARDOUS MATERIALS ......................................................65 ARTICLE 21 SANITARY FACILITIES ....................................................................................65 ARTICLE 22 AIR POLLUTION CONTROL ............................................................................66 ARTICLE 23 LAYOUT AND FIELD ENGINEERING ..............................................................66 ARTICLE 24 TESTS AND INSPECTIONS .............................................................................66 ARTICLE 25 PROTECTION OF WORK AND PROPERTY ....................................................67 ARTICLE 26 CONTRACTOR’S MEANS AND METHODS .....................................................67 ARTICLE 27 AUTHORIZED REPRESENTATIVES ...............................................................67 ARTICLE 28 HOURS OF WORK ...........................................................................................67 ARTICLE 29 PAYROLL RECORDS ......................................................................................68 ARTICLE 30 PREVAILING RATES OF WAGES ...................................................................70 38077.00180\29080232.10

GENERAL CONDITIONS

TABLE OF CONTENTS
(continued)
Page
-50- 00 72 13 - GENERAL CONDITIONS

TABLE OF CONTENTS
ARTICLE 31 PUBLIC WORKS CONTRACTOR REGISTRATION .........................................71 ARTICLE 32 EMPLOYMENT OF APPRENTICES .................................................................71 ARTICLE 33 NONDISCRIMINATION/EQUAL EMPLOYMENT OPPORTUNITY ...................71 ARTICLE 34 DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS .....................72 ARTICLE 35 LABOR/EMPLOYMENT SAFETY .....................................................................72 ARTICLE 36 INSURANCE .....................................................................................................73 ARTICLE 37 FORM AND PROOF OF CARRIAGE OF INSURANCE ....................................75 ARTICLE 38 TIME FOR COMPLETION AND LIQUIDATED DAMAGES ...............................76 ARTICLE 39 SCHEDULE OF VALUES, COST BREAKDOWN AND PERIODIC ESTIMATES .....................................................................................................77 ARTICLE 40 PROGRESS ESTIMATES AND PAYMENT ......................................................78 ARTICLE 41 SECURITIES FOR MONEY WITHHELD...........................................................79 ARTICLE 42 CHANGES AND EXTRA WORK. ......................................................................80 ARTICLE 43 FINAL ACCEPTANCE AND PAYMENT ............................................................93 ARTICLE 44 OCCUPANCY ...................................................................................................94 ARTICLE 45 INDEMNIFICATION ..........................................................................................94 ARTICLE 46 PROCEDURE FOR RESOLVING DISPUTES ..................................................95 ARTICLE 47 CITY’S RIGHT TO TERMINATE CONTRACT ..................................................95 ARTICLE 48 WARRANTY AND GUARANTEE OF WORK .................................................. 101 ARTICLE 49 DOCUMENT RETENTION & EXAMINATION ................................................. 104 ARTICLE 50 SEPARATE CONTRACTS .............................................................................. 104 ARTICLE 51 NOTICE AND SERVICE THEREOF ............................................................... 105 ARTICLE 52 NOTICE OF THIRD PARTY CLAIMS .............................................................. 105 ARTICLE 53 STATE LICENSE BOARD NOTICE ................................................................ 105 ARTICLE 54 INTEGRATION ............................................................................................... 105 ARTICLE 55 ASSIGNMENT OF CONTRACT ...................................................................... 106 ARTICLE 56 CHANGE IN NAME AND NATURE OF CONTRACTOR’S LEGAL ENTITY .... 106 ARTICLE 57 ASSIGNMENT OF ANTITRUST ACTIONS ..................................................... 106 ARTICLE 58 PROHIBITED INTERESTS ............................................................................. 106 ARTICLE 59 CONTROLLING LAW ..................................................................................... 106 ARTICLE 60 JURISDICTION; VENUE ................................................................................. 106 ARTICLE 61 LAWS AND REGULATIONS ........................................................................... 107 38077.00180\29080232.10

GENERAL CONDITIONS

TABLE OF CONTENTS
(continued)
Page
-51- 00 72 13 - GENERAL CONDITIONS

TABLE OF CONTENTS
ARTICLE 62 PATENTS ....................................................................................................... 107 ARTICLE 63 OWNERSHIP OF CONTRACT DOCUMENTS ............................................... 107 ARTICLE 64 NOTICE OF TAXABLE POSSESSORY INTEREST ....................................... 107 ARTICLE 65 SURVIVAL OF OBLIGATIONS ....................................................................... 107 ARTICLE 66 SLFRF CONTRACT PROVISIONS ……………………………………………….105

38077.00180\29080232.10
-52- 00 72 13 – GENERAL CONDITIONS
00 72 13 – GENERAL CONDITIONS
ARTICLE 1 DEFINED TERMS
Whenever used in the Contract Documents and printed with initial capital letters, the terms listed below will have the meanings indicated which are applicable to both the singular and plural thereof. In addition to terms specifically defined below, terms with initial capital letters in the Contract Documents include references to identified articles and paragraphs, and the titles of other documents or forms.

A. Act of God – An earthquake of magnitude of 3.5 or higher on the Richter scale or a tidal wave.

B. Addenda -- Written or graphic instruments issued prior to the submission of Bids which clarify, correct, or change the Contract Documents.

C. Additional Work -- New or unforeseen work will be classified as “Additional Work” when the City’s Representative determines that it is not covered by the Contract.

D. Applicable Laws -- The laws, statutes, ordinances, rules, codes, regulations, permits, and licenses of any kind, issued by local, state or federal governmental authorities or private authorities with jurisdiction (including utilities), to the extent they apply to the Work.

E. Bid -- The offer or proposal of a Bidder submitted on the prescribed form setting forth the prices and other terms for the Work to be performed.

F. Bidder -- The individual or entity who submits a Bid directly to the City.

G. Caltrans Standard Specifications - Standard Specifications of the State of California, Department of Transportation, Current Edition. Any reference therein to a State agency or officer shall be interpreted as if the corresponding City office or agent acting under this contract were so specified.

H. Caltrans Standard Plans - Standard plans of the State of California, Department of Transportation, Current Addition. All metric measurements or quantities in the Caltrans Standard Plans shall be disregarded, and equivalent United States measures used.

I. Change Order (“CO”) -- A document that authorizes an addition, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Times, issued on or after the Effective Date of the Contract, in accordance with the Contract Documents and in the form contained in the Contract Documents.

J. Change Order Request (“COR”) -- A request made by the Contractor for an adjustment in the Contract Price and/or Contract Times as the result of a Contractor-claimed change to the Work. This term may also be referred to as a Change Order Proposal (“COP”), or Request for Change (“RFC”).

K. City -- The City of Milpitas.
38077.00180\29080232.10
-53- 00 72 13 – GENERAL CONDITIONS
L. City Council, Council -- The City Council of the City.

M. City’s Representative -- The individual or entity as identified in the Special Conditions to act as the City’s Representative.

N. Claim -- A demand or assertion by the City or Contractor seeking an adjustment of Contract Price or Contract Times, or both, or other relief with respect to the terms of the Contract. A demand for money or services by a third party is not a Claim.

O. Contract -- The entire integrated written agreement between the City and Contractor concerning the Work. “Contract” may be used interchangeably with “Agreement” in the Contract Documents. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral, and includes all Contract Documents.

P. Contract Documents -- The documents listed in Section 00 52 13, Article 5.

Some documents provided by the City to the Bidders and Contractor, including but not limited to reports and drawings of subsurface and physical conditions are not Contract Documents.

Q. Contract Price -- Amount to be paid by the City to the Contractor as full compensation for the performance of the Contract and completion of the Work, subject to any additions or deductions as provided in the Contract Documents, and including all applicable taxes and costs.

R. Contract Times -- The number of days or the dates stated in the Contract Documents to: achieve defined Milestones, if any; and to complete the Work so that it is ready for final payment.

S. Contractor -- The individual or entity with which the City has contracted for performance of the Work.

T. Contractor’s Designated On-Site Representative -- The Contractor’s Designated On-Site Representative will be as identified in Section 00 72 13, Article 3 and shall not be changed without prior written consent of the City.

U. Daily Rate -- The Daily Rate stipulated in the Contract Documents as full compensation to the Contractor due to the City’s unreasonable delay to the Project that was not contemplated by the parties.

V. Day -- A calendar day of 24 hours measured from midnight to the next midnight.

W. Defective Work -- Work that is unsatisfactory, faulty, or deficient; or that does not conform to the Contract Documents; or that does not meet the requirements of any inspection, reference standard, test, or approval referenced in the Contract Documents.

X. Demobilization -- The complete dismantling and removal by the Contractor of all of the Contractor’s temporary facilities, equipment, and personnel at the Site. 38077.00180\29080232.10
-54- 00 72 13 – GENERAL CONDITIONS
Y. Drawings -- That part of the Contract Documents prepared by of the Engineer of Record which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Shop Drawings and other Contractor submittals are not Drawings as so defined.

Z. Effective Date of the Contract -- The date indicated in the Contract on which it becomes effective, but if no such date is indicated, it means the date on which the Contract is signed and delivered by the last of the two parties to sign and deliver.

AA. Engineer, whenever not qualified, shall mean the City Engineer or its designee, acting either directly or through properly authorized agents, such agents acting severally within the scope of the particular duties entrusted to them. On all questions concerning the acceptance of materials, machinery, the classifications of material, the execution of work, conflicting interest of the contractors performing related work and the determination of costs, the decision of the Engineer, duly authorized by the City Council, shall be binding and final upon both parties.

BB. Engineer of Record -- The individual, partnership, corporation, joint venture, or other legal entity named as such in Section 00 73 13, Article 1.1. or any succeeding entity designated by the City.

CC. Hazardous Waste -- The term “Hazardous Waste” shall have the meaning provided in Section 104 of the Solid Waste Disposal Act (42 U.S.C. § 6903) as amended from time to time or, as defined in Section 25117 of the Health and Safety Code, that is required to be removed to a class I, class II, or class III disposal site in accordance with provisions of existing law, whichever is more restrictive.

DD. Holiday – The Holidays are defined as legal Federal, State, and City holidays including:

New Year’s Day - January 1
Martin Luther King Jr.'s Birthday – Third Monday in January Lincoln's Birthday – Febraury 12
President’s Day – Third Monday in February
Memorial Day - Last Monday in May
Independence Day - July 4
Labor Day - First Monday in September
Veteran’s Day - November 11
Thanksgiving Day - Fourth Thursday in November
Friday after Thanksgiving
Christmas Eve – December 24
Christmas Day - December 25
If any Holiday listed above falls on a Saturday, Saturday and the preceding Friday are both Holidays. If the Holiday should fall on a Sunday, Sunday and the following Monday are both Holidays.
38077.00180\29080232.10
-55- 00 72 13 – GENERAL CONDITIONS
EE. Notice of Award -- The written notice by the City to the Successful Bidder stating that upon timely compliance by the Successful Bidder with the conditions precedent listed therein, the City will sign and deliver the Contract.

FF. Notice of Completion -- The form which may be executed by the City and recorded by the county where the Project is located constituting final acceptance of the Project.

GG. Notice to Proceed -- A written notice given by the City to Contractor fixing the date on which the Contractor may proceed with the Work and when Contract Times will commence to run.

HH. Project -- The total construction of which the Work to be performed under the Contract Documents may be the whole, or a part.

II. Recyclable Waste Materials -- Materials removed from the Site which are required to be diverted to a recycling center rather than an area landfill.

Recyclable Waste Materials include asphalt, concrete, brick, concrete block, and rock.

JJ. Schedule of Submittals -- A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to facilitate scheduled performance of related construction activities.

KK. Shop Drawings -- All drawings, diagrams, illustrations, schedules, and other data or information which are specifically prepared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work.

LL. Specifications -- That part of the Contract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain administrative requirements and procedural matters applicable thereto.

MM. Stop Payment Notice -- A written notice as defined in Civil Code section 8044.

NN. Subcontractor -- An individual or entity other than a Contractor having a contract with any other entity than the City for performance of any portion of the Work at the Site.

OO. Submittal -- Written and graphic information and physical samples prepared and supplied by the Contractor demonstrating various portions of the Work.

PP. Successful Bidder -- The Bidder submitting a responsive Bid to whom the City makes an award.

QQ. Supplier -- A manufacturer, fabricator, supplier, distributor, material man, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment used in the performance of the Work or to be incorporated in the Work.
38077.00180\29080232.10
-56- 00 72 13 – GENERAL CONDITIONS
RR. Underground Facilities -- All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including those that convey electricity, gases, steam, liquid petroleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems.

SS. Unit Price Work -- Work to be paid for on the basis of unit prices as provided by the Contractor in its bid or as adjusted in accordance with the Contract Documents.

TT. Warranty -- A written guarantee provided to the City by the Contractor that the Work will remain free of defects and suitable for its intended use for the period required by the Contract Documents or the longest period permitted by the law of this State, whichever is longer.

UU. Work -- The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction, and furnishing, installing, and incorporating all materials and equipment into such construction, all as required by the Contract Documents.

ARTICLE 2 CONTRACT DOCUMENTS
A. Contract Documents. The Contract Documents are complementary, and what is called for by one shall be as binding as if called for by all.

B. Interpretations. The Contract Documents are intended to be fully cooperative and complementary. If the Contractor observes that any documents are in conflict, the Contractor shall promptly notify the Engineer in writing. In case of conflicts between the Contract Documents, the order of precedence shall be as follows:

1. Change Orders

2. Contract

3. Addenda

4. Special Conditions

5. Technical Specifications

6. Plans (Contract Drawings)

7. General Conditions

8. Instructions to Bidders

9. Notice Inviting Bids

10. Contractor’s Bid Forms

11. City Standard Specifications

12. City Standard Drawings

13. Caltrans Standard Specifrications, except Division 1

14. Caltrans Standard Plans

15. Reference Documents
38077.00180\29080232.10
-57- 00 72 13 – GENERAL CONDITIONS
With reference to the Drawings, the order of precedence shall be as follows:

1. Figures govern over scaled dimensions

2. Detail drawings govern over general drawings

3. Addenda or Change Order drawings govern over Contract Drawings

4. Contract Drawings govern over Standard Drawings

5. Contract Drawings govern over Shop Drawings
C. Conflicts in Contract Documents. Notwithstanding the orders of precedence established above, in the event of conflicts, the higher standard, higher quality, and most expensive shall always apply.

D. Organization of Contract Documents.Organization of the Contract Documents into divisions, sections, and articles, and arrangement of drawings shall not control the Contractor in dividing Project Work among subcontractors or in establishing the extent of Work to be performed by any trade.

ARTICLE 3 PRECONSTRUCTION AND CONSTRUCTION COMMUNICATION Before any Work at the site is started, a conference attended by the City, Contractor, City’s Representative, and others as appropriate will be held to establish a working understanding among the parties as to the Work and to discuss the schedules referred to herein, procedures for handling Shop Drawings and other submittals, processing Applications for Payment, and maintaining required records.

At this conference the City and Contractor each shall designate, in writing, a specific individual to act as its authorized representative with respect to the services and responsibilities under the Contract. Such individuals shall have the authority to transmit instructions, receive information, render decisions relative to the Contract, and otherwise act on behalf of each respective party.

ARTICLE 4 CONTRACT DOCUMENTS: COPIES & MAINTENANCE
Contractor will be furnished, free of charge, five (5) copies of the Contract Documents.

Additional copies may be obtained at cost of reproduction.

Contractor shall maintain a clean, undamaged set of Contract Documents, including submittals, at the Project site.

ARTICLE 5 EXAMINATION OF DRAWINGS, SPECIFICATIONS AND SITE OF WORK
A. Examination of Contract Documents. Before commencing any portion of the Work, Contractor shall again carefully examine all applicable Contract Documents, the Project site, and other information given to Contractor as to materials and methods of construction and other Project requirements.

Contractor shall immediately notify the Engineer of any potential error, inconsistency, ambiguity, conflict, or lack of detail or explanation. If Contractor performs, permits, or causes the performance of any Work which is in error, inconsistent or ambiguous, or not sufficiently detailed or explained, Contractor shall bear any and all resulting costs, including, without limitation, the cost of 38077.00180\29080232.10
-58- 00 72 13 – GENERAL CONDITIONS
correction. In no case shall the Contractor or any subcontractor proceed with Work if uncertain as to the applicable requirements.

B. Additional Instructions. After notification of any error, inconsistency, ambiguity, conflict, or lack of detail or explanation, the Engineer will provide any required additional instructions, by means of drawings or other written direction, necessary for proper execution of Work.

C. Quality of Parts, Construction and Finish. All parts of the Work shall be of the best quality of their respective kinds and the Contractor must use all diligence to inform itself fully as to the required construction and finish.

D. Contractor’s Variation from Contract Document Requirements. If it is found that the Contractor has varied from the requirements of the Contract Documents including the requirement to comply with all applicable laws, ordinances, rules and regulations, the Engineer may at any time, before or after completion of the Work, order the improper Work removed, remade or replaced by the Contractor at the Contractor’s expense.

ARTICLE 6 EXISTENCE OF UTILITIES AT THE WORK SITE
A. The City has endeavored to determine the existence of utilities at the Project site from the records of the owners of known utilities in the vicinity of the Project. The positions of these utilities as derived from such records are shown on the Plans.

B. Unless indicated otherwise on the Plans and Specifications, no excavations were made to verify the locations shown for underground utilities. The service connections to these utilities may not be not shown on the Plans. Any connections shown on the Plans are general locations. It shall be the responsibility of the Contractor to determine the exact location of all service connections. The Contractor shall make its own investigations, including exploratory excavations, to determine the locations and type of service connections, prior to commencing Work which could result in damage to such utilities. The Contractor shall immediately notify the City in writing of any utility discovered in a different position than shown on the Plans or which is not shown on the Plans.

C. If applicable, all water meters, water valves, fire hydrants, electrical utility vaults, telephone vaults, gas utility valves, and other subsurface structures shall be relocated or adjusted to final grade by the Contractor. Locations of existing utilities shown on the Plans are approximate and may not be complete. The Contractor shall be responsible for coordinating its Work with all utility companies during the construction of the Work.

D. Notwithstanding the above, pursuant to section 4215 of the Government Code, the City has the responsibility to identify, with reasonable accuracy, main or trunkline facilities on the plans and specifications. In the event that main or trunkline utility facilities are not identified with reasonable accuracy in the plans and specifications made a part of the invitation for Bids, the City shall assume the responsibility for their timely removal, relocation, or protection. 38077.00180\29080232.10
-59- 00 72 13 – GENERAL CONDITIONS
E. Contractor, except in an emergency, shall contact the appropriate regional notification center (USA North), Northern California Underground Service Alert at 811 or 1-800-227-2600 or on-line at usanorth811.org at least two working days prior to commencing any excavation if the excavation will be performed in an area which is known, or reasonably should be known, to contain subsurface installations other than the underground facilities owned or operated by the City, and obtain an inquiry identification number from that notification center. No excavation shall be commenced or carried out by the Contractor unless such an inquiry identification number has been assigned to the Contractor or any subcontractor of the Contractor and the City has been given the identification number by the Contractor.

ARTICLE 7 SOILS INVESTIGATIONS
A. Reports and Drawings. The Special Conditions identify:

1. those reports known to the City of explorations and tests of subsurface conditions at or contiguous to the site; and

2. those drawings known to the City of physical conditions relating to existing surface or subsurface structures at the site (except Underground Facilities).

B. Limited Reliance by Contractor on Technical Data Authorized. Contractor may rely upon the accuracy of the “technical data” contained in such reports and drawings, which were expressly not created or obtained to evaluate or assist in the evaluation of constructability, and are not Contract Documents. Contractor shall make its own interpretation of the “technical data” and shall be solely responsible for any such interpretations. Except for reliance on the accuracy of such “technical data,” Contractor may not rely upon or make any claim against the City, City’s Representative, or Engineer of Record, or any of their officers, directors, members, partners, employees, agents, consultants, or subcontractors, with respect to:

1. the completeness of such reports and drawings for Contractor’s purposes, including without limitation any aspects of the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, and safety precautions and programs incident thereto; or

2. other data, interpretations, opinions, conclusions and information contained in such reports or shown or indicated in such drawings; or

3. any Contractor interpretation of or conclusion drawn from any “technical data” or any such other data, interpretations, opinions, or information.

ARTICLE 8 CONTRACTOR’S SUPERVISION
Contractor shall continuously keep at the Project site, a competent and experienced full-time Project superintendent acceptable to the City. Superintendent must be able to proficiently speak, read and write in English and shall have the authority to make decisions on behalf of the Contractor.Contractor shall continuously provide efficient supervision of the Project. 38077.00180\29080232.10
-60- 00 72 13 – GENERAL CONDITIONS
ARTICLE 9 WORKERS
A. Contractor shall at all times enforce strict discipline and good order among its employees. Contractor shall not employ on the Project any unfit person or any one not skilled in the Work assigned to him or her.

B. Any person in the employ of the Contractor whom the City may deem incompetent or unfit shall be dismissed from the Work and shall not be employed on this Project.

