38077.00180\29080232.10

-42- 00 61 13 – BOND FORMS

IN WITNESS WHEREOF, we have hereunto set our hands and seals this _______ day of ______________, 20___.
(Corporate Seal)
Contractor/Principal

By

Title

(Corporate Seal)
Surety

By

Attorney-in-Fact

(Attach Attorney-in-Fact Certificate) Title

(The rate of premium on this bond is ____________ per thousand. The total amount of premium charges is $_______________________________.
(The above must be filled in by corporate attorney.)

THIS IS A REQUIRED FORM
Any claims under this bond may be addressed to:
(Name and Address of Surety)

(Name and Address of Agent or
Representative for service of
process in California, if different
from above)
(Telephone number of Surety
and Agent or Representative for
service of process in California)






 





Page 187 of 396 ends

38077.00180\29080232.10

-43- 00 61 13 – BOND FORMS

Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.

STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally

appeared , who proved to me on the basis of satisfactory

evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/thei r authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WITNESS my hand and official seal.

Signature of Notary Public

OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.

CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT ¨ Individual
¨ Corporate Officer
Title(s) Title or Type of Document
¨ Partner(s) ¨ Limited
¨ General Number of Pages
¨ Attorney-In-Fact
¨ Trustee(s)
¨ Guardian/Conservator Date of Document
¨ Other:

Signer is representing:

Name Of Person(s) Or Entity(ies)

Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for Contractor/Principal.






 





Page 188 of 396 ends

38077.00180\29080232.10

-44- 00 61 13 – BOND FORMS

Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.

STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally

appeared , who proved to me on the basis of satisfactory

evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/thei r authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WITNESS my hand and official seal.

Signature of Notary Public

OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.

CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT ¨ Individual
¨ Corporate Officer
Title(s) Title or Type of Document
¨ Partner(s) ¨ Limited
¨ General Number of Pages
¨ Attorney-In-Fact
¨ Trustee(s)
¨ Guardian/Conservator Date of Document
¨ Other:

Signer is representing:

Name Of Person(s) Or Entity(ies)

Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for the Attorney-in-Fact. The Power-of Attorney to local representatives of the bonding company must also be attached.

END OF PERFORMANCE BOND





 





Page 189 of 396 ends

38077.00180\29080232.10

-45- 00 61 13 – BOND FORMS

1.2 Payment Bond (Labor and Materials).

KNOW ALL MEN BY THESE PRESENTS That
WHEREAS, the City of Milpitas (hereinafter design ated as the “City”), by action taken or a resolution passed _______________ , 20_____, has awarded to ________________________ hereinafter designated as the “Principal,” a contract for the work described as follows:
__________________________________ (the “Project”); and WHEREAS, said Principal is required to furnish a bond in connection with said contract; providing that if said Principal or any of its Subcontractors shall fail to pay for any materials, provisions, provender, equipment, or other supplies used in, upon, for or about the performance of the work contracted to be done, or for any work or labo r done thereon of any ki nd, or for amounts due under the Unemployment Insurance Code or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department from the wages of employees of said Principal and its Subcontractors with respect to such work or labor the Surety on this bond will pay for the same to the extent hereinafter set forth.

NOW THEREFORE, we, the Principal and ______ ____________________ as Surety, are held and firmly bound unto the City in the penal su m of ______________ Dollars ($___________) lawful money of the United States of America, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH that if said Principal, his or its subcontractors, heirs, executors, administrators, successors or assigns, shall fail to pay any of the persons named in Civil Code Section 9100, fail to pay for any materials, provisions or other supplies, used in, upon, for or about the performance of the work contracted to be done, or for any work or labor thereon of any kind, or amount s due under the Unemployment Insurance Code with respect to work or labor performed under the contract, or for any amounts required to be deducted, withheld, and paid over to the Employment Development Department or Franchise Tax Board from the wages of employees of the contractor and his subcontractors pursuant to Revenue and Taxation Code Section 18663, with respect to such work an d labor the Surety or Sureties will pay for the same, in an amount not exceeding the sum herein above specified, and also, in case suit is brought upon this bond, all lit igation expenses incurred by the City in such suit, including reasonable attorneys’ fees, court costs, expert witness fees and investigation expenses.

This bond shall inure to the benefit of any of the persons named in Civil Code Section 9100 so as to give a right of action to such persons or their assigns in any suit brought upon this bond.

It is further stipulated and agreed that the Surety on this bond shall not be exonerated or released from the obligation of this bond by any change , extension of time for performance, addition, alteration or modification in, to, or of any contract, plans, specifications, or agreement pertaining or relating to any scheme or work of improvement herein above described, or pertaining or relating to the furnishing of labor, materials, or equipment therefore, nor by any change or modification of any terms of payment or extension of the time for any payment pertaining or relating to any scheme or work of improvement herein above described, nor by any rescission or attempted rescission or attempted rescission of the contra ct, agreement or bond, nor by any conditions precedent or subsequent in the bond attempting to limit the right of recovery of claimants otherwise entitled to recover under any such contract or agreement or under the bond, nor by any fraud practiced by any person other than the clai mant seeking to recover on the bond and that 




 





Page 190 of 396 ends

38077.00180\29080232.10

-46- 00 61 13 – BOND FORMS

this bond be construed most strongly against th e Surety and in favor of all persons for whose benefit such bond is given, and under no circumstances shall Surety be released from liability to those for whose benefit such bond has been given, by reason of any breach of contract between the owner or City and original contractor or on the part of any obligee named in such bond, but the sole conditions of recovery shall be that claimant is a person described in Civil Code Section 9100, and has not been paid the full amount of his claim and that Surety does hereby waive notice of any such change, extension of time, addition, alteration or modification herein mentioned, including but not limited to the provisions of sections 2819 and 2845 of the California Civil Code.

IN WITNESS WHEREOF, we have hereunto set our hands and seals this _______ day of ______________, 20__.
(Corporate Seal)
Contractor/Principal

By

Title

(Corporate Seal)
Surety

By

Attorney-in-Fact

(Attach Attorney-in-Fact Certificate) Title






 





Page 191 of 396 ends

38077.00180\29080232.10

-47- 00 61 13 – BOND FORMS

Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.

STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally

appeared , who proved to me on the basis of satisfactory

evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/thei r authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WITNESS my hand and official seal.

Signature of Notary Public

OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.

CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT ¨ Individual
¨ Corporate Officer
Title(s) Title or Type of Document
¨ Partner(s) ¨ Limited
¨ General Number of Pages
¨ Attorney-In-Fact
¨ Trustee(s)
¨ Guardian/Conservator Date of Document
¨ Other:

Signer is representing:

Name Of Person(s) Or Entity(ies)

Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for Contractor/Principal. 




 





Page 192 of 396 ends

38077.00180\29080232.10

-48- 00 61 13 – BOND FORMS

Notary Acknowledgment
A notary public or other officer completing this certificate verifies only the identity of the individual who signed the document to which this certificate is attached, and not the truthfulness, accuracy, or validity of that document.

STATE OF CALIFORNIA
COUNTY OF ______________
On , 20___, before me, _______________________________, Notary Public, personally

appeared , who proved to me on the basis of satisfactory

evidence to be the person(s) whose name(s) is/are subscribed to the within instrument and acknowledged to me that he/she/they executed the same in his/her/thei r authorized capacity(ies), and that by his/her/their signature(s) on the instrument the person(s), or the entity upon behalf of which the person(s) acted, executed the instrument.

I certify under PENALTY OF PERJURY under the laws of the State of California that the foregoing paragraph is true and correct.

WITNESS my hand and official seal.

Signature of Notary Public

OPTIONAL
Though the information below is not required by law, it may prove valuable to persons relying on the document and could prevent fraudulent removal and reattachment of this form to another document.

