2 Agenda
Background
Current Pavement Condition
Pavement Maintenance Strategy
Budget Scenarios / Summary
Questions
3 Background
Metropolitan Transportation Commission (MTC) is the regional transportation authority over the nine Bay Area county region.
MTC is responsible for overseeing the Bay Area’s transportation network, including transportation planning, financing, coordination, and management.
MTC manages their Pavement Management Program (PMP) that local agencies can be certified through to qualify for regional discretionary funds.
Agencies typically look for certification/recertification every other year.
The City has historically participated in MTC’s PMP and received a pavement condition report, aka the Pavement Management Technical Assistance Program (PTAP) report.
4 Pavement Management Technical
Assistant Program (PTAP – 24)
The PTAP process includes:
• Quality Management Report outlining pavement condition assessment procedures. • Budget Options Report with various funding scenarios, current PCI, future projected PCI. • Five-year plan / recommendation tailored to the individual local agency. • PMP certification to qualify the local agency to apply for regional funding opportunities.
5 Current Overall Network PCI = 71
Current PCI Condition
6 Current PCI Condition
Pavement Condition Definitions
1. Good (100-70)
2. Fair (Non-Load) (70-50)
3. Fair (Load) (70-50)
4. Poor (50-25)
5. Very Poor (25-0)
7 AB 1550 & SB 535 guide Climate
Investments in the State
Bills prioritize investments in
lower income communities
3 census tracts in Milpitas meet
AB 1550 low-income definition
Factor in decision making
process for investments
Current PCI Condition
Lower Income Census
Tracts
8 Past Resurfacing
Projects
Project Locations
• 2025 (Construction Summer 2025)
• 2024 (Construction Summer 2024)
• 2023
• 2022
• 2021
• 2020
2023
2023
2022
2022
2021
2021
2020
2020
2024
20252025
2020
2021
2022
2023
2024
2025
9 MTC’s Pavement Management Strategy
The Pavement Management Strategy is designed to focus on streets that require a lower-cost preventative maintenance, such as slurry seals, microsurfacing, and crack sealing, to extend the functional life.
This strategy is contrary to conventional wisdom of “worst-first”. However, this is a more cost-effective approach.
The budget and treatment recommendations described in the PTAP report follow this “best-first” approach.
MTC’s Maintenance Philosophies PCI Thresholds
0 100
70 50
25 V
IV
I
II III
Load
90 Maintenance Philosophies
Do Nothing
Slurry Seal
Thin Overlay
Thick Overlay/ Mill & Fill/
Cold In-Place Recycling
Reconstruct /
Full Depth Reclamation
Cape Seal
10 11
Pavement Strategy
Pavement Condition Treatments
• Good (100-70)
➢ Slurry Seal, Crack Seal, Etc
• Fair (Non-Load) (70-50)
➢ Cape Seal, Microsurfacing, Etc
• Fair (Load) (70-50)
➢ Thin Overlay (<2”)
• Poor (50-25)
➢ Mill & Fill
➢ Thick Overlay (>2”)
• Very Poor (25-0)
➢ Full Reconstruction
Four Budget Scenarios
• Deferred Maintenance = $ amount of maintenance and rehabilitation work that should have been completed to maintain the street in ‘Good’ condition, but had to be deferred due to funding deficiencies
12 Budget Scenarios
13 Budget Scenarios
Scenario 1 – Unconstrained
• Implementing the investment strategy recommended by MTC’s Pavement Maintenance Program needs module
• Eliminates the “deferred maintenance” backlog as quickly as possible • Average Annual Budget = $19 million
14 Budget Scenarios
Scenario 2 – Current Investment Level
• Implementing the current investment strategy programmed into the CIP to maintain a 71 PCI
• Accumulates deferred maintenance
• Average Annual Budget = $4.5 million
15 Budget Scenarios
Scenario 3 – Increase PCI by 5
• Implements a funding scenario to increase the PCI by 5 points • Accumulates deferred maintenance
• Average Annual Budget = $8 million
16 Budget Recommendation
Current Proposed Street Resurfacing Funding
• Street Resurfacing budget covers design, inspection, construction, and administration *ADA Curb Ramp upgrades (CP 4283) is funded by Gas Tax ($220k) and TDA III ($80k) Revenue vs Expenses
• Scenario 1 = $4.7M - $19M = ($14.3M) Deficit
• Scenario 2 = $4.7M - $4.5M = $0.2M
• Scenario 3 = $4.7M - $8.0M = ($3.3M) Deficit
2016 Measure B SB1 RMRA VRF CP4283* Total Available
Proposed Budget $1.9M $2.0M $0.5M $0.3M $4.7M
Preliminary 5-Year
Plan
20242025
2025/
2026
N Abbott Ave
Neighborhood
N Park
Victoria Dr/
Jacklin Rd
S Temple Dr
Neighborhood
2025
2024
• Great Mall Pkwy Phase 1
• Thompson St / Ct
2025
• Great Mall Pkwy Phase 2
• Tasman Dr & Alder Dr
2025/2026
• Dempsey Rd
Future Project Areas
• S Temple Dr Neighborhood
• N Park Victoria & Jacklin Rd
• N Abbott Ave Neighborhood
18 Questions?