ARTICLE 10 INDEPENDENT CONTRACTORS
Contractor shall be an independent contractor for the City and not an employee. Contractor understands and agrees that it and all of its employees shall not be considered officers, employees, or agents of City and are not entitled to benefits of any kind normally provided employees of City, including but not limited to, state unemployment compensation or workers’ compensation. Contractor assumes full responsibility for the acts and omissions of its employees or agents related to the Work.

ARTICLE 11 SUBCONTRACTS
A. Contractor agrees to bind every subcontractor to the terms of the Contract Documents as far as such terms are applicable to subcontractor’s portion of the Work. Contractor shall be as fully responsible to the City for the acts and omissions of its subcontractors and of persons either directly or indirectly employed by its subcontractors, as Contractor is for acts and omissions of persons directly employed by Contractor. Nothing contained in these Contract Documents shall create any contractual relationship between any subcontractor and the City.

B. The City reserves the right to accept all subcontractors. The City’s acceptance of any subcontractor under this Contract shall not in any way relieve Contractor of its obligations in the Contract Documents.

C. Prior to substituting any subcontractor listed in the Bid Forms, Contractor must comply with the requirements of the Subletting and Subcontracting Fair Practices Act pursuant to California Public Contract Code section 4100 et seq.

ARTICLE 12 VERIFICATION OF EMPLOYMENT ELIGIBILITY
By executing this Contract, Contractor verifies that it fully complies with all requirements and restrictions of state and federal law respecting the employment of undocumented aliens, including, but not limited to, the Immigration Reform and Control Act of 1986, as may be amended from time to time, and shall require all subcontractors, sub-subcontractors and consultants to comply with the same. Each person executing this Contract on behalf of Contractor verifies that he or she is a duly authorized officer of Contractor and that any of the following shall be grounds for the City to terminate the Contract for cause: (1) failure of the Contractor or its subcontractors, sub-subcontractors or consultants to meet any of the requirements provided for in this Article; (2) any misrepresentation or material omission concerning compliance with such requirements; or (3) failure to immediately remove from the Work any person found not to be in compliance with such requirements. 38077.00180\29080232.10
-61- 00 72 13 – GENERAL CONDITIONS
ARTICLE 13 REQUESTS FOR SUBSTITUTION
A. For the purposes of this provision, the term “substitution” shall mean the substitution of any material, method or service substantially equal to or better in every respect to that indicated in the Standard Specifications or otherwise referenced herein.

B. Pursuant to Public Contract Code section 3400(b), the City may make a finding that is described in the Notice Inviting Bids that designates certain products, things, or services by specific brand or trade name.

C. Unless specifically designated in the Special Conditions, whenever any material, process, or article is indicated or specified by grade, patent, or proprietary name or by name of manufacturer, such specifications shall be deemed to be used for the purpose of facilitating the description of the material, process, or article desired and shall be deemed to be followed by the words “or equal.” Contractor may, unless otherwise stated, offer for substitution any material, process, or article which may be substantially equal to or better in every respect to that so indicated or specified in the Contract Documents. However, the City has adopted uniform standards for certain materials, processes, and articles.

D. The Contractor shall submit substitution requests, together with substantiating data, for substitution of any “or equal” material, process, or article no later than 15 (15) calendar days after award of Contract. Provisions regarding submission of substitution requests shall not in any way authorize an extension of time for the performance of this Contract. If a substitution request is rejected by the City, the Contractor shall provide the material, method or service specified herein.

The City shall not be responsible for any costs incurred by the Contractor associated with substitution requests. The burden of proof as to the equality of any material, process, or article shall rest with the Contractor. The Engineer has the complete and sole discretion to determine if a material, process, or article is substantially equal to or better than that specified and to approve or reject all substitution requests.

E. Substantiating data as described above shall include, at a minimum, the following information:

1. A signed affidavit from the Contractor stating that the material, process, or article proposed as a substitution is substantially equal to or better than that specified in every way except as may be listed on the affidavit.

2. Illustrations, specifications, catalog cut sheets, and any other relevant data required to prove that the material, process, or article is substantially equal to or better than that specified.

3. A statement of the cost implications of the substitution being requested, indicating whether and why the proposed substitution will reduce or increase the amount of the contract.

4. Information detailing the durability and lifecycle costs of the proposed substitution.
38077.00180\29080232.10
-62- 00 72 13 – GENERAL CONDITIONS
F. Failure to submit all the required substantiating data detailed above in a timely manner so that the substitution request can be adequately reviewed may result in rejection of the substitution request. The Engineer is not obligated to review multiple submittals related the same substitution request resulting from the Contractor’s failure to initially submit a complete package.

G. Time limitations within this Article shall be strictly complied with and in no case will an extension of time for completion of the contract be granted because of Contractor’s failure to provide substitution requests at the time and in the manner described herein.

H. The Contractor shall bear the costs of all City work associated with the review of substitution requests.

I. If substitution requests approved by the Engineer require that Contractor furnish materials, methods or services more expensive than that specified, the increased costs shall be borne by Contractor.

ARTICLE 14 SHOP DRAWINGS
A. Contractor shall check and verify all field measurements and shall submit with such promptness as to provide adequate time for review and cause no delay in its own Work or in that of any other contractor, subcontractor, or worker on the Project, six (6) copies of all shop drawings, calculations, schedules, and materials list, and all other provisions required by the Contract Documents.

Contractor shall sign all submittals affirming that submittals have been reviewed and approved by Contractor prior to submission to Engineer. Each signed submittal shall affirm that the submittal meets all the requirements of the Contract Documents except as specifically and clearly noted and listed on the transmittal letter of the submittal.

B. Contractor shall make any corrections required by the Engineer, and file with the Engineer six (6) corrected copies each, and furnish such other copies as may be needed for completion of the Work. Engineer’s acceptance of shop drawings shall not relieve Contractor from responsibility for deviations from the Contract Documents unless Contractor has, in writing, called Engineer’s attention to such deviations at time of submission and has secured the Engineer’s written acceptance. Engineer’s acceptance of shop drawings shall not relieve Contractor from responsibility for errors in shop drawings.

ARTICLE 15 SUBMITTALS
A. Contractor shall furnish to the Engineer for approval, prior to purchasing or commencing any Work, a log of all samples, material lists and certifications, mix designs, schedules, and other submittals, as required in the Contract Documents. The log shall indicate whether samples will be provided in accordance with other provisions of this Contract.

B. Contractor will provide samples and submittals, together with catalogs and supporting data required by the Engineer, to the Engineer within a reasonable time period to provide for adequate review and avoid delays in the Work. 38077.00180\29080232.10
-63- 00 72 13 – GENERAL CONDITIONS
C. These requirements shall not authorize any extension of time for performance of this Contract. Engineer will check and approve such samples, but only for conformance with design concept of work and for compliance with information given in the Contract Documents. Work shall be in accordance with approved samples and submittals.

ARTICLE 16 MATERIALS
A. Except as otherwise specifically stated in the Contract Documents, Contractor shall provide and pay for all materials, labor, tools, equipment, lights, power, transportation, superintendence, temporary constructions of every nature, and all other services and facilities of every nature whatsoever necessary to execute and complete this Contract within specified time.

B. Unless otherwise specified, all materials shall be new and the best of their respective kinds and grades as noted and/or specified, and workmanship shall be of good quality.

C. Materials shall be furnished in ample quantities and at such times as to ensure uninterrupted progress of the Work and shall be stored properly and protected as required by the Contract Documents. Contractor shall be entirely responsible for damage or loss by weather or other causes to materials or Work.

D. No materials, supplies, or equipment for Work under this Contract shall be purchased subject to any chattel mortgage or under a conditional sale or other agreement by which an interest therein or in any part thereof is retained by the seller or supplier. Contractor warrants good title to all material, supplies, and equipment installed or incorporated in the Work and agrees upon completion of all work to deliver the Project, to the City free from any claims, liens, or charges.

E. Materials shall be stored on the Project site in such manner so as not to interfere with any operations of the City or any independent contractor.

F. Contractor shall verify all measurements, dimensions, elevations, and quantities before ordering any materials or performing any Work, and the City shall not be liable for Contractor’s failure to so. No additional compensation, over and above payment for the actual quantities at the prices set out in the Bid Form, will be allowed because of differences between actual measurements, dimension, elevations and quantities and those indicated on the Plans and in the Specifications.Any difference therein shall be submitted to the Engineer for consideration before proceeding with the Work.

G. The City shall provide compensation for actual quantities of materials installed in accordance with the Contract Documents and at the price set forth in the Contractor’s bid and/or executed change order. The City is not obligated to pay for materials stored on/off site but not yet installed in accordance with the Contract Documents.
38077.00180\29080232.10
-64- 00 72 13 – GENERAL CONDITIONS
ARTICLE 17 PERMITS AND LICENSES
A. Contractor shall obtain all other necessary permits and licenses for the construction of the Project, including encroachment permits, and shall pay all fees required by law and shall comply with all laws, ordinances, rules and regulations relating to the Work and to the preservation of public health and safety. Before acceptance of the Project, the Contractor shall submit all licenses, permits, certificates of inspection and required approvals to the City.Any construction permits required by City for performing any work on this project will be issued by City at no charge to Contractor. Contractor and all subcontractors shall maintain a City business license at all times they are performing the Work.

ARTICLE 18 TRENCHES
A. Trenches Five Feet or More in Depth. Contractor shall submit to the Engineer at the preconstruction meeting, a detailed plan showing the design of shoring, bracing, sloping or other provisions to be made for worker protection from hazards of caving ground during the excavation of any trench or trenches five feet or more in depth. If such plan varies from shoring system standards established by the Construction Safety Orders of the California Code of Regulations, Department of Industrial Relations, the plan shall be prepared by a California registered civil or structural engineer. The plan shall not be less effective than the shoring, bracing, sloping, or other provisions of the Construction Safety Orders, as defined in the California Code of Regulations.

The Contractor shall designate in writing the “competent person” as defined in Title 8, California Code of Regulations, who shall be present at the Work Site each day that trenching/excavation is in progress. The “competent person” shall prepare and provide daily trenching/excavation inspection reports to the Engineer. Contractor shall also submit a copy of its annual California Occupational Safety and Health Administration (Cal/OSHA) trench/excavation permit.

B. Excavations Deeper than Four Feet. If the Work involves excavating trenches or other excavations that extend deeper than four feet below the surface, Contractor shall promptly, and before the excavation is further disturbed, notify the City in writing of any of the following conditions:

1. Material that the Contractor believes may be material that is hazardous waste, as defined in section 25117 of the Health and Safety Code, that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law.

2. Subsurface or latent physical conditions at the site differing from those indicated.

3. Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily encountered and generally recognized as inherent in work of the character provided for in the Contract The City shall promptly investigate the conditions, and if it finds that the conditions do so materially differ, or do involve hazardous waste, and cause a 38077.00180\29080232.10
-65- 00 72 13 – GENERAL CONDITIONS
decrease or increase in Contractor’s cost of, or the time required for, performance of any part of the Work, shall issue a change order under the procedures described in the Contract Documents.

In the event that a dispute arises between the City and the Contractor as to whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the Contractor’s cost of, or time required for, performance of any part of the Work, the Contractor shall not be excused from any scheduled completion date provided for by the Contract, but shall proceed with all Work to be performed under the Contract. Contractor shall retain any and all rights provided either by contract or by law which pertain to the resolution of disputes and protests between the parties.

ARTICLE 19 DIVERSION OF RECYCLABLE WASTE MATERIALS
In compliance with the applicable City’s waste reduction and recycling efforts, Contractor shall divert all Recyclable Waste Materials to appropriate recycling centers as required for compliance with the local jurisdiction’s waste diversion ordinances, and provide the City Engineer with detailed records and quantities of the materials that were sent to recycling centers. Contractor will be required to submit weight tickets and written proof of diversion with its monthly progress payment requests. Contractor shall complete and execute any certification forms required by City or other applicable agencies to document Contractor’s compliance with these diversion requirements. All costs incurred for these waste diversion efforts shall be the responsibility of the Contractor.

ARTICLE 20 REMOVAL OF HAZARDOUS MATERIALS
Should Contractor encounter material reasonably believed to be polychlorinated biphenyl (PCB) or other toxic wastes and hazardous materials which have not been rendered harmless at the Project site, the Contractor shall immediately stop work at the affected Project site and shall report the condition to the City in writing. The City shall contract for any services required to directly remove and/or abate PCBs and other toxic wastes and hazardous materials, if required by the Project site(s), and shall not require the Contractor to subcontract for such services. The Work in the affected area shall not thereafter be resumed except by written agreement of the City and Contractor.

ARTICLE 21 SANITARY FACILITIES
Contractor shall provide sanitary temporary toilet buildings and hand washing facilities for the use of all workers. All toilets and hand washing facilities shall comply with all applicable federal, state and local laws, codes, ordinances, and regulations. Toilets shall be kept supplied with toilet paper and shall have workable door fasteners. Toilets and hand washing facilities shall be serviced no less than once weekly and shall be present in a quantity of not less than 1 per 20 workers as required by Cal/OSHA regulations. The toilets and hand washing facilities shall be maintained in a sanitary condition at all times. Use of toilet and hand washing facilities in the Work under construction shall not be permitted. Any other sanitary facilities required by Cal/OSHA shall be the responsibility of the Contractor. 38077.00180\29080232.10
-66- 00 72 13 – GENERAL CONDITIONS
ARTICLE 22 AIR POLLUTION CONTROL
Contractor shall comply with all air pollution and dust control rules, regulations, ordinances and statutes, including, but not limited to, those required by thet Air Quality Management District. All containers of paint, thinner, curing compound, solvent or liquid asphalt shall be labeled to indicate that the contents fully comply with the applicable material requirements.

ARTICLE 23 LAYOUT AND FIELD ENGINEERING
All field engineering required for laying out the Work and establishing grades for earthwork operations shall be furnished by the Contractor at its expense.

ARTICLE 24 TESTS AND INSPECTIONS
A. If the Contract Documents, the Engineer, or any instructions, laws, ordinances, or public authority requires any part of the Work to be tested or Approved, Contractor shall provide the Engineer at least two (2) working days’ notice of its readiness for observation or inspection. If inspection is by a public authority other than the City, Contractor shall promptly inform the City of the date fixed for such inspection. Required certificates of inspection (or similar) shall be secured by Contractor. Costs for City testing and City inspection shall be paid by the City.

Costs of tests for Work found not to be in compliance shall be paid by the Contractor.

B. If any Work is done or covered up without the required testing or approval, the Contractor shall uncover or deconstruct the Work, and the Work shall be redone after completion of the testing at the Contractor’s cost in compliance with the Contract Documents.

C. Where inspection and testing are to be conducted by an independent laboratory or agency, materials or samples of materials to be inspected or tested shall be selected by such laboratory or agency, or by the City, and not by Contractor. All tests or inspections of materials shall be made in accordance with the commonly recognized standards of national organizations.

D. In advance of manufacture of materials to be supplied by Contractor which must be tested or inspected, Contractor shall notify the City so that the City may arrange for testing at the source of supply. Any materials which have not satisfactorily passed such testing and inspection shall not be incorporated into the Work.

E. If the manufacture of materials to be inspected or tested will occur in a plant or location greater than sixty (60) miles from the City, the Contractor shall pay for any excessive or unusual costs associated with such testing or inspection, including but not limited to excessive travel time, standby time and required lodging.

F. Reexamination of Work may be ordered by the City. If so ordered, Work must be uncovered or deconstructed by Contractor. If Work is found to be in accordance with the Contract Documents, the City shall pay the costs of reexamination and 38077.00180\29080232.10
-67- 00 72 13 – GENERAL CONDITIONS
reconstruction. If such work is found not to be in accordance with the Contract Documents, Contractor shall pay all costs.

ARTICLE 25 PROTECTION OF WORK AND PROPERTY
A. The Contractor shall be responsible for all damages to persons or property that occurs as a result of the Work. Contractor shall be responsible for the proper care and protection of all materials delivered and Work performed until completion and final Acceptance by the City. All Work shall be solely at the Contractor’s risk. Contractor shall adequately protect adjacent property from settlement or loss of lateral support as necessary. Contractor shall comply with all applicable safety laws and building codes to prevent accidents or injury to persons on, about, or adjacent to the Project site where Work is being performed.

Contractor shall erect and properly maintain at all times, as required by field conditions and progress of work, all necessary safeguards, signs, barriers, lights, and watchmen for protection of workers and the public, and shall post danger signs warning against hazards created in the course of construction.

B. In an emergency affecting safety of life or of work or of adjoining property, Contractor, without special instruction or authorization from the Engineer, is hereby permitted to act to prevent such threatened loss or injury; and Contractor shall so act, without appeal, if so authorized or instructed by the Engineer or the City. Any compensation claimed by Contractor on account of emergency work shall be determined by and agreed upon by the City and the Contractor.

ARTICLE 26 CONTRACTOR’S MEANS AND METHODS
Contractor is solely responsible for the means and methods utilized to perform the Work. In no case shall the Contractor’s means and methods deviate from commonly used industry standards.

ARTICLE 27 AUTHORIZED REPRESENTATIVES
The City shall designate representatives, who shall have the right to be present at the Project site at all times. The City may designate an inspector who shall have the right to observe all of the Contractor’s Work. The inspector shall not be responsible for the Contractor’s failure to carry out the Work in accordance with the Contract Documents.Contractor shall provide safe and proper facilities for such access.

ARTICLE 28 HOURS OF WORK
A. As provided in Article 3 (commencing at section 1810), Chapter 1, Part 7, Division 2 of the Labor Code, Contractor stipulates that eight (8) hours of labor shall constitute a legal day’s work. The time of service of any worker employed at any time by the Contractor or by any subcontractor on any subcontract under this Contract upon the Work or upon any part of the Work contemplated by this Contract is limited and restricted to eight (8) hours during any one calendar day and 40 hours during any one calendar week, except as hereinafter provided.

Notwithstanding the provisions herein above set forth, work performed by employees of Contractor in excess of eight (8) hours per day, and 40 hours during any one week, shall be permitted upon this public work upon 38077.00180\29080232.10
-68- 00 72 13 – GENERAL CONDITIONS
compensation for all hours worked in excess of eight (8) hours per day at not less than one and one-half times the basic rate of pay.

B. The Contractor and every subcontractor shall keep an accurate record showing the name of and actual hours worked each calendar day and each calendar week by each worker employed in connection with the Work or any part of the Work contemplated by this Contract. The record shall be kept open at all reasonable hours to the inspection of the City and to the Division of Labor Law Enforcement, Department of Industrial Relations of the State of California.

C. The Contractor shall pay to the City a penalty of twenty-five dollars ($25.00) for each worker employed in the execution of this Contract by the Contractor or by any subcontractor for each calendar day during which such worker is required or permitted to work more than eight (8) hours in any calendar day and 40 hours in any one calendar week in violation of the provisions of Article 3 (commencing at section 1810), Chapter 1, Part 7, Division 2 of the Labor Code.

D. Any work necessary to be performed after regular working hours, or on Saturdays and Sundays or other holidays, shall be performed without additional expense to the City. Contractor shall also timely notify the City when work will be perfomed outside regular working hours or on weekends or holidays.

E. City will provide inspection during normal working hours from 7:00 a.m. to 3:30 p.m. Monday through Friday. Inspection before or after this time will be charged to the Contractor as reimbursable inspection time. Inspections on weekends requires two days’ notice for review and approval. Upon written request and approval the 8.5 hour working day may be changed to other limits subject to city/county ordinance.

F. Refer to the most current version of the City of Milpitas Noise Abatement Ordinance, Ord. 196.6 of the Municipal Code Section V-213. It shall be unlawful for any person to engage or permit to engage in construction of any building or related road or walkway, pool, or landscape improvement or in the construction operations related thereto including to operate, permit, use, or cause to operate any of the following at the Project site, other than between the hours of 7:00 a.m. to 7:00 p.m., Monday through Sunday, unless otherwise approved by the City:

1. Powered Vehicles

2. Construction Equipment

3. Loading and Unloading Vehicles

4. Domestic Power Tools
ARTICLE 29 PAYROLL RECORDS; LABOR COMPLIANCE
A. Pursuant to Labor Code section 1776, Contractor and all subcontractors shall maintain weekly certified payroll records, showing the names, addresses, Social Security numbers, work classifications, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, 38077.00180\29080232.10
-69- 00 72 13 – GENERAL CONDITIONS
apprentice, worker, or other employee employed by them in connection with the Work under this Contract. Contractor shall certify under penalty of perjury that records maintained and submitted by Contractor are true and accurate.

Contractor shall also require subcontractor(s) to certify weekly payroll records under penalty of perjury.

B. In accordance with Labor Code section 1771.4, the Contractor and each subcontractor shall furnish the certified payroll records directly to the Department of Industrial Relations (“DIR”) on the specified interval and format prescribed by the DIR, which may include electronic submission. Contractor shall comply with all requirements and regulations from the DIR relating to labor compliance monitoring and enforcement. The requirement to submit certified payroll records directly to the Labor Commissioner under Labor Code section 1771.4 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Section 1771.4.

C. Any stop orders issued by the Department of Industrial Relations against Contractor or any subcontractor that affect Contractor’s performance of Work, including any delay, shall be Contractor’s sole responsibility. Any delay arising out of or resulting from such stop orders shall be considered Contractor caused delay subject to any applicable liquidated damages and shall not be compensable by the City. Contractor shall defend, indemnify and hold the City, its officials, officers, employees and agents free and harmless from any claim or liability arising out of stop orders issued by the Department of Industrial Relations against Contractor or any subcontractor.