CAPACITY CLAIMED BY SIGNER DESCRIPTION OF ATTACHED DOCUMENT Individual
Corporate Officer
Title(s) Title or Type of Document
Partner(s)
Limited
General Number of Pages
Attorney-In-Fact
Trustee(s)
Guardian/Conservator Date of Document
Other:

Signer is representing:

Name Of Person(s) Or Entity(ies)

Signer(s) Other Than Named Above
NOTE: This acknowledgment is to be completed for the Attorney-in-Fact. The Power-of-Attorney to local representatives of the bonding company must also be attached.

END OF PAYMENT BOND





 





Page 193 of 396 ends

38077.00180\29080232.10

GENERAL CONDITIONS

TABLE OF CONTENTS

Page

-49- 00 72 13 – GENERAL CONDITIONS

TABLE OF CONTENTS

00 72 13 – GENERAL CONDITIONS .......................................................................................52 ARTICLE 1 DEFINED TERMS .............................................................................................52 ARTICLE 2 CONTRACT DOCUMENTS ..............................................................................56 ARTICLE 3 PRECONSTRUCTION AND CONSTRUCTION COMMUNICATION ................57 ARTICLE 4 CONTRACT DOCUMENTS: COPIES & MAINTENANCE ................................57 ARTICLE 5 EXAMINATION OF DRAWINGS, SPECIFICATIONS AND SITE OF WORK ..............................................................................................................57 ARTICLE 6 EXISTENCE OF UTILITIES AT THE WORK SITE ............................................58 ARTICLE 7 SOILS INVESTIGATIONS ................................................................................58 ARTICLE 8 ARTICLE 8. CONTRACTOR’S SUPERVISION ................................................59 ARTICLE 9 WORKERS .......................................................................................................59 ARTICLE 10 INDEPENDENT CONTRACTORS ....................................................................59 ARTICLE 11 SUBCONTRACTS ............................................................................................60 ARTICLE 12 VERIFICATION OF EMPLOYMENT ELIGIBILITY ............................................60 ARTICLE 13 REQUESTS FOR SUBSTITUTION ...................................................................60 ARTICLE 14 SHOP DRAWINGS ...........................................................................................62 ARTICLE 15 SUBMITTALS ...................................................................................................62 ARTICLE 16 MATERIALS .....................................................................................................62 ARTICLE 17 PERMITS AND LICENSES ...............................................................................63 ARTICLE 18 TRENCHES ......................................................................................................63 ARTICLE 19 DIVERSION OF RECYCLABLE WASTE MATERIALS .....................................64 ARTICLE 20 REMOVAL OF HAZARDOUS MATERIALS ......................................................65 ARTICLE 21 SANITARY FACILITIES ....................................................................................65 ARTICLE 22 AIR POLLUTION CONTROL ............................................................................65 ARTICLE 23 LAYOUT AND FIELD ENGINEERING ..............................................................65 ARTICLE 24 TESTS AND INSPECTIONS .............................................................................65 ARTICLE 25 PROTECTION OF WORK AND PROPERTY ....................................................66 ARTICLE 26 CONTRACTOR’S MEANS AND METHODS .....................................................66 ARTICLE 27 AUTHORIZED REPRESENTATIVES ...............................................................67 ARTICLE 28 HOURS OF WORK ...........................................................................................67 ARTICLE 29 PAYROLL RECORDS ......................................................................................68 ARTICLE 30 PREVAILING RATES OF WAGES ...................................................................69 




 





Page 194 of 396 ends

38077.00180\29080232.10

GENERAL CONDITIONS

TABLE OF CONTENTS
(continued)
Page

-50- 00 72 13 - GENERAL CONDITIONS

TABLE OF CONTENTS

ARTICLE 31 PUBLIC WORKS CONTRACTOR REGISTRATION .........................................70 ARTICLE 32 EMPLOYMENT OF APPRENTICES .................................................................70 ARTICLE 33 NONDISCRIMINATION/EQUAL EMPLOYMENT OPPORTUNITY ...................70 ARTICLE 34 DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS .....................71 ARTICLE 35 LABOR/EMPLOYMENT SAFETY .....................................................................72 ARTICLE 36 INSURANCE .....................................................................................................72 ARTICLE 37 FORM AND PROOF OF CARRIAGE OF INSURANCE ....................................74 ARTICLE 38 TIME FOR COMPLETION AND LIQUIDATED DAMAGES ...............................75 ARTICLE 39 SCHEDULE OF VALUES, COST BREAKDOWN AND PERIODIC ESTIMATES .....................................................................................................77 ARTICLE 40 PROGRESS ESTIMATES AND PAYMENT ......................................................78 ARTICLE 41 SECURITIES FOR MONEY WITHHELD...........................................................79 ARTICLE 42 CHANGES AND EXTRA WORK. ......................................................................79 ARTICLE 43 FINAL ACCEPTANCE AND PAYMENT ............................................................92 ARTICLE 44 OCCUPANCY ...................................................................................................93 ARTICLE 45 INDEMNIFICATION ..........................................................................................93 ARTICLE 46 PROCEDURE FOR RESOLVING DISPUTES ..................................................94 ARTICLE 47 CITY’S RIGHT TO TERMINATE CONTRACT ..................................................94 ARTICLE 48 WARRANTY AND GUARANTEE OF WORK .................................................. 100 ARTICLE 49 DOCUMENT RETENTION & EXAMINATION ................................................. 103 ARTICLE 50 SEPARATE CONTRACTS .............................................................................. 103 ARTICLE 51 NOTICE AND SERVICE THEREOF ............................................................... 104 ARTICLE 52 NOTICE OF THIRD PARTY CLAIMS .............................................................. 104 ARTICLE 53 STATE LICENSE BOARD NOTICE ................................................................ 104 ARTICLE 54 INTEGRATION ............................................................................................... 104 ARTICLE 55 ASSIGNMENT OF CONTRACT ...................................................................... 105 ARTICLE 56 CHANGE IN NAME AND NATURE OF CONTRACTOR’S LEGAL ENTITY .... 105 ARTICLE 57 ASSIGNMENT OF ANTITRUST ACTIONS ..................................................... 105 ARTICLE 58 PROHIBITED INTERESTS ............................................................................. 105 ARTICLE 59 CONTROLLING LAW ..................................................................................... 105 ARTICLE 60 JURISDICTION; VENUE ................................................................................. 105 ARTICLE 61 LAWS AND REGULATIONS ........................................................................... 106 




 





Page 195 of 396 ends

38077.00180\29080232.10

GENERAL CONDITIONS

TABLE OF CONTENTS
(continued)
Page

-51- 00 72 13 - GENERAL CONDITIONS

TABLE OF CONTENTS

ARTICLE 62 PATENTS ....................................................................................................... 106 ARTICLE 63 OWNERSHIP OF CONTRACT DOCUMENTS ............................................... 106 ARTICLE 64 NOTICE OF TAXABLE POSSESSORY INTEREST ....................................... 106 ARTICLE 65 SURVIVAL OF OBLIGATIONS ....................................................................... 106






 





Page 196 of 396 ends

38077.00180\29080232.10

-52- 00 72 13 – GENERAL CONDITIONS

00 72 13 – GENERAL CONDITIONS
ARTICLE 1 DEFINED TERMS
Whenever used in the Contract Documents and printed with initial capital letters, the terms listed below will have the meanings indicated which are applicable to both the singular and plural thereof. In addition to terms specifically defined below, terms with initial capital letters in the Contract Documents include references to identifi ed articles and paragrap hs, and the titles of other documents or forms.

A. Act of God – An earthquake of magnitude of 3.5 or higher on the Richter scale or a tidal wave.

B. Addenda -- Written or graphic instruments issued prior to the submission of Bids which clarify, correct, or change the Contract Documents.

C. Additional Work -- New or unforeseen work will be classified as “Additional Work” when the City’s Representative determines that it is not covered by the Contract.