D. The payroll records described herein shall be certified and submitted by the Contractor at a time designated by the City. The Contractor shall also provide the following:

1. A certified copy of the employee’s payroll records shall be made available for inspection or furnished to such employee or his or her authorized representative on request.

2. A certified copy of all payroll records described herein shall be made available for inspection or furnished upon request of the DIR.

E. Unless submitted electronically, the certified payroll records shall be on forms provided by the Division of Labor Standards Enforcement (“DLSE”) of the DIR or shall contain the same information as the forms provided by the DLSE.

F. Any copy of records made available for inspection as copies and furnished upon request to the public or any public agency, the City, the Division of Apprenticeship Standards or the Division of Labor Standards Enforcement shall be marked or obliterated in such a manner as to prevent disclosure of an individual's name, address and social security number. The name and address of the Contractor awarded the Contract or performing the contract shall not be marked or obliterated.

G. In the event of noncompliance with the requirements of this Article, the Contractor shall have ten (10) calendar days in which to comply subsequent to 38077.00180\29080232.10
-70- 00 72 13 – GENERAL CONDITIONS
receipt of written notice specifying in what respects the Contractor must comply with this Article. Should noncompliance still be evident after such 10-day period, the Contractor shall pay a penalty of one hundred dollars ($100.00) to the City for each calendar day, or portion thereof, for each worker, until strict compliance is effectuated. Upon the request of the Division of Apprenticeship Standards or the Division of Labor Standards Enforcement, such penalties shall be withheld from progress payment then due.

H. The responsibility for compliance with this Article shall rest upon the Contractor.

ARTICLE 30 PREVAILING RATES OF WAGES
A. The Contractor is aware of the requirements of Labor Code sections 1720 et seq. and 1770 et seq., as well as California Code of Regulations, Title 8, Section 16000 et seq. (“Prevailing Wage Laws”), which require the payment of prevailing wage rates and the performance of other requirements on certain “public works” and “maintenance” projects. Since this Project involves an applicable “public works” or “maintenance” project, as defined by the Prevailing Wage Laws, and since the total compensation is $1,000 or more, Contractor agrees to fully comply with such Prevailing Wage Laws. The Contractor shall obtain a copy of the prevailing rates of per diem wages at the commencement of this Contract from the website of the Division of Labor Statistics and Research of the Department of Industrial Relations located at www.dir.ca.gov. In the alternative, the Contractor may view a copy of the prevailing rate of per diem wages which are on file at the City’s Administration Office and shall be made available to interested parties upon request. Contractor shall make copies of the prevailing rates of per diem wages for each craft, classification, or type of worker needed to perform work on the Project available to interested parties upon request, and shall post copies at the Contractor’s principal place of business and at the Project site. Contractor shall defend, indemnify and hold the City, its officials, officers, employees and authorized volunteers free and harmless from any claims, liabilities, costs, penalties or interest arising out of any failure or allege failure to comply with the Prevailing Wage Laws.

B. The Contractor shall forfeit as a penalty to the City not more than Two Hundred Dollars ($200.00), pursuant to Labor Code section 1775, for each calendar day, or portion thereof, for each worker paid less than the prevailing wage rate as determined by the Director of the Department of Industrial Relations for such work or craft in which such worker is employed for any public work done under the Contract by it or by any subcontractor under it. The difference between such prevailing wage rate and the amount paid to each worker for each calendar day or portion thereof, for which each worker was paid less than the prevailing wage rate, shall be paid to each worker by the Contractor.

C. Contractor shall post, at appropriate conspicuous points on the Project site, a schedule showing all determined general prevailing wage rates and all authorized deductions, if any, from unpaid wages actually earned. 38077.00180\29080232.10
-71- 00 72 13 – GENERAL CONDITIONS
ARTICLE 31 PUBLIC WORKS CONTRACTOR REGISTRATION
Pursuant to Labor Code sections 1725.5 and 1771.1, the Contractor and its subcontractors must be registered with the Department of Industrial Relations prior to the execution of a contract to perform public works. By entering into this Contract, Contractor represents that it is aware of the registration requirement and is currently registered with the DIR. Contractor shall maintain a current registration for the duration of the Project. Contractor shall further include the requirements of Labor Code sections 1725.5 and 1771.1 in any subcontract and ensure that all subcontractors are registered at the time this Contract is entered into and maintain registration for the duration of the Project. Notwithstanding the foregoing, the contractor registration requirements mandated by Labor Code Sections 1725.5 and 1771.1 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Sections 1725.5 and 1771.1.

ARTICLE 32 EMPLOYMENT OF APPRENTICES
A. Contractor and all subcontractors shall comply with the requirements of Labor Code sections 1777.5 and 1777.6 in the employment of apprentices.

B. Information relative to apprenticeship standards, wage schedules, and other requirements may be obtained from the Director of Industrial Relations, ex officio the Administrator of Apprenticeship, San Francisco, California, or from the Division of Apprenticeship Standards and its branch offices.

C. Knowing violations of Labor Code section 1777.5 will result in forfeiture not to exceed one hundred dollars ($100.00) for each calendar day of non-compliance pursuant to Labor Code section 1777.7.

D. The responsibility for compliance with this Article shall rest upon the Contractor.

ARTICLE 33 NONDISCRIMINATION/EQUAL EMPLOYMENT OPPORTUNITY Pursuant to Labor Code section 1735 and other applicable provisions of law, the Contractor and its subcontractors shall not discriminate against any employee or applicant for employment because of race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, marital status, sex, age, sexual orientation, or any other classifications protected by law on this Project. The Contractor will take affirmative action to insure that employees are treated during employment or training without regard to their race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, marital status, sex, age, sexual orientation, or any other classifications protected by law.

Employment Eligibility; Contractor. By executing this Contract, Contractor verifies that it fully complies with all requirements and restrictions of state and federal law respecting the employment of undocumented aliens, including, but not limited to, the Immigration Reform and Control Act of 1986, as may be amended from time to time. Such requirements and restrictions include, but are not limited to, examination and retention of documentation confirming the identity and immigration status of each employee of the Contractor. Contractor also verifies that it has not committed a violation of any such law within the five (5) years immediately preceding the date of execution of this Contract, and shall not violate any such law at any time during the term of the Contract. Contractor shall avoid any violation of any such law during the term of this 38077.00180\29080232.10
-72- 00 72 13 – GENERAL CONDITIONS
Contract by participating in an electronic verification of work authorization program operated by the United States Department of Homeland Security, by participating in an equivalent federal work authorization program operated by the United States Department of Homeland Security to verify information of newly hired employees, or by some other legally acceptable method.

Contractor shall maintain records of each such verification, and shall make them available to the City or its representatives for inspection and copy at any time during normal business hours.

The City shall not be responsible for any costs or expenses related to Contractor’s compliance with the requirements provided for or referred to herein.

Employment Eligibility; Subcontractors, Sub-subcontractors and Consultants. To the same extent and under the same conditions as Contractor, Contractor shall require all of its subcontractors, sub-subcontractors and consultants performing any part of the Work or of this Contract to make the same verifications and comply with all requirements and restrictions provided for herein.

Employment Eligibility; Failure to Comply. Each person executing this Contract on behalf of Contractor verifies that he or she is a duly authorized officer of Contractor, and understands that any of the following shall be grounds for the City to terminate the Contract for cause: (1) failure of Contractor or its subcontractors, sub-subcontractors or consultants to meet any of the requirements provided for herein; (2) any misrepresentation or material omission concerning compliance with such requirements; or (3) failure to immediately remove from the Work any person found not to be in compliance with such requirements.

ARTICLE 34 DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS
Contractors or subcontractors may not perform work on a public works project with a subcontractor who is ineligible to perform work on a public project pursuant to Labor Code section 1777.1 or 1777.7. Any contract on a public works project entered into between a contractor and a debarred subcontractor is void as a matter of law. A debarred subcontractor may not receive any public money for performing work as a subcontractor on a public works contract. Any public money that is paid, or may have been paid to a debarred subcontractor by a contractor on the project shall be returned to the City. The Contractor shall be responsible for the payment of wages to workers of a debarred subcontractor who has been allowed to work on the project.

ARTICLE 35 LABOR/EMPLOYMENT SAFETY
The Contractor shall comply with all applicable laws and regulations of the federal, state, and local government, including Cal/OSHA requirements and requirements for verification of employees’ legal right to work in the United States.

The Contractor shall maintain emergency first aid treatment for his employees which complies with the Federal Occupational Safety and Health Act of 1970 (29 U.S.C. § 651 et seq.), and California Code of Regulations, Title 8, Industrial Relations Division 1, Department of Industrial Relations, Chapter 4. The Contractor shall ensure the availability of emergency medical services for its employees in accordance with California Code of Regulations, Title 8, Section 1512.

The Contractor shall submit the Illness and Injury Prevention Program and a Project site specific safety program to the City prior to beginning Work at the Project site. Contractor shall maintain 38077.00180\29080232.10
-73- 00 72 13 – GENERAL CONDITIONS
a confined space program that meets or exceeds the City Standards. Contractor shall adhere to the City’s lock out tag out program.

ARTICLE 36 INSURANCE
The Contractor shall obtain, and at all times during performance of the Work of Contract, maintain all of the insurance described in this Article. Contractor shall not commence Work under this Contract until it has provided evidence satisfactory to the City that it has secured all insurance required hereunder. Contractor shall not allow any subcontractor to commence work on any subcontract until it has provided evidence satisfactory to the City that the subcontractor has secured all insurance required under this Article. Failure to provide and maintain all required insurance shall be grounds for the City to terminate this Contract for cause. Contractor shall furnish City with original certificates of insurance and endorsements effective coverage required by this Contract on forms satisfactory to the City. The certificates and endorsements for each insurance policy shall be signed by a person authorized by that insurer to bind coverage on its behalf, and shall be on forms acceptable to the City. All certificates and endorsements must be received and approved by the City before Work commences.

A. Additional Insureds; Waiver of Subrogation. The City, its elected and appointed officials, officers, attorneys, agents employees and volunteers shall be named as Additional Insureds on Contractor’s All Risk policy and on Contractor’s and its subcontractors’ policies of Commercial General Liability and Automobile Liability insurance using, for Contractor’s policy/ies of Commercial General Liability insurance, ISO CG forms 20 10 and 20 37 (or endorsements providing the exact same coverage, including completed operations), and, for subcontractors’ policies of Commercial General Liability insurance, ISO CG form 20 38 (or endorsements providing the exact same coverage). Notwithstanding the minimum limits set forth in this Contract for any type of insurance coverage, all available insurance proceeds in excess of the specified minimum limits of coverage shall be available to the parties required to be named as Additional Insureds hereunder. Contractor and its insurance carriers shall provide a Waiver of Subrogation in favor of those parties.

B. Workers’ Compensation Insurance. The Contractor shall provide workers’ compensation insurance for all of the employees engaged in Work under this Contract, on or at the Site, and, in case of any sublet Work, the Contractor shall require the subcontractor similarly to provide workers’ compensation insurance for all the latter’s employees as prescribed by State law. Any class of employee or employees not covered by a subcontractor’s insurance shall be covered by the Contractor’s insurance. In case any class of employees engaged in work under this Contract, on or at the Site, is not protected under the Workers’ Compensation Statutes, the Contractor shall provide or shall cause a subcontractor to provide, adequate insurance coverage for the protection of such employees not otherwise protected. The Contractor is required to secure payment of compensation to his employees in accordance with the provisions of section 3700 of the Labor Code. The Contractor shall file with the City certificates of his insurance protecting workers. Company or companies providing insurance coverage shall be acceptable to the City, if in the form and coverage as set forth in the Contract Documents.
38077.00180\29080232.10
-74- 00 72 13 – GENERAL CONDITIONS
C. Employer’s Liability Insurance. Contractor shall provide Employer’s Liability Insurance, including Occupational Disease, in the amount of at least one million dollars ($1,000,000.00) per person per accident. Contractor shall provide City with a certificate of Employer’s Liability Insurance. Such insurance shall comply with the provisions of the Contract Documents. The policy shall be endorsed, if applicable, to provide a Borrowed Servant/Alternate Employer Endorsement and contain a Waiver of Subrogation in favor of the City.

D. Commercial General Liability Insurance. Contractor shall provide “occurrence” form Commercial General Liability insurance coverage at least as broad as the most current ISO CGL Form 00 01, including but not limited to, premises liability, contractual liability, products/completed operations, personal and advertising injury which may arise from or out of Contractor’s operations, use, and management of the Site, or the performance of its obligations hereunder. The policy shall not contain any exclusion contrary to this Contract including but not limited to endorsements or provisions limiting coverage for (1) contractual liability (including but not limited to ISO CG 24 26 or 21 39); or (2) cross-liability for claims or suits against one insured against another. Policy limits shall not be less than $1,000,000 per occurrence for bodily injury, personal injury and property damage. If Commercial General Liability Insurance or other form with a general aggregate limit is used, either the general aggregate limit shall apply separately to this project/location or the general aggregate limit shall be twice the required occurrence limit. Defense costs shall be paid in addition to the limits.

1. Such policy shall comply with all the requirements of this Article. The limits set forth herein shall apply separately to each insured against whom claims are made or suits are brought, except with respect to the limits of liability. Further the limits set forth herein shall not be construed to relieve the Contractor from liability in excess of such coverage, nor shall it limit Contractor’s indemnification obligations to the City, and shall not preclude the City from taking such other actions available to the City under other provisions of the Contract Documents or law.

2. All general liability policies provided pursuant to the provisions of this Article shall comply with the provisions of the Contract Documents.

3. All general liability policies shall be written to apply to all bodily injury, including death, property damage, personal injury, owned and non-owned equipment, blanket contractual liability, completed operations liability, explosion, collapse, under-ground excavation, removal of lateral support, and other covered loss, however occasioned, occurring during the policy term, and shall specifically insure the performance by Contractor of that part of the indemnification contained in these General Conditions relating to liability for injury to or death of persons and damage to property.

4. If the coverage contains one or more aggregate limits, a minimum of 50% of any such aggregate limit must remain available at all times; if over 50% of any aggregate limit has been paid or reserved, the City may require additional coverage to be purchased by Contractor to restore the required limits. Contractor may combine primary, umbrella, and as broad as 38077.00180\29080232.10
-75- 00 72 13 – GENERAL CONDITIONS
possible excess liability coverage to achieve the total limits indicated above. Any umbrella or excess liability policy shall include the additional insured endorsement described in the Contract Documents.

5. All policies of general liability insurance shall permit and Contractor does hereby waive any right of subrogation which any insurer of Contractor may acquire from Contractor by virtue of the payment of any loss.

E. Automobile Liability Insurance. Contractor shall provide “occurrence” form Automobile Liability Insurance at least as broad as ISO CA 00 01 (Any Auto) in the amount of, at least, one million dollars ($1,000,000) per accident for bodily injury and property damage. Such insurance shall provide coverage with respect to the ownership, operation, maintenance, use, loading or unloading of any auto owned, leased, hired or borrowed by Contractor or for which Contractor is responsible, in a form and with insurance companies acceptable to the City. All policies of automobile insurance shall permit and Contractor does hereby waive any right of subrogation which any insurer of Contractor may acquire from Contractor by virtue of the payment of any loss.

F. Builder’s Risk [“All Risk”] [RESERVED]
G. Contractor’s Pollution Liability Coverage. [RESERVED] H. Contractor shall require all tiers of sub-contractors working under this Contract to provide the insurance required under this Article unless otherwise agreed to in writing by City. Contractor shall make certain that any and all subcontractors hired by Contractor are insured in accordance with this Contract. If any subcontractor’s coverage does not comply with the foregoing provisions, Contractor shall indemnify and hold the City harmless from any damage, loss, cost, or expense, including attorneys’ fees, incurred by the City as a result thereof.

ARTICLE 37 FORM AND PROOF OF CARRIAGE OF INSURANCE
A. Any insurance carrier providing insurance coverage required by the Contract Documents shall be admitted to and authorized to do business in the State of California unless waived, in writing, by the City’s Risk Manager. Carrier(s) shall have an A.M. Best rating of not less than an A:VII. Insurance deductibles or selfinsured retentions must be declared by the Contractor. At the election of the City the Contractor shall either 1) reduce or eliminate such deductibles or self-insured retentions, or 2) procure a bond which guarantees payment of losses and related investigations, claims administration, and defense costs and expenses. If umbrella or excess liability coverage is used to meet any required limit(s) specified herein, the Contractor shall provide a “follow form” endorsement satisfactory to the City indicating that such coverage is subject to the same terms and conditions as the underlying liability policy.

B. Each insurance policy required by this Contract shall be endorsed to state that:
(1) coverage shall not be suspended, voided, reduced or cancelled except after thirty (30) days prior written notice by certified mail, return receipt requested, has been given to the City; and (2) any failure to comply with reporting or other 38077.00180\29080232.10
-76- 00 72 13 – GENERAL CONDITIONS
provisions of the policies, including breaches of warranties, shall not affect coverage provided to the City, its officials, officers, agents, employees, and volunteers.

C. The Certificates(s) and policies of insurance shall contain or shall be endorsed to contain the covenant of the insurance carrier(s) that it shall provide no less than thirty (30) days written notice be given to the City prior to any material modification or cancellation of such insurance. In the event of a material modification or cancellation of coverage, the City may terminate the Contract or stop the Work in accordance with the Contract Documents, unless the City receives, prior to such effective date, another properly executed original Certificate of Insurance and original copies of endorsements or certified original policies, including all endorsements and attachments thereto evidencing coverage’s set forth herein and the insurance required herein is in full force and effect. Contractor shall not take possession, or use the Site, or commence operations under this Contract until the City has been furnished original Certificate(s) of Insurance and certified original copies of endorsements or policies of insurance including all endorsements and any and all other attachments as required in this Article. The original endorsements for each policy and the Certificate of Insurance shall be signed by an individual authorized by the insurance carrier to do so on its behalf.

D. The Certificate(s) of Insurance, policies and endorsements shall so covenant and shall be construed as primary, and the City’s insurance and/or deductibles and/or self-insured retentions or self-insured programs shall not be construed as contributory.

E. City reserves the right to adjust the monetary limits of insurance coverages during the term of this Contract including any extension thereof if, in the City’s reasonable judgment, the amount or type of insurance carried by the Contractor becomes inadequate.

F. Contractor shall report to the City, in addition to the Contractor’s insurer, any and all insurance claims submitted by the Contractor in connection with the Work under this Contract.

ARTICLE 38 TIME FOR COMPLETION AND LIQUIDATED DAMAGES
A. Time for Completion/Liquidated Damages. Time is of the essence in the completion of the Work. Work shall be commenced within ten (10) Days of the date stated in the City’s Notice to Proceed and shall be completed by Contractor specified in the Contract Documents. The City is under no obligation to consider early completion of the Project; and the Contract completion date shall not be amended by the City’s receipt or acceptance of the Contractor’s proposed earlier completion date. Furthermore, Contractor shall not, under any circumstances, receive additional compensation from the City (including but not limited to indirect, general, administrative or other forms of overhead costs) for the period between the time of earlier completion proposed by the Contractor and the Contract completion date. If the Work is not completed as stated in the Contract Documents, it is understood that the City will suffer damage. In accordance with Government Code section 53069.85, being impractical and infeasible to 38077.00180\29080232.10
-77- 00 72 13 – GENERAL CONDITIONS
determine the amount of actual damage, it is agreed that Contractor shall pay to the City as fixed and liquidated damages, and not as a penalty, the sum stipulated in the Contract for each calendar day of delay until the Work is fully completed as determined by the City. Contractor and its surety shall be liable for any liquidated damages. Any money due or to become due the Contractor may be retained to cover liquidated damages.

B. Inclement Weather. Contractor shall abide by the Engineer’s determination of what constitutes inclement weather. Time extensions for inclement weather shall only be granted when the Work stopped during inclement weather is on the critical path of the Project schedule. The Contractor shall implement measures and make contingencies as may be required to protect the Work and to all allow Work to proceed during wet or inclement weather to prevent delay or stoppage.

C. Extension of Time. Contractor shall not be charged liquidated damages because of any delays in completion of the Work due to unforeseeable causes beyond the control and without the fault or negligence of Contractor (or its subcontractors or suppliers). Contractor shall within five (5) Days of identifying any such delay notify the City in writing of causes of delay. The City shall ascertain the facts and extent of delay and grant extension of time for completing the Work when, in its judgment, the facts justify such an extension. Time extensions to the Project shall be requested by the Contractor as they occur and without delay. No delay claims shall be permitted unless the event or occurrence delays the completion of the Project beyond the Contract completion date.

D. No Damages for Reasonable Delay. The City’s liability to Contractor for delays for which the City is responsible shall be limited to only an extension of time unless such delays were unreasonable under the circumstances. In no case shall the City be liable for any costs which are borne by the Contractor in the regular course of business, including, but not limited to, home office overhead and other ongoing costs. Damages caused by unreasonable City delay, including delays caused by items that are the responsibility of the City pursuant to Government Code section 4215, shall be based on actual costs only, no proportions or formulas shall be used to calculate any delay damages.