D. Applicable Laws -- The laws, statutes , ordinances, rules, codes, regulations, permits, and licenses of any ki nd, issued by local, state or federal governmental authorities or private authorit ies with jurisdiction (including utilities), to the extent they apply to the Work.

E. Bid -- The offer or proposal of a Bidd er submitted on the prescribed form setting forth the prices and other terms for the Work to be performed.

F. Bidder -- The in dividual or entity who submits a Bid directly to the City.

G. Caltrans Standard Specifications - St andard Specifications of the State of California, Department of Transportation, 2022. Any reference therein to a State agency or officer shall be interpreted as if the corresponding City office or agent acting under this contract were so specified.

H. Caltrans Standard Plans - Standard plans of the State of California, Department of Transportation, 2022. All metric measurem ents or quantities in the Caltrans Standard Plans shall be disregarded, an d equivalent United States measures used.

I. Change Order (“CO”) -- A document that authorizes an addi tion, deletion, or revision in the Work or an adjustment in the Contract Price or the Contract Times, issued on or after the Effective Date of the Contract, in accordance with the Contract Documents and in the form contained in the Contract Documents.

J. Change Order Request (“COR”) -- A re quest made by the Contractor for an adjustment in the Contract Price and/or Contract Times as the result of a Contractor-claimed change to the Work. This term may also be referred to as a Change Order Proposal (“COP”), or Request for Change (“RFC”).

K. City -- The City of Milpitas.





 





Page 197 of 396 ends

38077.00180\29080232.10

-53- 00 72 13 – GENERAL CONDITIONS

L. City Council, Council -- The City Council of the City.

M. City’s Representative -- The individual or entity as identified in the Special Conditions to act as the City’s Representative.

N. Claim -- A demand or assertion by the City or Contractor seeking an adjustment of Contract Price or Contract Times, or both, or other relief with respect to the terms of the Contract. A demand for money or services by a third party is not a Claim.

O. Contract -- The entire integrated written agreement between the City and Contractor concerning the Work. “Contr act” may be used interchangeably with “Agreement” in the Contract Documents. The Contract supersedes prior negotiations, representations, or agreements, whether written or oral, and includes all Contract Documents.

P. Contract Documents -- The documents listed in Section 00 52 13, Article 5. Some documents provided by the City to the Bidders and Contractor, including but not limited to reports and drawings of subs urface and physical conditions are not Contract Documents.

Q. Contract Price -- Amount to be paid by the City to the Contractor as full compensation for the performance of the Contract and completion of the Work, subject to any additions or deductions as provided in the Contract Documents, and including all applicable taxes and costs.

R. Contract Times -- The number of days or the dates stated in the Contract Documents to: achieve defined Milestones, if any; and to complete the Work so that it is ready for final payment.

S. Contractor -- The individual or enti ty with which the City has contracted for performance of the Work.

T. Contractor’s Designated On-Site Repres entative -- The Contractor’s Designated On-Site Representative will be as identified in Section 00 72 13, Article 3 and shall not be changed without prior written consent of the City.

U. Daily Rate -- The Daily Rate stipul ated in the Contract Documents as full compensation to the Contractor due to the City’s unreasonable delay to the Project that was not contemplated by the parties.

V. Day -- A calendar day of 24 hours meas ured from midnight to the next midnight.

W. Defective Work -- Work that is unsatisfactory, faulty, or deficient; or that does not conform to the Contract Documents; or that does not meet the requirements of any inspection, reference standard, test, or approval referenced in the Contract Documents.

X. Demobilization -- The complete dismant ling and removal by the Contractor of all of the Contractor’s temporary facilities, equipment, and personnel at the Site. 




 





Page 198 of 396 ends

38077.00180\29080232.10

-54- 00 72 13 – GENERAL CONDITIONS

Y. Drawings -- That part of the Contract Documents prepared by of the Engineer of Record which graphically shows the scope, extent, and character of the Work to be performed by Contractor. Shop Drawin gs and other Contractor submittals are not Drawings as so defined.

Z. Effective Date of the Contract -- The date indicated in the Contract on which it becomes effective, but if no such date is indicated, it means the date on which the Contract is signed and delivered by the last of the two parties to sign and deliver.

AA. Engineer, whenever not qu alified, shall mean the City Engineer or its designee, acting either directly or through properl y authorized agents, such agents acting severally within the scope of the particul ar duties entrusted to them. On all questions concerning the acceptance of materials, machinery, the classifications of material, the execution of work, conflicting interest of the contractors performing related work and the determination of cost s, the decision of the Engineer, duly authorized by the City Council, shall be binding and final upon both parties.

BB. Engineer of Record -- Th e individual, partnership, corp oration, joint venture, or other legal entity named as such in Section 00 73 13, Article 1.1. or any succeeding entity designated by the City.

CC. Hazardous Waste -- The term “Hazardous Waste” shall have the meaning provided in Section 104 of the Solid Waste Dispo sal Act (42 U.S.C. § 6903) as amended from time to time or, as defined in Sect ion 25117 of the Health and Safety Code, that is required to be removed to a class I, class II, or class III disposal site in accordance with provisions of existing law, whichever is more restrictive.

DD. Holiday – The Holidays are defined as legal Federal, State, and City holidays including:

New Year’s Day - January 1
Martin Luther King Jr.'s Birthday – Third Monday in January Lincoln's Birthday – February 12
President’s Day – Third Monday in February
Memorial Day - Last Monday in May
Independence Day - July 4
Labor Day - First Monday in September
Veteran’s Day - November 11
Thanksgiving Day - Fourth Thursday in November
Friday after Thanksgiving
Christmas Eve – December 24
Christmas Day - December 25
If any Holiday listed above falls on a Saturday, Saturday and the preceding Friday are both Holidays. If the Holiday should fall on a Sunday, Sunday and the following Monday are both Holidays.

EE. Notice of Award -- The written notice by the City to the Successful Bidder stating that upon timely compliance by the Successful Bidder with the conditions precedent listed therein, the City will sign and deliver the Contract. 




 





Page 199 of 396 ends

38077.00180\29080232.10

-55- 00 72 13 – GENERAL CONDITIONS

FF. Notice of Completion -- The form whic h may be executed by the City and recorded by the county where the Project is located constituting final acceptance of the Project.

GG. Notice to Proceed -- A written notice given by the City to Contractor fixing the date on which the Contractor may proceed with the Work and when Contract Times will commence to run.

HH. Project -- The total construction of which the Work to be performed under the Contract Documents may be the whole, or a part.

II. Recyclable Waste Materials -- Materials removed from the Site which are required to be diverted to a recycling center rather than an area landfill. Recyclable Waste Materials include asphalt, concrete, brick, concrete block, and rock.

JJ. Schedule of Submittals -- A schedule, prepared and maintained by Contractor, of required submittals and the time requirements to facilitate scheduled performance of related construction activities.

KK. Shop Drawings -- All drawings, diagrams, illustrations, schedules, and other data or information which are specifically pre pared or assembled by or for Contractor and submitted by Contractor to illustrate some portion of the Work.

LL. Specifications -- That part of the Co ntract Documents consisting of written requirements for materials, equipment, systems, standards and workmanship as applied to the Work, and certain admini strative requirements and procedural matters applicable thereto.

MM. Stop Payment Notice -- A written notice as defined in Civil Code section 8044.

NN. Subcontractor -- An individual or entity other than a Contractor having a contract with any other entity than the City for performance of any portion of the Work at the Site.

OO. Submittal -- Written and graphic info rmation and physical sa mples prepared and supplied by the Contractor demonstrating various portions of the Work.

PP. Successful Bidder -- The Bidder submitting a responsive Bid to whom the City makes an award.

QQ. Supplier -- A manufacturer, fabricator, supplier, distributor, material man, or vendor having a direct contract with Contractor or with any Subcontractor to furnish materials or equipment used in the performance of the Work or to be incorporated in the Work.

RR. Underground Facilities -- All underground pipelines, conduits, ducts, cables, wires, manholes, vaults, tanks, tunnels, or other such facilities or attachments, and any encasements containing such facilities, including those that convey electricity, gases, steam, liquid petr oleum products, telephone or other communications, cable television, water, wastewater, storm water, other liquids or chemicals, or traffic or other control systems.





 





Page 200 of 396 ends

38077.00180\29080232.10

-56- 00 72 13 – GENERAL CONDITIONS

SS. Unit Price Work -- Work to be paid for on the basis of unit prices as provided by the Contractor in its bid or as adjusted in accordance with the Contract Documents.

TT. Warranty -- A written guarantee provided to the City by the Contractor that the Work will remain free of defects and suitable for its intended use for the period required by the Contract Documents or the longest period permitted by the law of this State, whichever is longer.

UU. Work -- The entire construction or the various separately identifiable parts thereof required to be provided under the Contract Documents. Work includes and is the result of performing or providing all labor, services, and documentation necessary to produce such construction, and furnishing, installing, and incorporating all materials and equipment into such construc tion, all as required by the Contract Documents.

ARTICLE 2 CONTRACT DOCUMENTS
A. Contract Documents. The Contract Documents are complementary, and what is called for by one shall be as binding as if called for by all.

B. Interpretations. The Contract Documents are intended to be fully cooperative and complementary. If the Contractor observes that any documents are in conflict, the Contractor shall promptly notify the Engineer in writing. In case of conflicts between the Contract Documents, the order of precedence shall be as follows:

1. Change Orders

2. Contract

3. Addenda

4. Special Conditions

5. Technical Specifications

6. Plans (Contract Drawings)

7. General Conditions

8. Instructions to Bidders

9. Notice Inviting Bids

10. Contractor’s Bid Forms

11. City Standard Specifications

12. City Standard Drawings

13. Caltrans Standard Specifrications, except Division 1

14. Caltrans Standard Plans
Reference DocumentsWith reference to the Drawings, the order of precedence shall be as follows:

1. Figures govern over scaled dimensions

2. Detail drawings govern over general drawings

3. Addenda or Change Order drawings govern over Contract Drawings

4. Contract Drawings govern over Standard Drawings

5. Contract Drawings govern over Shop Drawings
C. Conflicts in Contract Documents. Notwithstanding the orders of precedence established above, in the ev ent of conflicts, the higher standard, higher quality, and most expensive shall always apply.





 





Page 201 of 396 ends

38077.00180\29080232.10

-57- 00 72 13 – GENERAL CONDITIONS

D. Organization of Contract Documents.Organization of the Contract Documents into divisions, sections, and articles, and arrangement of drawings shall not control the Contractor in dividing Project Work among subcontractors or in establishing the extent of Work to be performed by any trade.

ARTICLE 3 PRECONSTRUCTION AND CONSTRUCTION COMMUNICATION Before any Work at the site is started, a conference attended by the City, Contractor, City’s Representative, and others as appropriate will be held to establish a working understanding among the parties as to the Work and to discuss the schedules referred to herein, procedures for handling Shop Drawings and other submittals , processing Applications for Payment, and maintaining required records.

At this conference the City and Contractor each shall designate, in writing, a specific individual to act as its authorized representative with respec t to the services and responsibilities under the Contract. Such individuals shall have the authority to transmit instructions, receive information, render decisions relative to the Contract, and otherwise act on behalf of each respective party.

ARTICLE 4 CONTRACT DOCUMENTS: COPIES & MAINTENANCE
Contractor will be furnished, free of charge, five (5) copies of the Contract Documents. Additional copies may be obtained at cost of reproduction.

Contractor shall maintain a clean, undamaged se t of Contract Documents, including submittals, at the Project site.

ARTICLE 5 EXAMINATION OF DRAWINGS, SPECIFICATIONS AND SITE OF WORK A. Examination of Contract Documents. Before commencing any portion of the Work, Contractor shall again carefully examine all applicable Contract Documents, the Project site, and other information gi ven to Contractor as to materials and methods of construction and other Proj ect requirements. Contractor shall immediately notify the Engine er of any potential error, inconsistency, ambiguity, conflict, or lack of detail or explanation. If Contractor performs, permits, or causes the performance of any Work which is in error, inconsistent or ambiguous, or not sufficiently detailed or explained, Contractor shall bear any and all resulting costs, including, without limitation, the cost of correction. In no case shall the Contractor or any subcontractor proceed with Work if uncertain as to the applicable requirements.

B. Additional Instructions. After notification of any error, inconsistency, ambiguity, conflict, or lack of detail or explanation, the Engineer will provide any required additional instructions, by means of drawings or other written direction, necessary for proper execution of Work.

C. Quality of Parts, Construction and Finish. All parts of the Work shall be of the best quality of their respec tive kinds and the Contractor must use all diligence to inform itself fully as to the required construction and finish.

D. Contractor’s Variation from Contract Document Requirements. If it is found that the Contractor has varied from the requirements of the Contract Documents 




 





Page 202 of 396 ends

38077.00180\29080232.10

-58- 00 72 13 – GENERAL CONDITIONS

including the requirement to comply with all applicable laws, ordinances, rules and regulations, the Engineer may at any time, before or after completion of the Work, order the improper Work removed, remade or replaced by the Contractor at the Contractor’s expense.

ARTICLE 6 EXISTENCE OF UTILITIES AT THE WORK SITE
A. The City has endeavored to determine the existence of utilities at the Project site from the records of the owners of known utilities in the vicinity of the Project. The positions of these utilities as derived from such records are shown on the Plans.

B. Unless indicated otherwise on the Plans and Specifications, no excavations were made to verify the locations shown for underground utilities. The service connections to these utilities may not be not shown on the Plans. Any connections shown on the Plans are general locations. It shall be the responsibility of the Contractor to determine the exact loca tion of all service connections. The Contractor shall make its own investigations, including exploratory excavations, to determine the locations and type of servi ce connections, prior to commencing Work which could result in damage to such utilities. The Contractor shall immediately notify the City in writing of any utility discovered in a different position than shown on the Plans or which is not shown on the Plans.

C. If applicable, all water meters, water valves , fire hydrants, electrical utility vaults, telephone vaults, gas utility valves, and other subsurface structures shall be relocated or adjusted to final grade by the Contractor. Locations of existing utilities shown on the Plans are approximate and may not be complete. The Contractor shall be responsible for coordinating its Work with all utility companies during the construction of the Work.

D. Notwithstanding the above, pursuant to section 4215 of the Government Code, the City has the responsibility to identify, with reasonable accuracy, main or trunkline facilities on the plans and specifications. In the event that main or trunkline utility facilities are not identified with reasonable accuracy in the plans and specifications made a part of the invitation for Bids, the City shall assume the responsibility for their timely removal, relocation, or protection.

E. Contractor, except in an emergency, shall contact the appropriate regional notification center (USA North), Northern California Underground Service Alert at 811 or 1-800-227-2600 or on-line at usanorth811.org at least two working days prior to commencing any excavation if the excavation will be performed in an area which is known, or reasonably should be known, to contain subsurface installations other than the underground facilities owned or operated by the City, and obtain an inquiry identification number from that notifi cation center. No excavation shall be commenced or carried out by the Contractor unless such an inquiry identification number has been assigned to the Contractor or any subcontractor of the Contractor and the City has been given the identification number by the Contractor.

ARTICLE 7 SOILS INVESTIGATIONS
A. Reports and Drawings. The Special Conditions identify:





 





Page 203 of 396 ends

38077.00180\29080232.10

-59- 00 72 13 – GENERAL CONDITIONS

1. those reports known to the City of explorations and tests of subsurface conditions at or contiguous to the site; and

2. those drawings known to the City of ph ysical conditions relating to existing surface or subsurface structures at the site (except Underground Facilities).