ARTICLE 39 SCHEDULE OF VALUES, COST BREAKDOWN AND PERIODIC

ESTIMATES
Contractor shall furnish on forms Approved by the City:

A. When requested by the Engineer, and within ten (10) Days of Notice to Proceed with the Contract, the Contractor shall provide a Schedule of Values consisting of a detailed estimate giving a complete breakdown of the Contract price for each lump sum bid item in the Contract.

B. A monthly itemized estimate of Work done for the purpose of making progress payments. In order for the City to consider and evaluate each progress payment application, the Contractor shall submit a detailed measurement of Work performed and a progress estimate of the value thereof before the tenth (10th) Day of the following month.
38077.00180\29080232.10
-78- 00 72 13 – GENERAL CONDITIONS
C. Contractor shall submit, with each of its payment requests, an adjusted list of actual quantities, verified by the Engineer, for unit price items listed, if any, in the Bid Form.

D. Following the City’s Acceptance of the Work, the Contractor shall submit to the City a written statement of the final quantities of unit price items for inclusion in the final payment request.

E. The City shall have the right to adjust any estimate of quantity and to subsequently correct any error made in any estimate for payment.

Contractor shall certify under penalty of perjury, that all cost breakdowns and periodic estimates accurately reflect the Work on the Project.

ARTICLE 40 PROGRESS ESTIMATES AND PAYMENT
A. By the tenth (10th) Day of the following calendar month, Contractor shall submit to Engineer a payment request which shall set forth in detail the value of the Work done for the period beginning with the date work was first commenced and ending on the end of the calendar month for which the payment request is prepared. Contractor shall include any amount earned for authorized extra work.

From the total thus computed, a deduction shall be made in the amount of five percent (5%) for retention, except where the City has adopted a finding that the Work done under the Contract is substantially complex, and then the amount withheld as retention shall be the percentage specified in the Notice Inviting Bids.

From the remainder a further deduction may be made in accordance with Section B below. The amount computed, less the amount withheld for retention and any amounts withheld as set forth below, shall be the amount of the Contractor’s payment request.

B. The Contractor shall provide an updated project schedule with each payment request.

C. The City may withhold a sufficient amount or amounts of any payment or payments otherwise due to Contractor, as in his judgment may be necessary to cover:

1. Payments which may be past due and payable for just claims against Contractor or any subcontractors for labor or materials furnished in and about the performance of work on the Project under this Contract.

2. Defective work not remedied.

3. Failure of Contractor to make proper payments to his subcontractor or for material or labor.

4. Completion of the Contract if there is a reasonable doubt that the Work can be completed for balance then unpaid.

5. Damage to another contractor or a third party.
38077.00180\29080232.10
-79- 00 72 13 – GENERAL CONDITIONS

6. Amounts which may be due the City for claims against Contractor.

7. Failure of Contractor to keep the record (“as-built”) drawings up to date.

8. Failure to provide update on construction schedule as required herein.

9. Site cleanup.

10. Failure to comply with Contract Documents.

11. Liquidated damages.

12. Legally permitted penalties.

D. The City may apply such withheld amount or amounts to payment of such claims or obligations at its discretion with the exception of subsections (B)(1), (3), and (5) of this Article, which must be retained or applied in accordance with applicable law. In so doing, the City shall be deemed the agent of Contractor and any payment so made by the City shall be considered as a payment made under contract by the City to Contractor and the City shall not be liable to Contractor for such payments made in good faith. Such payments may be made without prior judicial determination of claim or obligations. The City will render Contractor a proper accounting of such funds disbursed on behalf of Contractor.

E. Upon receipt, the Engineer shall review the payment request to determine whether it is undisputed and suitable for payment. If the payment request is determined to be unsuitable for payment, it shall be returned to Contractor as soon as practicable but not later than seven (7) Days after receipt, accompanied by a document setting forth in writing the reasons why the payment request is not proper. The City shall make the progress payment within 30 calendar days after the receipt of an undisputed and properly submitted payment request from Contractor, provided that a release of liens and claims has been received from the Contractor pursuant to Civil Code section 8132. The number of days available to the City to make a payment without incurring interest pursuant to this paragraph shall be reduced by the number of days by which the Engineer exceeds the seven (7) Day requirement.

F. A payment request shall be considered properly executed if funds are available for payment of the payment request and payment is not delayed due to an audit inquiry by the financial officer of the City.

ARTICLE 41 SECURITIES FOR MONEY WITHHELD
Pursuant to section 22300 of the Public Contract Code of the State of California, Contractor may request the City to make retention payments directly to an escrow agent or may substitute securities for any money withheld by the City to ensure performance under the contract. At the request and expense of Contractor, securities equivalent to the amount withheld shall be deposited with the City or with a state or federally chartered bank as the escrow agent who shall return such securities to Contractor upon satisfactory completion of the contract. Deposit of securities with an escrow agent shall be subject to a written agreement substantially in the form provided in section 22300 of the Public Contract Code.
38077.00180\29080232.10
-80- 00 72 13 – GENERAL CONDITIONS
ARTICLE 42 CHANGES AND EXTRA WORK.

A. Contract Change Orders.

1. The City, without invalidating the Contract, may order changes in the Work consisting of additions, deletions or other revisions, and the Contract Price and Contract Time shall be adjusted accordingly. Except as otherwise provided herein, all such changes in the Work shall be authorized by Change Order, and shall be performed under the applicable conditions of the Contract Documents. A Change Order signed by the Contractor indicates the Contractor's agreement therewith, including any adjustment in the Contract Price or the Contract Time, and the full and final settlement of all costs (direct, indirect and overhead) related to the Work authorized by the Change Order.

2. Contractor shall promptly execute changes in the Work as directed in writing by the City even when the parties have not reached agreement on whether the change increases the scope of Work or affects the Contract Price or Contract Time. All claims for additional compensation shall be presented in writing. No claim will be considered after the Work in question has been completed unless a written Change Order has been issued or a timely written notice of claim has been made by Contractor.

3. Whenever any change is made as provided for herein, such change shall be considered and treated as though originally included in the Contract, and shall be subject to all terms, conditions, and provisions of the original Contract.

4. Contractor shall not be entitled to claim or bring suit for damages, whether for loss of profits or otherwise, on account of any decrease or omission of any item or portion of Work to be done.

5. No dispute, disagreement, or failure of the parties to reach agreement on the terms of the Change Order shall relieve the Contractor from the obligation to proceed with performance of the work, including Additional Work, promptly and expeditiously.

6. Contractor shall make available to the City any of the Contractor’s documents related to the Project immediately upon request of the City, as set forth in Article 52.

7. Any alterations, extensions of time, Additional Work, or any other changes may be made without securing consent of the Contractor’s surety or sureties.

B. Contract Price Change.

1. Process for Determining Adjustments in Contract Price. a. Owner Initiated Change. The Contractor must submit a complete cost proposal, including any change in the Contract Price or 38077.00180\29080232.10
-81- 00 72 13 – GENERAL CONDITIONS
Contract Time, within seven (7) Days after receipt of a scope of a proposed change order initiated by the City, unless the City requests that proposals be submitted in less than seven (7) Days. b. Contractor Initiated Change. The Contractor must give written notice of a proposed change order required for compliance with the Contract Documents within seven (7) Days of discovery of the facts giving rise to the proposed change order.
c. Whenever possible, any changes to the Contract amount shall be in a lump sum mutually agreed to by the Contractor and the City. d. Price quotations from the Contractor shall be accompanied by sufficiently detailed supporting documentation to permit verification by the City, including but not limited to estimates and quotations from subcontractors or material suppliers, as the City may reasonably request. Contractor shall certify the accuracy of all Change Order Requests under penalty of perjury.
e. If the Contractor fails to submit a complete cost proposal within the seven (7) Day period (or as requested), the City has the right to order the Contractor in writing to commence the Work immediately on a time and materials basis and/or issue a lump sum change to the Contract Price and/or Contract Time in accordance with the City’s estimate. If the change is issued based on the City's estimate, the Contractor will waive its right to dispute the action unless within fifteen (15) Days following completion of the added/deleted work, the Contractor presents written proof that the City’s estimate was in error.

2. Unit Price Change Orders.
a. When the actual quantity of a Unit Price item is found to vary from the Bid Form, compensation for the change in quantity will be calculated by multiplying the actual quantity by the Unit Price.

This calculation may result in either an additive or deductive Final Change Order pursuant to the Contract Documents. Contractor shall immediately inform the Engineer when the actual quanities vary from estimated quantities.
b. No Mark up for Overhead and Profit. Because the Contract Unit Prices provided in the Bid Form include Overhead and Profit as determined by Contractor at the time of Bid submission, no mark up or deduction for Overhead and Profit will be included in Unit Price Change Orders.
c. Bid items included on the Bid Form may be deducted from the Work in their entirety without any negotiated extra costs. d. Contractor acknowledges that unit quantities are estimates and agrees that the estimated unit quantities listed on the Bid Form will 38077.00180\29080232.10
-82- 00 72 13 – GENERAL CONDITIONS
be adjusted to reflect the actual unit quantities which may result in an adjustment to the Contract Unit Prices. Such an adjustment will be made by execution of a final additive or deductive Change Order following Contractor’s completion of the Work. Upon notification, Contractor’s failure to respond within seven (7) Days will result in City’s issuance of a unit quantity adjustment to the Contract Unit Prices and/or Contract Time in accordance with the Contract Documents.

3. Lump Sum Change Orders. Compensation for Lump Sum Change Orders shall be limited to expenditures necessitated specifically by the Additional Work, and shall be segregated as follows:
a. Labor. The costs of labor will be the actual cost for wages prevailing locally for each craft or type of worker at the time the Additional Work is done, plus employer payments of payroll taxes and insurance, health and welfare, pension, vacation,
apprenticeship funds, and other direct costs resulting from Federal, State or local laws, as well as assessment or benefits required by lawful collective bargaining agreements. The use of a labor classification which would increase the Additional Work cost will not be permitted unless the Contractor establishes the necessity for such new classifications. Labor costs for equipment operators and helpers shall be reported only when such costs are not included in the invoice for equipment rental.
b. Materials. The cost of materials reported shall be at invoice or lowest current price at which such materials are locally available in the quantities involved, plus sales tax, freight, and delivery.

Materials costs shall be based upon supplier or manufacturer’s invoice. If invoices or other satisfactory evidence of cost are not furnished within fifteen (15) Days of delivery, then the City shall determine the materials cost, at its sole discretion.
c. Tool and Equipment Use. Costs for the use of small tools, which are tools that have a replacement value of $1,000 or less, shall be considered included in the Overhead and Profit mark-ups established below. Regardless of ownership, the rates to be used in determining equipment use costs shall not exceed listed rates prevailing locally at equipment rental agencies, or distributors, at the time the Work is performed.

4. Time and Materials Change Orders.
a. General. The term Time and Materials means the sum of all costs reasonably and necessarily incurred and paid by Contractor for labor, materials, and equipment in the proper performance of Additional Work. Except as otherwise may be agreed to in writing by the City, such costs shall be in amounts no higher than those prevailing in the locality of the Project, and shall include only the following items.
38077.00180\29080232.10
-83- 00 72 13 – GENERAL CONDITIONS
b. Timely and Final Documentation.
i. T&M Daily Sheets. Contractor must submit timesheets, materials invoices, records of equipment hours, and
records of rental equipment hours to the City’s
Representative for an approval signature each day
Additional Work is performed. Failure to get the City’s Representative’s approval signature each Day shall result in a waiver of Contractor’s right to claim these costs. The City’s Representative’s signature on time sheets only
serves as verification that the Work was performed and is not indicative of City’s agreement to Contractor’s
entitlement to the cost.
ii. T&M Daily Summary Sheets. All documentation of
incurred costs (“T&M Daily Summary Sheets”) shall be
submitted by Contractor within three (3) Days of incurring the cost for labor, material, equipment, and special
services as Additional Work is performed. Contractor’s
actual costs shall be presented in a summary table in an electronic spreadsheet file by labor, material, equipment, and special services. Each T&M Daily Summary Sheet
shall include Contractor’s actual costs incurred for the Additional Work performed that day and a cumulative total of Contractor’s actual costs incurred for the Additional Work. Contractor’s failure to provide a T&M Daily
Summary Sheet showing a total cost summary within three (3) Days but within five (5) Days of performance of the Work will result in the Contractor’s otherwise allowable overhead and profit being reduced by 50% for that portion of Additional Work which was not documented in a timely manner. Contractor’s failure to submit the T&M Daily
Summary Sheet within five (5) Days of performance of the Work will result in a total waiver of Contractor’s right to claim these costs.
iii. T&M Total Cost Summary Sheet. Contractor shall submit a T&M Total Cost Summary Sheet, which shall include
total actual costs, within seven (7) Days following
completion of City approved Additional Work. Contractor’s total actual cost shall be presented in a summary table in an electronic spreadsheet file by labor, material,
equipment, and special services. Contractor’s failure to submit the T&M Total Cost Summary Sheet within seven
(7) Days of completion of the Additional Work will result in Contractor’s waiver for any reimbursement of any costs
associated with the T&M Summary Sheets or the
performance of the Additional Work.
c. Labor. The Contractor will be paid the cost of labor for the workers used in the actual and direct performance of the Work. 38077.00180\29080232.10
-84- 00 72 13 – GENERAL CONDITIONS
The cost of labor will be the sum of the actual wages paid (which shall include any employer payments to or on behalf of the workers for health and welfare, pension, vacation, and similar purposes) substantiated by timesheets and certified payroll for wages prevailing for each craft or type of workers performing the Additional Work at the time the Additional Work is done, and the labor surcharge set forth in the Department of Transportation publication entitled Labor Surcharge and Equipment Rental Rates, which is in effect on the date upon which the Work is
accomplished and which is a part of the Contract. The labor surcharge shall constitute full compensation for all payments imposed by Federal, State, or local laws and for all other payments made to, or on behalf of, the workers, other than actual wages.
i. Equipment Operator Exception. Labor costs for equipment operators and helpers shall be paid only when such costs are not included in the invoice for equipment rental.
ii. Foreman Exception. The labor costs for foremen shall be proportioned to all of their assigned work and only that applicable to the Additional Work shall be paid. Indirect labor costs, including, without limitation, the
superintendent, project manager, and other labor identified in the Contract Documents will be considered Overhead.
d. Materials. The cost of materials reported shall be itemized at invoice or lowest current price at which materials are locally available and delivered to the Project site in the quantities involved, plus the cost of sales tax, freight, delivery, and storage. i. Trade discounts available to the purchaser shall be
credited to the City notwithstanding the fact that such discounts may not have been taken by Contractor.
ii. For materials secured by other than a direct purchase and direct billing to the purchaser, the cost shall be deemed to be the price paid to the actual supplier as determined by the City’s Representative.
iii. Payment for materials from sources owned wholly or in part by the purchaser shall not exceed the price paid by the purchaser for similar materials from said sources on Additional Work items or the current wholesale price for such materials delivered to the Project site, whichever price is lower.
iv. If, in the opinion of the City’s Representative, the cost of materials is excessive, or Contractor does not furnish
satisfactory evidence of the cost of such materials, then the cost shall be deemed to be the lowest current
38077.00180\29080232.10
-85- 00 72 13 – GENERAL CONDITIONS
wholesale price for the total quantity concerned delivered to the Project site less trade discounts.
v. The City reserves the right to furnish materials for the Additional Work and no Claim shall be allowed by
Contractor for costs of such materials or Indirect Costs or profit on City furnished materials.
e. Equipment.
i. Rental Time. The rental time to be paid for equipment on the Project site shall be the time the equipment is in
productive operation on the Additional Work being
performed and, in addition, shall include the time required to move the equipment to the location of the Additional Work and return it to the original location or to another location requiring no more time than that required to return it to its original location; except that moving time will not be paid if the equipment is used on other than the Additional Work, even though located at the site of the Additional Work.
(a) Rental Time Not Allowed. Rental time will not be
allowed while equipment is inoperative due to
breakdowns.
(b) Computation Method. The following shall be used
in computing the rental time of equipment on the
Project site.
(i) When hourly rates are paid, any part of an
hour less than 30 minutes of operation shall
be considered to be 1/2-hour of operation,
and any part of an hour in excess of 30
minutes will be considered one hour of
operation.
(ii) When daily rates are paid, any part of a day
less than 4 hours operation shall be
considered to be 1/2-day of operation, and
any part of an hour in excess of 4 hours will
be considered one day of operation.
ii. Rental Rates. Contractor will be paid for the use of equipment at the lesser of (i) the actual rental rate, or (ii) the rental rate listed for that equipment in the California Department of Transportation publication entitled Labor Surcharge and Equipment Rental Rates, which is in effect on the date upon which the Contract was executed. Such
rental rates will be used to compute payments for
equipment whether the equipment is under Contractor’s
38077.00180\29080232.10
-86- 00 72 13 – GENERAL CONDITIONS
control through direct ownership, leasing, renting, or
another method of acquisition. The rental rate to be
applied for use of each item of equipment shall be the rate (i.e., daily, monthly) resulting in the least total cost to the City for the total period of use. If it is deemed necessary by Contractor to use equipment not listed in the
publication, an equitable rental rate for the equipment will be established by the City’s Representative. Contractor may furnish cost data which might assist the City’s
Representative in the establishment of the rental rate. iii. Contractor-Owned Equipment.
(a) For Contractor-owned equipment, the allowed
equipment rental rate will be limited to the monthly
equipment rental rate using a utilization rate of 173
hours per month.
(b) For Contractor-owned equipment, the rental time to
be paid for equipment on the Site shall be the time
the equipment is in productive operation, unless, in
the instance of standby time, the equipment could
be actively used by Contractor on another project,
then City shall pay for the entirety of the time the
equipment is on Site. It shall be Contractor’s
burden to demonstrate to the City that the
equipment could be actively used on another
project.
(i) All equipment shall, in the opinion of the
City’s Representative, be in good working
condition and suitable for the purpose for
which the equipment is to be used.
(ii) Before construction equipment is used on
the Additional Work, Contractor shall plainly
stencil or stamp an identifying number
thereon at a conspicuous location, and shall
furnish to the City’s Representative, in
duplicate, a description of the equipment
and its identifying number and the
scheduled Additional Work activities
planned.
(iii) Unless otherwise specified, manufacturer’s
rating and manufacturer approved
modifications shall be used to classify
equipment for the determination of
applicable rental rates. Equipment which
has no direct power unit shall be powered
38077.00180\29080232.10
-87- 00 72 13 – GENERAL CONDITIONS
by a unit of at least the minimum rating
recommended by the manufacturer.
f. Special Services. Special work or services are defined as that Additional Work characterized by extraordinary complexity, sophistication, or innovation or a combination of the foregoing attributes which are unique to the construction industry. i. Invoices for Special Services. When the City’s
Representative and Contractor determine that a special
service is required which cannot be performed by the
forces of Contractor or those of any of its Subcontractors, the special service may be performed by an entity
especially skilled in the Additional Work. Invoices for special services based upon the current fair market value thereof may be accepted without complete itemization of labor, material, and equipment rental costs, after validation of market values by the City’s Representative.
ii. Discount and Allowance. All invoices for special services will be adjusted by deducting all trade discounts offered or available, whether the discounts were taken or not. In lieu of Overhead and Profit specified herein, a total allowance not to exceed fifteen percent (15%) for Overhead and
Profit will be added to invoices for Special Services.
iii. When the City determines, in its sole discretion, that competitive bidding is necessary for certain special
services, Contractor shall solicit competitive bids for those special services.
g. Excluded Costs. The term Time and Material shall not include any of the following costs or any other home or field office overhead costs, all of which are to be considered administrative costs covered by Contractor’s allowance for Overhead and Profit. i. Overhead Cost. Payroll costs and other compensation of Contractor’s officers, executives, principals, general
managers, engineers, architects, estimators, attorneys, auditors, accountants, purchasing and contracting agents, timekeepers, clerks, and other personnel employed by
Contractor whether at the Site or in Contractor’s principal office or any branch office, material yard, or shop for general administration of the Additional Work;
ii. Office Expenses. Expenses of Contractor’s principal and branch offices;
iii. Capital Expenses. Any part of Contractor’s capital expenses, including interest on Contractor’s capital
38077.00180\29080232.10
-88- 00 72 13 – GENERAL CONDITIONS
employed for the Additional Work and charges against
Contractor for delinquent payments;
iv. Negligence. Costs due to the negligence of Contractor or any Subcontractor or Supplier, or anyone directly or
indirectly employed by any of them or for whose acts any of them may be liable, including without limitation the correction of Defective Work, disposal of materials or
equipment wrongly supplied, and making good any
damage to property;
v. Other. Other overhead or general expense costs of any kind and the cost of any item not specifically and expressly included in the Contract Documents;
vi. Small Tools. Cost of small tools valued at less than $1,000 and that remain the property of Contractor;
vii. Administrative Costs. Costs associated with the
preparation of Change Orders (whether or not ultimately authorized), cost estimates, or the preparation or filing of Claims;
viii. Anticipated Lost Profits. Expenses of Contractor
associated with anticipated lost profits or lost revenues, lost income or earnings, lost interest on earnings, or
unpaid retention;
ix. Home Office Overhead. Costs derived from the
computation of a “home office overhead” rate by
application of the Eichleay, Allegheny, burden fluctuation, or other similar methods;
x. Special Consultants and Attorneys. Costs of special
consultants or attorneys, whether or not in the direct
employ of Contractor, employed for services specifically related to the resolution of a Claim, dispute, or other matter arising out of or relating to the performance of the
Additional Work.
h. Overhead, Profit and Other Charges. The mark-up for overhead (including supervision) and profit on work added to the Contract shall be according to the following:
i. “Net Cost” is defined as consisting of costs of labor, materials, and tools and equipment only excluding
overhead and profit. The costs of applicable insurance
and bond premium will be reimbursed to the Contractor
and subcontractors at cost only, without mark-up.

Contractor shall provide City with documentation of the costs, including, but not limited to, payroll records,
38077.00180\29080232.10
-89- 00 72 13 – GENERAL CONDITIONS
invoices, and such other information as City may
reasonably request.
ii. For Work performed by the Contractor’s forces, the added cost for overhead and profit shall not exceed fifteen
percent (15%) of the Net Cost of the Work.
iii. For Work performed by a subcontractor, the added cost for overhead and profit shall not exceed fifteen percent (15%) of the subcontractor’s Net Cost of the Work to which the Contractor may add five percent (5%) of the
subcontractor’s Net Cost.
iv. For Work performed by a sub-subcontractor, the added cost for overhead and profit shall not exceed fifteen
percent (15%) of the sub-subcontractor’s Net Cost for
Work to which the subcontractor and general contractor
may each add an additional five percent (5%) of the Net Cost of the lower tier subcontractor.
v. No additional mark-up will be allowed for lower tier subcontractors, and in no case shall the added cost for overhead and profit payable by City exceed twenty-five
percent (25%) of the Net Cost as defined herein, of the party that performs the Work.

5. All of the following costs are included in the markups for overhead and profit described above, and Contractor shall not receive any additional compensation for: Submittals, drawings, field drawings, Shop Drawings, including submissions of drawings; field inspection; General Superintendence; General administration and preparation of cost proposals, schedule analysis, Change Orders, and other supporting documentation; computer services; reproduction services; Salaries of project engineer, superintendent, timekeeper, storekeeper, and secretaries; Janitorial services; Small tools, incidentals and consumables; Temporary On-Site facilities (Offices, Telephones, High Speed Internet Access, Plumbing, Electrical Power, Lighting; Platforms, Fencing, Water), Jobsite and Home office overhead or other expenses; vehicles and fuel used for work otherwise included in the Contract Documents; Surveying; Estimating; Protection of Work; Handling and disposal fees; Final Cleanup; Other Incidental Work; Related Warranties; insurance and bond premiums.

6. For added or deducted Work by subcontractors, the Contractor shall furnish to the City the subcontractor’s signed detailed record of the cost of labor, material and equipment, including the subcontractor markup for overhead and profit. The same requirement shall apply to subsubcontractors 38077.00180\29080232.10
-90- 00 72 13 – GENERAL CONDITIONS

7. For added or deducted work furnished by a vendor or supplier, the Contractor shall furnish to the City a detailed record of the cost to the Contractor, signed by such vendor or supplier.

8. Any change in the Work involving both additions and deletions shall indicate a net total cost, including subcontracts and materials. Allowance for overhead and profit, as specified herein, shall be applied if the net total cost is an increase in the Contract Price; overhead and profit allowances shall not be applied if the net total cost is a deduction to the Contract Price. The estimated cost of deductions shall be based on labor and material prices on the date the Contract was executed.

9. Contractor shall not reserve a right to assert impact costs, extended job site costs, extended overhead, constructive acceleration and/or actual acceleration beyond what is stated in the Change Order for Work. No claims shall be allowed for impact, extended overhead costs, constructive acceleration and/or actual acceleration due to a multiplicity of changes and/or clarifications. The Contractor may not change or modify the City’s change order form in an attempt to reserve additional rights.

10. If the City disagrees with the proposal submitted by Contractor, it will notify the Contractor and the City will provide its opinion of the appropriate price and/or time extension. If the Contractor agrees with the City, a Change Order will be issued by the City. If no agreement can be reached, the City shall have the right to issue a unilateral Change Order setting forth its determination of the reasonable additions or savings in costs and time attributable to the extra or deleted work. Such determination shall become final and binding if the Contractor fails to submit a claim in writing to the City within fifteen (15) Days of the issuance of the unilateral Change Order, disputing the terms of the unilateral Change Order, and providing such supporting documentation for its position as the City may require.

C. Change of Contract Times.

1. The Contract Times may only be changed by a Change Order.

2. All changes in the Contract Price and/or adjustments to the Contract Times related to each change shall be included in Contractor’s COR pursuant to this Article. No cost or time will be allowed for cumulative effects of multiple changes. All Change Orders must state that the Contract Time is not changed or is either increased or decreased by a specific number of days. Failure to include a change to time shall waive any change to the time unless the parties mutually agree in writing to postpone a determination of the change to time resulting from the Change Order.

3. Notice of the amount of the request for adjustment in the Contract Times with supporting data shall be delivered within seven (7) Days after such start of occurrence, unless City’s Representative allows an additional period of time to ascertain more accurate data in support of the request. 38077.00180\29080232.10
-91- 00 72 13 – GENERAL CONDITIONS
No extension of time or additional compensation shall be given for a delay if the Contractor failed to give notice in the manner and within the time prescribed.

4. City may elect, at City’s sole discretion, to grant an extension in Contract Times, without Contractor’s request, because of delays or other factors.

5. Use of Float and Critical Path.
a. Float is for the benefit of the Project. Float shall not be considered for the exclusive use or benefit of either the City or the Contractor. b. Contractor shall not be entitled to compensation, and City will not compensate Contractor, for delays which impact early completion.

Any difference in time between the Contractor’s early completion and the Contract Time shall be considered a part of the Project float.

6. Contractor’s entitlement to an extension of the Contract Times is limited to a City-caused extension of the critical path, reduced by the Contractor’s concurrent delays, and established by a proper time impact analysis. No time extension shall be allowed unless, and then only to the extent that, the City-caused delay extends the critical path beyond the previously approved Contract Time. If approved, the increase in time required to complete the Work shall be added to the Contract Time. a. Contractor shall not be entitled to an adjustment in the Contract Price or Contract Times for delays within the control of Contractor.

Delays attributable to and within the control of a Subcontractor or Supplier shall be deemed to be delays within the control of Contractor.
b. If Contractor is delayed in the performance or progress of the Work by fire, flood, epidemic, abnormal weather conditions (as determined by the City), Acts of God, acts or failures to act of utility owners not under the control of City, or other causes not the fault of and beyond control of City and Contractor, then Contractor shall be entitled to an time extension when the Work stopped is on the critical path. Such a non-compensable adjustment shall be Contractor’s sole and exclusive remedy for such delays.

Contractor must submit a timely request in accordance with the requirements of this Article.
c. Utility-Related Delays.
i. Contractor shall immediately notify in writing the utility owner and City’s Representative of its construction
schedule and any subsequent changes in the construction schedule which will affect the time available for protection, removal, or relocation of utilities. Requests for extensions 38077.00180\29080232.10
-92- 00 72 13 – GENERAL CONDITIONS
of time arising out of utility relocation or repair delays shall be filed in accordance with this Article.
ii. Contractor shall not be entitled to damages or additional payment for delays attributable to utility relocations or alterations if correctly located, as noted in the Contract Documents or by the Underground Service Alert survey.

7. Content for Requests for Contract Extension. Contractor’s justification for entitlement shall be clear and complete citing specific Contract Document references and reasons on which Contractor’s entitlement is based. At a minimum, each request for a time extension must include:
a. Each request for an extension of Contract Time must identify the impacting event, in narrative form, providing a description of the delay event and sufficient justification as to why the Contractor is entitled to a time extension. Contractor must demonstrate that the delay arises from unforeseeable causes beyond the control and without the fault or negligence of both Contractor and any Subcontractors or Suppliers, or any other persons or
organizations employed by any of them or for whose acts any of them may be liable, and that such causes in fact lead to performance or completion of the Work, or specified part in question, beyond the corresponding Contract Times, despite Contractor’s reasonable and diligent actions to guard against those effects.
b. Each request for an extension of Contract Time must include a time impact analysis in CPM format, using the Contemporaneous Impacted As-Planned Schedule Analysis to calculate the impact of the delay event.

8. No Damages for Reasonable Delay.
a. City’s liability to Contractor for delays for which City is responsible shall be limited to only an extension of time unless such delays were unreasonable under the circumstances. In no case shall City be liable for any costs which are borne by the Contractor in the regular course of business, including, but not limited to, home office overhead and other ongoing costs.
b. City and City’s Representative, and the officers, members, partners, employees, agents, consultants, or subcontractors of each of them, shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other
professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project.
38077.00180\29080232.10
-93- 00 72 13 – GENERAL CONDITIONS

9. Contractor’s failure, neglect, or refusal to comply with the requirements of the Contract Documents, or any portion thereof, shall bar Contractor’s request for extensions of the Contract Times. Such failure, neglect, or refusal prejudices City’s and City’s Representative’s ability to recognize and mitigate delay, and such failure, neglect, or refusal prevent the timely analysis of requests for extensions of Contract Times, and whether such extensions may be warranted. Contractor hereby waives all rights to extensions of Contract Times due to delays or accelerations that result from or occur during periods of time for which Contractor fails, neglects, or refuses to fully comply with the requirements of this Article.

10. Contractors submission of daily construction reports and schedule updates in accordance with these Contract Documents is required for the evaluation of the merits of time extension request. Failure of the Contractor to submit daily construction reports and schedule updates shall constitute a waiver of its right to seek a time extension or additional compensation.

ARTICLE 43 FINAL ACCEPTANCE AND PAYMENT
A. Final Inspection. Upon written notice from Contractor that the entire Work is complete, the Engineer will promptly make a final inspection and will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies.

B. Final Acceptance. After Contractor has, in the opinion of the Engineer, satisfactorily completed all corrections identified during the final inspection and has delivered, in accordance with the Contract Documents, all maintenance and operating instructions, schedules, guarantees, bonds, certificates or other evidence of insurance, certificates of inspection, marked-up record documents (as-builts), and other documents required by the Contract Documents, the City shall execute and file with the County in which the Project is located a Notice of Completion, constituting final acceptance and completion of the Project, except as may be expressly noted.

C. Final Payment.

1. Application for Payment. Upon execution of the Notice of Completion, Contractor may make application for final payment following the procedure for progress payments. The final application for payment shall be accompanied (except as previously delivered) by: all documentation called for in the Contract Documents, including but not limited to a fully completed Conditional Waiver and Release on Final Payment

2. City’s Review of Application and Acceptance. If, on the basis of the City’s observation of the Work during construction and final inspection, and review of the final Application for Payment and accompanying documentation as required by the Contract Documents, the City is satisfied that the Work has been completed and Contractor has satisfied all other requirements for final payment, the City will process the final 38077.00180\29080232.10
-94- 00 72 13 – GENERAL CONDITIONS
payment appllication. Otherwise, the City will return the payment application to Contractor, indicating in writing the reasons for refusing to recommend final payment, in which case Contractor shall make the necessary corrections and resubmit the application for payment.

3. Payment Becomes Due. Within sixty (60) Days after the presentation to the City of the proper and complete final application for payment and accompanying documentation, the amount recommended by the Engineer, less any sum the City is entitled to set off pursuant to the Contract Documents, will become due and will be paid by the City to Contractor.

D. Waiver of Claims. The making and acceptance of final payment will constitute a waiver of all Claims by Contractor against the City other than those previously made in accordance with the requirements herein and expressly acknowledged by the City in writing as still unsettled.

ARTICLE 44 OCCUPANCY
The City reserves the right to occupy or utilize any portion of the Work at any time before completion, and such occupancy or use shall not constitute acceptance of any part of Work covered by this Contract.This use shall not relieve the Contractor of its responsibilities under the Contract.

ARTICLE 45 INDEMNIFICATION
To the fullest extent permitted by law, Contractor shall immediately defend (with counsel of the City’s choosing), indemnify and hold harmless the City, officials, officers, agents, employees, and representatives, and each of them from and against:

A. Any and all claims, demands, causes of action, costs, expenses, injuries, losses or liabilities, in law or in equity, of every kind or nature whatsoever, but not limited to, injury to or death, including wrongful death, of any person, and damages to or destruction of property of any person, arising out of, related to, or in any manner directly or indirectly connected with the Work or this Contract, including claims made by subcontractors for nonpayment, including without limitation the payment of all consequential damages and attorney’s fees and other related costs and expenses, however caused, regardless of whether the allegations are false, fraudulent, or groundless, and regardless of any negligence of the City or its officers, employees, or authorized volunteers (including passive negligence), except the sole negligence or willful misconduct or active negligence of the City or its officials, officers, employees, or authorized volunteers.

B. Contractor’s defense and indemnity obligation herein includes, but is not limited to damages, fines, penalties, attorney’s fees and costs arising from claims under the Americans with Disabilities Act (ADA) or other federal or state disability access or discrimination laws arising from Contractor’s Work during the course of construction of the improvements or after the Work is complete, as the result of defects or negligence in Contractor’s construction of the improvements. 38077.00180\29080232.10
-95- 00 72 13 – GENERAL CONDITIONS
C. Any and all actions, proceedings, damages, costs, expenses, fines, penalties or liabilities, in law or equity, of every kind or nature whatsoever, arising out of, resulting from, or on account of the violation of any governmental law or regulation, compliance with which is the responsibility of Contractor; D. Any and all losses, expenses, damages (including damages to the Work itself), attorney’s fees, and other costs, including all costs of defense which any of them may incur with respect to the failure, neglect, or refusal of Contractor to faithfully perform the Work and all of Contractor’s obligations under the agreement. Such costs, expenses, and damages shall include all costs, including attorney’s fees, incurred by the indemnified parties in any lawsuit to which they are a party.

Contractor shall immediately defend, at Contractor’s own cost, expense and risk, with the City Council’s choosing, any and all such aforesaid suits, actions or other legal proceedings of every kind that may be brought or instituted against the City, its officials, officers, agents, employees and representatives. Contractor shall pay and satisfy any judgment, award or decree that may be rendered against the City, its officials, officers, employees, agents, employees and representatives, in any such suit, action or other legal proceeding. Contractor shall reimburse the City, its officials, officers, agents, employees and representatives for any and all legal expenses and costs incurred by each of them in connection therewith or in enforcing the indemnity herein provided. The only limitations on this provision shall be those imposed by Civil Code section 2782.

ARTICLE 46 PROCEDURE FOR RESOLVING DISPUTES
Contractor shall timely comply with all notices and requests for changes to the Contract Time or Contract Price, including but not limited to all requirements of Article 42, Changes and Extra Work, as a prerequisite to filing any claim governed by this Article. The failure to timely submit a notice of delay or notice of change, or to timely request a change to the Contract Price or Contract Time, or to timely provide any other notice or request required herein shall constitute a waiver of the right to further pursue the claim under the Contract or at law.

A. Intent. Effective January 1, 1991, Section 20104 et seq., of the California Public Contract Code prescribes a process utilizing informal conferences, non-binding judicial supervised mediation, and judicial arbitration to resolve disputes on construction claims of $375,000 or less. Effective January 1, 2017, Section 9204 of the Public Contract Code prescribes a process for negotiation and mediation to resolve disputes on construction claims. The intent of this Article is to implement Sections 20104 et seq. and Section 9204 of the California Public Contract Code.

This Article shall be construed to be consistent with said statutes.

B. Claims. For purposes of this Article, “Claim” means a separate demand by the Contractor, after a change order duly requested in accordance with Article 42 “Changes and Extra Work” has been denied by the City, for (A) a time extension, (B) payment of money or damages arising from Work done by or on behalf of the Contractor pursuant to the Contract, or (C) an amount the payment of which is disputed by the City. Claims governed by this Article may not be filed unless and until the Contractor completes all procedures for giving notice of delay or change and for the requesting of a time extension or change order, including but not necessarily limited to the procedures contained in Article 42, Changes and Extra Work, and Contractor’s request for a change has been denied in whole or in part. Claims 38077.00180\29080232.10
-96- 00 72 13 – GENERAL CONDITIONS
governed by this Article must be filed no later than the date of final payment. The claim shall be submitted in writing to the City and shall include on its first page the following in 16 point capital font: “THIS IS A CLAIM.” Furthermore, the claim shall include the documents necessary to substantiate the claim. Nothing herein is intended to extend the time limit or supersede notice requirements otherwise provided by contract for the filing of claims, including all requirements pertaining to compensation or payment for extra Work, disputed Work, and/or changed conditions.

Failure to follow such contractual requirements shall bar any claims or subsequent lawsuits for compensation or payment thereon.

C. Supporting Documentation. The Contractor shall submit all claims in the following format:

1. Summary of claim merit and price, reference Contract Document provisions pursuant to which the claim is made

2. List of documents relating to claim:

Specifications
Drawings
Clarifications (Requests for Information)
Schedules
Other

3. Chronology of events and correspondence

4. Analysis of claim merit

5. Analysis of claim cost

6. Time Impact Analysis in CPM format
D. City’s Response. Upon receipt of a claim pursuant to this Article, City shall conduct a reasonable review of the claim and, within a period not to exceed 45 Days, shall provide the Contractor a written statement identifying what portion of the claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of the claim will be processed and made within 60 Days after the City issues its written statement.

1. If the City needs approval from its governing body to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the claim, and the City’s governing body does not meet within the 45 Days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the City shall have up to three Days following the next duly publicly noticed meeting of the City’s governing body after the 45-Day period, or extension, expires to provide the 38077.00180\29080232.10
-97- 00 72 13 – GENERAL CONDITIONS
Contractor a written statement identifying the disputed portion and the undisputed portion.

2. Within 30 Days of receipt of a claim, the City may request in writing additional documentation supporting the claim or relating to defenses or claims the City may have against the Contractor. If additional information is thereafter required, it shall be requested and provided pursuant to this subdivision, upon mutual agreement of City and the Contractor. The City’s written response to the claim, as further documented, shall be submitted to the Contractor within 30 Days (if the claim is less than $15,000, within 15 Days) after receipt of the further documentation, or within a period of time no greater than that taken by the Contractor in producing the additional information or requested documentation, whichever is greater.

E. Meet and Confer. If the Contractor disputes the City’s written response, or the City fails to respond within the time prescribed, the Contractor may so notify the City, in writing, either within 15 Days of receipt of the City’s response or within 15 Days of the City’s failure to respond within the time prescribed, respectively, and demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand, the City shall schedule a meet and confer conference within 30 Days for settlement of the dispute.

F. Mediation. Within 10 business Days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the City shall provide the Contractor a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 Days after the City issues its written statement. Any disputed portion of the claim, as identified by the Contractor in writing, shall be submitted to nonbinding mediation, with the City and the Contractor sharing the associated costs equally. The City and Contractor shall mutually agree to a mediator within 10 business Days after the disputed portion of the claim has been identified in writing, unless the parties agree to select a mediator at a later time.

1. If the parties cannot agree upon a mediator, each party shall select a mediator and those mediators shall select a qualified neutral third party to mediate with regard to the disputed portion of the claim. Each party shall bear the fees and costs charged by its respective mediator in connection with the selection of the neutral mediator.

2. For purposes of this section, mediation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.

3. Unless otherwise agreed to by the City and the Contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Public Contract Code Section 20104.4 to mediate after litigation has been commenced.
38077.00180\29080232.10
-98- 00 72 13 – GENERAL CONDITIONS

4. The mediation shall be held no earlier than the date the Contractor completes the Work or the date that the Contractor last performs Work, whichever is earlier. All unresolved claims shall be considered jointly in a single mediation, unless a new unrelated claim arises after mediation is completed.

G. Procedures After Mediation. If following the mediation, the claim or any portion remains in dispute, the Contractor must file a claim pursuant to Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code prior to initiating litigation.

For purposes of those provisions, the running of the period of time within which a claim must be filed shall be tolled from the time the Contractor submits his or her written claim pursuant to subdivision (a) until the time the claim is denied, including any period of time utilized by the meet and confer conference.

H. Civil Actions. The following procedures are established for all civil actions filed to resolve claims of $375,000 or less:

1. Within 60 Days, but no earlier than 30 Days, following the filing or responsive pleadings, the court shall submit the matter to non-binding mediation unless waived by mutual stipulation of both parties or unless mediation was held prior to commencement of the action in accordance with Public Contract Code section 9204 and the terms of this Contract. The mediation process shall provide for the selection within 15 Days by both parties of a disinterested third person as mediator, shall be commenced within 30 Days of the submittal, and shall be concluded within 15 Days from the commencement of the mediation unless a time requirement is extended upon a good cause showing to the court.