B. Limited Reliance by Contractor on Technical Data Authorized. Contractor may rely upon the accuracy of the “technical data” contained in such reports and drawings, which were expressly not created or obtained to evaluate or assist in the evaluation of constructability, and are not Contract Documents. Contractor shall make its own interpretation of the “technical data” and shall be solely responsible for any such interpretations. Except for reliance on the accuracy of such “technical data,” Contractor may not rely upon or ma ke any claim against the City, City’s Representative, or Engineer of Record, or any of their officers, directors, members, partners, employees, agents, consultants, or subcontractors, with respect to:

1. the completeness of such reports and drawings for Contractor’s purposes, including without limitation any aspects of the means, methods, techniques, sequences, and procedures of construction to be employed by Contractor, and safety precautions and programs incident thereto; or

2. other data, interpretations, op inions, conclusions and information contained in such reports or shown or indicated in such drawings; or

3. any Contractor interpretation of or conclusion drawn from any “technical data” or any such other data, interpretations, opinions, or information.

ARTICLE 8 CONTRACTOR’S SUPERVISION
Contractor shall continuously ke ep at the Project site, a competent and experienced full-time Project superintendent acceptable to the City. Superintendent must be able to proficiently speak, read and write in English and shall have the au thority to make decisions on behalf of the Contractor. Contractor shall continuously provide efficient supervision of the Project.

ARTICLE 9 WORKERS
A. Contractor shall at all times enforce strict discipline and good order among its employees. Contractor shall not employ on the Project any unfit person or any one not skilled in the Work assigned to him or her.

B. Any person in the employ of the Cont ractor whom the City may deem incompetent or unfit shall be dismissed from the Work and shall not be employed on this Project.

ARTICLE 10 INDEPENDENT CONTRACTORS
Contractor shall be an independent contractor for the City and not an employee. Contractor understands and agrees that it and all of it s employees shall not be considered officers, employees, or agents of City an d are not entitled to benefits of any ki nd normally provided employees of City, including but not limited to , state unemployment compensation or workers’ compensation. Contractor assumes full responsibility for the acts and omissions of its employees or agents related to the Work.





 





Page 204 of 396 ends

38077.00180\29080232.10

-60- 00 72 13 – GENERAL CONDITIONS

ARTICLE 11 SUBCONTRACTS
A. Contractor agrees to bind every subcontractor to the terms of the Contract Documents as far as such terms are applicable to subcontractor’s portion of the Work. Contractor shall be as fully responsible to the City for the acts and omissions of its subcontractors and of persons either directly or indirectly employed by its subcontractors, as Contractor is for acts and omissions of persons directly employed by Contractor. Nothing contai ned in these Contract Documents shall create any contractual relationship between any subcontractor and the City.

B. The City reserves the right to accept all subcontractors. The City’s acceptance of any subcontractor under this Contract shall not in any way relieve Contractor of its obligations in the Contract Documents.

C. Prior to substituting any subcontractor listed in the Bid Forms, Contractor must comply with the requirements of the Subletting and Subcontracting Fair Practices Act pursuant to California Public Contract Code section 4100 et seq.

ARTICLE 12 VERIFICATION OF EMPLOYMENT ELIGIBILITY
By executing this Contract, Contractor verifies that it fully complies with all requirements and restrictions of state and federal law respecting the employment of undocumented aliens, including, but not limited to, the Immigration Reform and Control Act of 1986, as may be amended from time to time, and shall require all subcontractors, sub-subcontractors and consultants to comply with the same. Each person executing this Contract on behalf of Contractor verifies that he or she is a duly authorized officer of Contractor and that any of the following shall be grounds for the City to terminate the Contract for cause: (1) failure of the Contractor or its subcontractors, sub-subcontractors or consultants to meet any of the requirements provided for in this Article; (2) any misrepresentation or material omission concerning compliance with such requirements; or (3) failure to immediately remove from the Work any person found not to be in compliance with such requirements.

ARTICLE 13 REQUESTS FOR SUBSTITUTION
A. For the purposes of this provision, the term “substitution” shall mean the substitution of any material, method or se rvice substantially equal to or better in every respect to that indicated in the Standard Specificat ions or otherwise referenced herein.

B. Pursuant to Public Contra ct Code section 3400(b), the City may make a finding that is described in the Notice Inviting Bids that designates certain products, things, or services by specific brand or trade name.

C. Unless specifically designated in the Special Conditions, whenever any material, process, or article is indicated or specif ied by grade, patent, or proprietary name or by name of manufacturer, such specif ications shall be deemed to be used for the purpose of facilitating the description of the material, process, or article desired and shall be deemed to be followed by the words “or equal.” Contractor may, unless otherwise stated, offer for substitu tion any material, pr ocess, or article which may be substantially equal to or better in every respect to that so indicated 




 





Page 205 of 396 ends

38077.00180\29080232.10

-61- 00 72 13 – GENERAL CONDITIONS

or specified in the Contract Documents. However, the City has adopted uniform standards for certain materials, processes, and articles.

D. The Contractor shall submit substitution requests, together with substantiating data, for substitution of any “or equal” material, process, or article no later than 15 (15) calendar days after award of Contract. Provisions regarding submission of substitution requests shall not in any way authorize an extension of time for the performance of this Contract. If a substitution request is rejected by the City, the Contractor shall provide the material, method or service specified herein. The City shall not be responsible for any costs in curred by the Contractor associated with substitution requests. The burden of pr oof as to the equality of any material, process, or article shall rest with the Co ntractor. The Engineer has the complete and sole discretion to determine if a material, process, or article is substantially equal to or better than that specified and to approve or reject all substitution requests.

E. Substantiating data as described above shall include, at a minimum, the following information:

1. A signed affidavit from the Contractor stating that the material, process, or article proposed as a substitution is substantially equal to or better than that specified in every way except as may be listed on the affidavit.

2. Illustrations, specifications, catalog cut sheets, and any other relevant data required to prove that the material, process, or article is substantially equal to or better than that specified.

3. A statement of the cost implications of the substitution being requested, indicating whether and why the proposed substitution will reduce or increase the amount of the contract.

4. Information detailing the durability and lifecycle costs of the proposed substitution.

F. Failure to submit all the required substantiating data detailed above in a timely manner so that the substitution request can be adequately reviewed may result in rejection of the substitution request. The Engineer is not obligated to review multiple submittals related the same substitution request resulting from the Contractor’s failure to initially submit a complete package.

G. Time limitations within this Article shall be strictly complied with and in no case will an extension of time for completion of the contract be granted because of Contractor’s failure to provide substitution requests at the time and in the manner described herein.

H. The Contractor shall bear the costs of all City work associated with the review of substitution requests.

I. If substitution requests approved by th e Engineer require that Contractor furnish materials, methods or services more expensive than that specified, the increased costs shall be borne by Contractor.





 





Page 206 of 396 ends

38077.00180\29080232.10

-62- 00 72 13 – GENERAL CONDITIONS

ARTICLE 14 SHOP DRAWINGS
A. Contractor shall check and verify all fi eld measurements and shall submit with such promptness as to provide adequate time for review and cause no delay in its own Work or in that of any other contractor, subcontractor, or worker on the Project, six (6) copies of all shop drawings, calculations, schedules, and materials list, and all other provisions required by the Contract Documents. Contractor shall sign all submittals affirming that submittals have been reviewed and approved by Contractor prior to submission to Engineer. Each signed submittal shall affirm that the submittal meets all the requirements of the Contract Documents except as specifically and clearly noted and listed on the transmittal letter of the submittal.

B. Contractor shall make any corrections required by the Engineer, and file with the Engineer six (6) corrected copies each, and furnish such other copies as may be needed for completion of the Work. Engineer’s acceptance of shop drawings shall not relieve Contractor from responsibi lity for deviations from the Contract Documents unless Contractor has, in writin g, called Engineer’s attention to such deviations at time of submission and has secure d the Engineer’s written acceptance. Engineer’s acceptance of shop drawings shall not relieve Contractor from responsibility for errors in shop drawings.