2. If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section 1114.11 of that code. The Civil Discovery Act of 1986 (Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Part 4 of the Code of Civil Procedure) shall apply to any proceeding brought under this subdivision consistent with the rules pertaining to judicial arbitration. In addition to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, (A) arbitrators shall, when possible, be experienced in construction law, and (B) any party appealing an arbitration award who does not obtain a more favorable judgment shall, in addition to payment of costs and fees under that chapter, also pay the attorney’s fees on appeal of the other party.

I. Government Code Claims. In addition to any and all contract requirements pertaining to notices of and requests for compensation or payment for extra Work, disputed Work, construction claims and/or changed conditions, the Contractor must comply with the claim procedures set forth in Government Code Sections 900, et seq. prior to filing any lawsuit against the City. Such Government Code claims and any subsequent lawsuit based upon the Government Code claims shall be limited to those matters that remain unresolved after all procedures pertaining to extra Work, disputed Work, construction claims, and/or changed conditions have been followed by Contractor. If no such Government Code claim is submitted, or if the prerequisite contractual requirements are not satisfied, no action against the City may be filed. A Government Code claim must be filed no earlier than the date the Work is 38077.00180\29080232.10
-99- 00 72 13 – GENERAL CONDITIONS
completed or the date the Contractor last performs Work on the Project, whichever occurs first. A Government Code claim shall be inclusive of all unresolved claims unless a new unrelated claim arises after the Government Code claim is submitted.

J. Non-Waiver. The City’s failure to respond to a claim from the Contractor within the time periods described in this Article or to otherwise meet the time requirements of this Article shall result in the claim being deemed rejected in its entirety.

ARTICLE 47 CITY’S RIGHT TO TERMINATE CONTRACT
A. Termination for Cause by the City:

1. In the sole estimation of the City, if the Contractor refuses or fails to prosecute the Work or any separable part thereof with such diligence as will insure its completion within the time specified by the Contract Documents, or any extension thereof, or fails to complete such Work within such time, or if the Contractor should be adjudged a bankrupt, or if it should make a general assignment for the benefit of its creditors, or if a receiver should be appointed on account of its insolvency, or the Contractor or any of its subcontractors should violate any of the provisions of this Contract, the City may serve written notice upon the Contractor and its Surety of the City's intention to terminate this Contract.

This notice of intent to terminate shall contain the reasons for such intention to terminate this Contract, and a statement to the effect that the Contractor's right to perform this Contract shall cease and terminate upon the expiration of ten (10) calendar days unless such violations have ceased and arrangements satisfactory to the City have been made for correction of said violations.

2. In the event that the City serves such written notice of termination upon the Contractor and the Surety, the Surety shall have the right to take over and perform the Contract. If the Surety does not: (1) give the City written notice of Surety's intention to take over and commence performance of the Contract within 15 calendar days of the City's service of said notice of intent to terminate upon Surety; and (2) actually commence performance of the Contract within 30 calendar days of the City's service of said notice upon Surety; then the City may take over the Work and prosecute the same to completion by separate contract or by any other method it may deem advisable for the account and at the expense of the Contractor.

3. In the event that the City elects to obtain an alternative performance of the Contract as specified above: (1) the City may, without liability for so doing, take possession of and utilize in completion of the Work such materials, appliances, plants and other property belonging to the Contractor that are on the site and reasonably necessary for such completion (A special lien to secure the claims of the City in the event of such suspension is hereby created against any property of Contractor taken into the possession of the City under the terms hereof and such lien may be enforced by sale of such property under the direction of the City Council without notice to Contractor. The proceeds of the sale after 38077.00180\29080232.10
-100- 00 72 13 – GENERAL CONDITIONS
deducting all expenses thereof and connected therewith shall be credited to Contractor. If the net credits shall be in excess of the claims of the City against Contractor, the balance will be paid to Contractor or Contractor’s legal representatives.); and (2) Surety shall be liable to the City for any cost or other damage to the City necessitated by the City securing an alternate performance pursuant to this Article.

B. Termination for Convenience by the City:

1. The City may terminate performance of the Work called for by the Contract Documents in whole or, from time to time, in part, if the City determines that a termination is in the City's interest.

2. The Contractor shall terminate all or any part of the Work upon delivery to the Contractor of a Notice of Termination specifying that the termination is for the convenience of the City, the extent of termination, and the Effective Date of such termination.

3. After receipt of Notice of Termination, and except as directed by the City's Representative, the Contractor shall, regardless of any delay in determining or adjusting any amounts due under this Termination for Convenience clause, immediately proceed with the following obligations:
a. Stop Work as specified in the Notice.
b. Complete any Work specified in the Notice of Termination in a least cost/shortest time manner while still maintaining the quality called for under the Contract Documents.
c. Leave the property upon which the Contractor was working and upon which the facility (or facilities) forming the basis of the Contract Document is situated in a safe and sanitary manner such that it does not pose any threat to the public health or safety. d. Terminate all subcontracts to the extent that they relate to the portions of the Work terminated.
e. Place no further subcontracts or orders, except as necessary to complete the continued portion of the Contract.
f. Submit to the City's Representative, within ten (10) calendar days from the Effective Date of the Notice of Termination, all of the usual documentation called for by the Contract Documents to substantiate all costs incurred by the Contractor for labor, materials and equipment through the Effective Date of the Notice of Termination. Any documentation substantiating costs incurred by the Contractor solely as a result of the City's exercise of its right to terminate this Contract pursuant to this clause, which costs the contractor is authorized under the Contract documents to incur, shall: (1) be submitted to and received by the Engineer no later than 30 calendar days after the Effective Date of the Notice 38077.00180\29080232.10
-101- 00 72 13 – GENERAL CONDITIONS
of Termination; (2) describe the costs incurred with particularity; and (3) be conspicuously identified as “Termination Costs occasioned by the City's Termination for Convenience.”

4. Termination of the Contract shall not relieve Surety of its obligation for any just claims arising out of or relating to the Work performed.

5. In the event that the City exercises its right to terminate this Contract pursuant to this clause, the City shall pay the Contractor, upon the Contractor's submission of the documentation required by this clause and other applicable provisions of the Contract Documents, the following amounts:
a. All actual reimbursable costs incurred according to the provisions of this Contract.
b. A reasonable allowance for profit on the cost of the Work performed, provided Contractor establishes to the satisfaction of the City's Representative that it is reasonably probable that Contractor would have made a profit had the Contract been completed and provided further, that the profit allowed shall in no event exceed fifteen (15%) percent of the costs.
c. A reasonable allowance for Contractor's administrative costs in determining the amount payable due to termination of the Contract under this Article.

C. Notwithstanding any other provision of this Article, when immediate action is necessary to protect life and safety or to reduce significant exposure or liability, the City may immediately order Contractor to cease Work on the Project until such safety or liability issues are addressed to the satisfaction of the City or the Contract is terminated.

ARTICLE 48 WARRANTY AND GUARANTEE OF WORK
A. Contractor hereby warrants that materials and Work shall be completed in conformance with the Contract Documents and that the materials and Work provided will fulfill the requirements of this Warranty. Contractor hereby agrees to repair or replace, at the discretion of the City, any or all Work that may prove to be defective in its workmanship, materials furnished, methods of installation or fail to conform to the Contract Document requirements together with any other Work which may be damaged or displaced by such defect(s) within a period of one (1) year from the date of the Notice of Completion of the Project without any expense whatever to the City, ordinary wear and tear and unusual abuse and neglect excepted. Contractor shall be required to promptly repair or replace defective equipment or materials, at Contractor’s option. All costs associated with such corrective actions and testing, including the removal, replacement, and reinstitution of equipment and materials necessary to gain access, shall be the sole responsibility of the Contractor.
38077.00180\29080232.10
-102- 00 72 13 – GENERAL CONDITIONS
B. For any Work so corrected, Contractor’s obligation hereunder to correct defective Work shall be reinstated for an additional one (1) year period, commencing with the date of acceptance of such corrected Work. The reinstatement of the one (1) year warranty shall apply only to that portion of work that was corrected.

Contractor shall perform such tests as City may require to verify that any corrective actions, including, without limitation, redesign, repairs, and replacements comply with the requirements of the Contract. In the event of Contractor’s failure to comply with the above-mentioned conditions within ten (10) calendar days after being notified in writing of required repairs, to the reasonable satisfaction of the City, the City shall have the right to correct and replace any defective or non-conforming Work and any work damaged by such work or the replacement or correction thereof at Contractor’s sole expense.

Contractor shall be obligated to fully reimburse the City for any expenses incurred hereunder immediately upon demand.

C. In addition to the warranty set forth in this Article, Contractor shall obtain for City all warranties that would be given in normal commercial practice and assign to City any and all manufacturer’s or installer’s warranties for equipment or materials not manufactured by Contractor and provided as part of the Work, to the extent that such third-party warranties are assignable and extend beyond the warranty period set forth in this Article. Contractor shall furnish the City with all warranty and guarantee documents prior to final Acceptance of the Project by the City as required.

D. When specifically indicated in the Contract Documents or when directed by the Engineer, the City may furnish materials or products to the Contractor for installation. In the event any act or failure to act by Contractor shall cause a warranty applicable to any materials or products purchased by the City for installation by the Contractor to be voided or reduced, Contractor shall indemnify City from and against any cost, expense, or other liability arising therefrom, and shall be responsible to the City for the cost of any repairs, replacement or other costs that would have been covered by the warranty but for such act or failure to act by Contractor.

E. The Contractor shall remedy at its expense any damage to City-owned or controlled real or personal property.

F. The City shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or damage. The Contractor shall within ten (10) calendar days after being notified commence and perform with due diligence all necessary Work. If the Contractor fails to promptly remedy any defect, or damage; the City shall have the right to replace, repair or otherwise remedy the defect, or damage at the Contractor’s expense.

G. In the event of any emergency constituting an immediate hazard to health, safety, property, or licensees, when caused by Work of the Contractor not in accordance with the Contract requirements, the City may undertake at Contractor’s expense, and without prior notice, all Work necessary to correct such condition.

H. Acceptance of Defective Work.
38077.00180\29080232.10
-103- 00 72 13 – GENERAL CONDITIONS

1. If, instead of requiring correction or removal and replacement of Defective Work, the City prefers to accept it, City may do so. Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) attributable to City’s evaluation of and determination to accept such Defective Work and for the diminished value of the Work.

2. If any acceptance of defective work occurs prior to release of the Project Retention, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work, and City shall be entitled to an appropriate decrease in the Contract Price, reflecting the diminished value of Work and all costs incurred by City.

3. If the Project Retention is held in an escrow account as permitted by the Contract Documents, Contractor will promptly alert the escrow holder, in writing, of the amount of Retention to be paid to City.

4. If the acceptance of Defective Work occurs after release of the Project Retention, an appropriate amount will be paid by Contractor to City.

I. City May Correct Defective Work.

1. If Contractor fails within a reasonable time after written notice from City’s Representative to correct Defective Work, or to remove and replace rejected Work as required by City, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, City may, after seven (7) Days’ written notice to Contractor, correct, or remedy any such deficiency.

2. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor’s services related thereto, take possession of Contractor’s tools, appliances, construction equipment and machinery at the Site, and incorporate in the Work all materials and equipment stored at the Site or for which City has paid Contractor but which are stored elsewhere. Contractor shall allow City and City’s Representative, and the agents, employees, other contractors, and consultants of each of them, access to the Site to enable City to exercise the rights and remedies to correct the Defective Work.

3. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) incurred or sustained by City correcting the Defective Work will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions into the Contract Documents with respect to the Work; and City shall be entitled to an appropriate decrease in the Contract Price.
38077.00180\29080232.10
-104- 00 72 13 – GENERAL CONDITIONS

4. Such claims, costs, losses and damages will include, but not be limited to, all costs of repair, or replacement of work of others destroyed or damaged by correction, removal, or replacement of Defective Work.

5. If the Change Order is executed after all payments under the Contract have been paid by City and the Project Retention is held in an escrow account as permitted by the Contract Documents, Contractor will promptly alert the escrow holder, in writing, of the amount of Retention to be paid to City.

6. If the Change Order is executed after release of the Project Retention, an appropriate amount will be paid by Contractor to City.

7. Contractor shall not be allowed an extension of the Contract Times because of any delay in the performance of the Work attributable to City correcting Defective work.

J. Nothing in the Warranty or in the Contract Documents shall be construed to limit the rights and remedies available to City at law or in equity, including, but not limited to, Code of Civil Procedure section 337.15.

ARTICLE 49 DOCUMENT RETENTION & EXAMINATION
A. In accordance with Government Code section 8546.7, records of both the City and the Contractor shall be subject to examination and audit by the State Auditor General for a period of three (3) years after final payment.

B. Contractor shall make available to the City any of the Contractor’s other documents related to the Project immediately upon request of the City.

C. In addition to the State Auditor rights above, the City shall have the right to examine and audit all books, estimates, records, contracts, documents, bid documents, subcontracts, and other data of the Contractor (including computations and projections) related to negotiating, pricing, or performing the modification in order to evaluate the accuracy and completeness of the cost or pricing data at no additional cost to the City, for a period of four (4) years after final payment.

ARTICLE 50 SEPARATE CONTRACTS
A. The City reserves the right to let other contracts in connection with this Work or on the Project site. Contractor shall permit other contractors reasonable access and storage of their materials and execution of their work and shall properly connect and coordinate its Work with theirs.

B. To ensure proper execution of its subsequent Work, Contractor shall immediately inspect work already in place and shall at once report to the Engineer any problems with the Work in place or discrepancies with the Contract Documents.

C. Contractor shall ascertain to its own satisfaction the scope of the Project and nature of any other contracts that have been or may be awarded by the City in 38077.00180\29080232.10
-105- 00 72 13 – GENERAL CONDITIONS
prosecution of the Project to the end that Contractor may perform this Contract in the light of such other contracts, if any. Nothing herein contained shall be interpreted as granting to Contractor exclusive occupancy at site of the Project.

Contractor shall not cause any unnecessary hindrance or delay to any other contractor working on the Project. If simultaneous execution of any contract for the Project is likely to cause interference with performance of some other contract or contracts, the Engineer shall decide which Contractor shall cease Work temporarily and which contractor shall continue or whether work can be coordinated so that contractors may proceed simultaneously. The City shall not be responsible for any damages suffered or for extra costs incurred by Contractor resulting directly or indirectly from award, performance, or attempted performance of any other contract or contracts on the Project site.

ARTICLE 51 NOTICE AND SERVICE THEREOF
All notices shall be in writing and either served by personal delivery or mailed to the other party as designated in the Bid Forms. Written notice to the Contractor shall be addressed to Contractor’s principal place of business unless Contractor designates another address in writing for service of notice. Notice to City shall be addressed to the City as designated in the Notice Inviting Bids unless City designates another address in writing for service of notice. Notice shall be effective upon receipt or five (5) calendar days after being sent by first class mail, whichever is earlier. Notice given by facsimile shall not be effective unless acknowledged in writing by the receiving party.

ARTICLE 52 NOTICE OF THIRD PARTY CLAIMS
Pursuant to Public Contract Code section 9201, the City shall provide the Contractor with timely notification of the receipt of any third-party claims relating to the Contract. The City is entitled to recover reasonable costs incurred in providing such notification.

ARTICLE 53 STATE LICENSE BOARD NOTICE
Contractors are required by law to be licensed and regulated by the Contractors’ State License Board which has jurisdiction to investigate complaints against contractors if a complaint regarding a patent act or omission is filed within four (4) years of the date of the alleged violation. A complaint regarding a latent act or omission pertaining to structural defects must be filed within ten (10) years of the date of the alleged violation. Any questions concerning a contractor may be referred to the Registrar, Contractors’ State License Board, P.O. Box 26000, Sacramento, California 95826.

ARTICLE 54 INTEGRATION
A. Oral Modifications Ineffective. No oral order, objection, direction, claim or notice by any party or person shall affect or modify any of the terms or obligations contained in the Contract Documents.

B. Contract Documents Represent Entire Contract.The Contract Documents represent the entire agreement of the City and Contractor. 38077.00180\29080232.10
-106- 00 72 13 – GENERAL CONDITIONS
ARTICLE 55 ASSIGNMENT OF CONTRACT
Contractor shall not assign, transfer, convey, sublet or otherwise dispose of the rights or title of interest of any or all of this contract without the prior written consent of the City. Any assignment or change of Contractor’s name of legal entity without the written consent of the City shall be void. Any assignment of money due or to become due under this Contract shall be subject to a prior lien for services rendered or Material supplied for performance of Work called for under the Contract Documents in favor of all persons, firms, or corporations rendering such services or supplying such Materials to the extent that claims are filed pursuant to the Civil Code, the Code of Civil Procedure or the Government Code.

ARTICLE 56 CHANGE IN NAME AND NATURE OF CONTRACTOR’S LEGAL ENTITY
Should a change be contemplated in the name or nature of the Contractor’s legal entity, the Contractor shall first notify the City in order that proper steps may be taken to have the change reflected on the Contract and all related documents. No change of Contractor’s name or nature will affect City’s rights under the Contract, including but not limited to the bonds.

ARTICLE 57 ASSIGNMENT OF ANTITRUST ACTIONS
Pursuant to Public Contract Code section 7103.5, in entering into a public works contract or subcontract to supply goods, services, or materials pursuant to a public works contract, Contractor or subcontractor offers and agrees to assign to the City all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 USC, Section 15) or under the Cartwright Act (Chapter 2 (commencing with Section 16700) of Part 2 of Division 7 of the Business and Professions Code), arising from the purchase of goods, services, or materials pursuant to this contract or any subcontract. This assignment shall be made and become effective at the time the City tenders final payment to the Contractor, without further acknowledgment by the parties.

ARTICLE 58 PROHIBITED INTERESTS
No City official or representative who is authorized in such capacity and on behalf of the City to negotiate, supervise, make, accept, or approve, or to take part in negotiating, supervising, making, accepting or approving any engineering, inspection, construction or material supply contract or any subcontract in connection with construction of the project, shall be or become directly or indirectly interested financially in the Contract.

ARTICLE 59 CONTROLLING LAW
Notwithstanding any subcontract or other contract with any subcontractor, supplier, or other person or organization performing any part of the Work, this Contract shall be governed by the law of the State of California excluding any choice of law provisions.

ARTICLE 60 JURISDICTION; VENUE
Contractor and any subcontractor, supplier, or other person or organization performing any part of the Work agrees that any action or suits at law or in equity arising out of or related to the bidding, award, or performance of the Work shall be maintained in the Superior Court of Santa 38077.00180\29080232.10
-107- 00 72 13 – GENERAL CONDITIONS
Clara County, California, and expressly consent to the jurisdiction of said court, regardless of residence or domicile, and agree that said court shall be a proper venue for any such action.

ARTICLE 61 LAWS AND REGULATIONS
A. Contractor shall give all notices and comply with all laws, ordinances, rules and regulations bearing on conduct of work as indicated and specified. If Contractor observes that drawings and specifications are at variance therewith, it shall promptly notify the Engineer in writing and any necessary changes shall be adjusted as provided for in this Contract for changes in work. If Contractor performs any work knowing it to be contrary to such laws, ordinances, rules and regulations, and without such notice to the Engineer, it shall bear all costs arising therefrom.

B. Contractor shall be responsible for familiarity with the Americans with Disabilities Act (“ADA”) (42 U.S.C. § 12101 et seq.). The Work will be performed in compliance with ADA regulations.

ARTICLE 62 PATENTS
Contractor shall hold and save the City, officials, officers, employees, and authorized volunteers harmless from liability of any nature or kind of claim therefrom including costs and expenses for or on account of any patented or unpatented invention, article or appliance manufactured, furnished or used by Contractor in the performance of this contract.

ARTICLE 63 OWNERSHIP OF CONTRACT DOCUMENTS
All Contract Documents furnished by the City are City property. They are not to be used by Contractor or any subcontractor on other work nor shall Contractor claim any right to such documents. With exception of one complete set of Contract Documents, all documents shall be returned to the City on request at completion of the Work.

ARTICLE 64 NOTICE OF TAXABLE POSSESSORY INTEREST
In accordance with Revenue and Taxation Code section 107.6, the Contract Documents may create a possessory interest subject to personal property taxation for which Contractor will be responsible.

ARTICLE 65 SURVIVAL OF OBLIGATIONS
All reresentations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor.

ARTICLE 66 SLFRF CONTRACT PROVISIONS
Funds from the Coronavirus State and Local Fiscal Recovery Fund (“SLFRF”) will be used to fund all or a portion of this contract. The Contractor shall comply with all federal requirements including, but not limited to, the following:
38077.00180\29080232.10
-108- 00 72 13 – GENERAL CONDITIONS

1. Sections 602 and 603 fo the Social Security Act as added by Section 9901 of the American Rescue Plan Act of 2021, U.S. Department of the Treasury Coronarivrus State and Local Fiscal Recovery Fund Award Terms and Conditions, Treasury’s Interim Final Rule, and SLFRF reporting requirements, as appilcable (collectively, the “SLFRF Compliance Requirements”). The SLFRF Compliance Requirements are expressly incorporated herein by reference.

2. 2 C.F.R. Part 200 – Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards, which is expressly incorporated herein by reference.

3. SLFRF Federal Contract Provisions attached hereto as Exhibit D and incorporated herein by reference.

Subcontracts, if any, shall contain a provision making them subject to all of the provisions stipulated in the contract, including but not limited to, SLFRF Compliance Requirements, 2 C.F.R. Part 200, and the SLFRF Federal Contract Provisions.

With respect to any conflict between such federal requirements and the terms herein and/or the provisions of state law and except as otherwise required under federal law or regulation, the more stringent requirement shall control.
38077.00180\29080232.10
-109- 00 73 13 – SPECIAL CONDITIONS
00 73 13 – SPECIAL CONDITIONS

1.1 Engineer of Record.

A For purposes of this Project, the Engineer of Record or Engineer shall be:
[To Be Determined].

1.2 Location of the Project.

A The Project is located at various locations identified in Exhibit C.

B The general location of the Project is shown in Exhibit C.

1.3 Status of the Project Area and Rights-of-Way.

A City, at its expense, will provide all rights-of-way or permits, or both, covering the crossing of private property and public and private rights-of-way necessary for the permanent Work; provided, however, Contractor shall, at its expense, obtain any bonds or insurance policies or pay any fees and enter into any agreements required by a controlling authority, e.g., Caltrans or Southern Pacific Railroad Company, before Contractor enters upon any property or right-of-way under the jurisdiction of any such controlling authority for the purpose of performing Work.

B City has acquired or is negotiating to acquire any rights-of-way, or both, necessary for the permanent Work.

C If such permits are required, all operations of Contractor shall conform to the restrictions, regulations, and requirements set forth in said permits, copies of which will be included in the Contract Documents.

D Contractor may be required, as a condition for receiving final payment, to obtain, and provide City’s Representative with copies of, executed damage releases from the owners of public and private property whose property has been damaged by the Work. The damage releases will be on a form provided by City.

E Contractor shall, also, as a condition for receiving final payment, obtain, and provide City’s Representative with copies of, executed damage releases from the owners of certain public and private property or areas which have been crossed by the Work or otherwise affected by the Work. The damage releases will be on a form provided by City.

1.4 Site Data.

A The data provided herein is for the information of Contractor and is subject to all limitations and conditions set forth in the Contract Documents.

B Subsurface Exploration Data. The following data are included in the Project Manual:

1. [Not applicable to this project]
38077.00180\29080232.10
-110- 00 73 13 – SPECIAL CONDITIONS
C Other Site Data. The following data are available for inspection at City’s office:

1. [Not applicable to this project]
Copies of these reports, drawings and other materials may be examined at City’s office during regular business hours.

1.5 Pre-Purchased or Pre-Negotiated Material.
[NOT USED.]

1.6 Designation of City’s Representative.

A Unless otherwise modified by City, City’s Representative shall be Joseph Aguilera, Public Works Manager.

1.7 Project Retention
In accordance with Public Contract Code § 7201, City will withhold 5% of each progress payment as retention on the Project.

1.8 Liquidated Damages Due to Contractor Delay.

A Time is of the essence. Should Contractor fail to complete all or any part of the Work within the time specified in the Contract Documents, City will suffer damage, the amount of which is difficult, if not impossible, to ascertain and, pursuant to the authority of Government Code section 53069.85, City shall therefore be entitled to Five Hundred Dollars and Zero Cents ($500.00) per Day as liquidated damages for each Day or part thereof that actual completion extends beyond the time specified.

B Liquidated damages may be deducted from progress payments due to Contractor, Project retention or may be collected directly from Contractor, or from Contractor's surety. These provisions for liquidated damages shall not prevent City, in case of Contractor's default, from terminating the Contractor.

1.9 Utility Outages – Notices to Residents.

A Should Contractor’s operations require interruption of any utility service, Contractor shall notify City at least ten (10) Days prior to the scheduled outage.

Contractor will notify all impacted residents on a form provided by City at least seven (7) Days prior to the scheduled outage.

B Contractor shall be responsible for providing, at its cost, any temporary utility or facilities necessitated by the utility outage.

1.10 Schedule Constraints.

NOT USED.
38077.00180\29080232.10
-111- 00 73 13 – SPECIAL CONDITIONS
A City has considered these Schedule Constraints when determining the Contract Times and no additional time or compensation will be added to the Contract due to these Constraints.

1.11 Safety Programs.
[NOT USED.

1.12 Coordination with Other Contractors.

NOT USED.

END OF SPECIAL CONDITIONS

38077.00180\29080232.10
-112- 01 00 00 – GENERAL REQUIREMENTS
01 00 00 – GENERAL REQUIREMENTS
PART 1 GENERAL

1.1 DESCRIPTION
A. Safety rehabilitation of City’s play structures and safety surfaces at elevent City parks identified in this solicitation.

1.2 RELATED REQUIREMENTS SPECIFIED ELSEWHERE
A. Attachment A – 23-035 Scope of Work, Plans, and Specifications PART 2 (NOT USED)
PART 3 EXECUTION

3.1 LAYOUT OF WORK AND QUANTITY SURVEYS
A. General. The Contractor shall utilize a properly licensed surveyor to perform all layout surveys required for the control and completion of the Work, and all necessary surveys to compute quantities of Work performed.

City and/or the Engineer of Record has established primary control to be used by the Contractor for establishing lines and grades required for the Work.

Primary control consists of benchmarks and horizontal control points in the vicinity of the Work.A listing and identification of the primary control is provided on the Drawings. Before beginning any layout work or construction activity, the Contractor shall check and verify primary control, and shall advise the City Representative of any discrepancies.

B. Quantity surveys. The Contractor shall perform such surveys and computations as are necessary to determine quantities of Work performed or placed during each progress payment period, and shall perform all surveys necessary for the City Representative to determine final quantities of Work in place.The City Representative will determine final quantities based upon the survey data provided by the Contractor, and the design lines and grades.If requested by the City Representative, the Contractor shall provide an electronic copy of data used for quantity computations.

All surveys performed for measurement of final quantities of Work and material shall be subject to approval of City’s Representative. Unless waived by City’s Representative in each specific case, quantity surveys made by the Contractor shall be made in the presence of City’s Representative.

C. Surveying

1. Accuracy. Degree of accuracy shall be an order high enough to satisfy tolerances specified for the Work and the following:
38077.00180\29080232.10
-113- 01 00 00 – GENERAL REQUIREMENTS
(a) Right-of-way and alignment of tangents and curves shall be within

0.1 foot.
(b) Structure points shall be set within 0.01 foot, except where operational function of the special features or installation of metalwork and equipment require closer tolerances. When formwork has been placed and is ready for concrete, the Contractor shall check the formwork for conformance with the drawings and to ensure that the forms are sufficiently within the tolerance limits for the completed work.
(c) Cross-section points shall be located within 0.1 foot, horizontally and vertically.
(d) Aerial Mapping shall meet National Mapping Standards for 2- foot contour intervals.

D. Records. Survey data shall be recorded in accordance with recognized professional surveying standards. Original field notes, computations, and other surveying data shall be recorded on electronic data collectors or in standard field books and must be of sufficient quality to enable the Contractor to prepare accurate record drawings as required by the Contract Documents.

E. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required for surveys for the layout of work and quantity surveys shall be included in the Schedule of Pay Items for items of work requiring the surveys. No additional compensation shall be made to the Contractor for this Work.

3.2 SCHEDULE
A. Estimated Schedule. Within 21 Days after the issuance of the Notice of Award, Contractor shall prepare a Project schedule and shall submit this to the Engineer for Approval. The receipt or Approval of any schedules by the Engineer or the City shall not in any way relieve the Contractor of its obligations under the Contract Documents. The Contractor is fully responsible to determine and provide for any and all staffing and resources at levels which allow for good quality and timely completion of the Project. Contractor’s failure to incorporate all elements of Work required for the performance of the Contract or any inaccuracy in the schedule shall not excuse the Contractor from performing all Work required for a completed Project within the specified Contract time period. If the required schedule is not received by the time the first payment under the Contract is due, Contractor shall not be paid until the schedule is received, reviewed and accepted by the Engineer.

B. Schedule Contents. The schedule shall indicate the beginning and completion dates of all phases of construction; critical path for all critical, sequential time related activities; and “float time” for all “slack” or “gaps” in the non-critical activities. The schedule shall clearly identify all staffing and other resources which in the Contractor’s judgment are needed to complete the Project within the 38077.00180\29080232.10
-114- 01 00 00 – GENERAL REQUIREMENTS
time specified for completion. The overall Project Schedule duration shall be within the Contract time.

C. Weather Allowance. The schedule shall allow adequate time for inclement weather.

D. Schedule Updates. Contractor shall continuously update its construction schedule. Contractor shall submit an updated and accurate construction schedule to the Engineer monthly when requested to do so by Engineer.

Contractor shall also submit schedules showing a three week detailed lookahead at bi-weekly meetings conducted with the City. The Engineer may withhold progress payments or other amounts due under the Contract Documents if Contractor fails to submit an updated and accurate construction schedule.

3.3 TEMPORARY FIELD OFFICE
NOT USED.

3.4 PROTECTION OF WORK AND PROPERTY
A. All traffic detector loops, fences, walls, culverts, monuments, or other obstructions (except property line monuments within five (5) feet of the centerline of the mains) which are removed, damaged, or destroyed in the course of the Work, shall be replaced or repaired to the original condition at no additional cost to City. Contractor shall be responsible for the cost to repair, replace, relocate, and replacement of utilities whether or not those obstructions have been shown on the Plans, unless otherwise stated herein. It is then the Contractor’s responsibility to employ at its expense a Licensed Land Surveyor to restore all property line monuments located more than five (5) feet from the centerline of the mains, which are destroyed or obliterated. Property line monuments located within five (5) feet of the centerline of the mains will be replaced by the City at no expense to the Contractor, provided the City is notified at least 48 hours before the property line monuments are damaged.

B. Contractor shall provide such heat, covering, and enclosures as are necessary to protect all Work, materials, equipment, appliances, and tools against damage by weather conditions.

C. Contractor shall take adequate precautions to protect existing sidewalks, curbs, pavements, utilities, and other adjoining property and structures, and to avoid damage thereto, and Contractor shall repair any damage thereto caused by the Work operations. Contractor shall:

1. Enclose the working area with a substantial barricade, and arrange work to cause minimum amount of inconvenience and danger to the public.

2. Provide substantial barricades around any shrubs or trees indicated to be preserved.
38077.00180\29080232.10
-115- 01 00 00 – GENERAL REQUIREMENTS

3. Deliver materials to the Project site over a route designated by the Engineer.

4. Provide any and all dust control required and follow the Applicable air quality regulations as appropriate. If the Contractor does not comply, the City shall have the immediate authority to provide dust control and deduct the cost from payments to the Contractor.

5. Confine Contractor’s apparatus, the storage of materials, and the operations of its workers to limits required by law, ordinances, permits, or directions of the Engineer. Contractor shall not unreasonably encumber the Project site with its materials.

6. Take care to prevent disturbing or covering any survey markers, monuments, or other devices marking property boundaries or corners. If such markers are disturbed by accident, they shall be replaced by a civil engineer or land surveyor acceptable to the City, at no cost to the City.

7. Ensure that existing facilities, fences and other structures are all adequately protected and that, upon completion of all Work, all facilities that may have been damaged are restored to a condition acceptable to the City.

8. Preserve and protect from injury all buildings, pole lines and all direction, warning and mileage signs that have been placed within the right-of-way.

9. At the completion of work each day, leave the Project site in a clean, safe condition.

10. Comply with any approved stage construction and traffic control plans.

Access to residences and businesses shall be maintained at all times, unless otherwise permitted in writing by the City.

11. Cover and or protect work and project site as may be required to prevent or mitigate schedule delay and to allow work to proceed during wet weather or wet conditions.

D. These precautionary measures will apply continuously and not be limited to normal working hours. Full compensation for the Work involved in the preservation of life, safety and property as above specified shall be considered as included in the prices paid for the various contract items of Work, and no additional allowance will be made therefore.

E. Should damage to persons or property occur as a result of the Work, Contractor shall be responsible for proper investigation, documentation, including video or photography, to adequately memorialize and make a record of what transpired.

The City shall be entitled to inspect and copy any such documentation, video, or photographs.

3.5 SITE CONDITIONS SURVEYS
38077.00180\29080232.10
-116- 01 00 00 – GENERAL REQUIREMENTS
A. Work Included.

Contractor shall conduct thorough pre-construction and post-construction site condition surveys of the entire project area. Site Conditions surveys shall include written documentation of the conditions found, as well as photographs and video recordings of the area within at least 80 feet of any construction area and staging area. The written notes, photographs, and video shall be suitable for forensic purposes to resolve any damage claims that may arise as a result of construction.

B. Submittals.

1. Written documentation of site condition survey at pre-construction and post-construction.

2. Photographs as described herein of pre-construction and postconstruction conditions.

3. Video recordings as described herein of pre-construction and postconstruction conditions.

4. Submittals shall be made within three days of the surveys. All postconstruction data shall be submitted prior to the final project inspection.

C. Site Condition Written Documentation.

Written documentation shall include the time, date, and conditions under which the site survey was made. The documentation shall note the condition of structures, pavement, sidewalks, utilities, fences, and etc. within the work areas.

D. Photographs & Video Recording.

1. General – Prior to starting Work, Contractor shall provide a video recording of the project site. Contract shall take enough photographs during each site survey to provide a record of conditions existing prior to construction and conditions after construction. Pre-construction video and photographs shall be taken prior to any construction or mobilization of equipment, but not more that one week prior to actual start of work.

The pre-construction photographs may be staged at different times to match the progression of the Work.

2. The photographs shall document existing damage to public and private facilities, both prior to and after construction. Conditions to be documented include, but are not limited to: sidewalk cracks, broken curbs, separated property walls, improvements within public right-ofways, access roads used, utility covers and markings, signs, pavement striping, pavement, unique or unusual conditions, adjacent driveways, landscaping, survey markers, and any feature directed by the Engineer.

Private property that is adjacent to the public right-of-way shall be documented to the extent visible from the public right-of-way. 38077.00180\29080232.10
-117- 01 00 00 – GENERAL REQUIREMENTS

3. Photographs shall include items to indicate scale, as needed. In particular, scales or other items shall be laid next to close ups of structural cracks and other damaged areas being recorded. Scaling shall also be used to document elevation differences, as needed.

4. One set of color prints and the preconstruction site video shall be submitted. Additional sets shall be available for reviewing in settling any construction disputes. A set of photos shall also be furnished in electronic format. The resolution shall be at least equal to 7 mega-pixels.

All photos shall be documented as to time and date taken, photographer, project number, location, and orientation. Documentation shall include a brief description of objects photographed.

E. Video Recording.

1. Video recordings shall document the conditions of the entire area affected by construction, as well as nearby structures and facilities. The general documentation requirements for videos are the same as for photographs.

Video recorders shall accurately and continuously record the time and date.

2. Video recordings shall include an audio portion made simultaneously during the videoing. The audio recording shall describe the location, time, orientation, and objects being recorded. Special commentary shall be provided for unusual conditions or damage noted.

3. Video equipment shall be capable of producing high resolution images and shall have zoom capabilities.

4. Video recordings shall provide an overall picture of the sites and shall provide detailed images of damaged areas. Video shall extend to the maximum height of structures.

5. The Engineer shall have the right to reject any audio video recordings submitted with unintelligible audio, uncontrolled pan or zoom, or of poor quality. Video recordings shall be repeated when rejected.

6. Video recordings shall be submitted with labels indicating the project, date, recorder, and other pertinent information. Recordings shall be submitted on standard DVDs in a standard format.

F. Timing.

Contractor shall provide written notice of the time scheduled for the site conditions survey and the place it is to begin. Contractor shall obtain the Engineer’s concurrence prior to beginning the condition survey. The Engineer reserves the right to cancel the survey due to weather conditions or other problems. Videoing shall be done during times of good visibility and no videoing or photography shall be done during periods of visible precipitation or when standing water obscures pavement. Contractor shall provide the Engineer with 38077.00180\29080232.10
-118- 01 00 00 – GENERAL REQUIREMENTS
an opportunity to have a representative present when taking the photos and provide guidance during photographing.

G. Site Surveyor.

The site condition surveyor(s) shall be experienced in construction and potential damage concerns. The site condition surveyor(s) shall be familiar with the photography and video equipment being used.

H. Field Quality Control.

Prior to submitting videos and photographs, the Contractor shall spot check the photos and videos in the field to insure they accurately reflect the actual conditions and to insure they are correctly labeled.

I. Soils Compaction Testing.

1. All soils compaction testing will be done by a licensed geotechnical engineer furnished by the City. Soils compaction testing will be done for all footings and foundations prior to placement of rebar or concrete.

2. For pipeline construction, soil compaction testing will be done at 100-foot intervals or as ordered by the project soils/geotechnical report at the bottom of the trench prior to placement of pipe bedding; at the top of the pipe bedding above the pipe; every two vertical feet of trench backfill or as otherwise ordered by the project soils/geotechnical report; at the top of the trench backfill, which sould be the bottom of the pavement section; and at the top of the aggregate base prior to pavement construction.

3.6 SUBMITTAL REQUIREMENTS FOR MANUALS AND RECORD DRAWINGS A. General. The Contractor shall furnish all materials and perform all Work required for furnishing submittals to City in accordance with Contract Documents.The Contractor shall submit Project Record Drawings, Technical Manual, Spare Parts, and other required items within 5 days following completion of project construction, and prior to Contractors request for Project Acceptance.

B. Technical Manuals.

1. The Contractor shall submit technical operation and maintenance information for each item of mechanical, electrical and instrumentation equipment in an organized manner in the Technical Manual. It shall be written so that it can be used and understood by City’s operation and maintenance staff.

2. The Technical Manual shall be subdivided first by specification section number; second, by equipment item; and last, by "Category." The Contractor shall furnish to City four (4) identical Technical Manuals.

Each set shall consist of one or more volumes, each of which shall be bound in a standard binder.
38077.00180\29080232.10
-119- 01 00 00 – GENERAL REQUIREMENTS
C. Spare Parts List - The Contractor shall furnish to City six (6) identical sets of spare parts information for all mechanical, electrical, and instrumentation equipment.

The spare parts list shall include the current list price of each spare part. The spare parts list shall include those spare parts which each manufacturer recommends be maintained by City in inventory. Each manufacturer or supplier shall indicate the name, address, and telephone number of its nearest outlet of spare parts to assist City in ordering. The Contractor shall cross-reference all spare parts lists to the equipment numbers designated in the Contract Documents. The spare parts lists shall be bound in standard size, 3-ring binder.

D. Record Drawings

1. The Contractor shall maintain one record set of Drawings at the Site. On these, it shall mark all Project conditions, locations, configurations, and any other changes or deviations which may vary from the information represented in the original Contract Documents, including buried or concealed construction and utility features which are revealed during the course of construction. Special attention shall be given to recording the horizontal and vertical location of all buried utilities that differ from the locations indicated, or which were not indicated on the Contract Drawings.

Said record drawings shall be supplemented by any detailed sketches as necessary or directed to fully indicate the Work as actually constructed.

These master record drawings of the as-built conditions, including all revisions made necessary by Addenda and Change Orders shall be maintained up-to-date during the progress of the Project. Red ink shall be used for alterations and notes. Notes shall identify relevant Change Orders by number and date.

2. For all Projects involving the installation of any pipeline, Contractor shall survey and record the top of the pipe at a minimum of every 100 linear feet, and at each bend, recording both the horizontal and vertical locations.

3. Record drawings shall be accessible to City’s Representative at all times during the construction period. The record drawings shall be kept up to date and will be checked by the City prior to each progress payment.

Failure on the Contractor’s part to keep record drawings current could result in withholding partial payment.

4. Upon Completion of the Project and as a condition of final acceptance, the Contractor shall finalize and deliver a complete set of Record Drawings to City’s Representative. The information submitted by the Contractor will be assumed to be correct, and the Contractor shall be responsible for, and liable to City, for the accuracy of such information, and for any errors or omissions which may or may not appear on the Record Drawings.

E. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete the Manuals and Record Drawings shall be included in Contractor’s bid and distributed in the Schedule of Pay. No additional compensation shall be made to the Contractor for this Work. 38077.00180\29080232.10
-120- 01 00 00 – GENERAL REQUIREMENTS

3.7 MATERIALS
A. Materials to be Furnished by the Contractor

1. Inspection of Materials. Materials furnished by the Contractor which will become a part of the Project shall be subject to inspection at any one or more of the following locations, as determined by City’s Representative:
at the place of production or manufacture, at the shipping point, or at the site of the Work. To allow sufficient time to provide for inspection, the Contractor shall submit to City’s Representative, at the time of issuance, copies of purchase orders or other written instrument confirming procurement of the materials, including drawings and other pertinent information, covering materials on which inspection will be made.

2. No later than fourteen (14) Days prior to manufacture of material, Contractor shall inform City’s Representative, in writing, the date the material is to be manufactured.

3. Contractors Obligations. The inspection of materials at any of the locations specified above or the waiving of the inspection thereof shall not impact whether the materials and equipment conform to the Contract Documents. Contractor will not be relieved from furnishing materials meeting the requirements of the Contract Documents due to City’s inspection or lack of inspection of the equipment or materials.