ARTICLE 15 SUBMITTALS
A. Contractor shall furnish to the Engine er for approval, prior to purchasing or commencing any Work, a log of all samples, material lists and certifications, mix designs, schedules, and other submittals, as required in the Contract Documents.

The log shall indicate whether samples will be provided in accordance with other provisions of this Contract.

B. Contractor will provide samples and submittals, together with catalogs and supporting data required by the Engineer, to the Engineer within a reasonable time period to provide for adequate review and avoid delays in the Work.

C. These requirements shall not authorize any extension of time for performance of this Contract. Engineer will check and approve such samples, but only for conformance with design concept of work and for compliance with information given in the Contract Documents. Work shall be in accordance with approved samples and submittals.

ARTICLE 16 MATERIALS
A. Except as otherwise spec ifically stated in the Contract Documents, Contractor shall provide and pay for all materials, la bor, tools, equipment, lights, power, transportation, superintendence, temporary constructions of every nature, and all other services and facilities of every nature whatsoever necessary to execute and complete this Contract within specified time.

B. Unless otherwise specified, all material s shall be new and the best of their respective kinds and grades as noted and/or specified, and workmanship shall be of good quality.





 





Page 207 of 396 ends

38077.00180\29080232.10

-63- 00 72 13 – GENERAL CONDITIONS

C. Materials shall be furnished in ample qu antities and at such times as to ensure uninterrupted progress of the Work and shall be stored properly and protected as required by the Contract Documents. Contractor shall be entirely responsible for damage or loss by weather or other causes to materials or Work.

D. No materials, supplies, or equipment for Work under this Contract shall be purchased subject to any chattel mortgage or under a conditional sale or other agreement by which an interest therein or in any part thereof is retained by the seller or supplier. Contractor warrants good title to all ma terial, supplies, and equipment installed or incorporated in the Work and agrees upon completion of all work to deliver the Project, to the City free from any claims, liens, or charges.

E. Materials shall be stored on the Project si te in such manner so as not to interfere with any operations of the City or any independent contractor.

F. Contractor shall verify all measuremen ts, dimensions, elevations, and quantities before ordering any materials or perfor ming any Work, and the City shall not be liable for Contractor’s failure to so. No additional compensation, over and above payment for the actual quantities at the prices set out in the Bid Form, will be allowed because of differences between actual measurements, dimension, elevations and quantities and those indicated on the Plans and in the Specifications.Any difference therein sh all be submitted to the Engineer for consideration before proceeding with the Work.

G. The City shall provide compensation for actual quantities of materials installed in accordance with the Contract Documents and at the price set forth in the Contractor’s bid and/or executed change order. The City is not obligated to pay for materials stored on/off site but not yet installed in accordance with the Contract Documents.

ARTICLE 17 PERMITS AND LICENSES
A. Contractor shall obta in all other necessary permits and licenses for the construction of the Project, including encroachment permits, and shall pay all fees required by law and shall comply with all laws, ordinances, rules and regulations relating to the Work and to the preservation of public health and safety. Before acceptance of the Project, the Contractor shall submit all licenses, permits, certificates of inspection and required approvals to the City. Any construction permits required by City for performing any work on this project will be issued by City at no charge to Contractor. Contractor and all subcontractors shall maintain a City business license at all times they are performing the Work.

ARTICLE 18 TRENCHES
A. Trenches Five Feet or More in Depth. Contractor shall submit to the Engineer at the preconstruction meeting, a detailed plan showing the design of shoring, bracing, sloping or other provisions to be made for worker protection from hazards of caving ground during the excavation of any trench or trenches five feet or more in depth. If such plan varies from shoring system standards established by the Construction Safety Orders of the California Code of Regulations, Department of Industrial Relations, the plan shall be prepared by a California registered civil or 




 





Page 208 of 396 ends

38077.00180\29080232.10

-64- 00 72 13 – GENERAL CONDITIONS

structural engineer. The plan shall not be less effective than the shoring, bracing, sloping, or other provisions of the Constr uction Safety Orders, as defined in the California Code of Regulati ons. The Contractor shall designate in writing the “competent person” as defined in Title 8, California Code of Regulations, who shall be present at the Work Site each day that trenching/excavation is in progress. The “competent person” shall prepare and provide daily trenching/excavation inspection reports to the Engineer. Cont ractor shall also submit a copy of its annual California Occupational Safety and Health Administration (Cal/OSHA) trench/excavation permit.

B. Excavations Deeper than Four Feet. If the Work involves excavating trenches or other excavations that extend deeper than four feet below the surface, Contractor shall promptly, and before the excavation is further disturbed, notify the City in writing of any of the following conditions:

1. Material that the Contractor believes may be material that is hazardous waste, as defined in section 25117 of the Health and Safety Code, that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law.

2. Subsurface or latent physical conditions at the site differing from those indicated.

3. Unknown physical conditions at the site of any unusual nature, different materially from those ordinarily enco untered and generally recognized as inherent in work of the character provided for in the Contract The City shall promptly investigate the conditions, and if it finds that the conditions do so materially differ, or do involve hazardous waste, and cause a decrease or increase in Contractor’s cost of, or the time required for, performance of any part of the Work, shall issue a change orde r under the procedures described in the Contract Documents.

In the event that a dispute arises between the City and the Contractor as to whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the Contractor’s cost of, or time required for, performance of any part of the Work, the Contractor sha ll not be excused from any scheduled completion date provided for by the Contract, but shall proceed with all Work to be performed under the Contract. Contractor sh all retain any and all rights provided either by contract or by law which pertain to the resolution of disputes and protests between the parties.

ARTICLE 19 DIVERSION OF RECYCLABLE WASTE MATERIALS
In compliance with the applicable City’s waste re duction and recycling efforts, Contractor shall divert all Recyclable Waste Materials to appropriate recycling centers as required for compliance with the local jurisdiction’s waste diversion ordinances, and provide the City Engineer with detailed records and quantities of the materials that were sent to recycling centers. Contractor will be required to submit weight tickets and written proof of diversion with its monthly progress payment requests. Contractor shall complete and execute any certification forms required by City or other 




 





Page 209 of 396 ends

38077.00180\29080232.10

-65- 00 72 13 – GENERAL CONDITIONS

applicable agencies to document Contractor’s compliance with these diversion requirements. All costs incurred for these waste diversion efforts shall be the responsibility of the Contractor.

ARTICLE 20 REMOVAL OF HAZARDOUS MATERIALS
Should Contractor encounter material reasonably believed to be polychlorinated biphenyl (PCB) or other toxic wastes and hazardous materials which have not been rendered harmless at the Project site, the Contractor shall immediately stop work at the affected Project site and shall report the condition to the City in writing. The City shall contract for any services required to directly remove and/or abate PCBs and other toxic wastes and hazardous materials, if required by the Project site(s), and shall not require the Contractor to subcontract for such services. The Work in the affected area shall not thereafter be resu med except by written agreement of the City and Contractor.

ARTICLE 21 SANITARY FACILITIES
Contractor shall provide sanitary temporary toilet buildings and hand washing facilities for the use of all workers. All toilets and hand washing facilities shall comply with all applicable federal, state and local laws, codes, ordinances, and regulations. Toilets shall be kept supplied with toilet paper and shall have workable door fasteners. Toilets and hand washing facilities shall be serviced no less than once weekly and shall be present in a quantity of not less than 1 per 20 workers as required by Cal/OSHA regulations. The toilets and hand washing facilities shall be maintained in a sanitary condition at all times. Use of toil et and hand washing facilities in the Work under construction shall not be permitted. Any other sa nitary facilities required by Cal/OSHA shall be the responsibility of the Contractor.