Acceptance of any materials will be made only after materials are installed in the Project.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to accommodate City’s testing efforts, including any travel required by Contractor’s forces, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items related to the materials requiring testing. No additional compensation shall be made to the Contractor for this Work.

3.8 LOCAL CONDITIONS AND REQUIREMENTS
A. Access to Work and Haul Routes

1. General. All work on the rights-of-way necessary for access to the Site shall be performed by the Contractor. Contractors anticipated Haul Routes shall be in compliance with the City's approved Truck Routes available from the Engineer.

2. Access, Damage, Restoration. The Contractor shall make his own investigation of the condition of available public or private roads and of clearances, restrictions, bridge-load limits, permit or bond requirements, and other limitations that affect or may affect transportation and ingress or egress at the Site.

3. The Contractor shall maintain and repair any damage arising out of Contractor’s operations to all roads used during construction of the 38077.00180\29080232.10
-121- 01 00 00 – GENERAL REQUIREMENTS
Project, and upon completion of all Work, but prior to final acceptance, the roads shall be restored to their original condition. Prior to using any road for access to the Site, the Contractor shall conduct a photograph and/or video survey of the roadway with a copy submitted to City’s Representative.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items.

No additional compensation shall be made to the Contractor for this Work.

B. Power. Contractor shall provide at its own expense all necessary power required for operations under the contract. The Contractor shall provide and maintain in good order such modern equipment and installations as shall be adequate in the opinion of the Engineer to perform in a safe and satisfactory manner the Work required by the contract.

C. Construction Water.

1. Construction water shall not be used for purposes other than those required to satisfactorily complete the contract.

2. Construction recycled water will be made available to the contractor from one of three fill locations within the city limits. If there is a need for construction recycled water during construction, the contractor shall apply for a city construction recycled water meter at the city hall finance counter prior to the beginning of work. A security deposit of $2,000 is required for the construction water meter from which the meter rental fee and cost of water will be deducted. if the rental fee and the water costs exceed the $2,000.00 deposited, an invoice will be issued to the contractor for payment.

3. Construction potable water will only be made available to the contractor if it can be demonstrated that recycled water cannot be used for the construction activities. potable water will be made available from existing city fire hydrant(s) nearest the proposed construction site as approved by the engineer, or by such other means as may be expressly approved in writing by the engineer. If there is a need for water during construction, the contractor shall apply for a city construction water meter at the city hall finance counter prior to the beginning of work. a security deposit of $2,000 is required for the construction water meter from which the meter rental fee and cost of water will be deducted. If the rental fee and the water costs exceed the $2,000.00 deposited, an invoice will be issued to the contractor for payment.

4. All required water, all work and materials required for obtaining, pumping, transporting and applying and otherwise disposing of said water shall be in an approved manner and shall be performed by, and at the expense of the contractor and no extra or separate compensation will be made thereof.
38077.00180\29080232.10
-122- 01 00 00 – GENERAL REQUIREMENTS
D. Operation of Existing Water Facilities

1. The Contractor shall not operate any of the existing water systems, including pumps, motors, valves, and hydrants, but shall contact the City two (2) working days in advance with a list and location of the water system facilities that will require operating, opening, stopping, or closure by the City.

2. At the option of the Engineer, the Contractor may be permitted to operate valves for the purpose of making connections to existing mains. The City will perform all notification to existing customers regarding temporary loss of service.

3. Contractor shall submit a request on City’s standard form for any shutdown of existing water facilities.

E. Construction at Existing Utilities

1. General. Where the Work to be performed crosses or otherwise interferes with water, sewer, gas, or oil pipelines; buried cable; or other public or private utilities, the Contractor shall perform construction in such a manner so that no damage will result to either public or private utilities. It shall be the responsibility of the Contractor to determine the actual locations of, and make accommodates to maintain, all utilities.

2. Permission, Notice and Liability. Before any utility is taken out of service, permission shall be obtained by the Contractor from the owner. The owner, any impacted resident or business owner and the City Representative will be advised of the nature and duration of the utility outage as well as the Contractor’s plan for providing temporary utilities if required by the owner. The Contractor shall be liable for all damage which may result from its failure to maintain utilities during the progress of the Work, and the Contractor shall indemnify City as required by the Contract Documents from all claims arising out of or connected with damage to utilities encountered during construction; damages resulting from disruption of service; and injury to persons or damage to property resulting from the negligent, accidental, or intentional breaching of utilities.

3. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items.

No additional compensation shall be made to the Contractor for this Work.

F. Traffic Control

1. General. Contractor shall abide by traffic control plans approved by the City.

2. Protections. Roads subject to interference by the Work shall be kept open or suitable temporary passages through the Work shall be provided and 38077.00180\29080232.10
-123- 01 00 00 – GENERAL REQUIREMENTS
maintained by the Contractor. The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient flasher lights, flag persons, danger signals, and signs, and shall take all necessary precautions for the protection of the Work and the safety of the public.

No construction work along public or private roads may proceed until the Contractor has proper barricades, flasher lights, flag persons, signals, and signs in place at the construction site.

3. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items.

No additional compensation shall be made to the Contractor for this Work.

G. Cleaning Up

1. Contractor at all times shall keep premises free from debris such as waste, rubbish, and excess materials and equipment. Contractor shall not store debris under, in, or about the premises. Contractor shall also clean all asphalt and concrete areas to the degree necessary to remove oil, grease, fuel, or other stains caused by Contractor operations or equipment, including all USA markings. The use of water, resulting in mud on streets, will not be permitted as substitute for sweeping or other methods. Dust control may require having a water truck onsite for the duration of the project, and/or use of temporary hoses and pipelines to convey water.

2. Contractor shall fully clean up the site at the completion of the Work. If the Contractor fails to immediately clean up at the completion of the Work, the City may do so and the cost of such clean up shall be charged back to the Contractor.

3.9 ENVIRONMENTAL QUALITY PROTECTION
A. Environmental Conditions
NOT USED.

B. Landscape and Vegetation Preservation

1. General. The Contractor shall exercise care to preserve the natural landscape and vegetation, and shall conduct operations so as to prevent unnecessary destruction, scarring, or defacing of the natural surroundings in the vicinity of the Work.

2. Damage and Restoration. Movement of crews and equipment within the rights-of-way and over routes provided for access to the Work shall be performed in a manner to prevent damage to property. When no longer required, construction roads shall be restored to original contours.

3. Upon completion of the Work, and following removal of construction facilities and required cleanup, land used for construction purposes and 38077.00180\29080232.10
-124- 01 00 00 – GENERAL REQUIREMENTS
not required for the completed installation shall be scarified and regraded, as required, so that all surfaces are left in a condition that will facilitate natural revegetation, provide for proper drainage, and prevent erosion.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items.

No additional compensation shall be made to the Contractor for this Work.

C. Protected Species

1. General. If, in the performance of the Work, evidence of the possible occurrence of any State or Federally listed threatened or endangered plant or animal is discovered, the Contractor shall notify the City Representative immediately, giving the location and nature of the findings.

Written confirmation of the evidence, location and nature of the findings shall be forwarded to City within 2 Days.

2. Procedures. The Contractor shall immediately cease all construction activities in the immediate area of the discovery to the extent necessary to protect the endangered plant or animal.

If directed by the City Representative, Contractor will refrain from working in the immediate area, suspend the Work in its entirety, or alter its performance to ensure full compliance with all applicable permits, laws and regulations. Any City directed changes to the Work as a result of a siting will be pursuant to the Contract Documents.

3. False Siting. Any costs or delays incurred by City or the Contractor due to unreasonable or false notification of an endangered plant or animal will be borne by the Contractor.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to comply with this paragraph, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

D. Preservation of Historical and Archeological Resources

1. General. If, in the performance of the Work, Contractor should unearth cultural resources (for example, human remains, animal bones, stone tools, artifacts and/or midden deposits) through excavation, grading, watering or other means, the Contractor notify the
Construction/Archeological Monitor and/or the City Representative immediately, giving the location and nature of the findings. Written confirmation of the evidence, location and nature of the findings shall be forwarded to the Construction/Archeological Monitor and/or City within 2 Days.
38077.00180\29080232.10
-125- 01 00 00 – GENERAL REQUIREMENTS

2. Procedures. The Contractor shall immediately cease all construction activities in the immediate area of the discovery to the extent necessary to protect the cultural resource.

If directed by the City Representative, Contractor will refrain from working in the immediate area, suspend the Work in its entirety, or resequence and/or alter its performance to ensure full compliance with all applicable permits, laws and regulations. Should the presence of cultural resources be confirmed, the Contractor will assist the City Representative and the Construction/Archeological Monitor in the preparation and implementation of a data recovery plan. The Contractor shall provide such cooperation and assistance as may be necessary to preserve the cultural resources for removal or other disposition. Any City directed changes to the Work as a result of the cultural resource will be pursuant to the Contract Documents.

3. Contractor’s Liability. Should Contractor, without permission, injure, destroy, excavate, appropriate, or remove any cultural resource on or adjacent to the Site, it will be subject to disciplinary action, arrest and penalty under applicable law. The Contractor shall be principally responsible for all costs of mitigation and/or restoration of cultural resources related to the unauthorized actions identified above.

Contractor shall be required to pay for unauthorized damage and mitigation costs to cultural resources (historical and archeological resources) as a result of unauthorized activities that damage cultural resources and shall indemnify City pursuant to the Contract Documents.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to comply with this paragraph, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

E. Dust and Pollution Control

1. Contractor shall provide all necessary material, equipment and labor to prevent and control the emission of dust and any other potential pollutant on site. Contractor shall remove construction caused debris from streets and sidewalks as directed by the Engineer.

2. Contractor shall not discharge into the atmosphere from any source smoke, dust or other air contaminants in violation of the law, rules, and regulations of the governing agency.

3. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to comply with this paragraph, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

F. Management of Storm, Surface and Other Waters
38077.00180\29080232.10
-126- 01 00 00 – GENERAL REQUIREMENTS

1. Storm water, surface water, groundwater, and nuisance, or other waters may be encountered at various times during construction of the Project.

Federal and State laws require the City and its contractors to manage such waters pursuant to the requirements of California State Water Resources Control Board Order Number 2009-0009-DWQ, the Federal Clean Water Act, and the California Porter Cologne Water Quality Control Act. Contractor acknowledges that it has investigated the risk arising from such waters in conjunction with the Project, has prepared its Bid accordingly, and assumes any and all risks and liabilities arising therefrom.

2. The Contractor shall keep itself and all subcontractors, staff, and employees fully informed of and in compliance with all local, state and federal laws, rules and regulations that may impact, or be implicated by the performance of the Work including, without limitation, all applicable provisions of the City’s ordinances regulating discharges of storm water; the Federal Water Pollution Control Act (33 U.S.C. § 1251 et seq.); the California Porter-Cologne Water Quality Control Act (Water Code § 13000 et seq.); and any and all regulations, policies, or permits issued pursuant to any such authority. These include, but are not limited to the San Francisco Bay Regional Water Quality Control Board Order No. R2-2015- 0049 (NPDES Permit No. CAS 612008), and State Water Resources Control Board Order No. 2010-0014-DWQ, Order No. 2009-0009-DWQ, and Order No. 2012-0006-DWQ, and any amendment or renewal thereof (“Construction General Permit”). Contractor must perform all construction operations in such a manner as to comply, and ensure all subcontractors to comply, with all applicable Federal, State, and local laws, orders, and regulations concerning the control and abatement of water pollution; and all terms and conditions of any applicable permits issued for the Project. In the event there is a conflict between Federal, State, and local laws, regulations, and requirements, the most stringent shall apply.

3. Compliance with Construction General Permit. Contractor must comply with all aspects of the Construction General Permit, State Water Resources Control Board (State Board) Water Quality Order No. 2009- 0009-DWQ, as amended by Order Nos. 2010-0014-DWQ and 2012- 0006-DWQ, and any amendment or renewal thereof (NPDES
CAS000002), for all projects that involve construction on or disturbance of one acre or more of land or which are part of a larger common plan of development or sale.
(a) Permit registration. Unless otherwise specified in the Special Conditions, Contractor must prepare the Notice of Intet for coverage under the Construction General Permit and all Permit Registration Documents (PRDs), including but not limited to the Storm Water Pollution Prevention Plan (SWPPP), as those terms are defined in the Construction General Permit. Contractor must coordinate submittal of all PRDs with th eCity’s Legally Responsible Person and/or Authorized Signatory, as those terms are defined in the Construction General Permit. The Contractor 38077.00180\29080232.10
-127- 01 00 00 – GENERAL REQUIREMENTS
must submit the PRDs, including the SWPPP to the City
Representative for review not less than fifteen (15) Days prior to the start of on- site construction work. City will file the Notice of Intent and PRDs and pay the filing fee.
(b) Before any Construction General Permit related documents may be submitted to the State Board or implemented on the Project site, they must first be reviewed and accepted by City.

Acceptance by the City does not relieve the Contractor from ensuring such documents comply with all lawsapplicable laws, regulations, and orders.
(c) Contractor must ensure that the SWPPP is developed by a Qualified SWPPP Developer and implemented by a Qualified SWPPP Practitioner as those terms are defined in the Permit.

Contractor must implement the SWPPP and all other provisions of the Construction General Permit, including the monitoring and reporting requirements, preparing and submitting all reports, plans, inspections, and monitoring information in compliance with the Construction General Permit. The SWPPP must include industry standard requirements for water quality control including but not be limited to the following:
(1) Sediment and erosion control measures to manage
sediment and erosion including vegetative practices,
structural control, silt fences, straw dikes, sediment
controls or operator controls as appropriate.Storm water management measures shall be instituted as required,
including velocity dissipaters, and solid waste controls shall address controls for building materials and offsite tracking of sediment.
(2) Wastewater and storm water management controls to
divert offsite surface flows around the Project site and to divert surface flows within the Project area away from
areas of open earth or stockpiles of building and other materials. Wastewater from general construction activities, such as drain water collection, aggregate processing,
concrete batching, drilling, grouting, or other construction operations, shall not enter flowing or dry watercourses without having met the authorized non-storm water
discharge requirements listed in State Board Water Quality Order No. 2009-0009-DWQ, Section III.C., including proper notification to the Regional Water Board.
(3) Pollution prevention measures including methods of
dewatering, unwatering, excavating, or stockpiling earth and rock materials which include prevention measures to control silting and erosion, and which will intercept and settle any runoff of sediment-laden waters.
38077.00180\29080232.10
-128- 01 00 00 – GENERAL REQUIREMENTS
(4) Turbidity prevention measures for prevention of excess turbidity including, but are not restricted to, intercepting ditches, settling ponds, gravel filter entrapment dikes, flocculating processes, recirculation, combinations thereof, or other approved methods that are not harmful to aquatic life. All such wastewaters discharged into surface waters, shall contain the least concentration of settleable material possible, and shall meet all conditions of section 402, the National Pollutant Discharge Elimination System (NPDES) permit.
(5) Overall construction site management measures to
address changes at the Project site as the Project moves through different phases and changes that account for
rainy and dry season management practices.
(6) Pollution control measures and construction activity methods that will prevent entrance, or accidental spillage, of solid matter, contaminants, debris, or other pollutants or wastes, into streams, flowing or dry watercourses, lakes, wetlands, reservoirs, or underground water sources. Such pollutants and wastes include, but are not restricted to:
refuse, garbage, cement, sanitary waste, industrial waste, hazardous materials, radioactive substances, oil and other petroleum products, aggregate processing, tailings,
mineral salts, and thermal pollution.
(7) Control measures for stockpiled or deposited materials prohibiting the stockpile or deposit of excavated materials, or other construction materials, near or on stream banks, lake shorelines, or other watercourse perimeters where
they can be washed away by high water or storm runoff, or can, in any way, encroach upon the watercourse.
(8) Develop and implement a Rain Event Action Plan (REAP), if required, that must be designed and implemented to
protect all exposed portions of the site 48 hours prior to any likely precipitation event.
(9) Monitoring, reporting and record keeping, as necessary to achieve compliance with applicable Permit requirements, including but not limited to annual reports and rain event reports.
(d) City retains the right to procure and maintain coverage under the Construction General Permit for the Project site if the Contractor fails to draft a SWPPP or other Construction General Permit related document, or fails to proceed in a manner that is satisfactory to City. City reserves the right to implement its own SWPPP at the Project site, and hire additional contractors to maintain compliance. Whether Contractor has adequately
38077.00180\29080232.10
-129- 01 00 00 – GENERAL REQUIREMENTS
maintained compliance with the Construction General Permit shall be City’s sole determination. In the event that Contractor has failed or is unable to maintain compliance with the Construction General Permit, any costs or fines incurred by City in
implementing a SWPPP, or otherwise maintaining compliance with the Construction General Permit shall be paid by the Contractor.

4. For those Work sites where construction activity results in the disturbance of less than one acre of total land area and/or do not need coverage under the Construction General Permit, the Contractor shall be responsible for preparing and implementing construction industry best management practices to eliminate or reduce the discharge of pollutants from construction sites, such as the best management practices set forth in the CASQA Construction BMP Handbook.

5. In addition to compliance with the Permit, Contractor shall comply with the lawful requirements of any applicable municipality, district, drainage district, flood control district, and other local agencies regarding discharges of storm water, surface water, groundwater or other nuisance waters off of the Project site.

6. Contractor violations.
(a) Failure to implement the SWPPP or otherwise comply with the Construction General Permit or local state and federal laws is a violation of this Contract. Notwithstanding any other indemnity contained in this Agreement, Contractor agrees to indemnify, defend – with counsel acceptable to the City – and hold harmless the City, its officials, officers, agents, employees and authorized volunteers from and against any and all claims, demands, losses or liabilities of any kind or nature which the City, its officials, officers, agents, employees and authorized volunteers may sustain or incur for noncompliance with the laws, regulations, and ordinances listed above, arising out of or in connection with the Work, except for liability resulting from the sole established negligence, willful misconduct or active negligence of the City, its officials, officers, agents, employees or authorized volunteers. (b) City reserves the right to defend any enforcement action or civil action brought against the City for Contractor’s failure to comply with any applicable water quality law, regulation, or policy.

Contractor hereby agrees to be bound by, and to reimburse the City for the costs associated with, any enforcement action and/or settlement reached between the City and any relevant
enforcement entity.
(c) City may seek damages from Contractor for delay in completing the Contract in accordance with the Contract Documents, caused by Contractor’s failure to comply with the the laws, regulations and 38077.00180\29080232.10
-130- 01 00 00 – GENERAL REQUIREMENTS
policies described in this Article, or any other relevant water quality law, regulation, order, or policy.
(d) If noncompliance with any relevant law, regulation or permit, order, or policy occurs, the Contractor shall report this to the City Representative immediately, with the specific information submitted in writing within 2 Days. Consistent violations of applicable Federal, State, or local laws, orders, regulations, or Water Quality Standards may result in City stopping all site activity until compliance is ensured. The Contractor shall not be entitled to any change in Contract Price or Contract Times, claim for damage, or additional compensation by reason of such a work stoppage. Corrective measures required to bring activities into compliance shall be at the Contractor's expense.

7. Oil storage tanks management.
(a) Storage tank placement. All oil or other petroleum product (hereinafter referred to collectively as oil) storage tanks shall be placed at least 20 feet from streams, flowing or dry watercourses, lakes, wetlands, reservoirs, and any other water source. (b) Storage area dikes. Storage areas shall be diked at least 12 inches high or graded and sloped to permit safe containment of leaks and spills equal to the capacity of all tanks and/or containers located within each area, plus a sufficient amount of freeboard to contain the 25-year rainstorm.
(c) Diked area barriers. Diked areas shall have an impermeable barrier at least 10 mils thick. Areas used for refueling operations shall have an impermeable liner at least 10 mils thick buried under 2 to 4 inches of soil.
(d) Spill Prevention Control and Countermeasure Plan (SPCC).

Where the location of a construction site is such that oil from an accidental spillage could reasonably be expected to enter into or upon the navigable waters of the United States or adjoining shorelines, and the aggregate storage of oil at the site is over 1,320 gallons or a single container has a capacity in excess of 660 gallons, the Contractor shall prepare an SPCC Plan. The Contractor shall submit the SPCC Plan to the Engineer at least 30 days prior to delivery or storage of oil at the site. The Plan must have been reviewed and certified by a registered professional engineer in accordance with 40 C.F.R., part 112

8. Underground tank prohibition. The Contractor shall not use underground storage tanks.

9. Construction safety standards. The Contractor shall comply with the sanitation and potable water requirements of Section 7 of United States 38077.00180\29080232.10
-131- 01 00 00 – GENERAL REQUIREMENTS
Bureau of Reclamation's publication “Reclamation Safety And Health Standards.”

10. Other Permits.
(a) Other permits applicable to the Project are listed in the Special Conditions. The Contractor shall obtain all other necessary licenses and permits.
(b) Monitoring. The Contractor is required to conduct monitoring in order to meet the requirements of the permits, which may include sampling, testing and inspections.
(c) Recordkeeping. The Contractor shall retain all records and data required by the permits for the time specified in the contract.

11. Cost. Except as specified herein, the cost of complying with this section shall be included in the Schedule of Pay Items for work which necessitate the water pollution prevention measures required by this paragraph.

END OF GENERAL REQUIREMENTS