ARTICLE 22 AIR POLLUTION CONTROL
Contractor shall comply with all air pollution and dust control rules, regulations, ordinances and statutes, including, but not limited to, those required by thet Air Quality Management District. All containers of paint, thinner, curing compound, solvent or liquid asphalt shall be labeled to indicate that the contents fully comply with the applicable material requirements.

ARTICLE 23 LAYOUT AND FIELD ENGINEERING
All field engineering required for laying out the Work and establishing grades for earthwork operations shall be furnished by the Contractor at its expense.

ARTICLE 24 TESTS AND INSPECTIONS
A. If the Contract Documents, the Engineer, or any instructions, laws, ordinances, or public authority requires any part of the Work to be tested or Approved, Contractor shall provide the Engineer at least two (2) working days’ notice of its readiness for observation or inspection. If inspection is by a public authority other than the City, Contractor shall promptly inform the City of the date fixed for such inspection.

Required certificates of inspection (or si milar) shall be secured by Contractor.

Costs for City testing and City inspection shall be paid by the City. Costs of tests for Work found not to be in compliance shall be paid by the Contractor.

B. If any Work is done or covered up without the required testing or approval, the Contractor shall uncover or deconstruct the Work, and the Work shall be redone 




 





Page 210 of 396 ends

38077.00180\29080232.10

-66- 00 72 13 – GENERAL CONDITIONS

after completion of the testing at the Contractor’s cost in compliance with the Contract Documents.

C. Where inspection and testing are to be conducted by an in dependent laboratory or agency, materials or samples of materi als to be inspected or tested shall be selected by such laboratory or agency, or by the City, and not by Contractor. All tests or inspections of materials shall be made in accordance with the commonly recognized standards of national organizations.

D. In advance of manufacture of materials to be supplied by Contractor which must be tested or inspected, Contractor shall notify the City so that the City may arrange for testing at the source of supply. Any materials which have not satisfactorily passed such testing and inspection shall not be incorporated into the Work.

E. If the manufacture of materials to be inspected or tested will occur in a plant or location greater than sixty (60) miles from the City, the Contractor shall pay for any excessive or unusual costs associated with such testing or inspection, including but not limited to excessive travel time, standby time and required lodging.

F. Reexamination of Work may be ordered by the City. If so ordered, Work must be uncovered or deconstructed by Contractor. If Work is found to be in accordance with the Contract Documents, the City shall pay the costs of reexamination and reconstruction. If such work is found not to be in accordance with the Contract Documents, Contractor shall pay all costs.

ARTICLE 25 PROTECTION OF WORK AND PROPERTY
A. The Contractor shall be responsible for all damages to persons or property that occurs as a result of the Work. Contractor shall be responsible for the proper care and protection of all materials delivered and Work performed until completion and final Acceptance by the City. All Work sh all be solely at the Contractor’s risk.

Contractor shall adequately protect adjace nt property from settlement or loss of lateral support as necessary. Contractor shall comply with all applicable safety laws and building codes to prevent accidents or injury to persons on, about, or adjacent to the Project site where Work is being performed. Contractor shall erect and properly maintain at all times, as required by field conditions and progress of work, all necessary safeguards, signs, barriers, lights, and watchmen for protection of workers and the public, and shall post danger signs warning against hazards created in the course of construction.

B. In an emergency affecting safety of life or of work or of adjoining property, Contractor, without special instruction or authorization from the Engineer, is hereby permitted to act to prevent such threatened loss or injury; and Contractor shall so act, without appeal, if so authorized or instructed by the Engineer or the City. Any compensation claimed by Contractor on account of emergency work shall be determined by and agreed upon by the City and the Contractor.

ARTICLE 26 CONTRACTOR’S MEANS AND METHODS
Contractor is solely responsible for the means and methods utilized to perform the Work. In no case shall the Contractor’s means and methods deviate from commonly used industry standards. 




 





Page 211 of 396 ends

38077.00180\29080232.10

-67- 00 72 13 – GENERAL CONDITIONS

ARTICLE 27 AUTHORIZED REPRESENTATIVES
The City shall designate representatives, who shall have the right to be present at the Project site at all times. The City may design ate an inspector who shall have the right to observe all of the Contractor’s Work. The inspector shall not be responsible for the Contractor’s failure to carry out the Work in accordance with the Contract Documents.Contractor shall provide safe and proper facilities for such access.

ARTICLE 28 HOURS OF WORK
A. As provided in Article 3 (commencing at section 1810), Chapter 1, Part 7, Division 2 of the Labor Code, Contractor stipulat es that eight (8) hours of labor shall constitute a legal day’s work. The time of service of any worker employed at any time by the Contractor or by any subc ontractor on any subcontract under this Contract upon the Work or upon any part of the Work contemplated by this Contract is limited and restricted to ei ght (8) hours during any one calendar day and 40 hours during any one calendar week, except as hereinafter provided.

Notwithstanding the provisions herein above set forth, work performed by employees of Contractor in excess of eight (8) hours per day, and 40 hours during any one week, shall be permitted upon this public work upon compensation for all hours worked in excess of eight (8) ho urs per day at not less than one and one- half times the basic rate of pay.

B. The Contractor and every subcontractor shall keep an accurate record showing the name of and actual hours worked each calendar day and each calendar week by each worker employed in connection with the Work or any part of the Work contemplated by this Contract. The record shall be kept open at all reasonable hours to the inspection of the City and to the Division of Labor Law Enforcement, Department of Industrial Relations of the State of California.

C. The Contractor shall pay to the City a penalty of twenty-five dollars ($25.00) for each worker employed in the execution of this Contract by the Contractor or by any subcontractor for each calendar day during which such worker is required or permitted to work more than eight (8) ho urs in any calendar day and 40 hours in any one calendar week in violation of th e provisions of Article 3 (commencing at section 1810), Chapter 1, Part 7, Division 2 of the Labor Code.

D. Any work necessary to be performed afte r regular working hours, or on Saturdays and Sundays or other holidays, shall be performed without additional expense to the City. Contractor shall also timely notify the City when work will be perfomed outside regular working hours or on weekends or holidays.

E. City will provide inspection during normal working hours from 7:00 a.m. to 3:30 p.m. Monday through Friday. Inspection before or after this time will be charged to the Contractor as reimbursable inspection time. Inspections on weekends requires two days’ notice for review and approval. Upon written request and approval the

8.5 hour working day may be changed to other limits subject to city/county ordinance.

F. Refer to the most current version of the City of Milpitas Noise Abatement Ordinance, Ord. 196.6 of the Municipal Co de Section V-213. It shall be unlawful 




 





Page 212 of 396 ends

38077.00180\29080232.10

-68- 00 72 13 – GENERAL CONDITIONS

for any person to engage or permit to en gage in construction of any building or related road or walkway, pool, or landscape improvement or in the construction operations related thereto including to operate, permit, use, or cause to operate any of the following at the Project site, other than between the hours of 7:00 a.m. to 7:00 p.m., Monday through Sunday, unless otherwise approved by the City:

1. Powered Vehicles

2. Construction Equipment

3. Loading and Unloading Vehicles

4. Domestic Power Tools
ARTICLE 29 PAYROLL RECORDS; LABOR COMPLIANCE
A. Pursuant to Labor Code section 1776, Contractor and all subcontractors shall maintain weekly certified payroll records, showing the names, addresses, Social Security numbers, work classifications, straight time and overtime hours worked each day and week, and the actual per diem wages paid to each journeyman, apprentice, worker, or other employee employed by them in connection with the Work under this Contract. Contractor shall certify under penalty of perjury that records maintained and submitted by Contractor are true and accurate. Contractor shall also require subcontractor(s) to certify weekly payroll records under penalty of perjury.

B. In accordance with Labor Code sect ion 1771.4, the Contractor and each subcontractor shall furnish the certified payroll records directly to the Department of Industrial Relations (“DIR”) on the specified interval and format prescribed by the DIR, which may include electronic submission. Contractor shall comply with all requirements and regulations from the DIR relating to labor compliance monitoring and enforcement. The requirement to submit certified payroll records directly to the Labor Commissioner unde r Labor Code section 1771.4 shall not apply to work performed on a public works project that is exempt pursuant to the small project exemption specified in Labor Code Section 1771.4.

C. Any stop orders issued by the Department of Industrial Relations against Contractor or any subcontractor that af fect Contractor’s performance of Work, including any delay, shall be Contractor’s sole responsibility. Any delay arising out of or resulting from such stop orders shall be considered Contractor caused delay subject to any applicable liquidated damages and shall not be compensable by the City. Contractor shall defend, indemnify an d hold the City, its officials, officers, employees and agents free and harmless from any claim or liability arising out of stop orders issued by the Department of Industrial Relations against Contractor or any subcontractor.

D. The payroll records described herein shall be certified and submitted by the Contractor at a time designated by the City. The Contractor shall also provide the following:





 





Page 213 of 396 ends

38077.00180\29080232.10

-69- 00 72 13 – GENERAL CONDITIONS

1. A certified copy of the employee’s payroll records shall be made available for inspection or furnished to such employee or his or her authorized representative on request.

2. A certified copy of all payroll records described herein shall be made available for inspection or furnished upon request of the DIR.

E. Unless submitted electronically, the certified payroll records shall be on forms provided by the Division of Labor Standa rds Enforcement (“DLSE”) of the DIR or shall contain the same information as the forms provided by the DLSE.

F. Any copy of records made available for inspection as copies and furnished upon request to the public or any public agency, the City, the Division of Apprenticeship Standards or the Division of Labor Stan dards Enforcement shall be marked or obliterated in such a manner as to prev ent disclosure of an individual's name, address and social security number. Th e name and address of the Contractor awarded the Contract or performing the contract shall not be marked or obliterated.

G. In the event of noncompliance with the requ irements of this Article, the Contractor shall have ten (10) calendar days in wh ich to comply subsequent to receipt of written notice specifying in what respects the Contractor must comply with this Article. Should noncompliance still be evident after such 10-day period, the Contractor shall pay a penalty of one hundred dollars ($100.00) to the City for each calendar day, or portion thereof, for each worker, until strict compliance is effectuated. Upon the request of the Division of Apprenticeship Standards or the Division of Labor Standards Enforcement, such penalties shall be withheld from progress payment then due.

H. The responsibility for compliance with th is Article shall rest upon the Contractor.

ARTICLE 30 PREVAILING RATES OF WAGES
A. The Contractor is aware of the requirements of Labor Code sections 1720 et seq. and 1770 et seq., as well as California Code of Regulations, Title 8, Section 16000 et seq. (“Prevailing Wage Laws”), which require the payment of prevailing wage rates and the performance of other requirements on certain “public works” and “maintenance” projects. Since this Project involves an applicable “public works” or “maintenance” project, as defined by the Prevailing Wage Laws, and since the total compensation is $1,000 or more, Contractor agrees to fully comply with such Prevailing Wage Laws. The Contractor shall obtain a copy of the prevailing rates of per diem wages at the commencement of this Contract from the website of the Division of Labor Statistics and Research of the Department of Industrial Relations located at www.dir.ca.gov. In the alternative, the Contractor may view a copy of the prevailing rate of per diem wages which are on file at the City’s Administration Office and shall be made available to interested parties upon request. Contractor shall make copies of the prevailing rates of per diem wages for each craft, classification, or type of worker needed to perform work on the Project available to interested parties upon request, and shall post copies at the Contractor’s principal place of business and at the Project site. Contractor shall defend, indemnify and hold the City, its officials, officers, employees and authorized volunteers free and 




 





Page 214 of 396 ends

38077.00180\29080232.10

-70- 00 72 13 – GENERAL CONDITIONS

harmless from any claims, liabilities, costs, penalties or interest arising out of any failure or allege failure to comply with the Prevailing Wage Laws.

B. The Contractor shall forfeit as a penalty to the City not more than Two Hundred Dollars ($200.00), pursuant to Labor Code section 1775, for each calendar day, or portion thereof, for each worker paid less than the prevailing wage rate as determined by the Director of the Department of Industrial Relations for such work or craft in which such worker is employed for any public work done under the Contract by it or by any subcontractor under it. The difference between such prevailing wage rate and the amount paid to each worker for each calendar day or portion thereof, for which each worker was paid less than the prevailing wage rate, shall be paid to each worker by the Contractor.

C. Contractor shall post, at appropriate conspicuous points on the Project site, a schedule showing all determined general prevailing wage rates and all authorized deductions, if any, from unpaid wages actually earned.

ARTICLE 31 PUBLIC WORKS CONTRACTOR REGISTRATION
Pursuant to Labor Code sections 1725.5 and 1771.1, the Contractor and its subcontractors must be registered with the Department of Industrial Re lations prior to the execution of a contract to perform public works. By entering into this Contract, Contractor represents that it is aware of the registration requirement and is currently registered with the DIR. Contractor shall maintain a current registration for the duration of the Project. Contractor shall further include the requirements of Labor Code sections 1725.5 and 1771.1 in any subcontract and ensure that all subcontractors are registered at the time this Co ntract is entered into and maintain registration for the duration of the Project. Notwithstandi ng the foregoing, the contractor registration requirements mandated by Labor Code Sections 1725.5 and 1771.1 shall not apply to work performed on a public works project that is ex empt pursuant to the small project exemption specified in Labor Code Sections 1725.5 and 1771.1.

ARTICLE 32 EMPLOYMENT OF APPRENTICES
A. Contractor and all subcontractors shal l comply with the requirements of Labor Code sections 1777.5 and 1777.6 in the employment of apprentices.

B. Information relative to apprenticeshi p standards, wage schedules, and other requirements may be obtained from the Director of Industrial Relations, ex officio the Administrator of Apprenticeship, San Francisco, California, or from the Division of Apprenticeship Standards and its branch offices.

C. Knowing violations of Labor Code section 1777.5 will result in forfeiture not to exceed one hundred dollars ($100.00) for each calendar day of non-compliance pursuant to Labor Code section 1777.7.

D. The responsibility for compliance with th is Article shall rest upon the Contractor.

ARTICLE 33 NONDISCRIMINATION/EQUAL EMPLOYMENT OPPORTUNITY Pursuant to Labor Code section 1735 and other applicable provisions of law, the Contractor and its subcontractors shall not discriminate agains t any employee or applicant for employment 




 





Page 215 of 396 ends

38077.00180\29080232.10

-71- 00 72 13 – GENERAL CONDITIONS

because of race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, marital status, sex, age, sexual orientation, or any other classifications protected by law on this Project. The Contractor will take affirmative action to insure that employees are treated during employm ent or training without regard to their race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, marital status, sex, age, sexual orient ation, or any other classifications protected by law.

Employment Eligibility; Contractor . By executing this Contract, Contractor verifies that it fully complies with all requirements and restrictions of state and federal law respecting the employment of undocumented aliens, including, but not limited to, the Immigration Reform and Control Act of 1986, as may be amended from time to time. Such requirements and restrictions include, but are not limited to, examination and retention of documentation confirming the identity and immigration status of each employee of the Contractor. Cont ractor also verifies that it has not committed a violation of any such law within the five (5) years immediately preceding the date of execution of this Contract, and shall not violate any such law at any time during the term of the Contract.

Contractor shall avoid any violation of any such law during the term of this Contract by participating in an electronic verification of work authorization program operated by the United States Department of Homeland Security, by participating in an equivalent federal work authorization program operated by the United States Department of Homeland Security to verify information of newly hired employees, or by some other legally acceptable method. Contractor shall maintain records of each such verification, and shall make them available to the City or its representatives for inspection and copy at any time during normal business hours. The City shall not be responsible for any costs or expenses related to Contractor’s compliance with the requirements provided for or referred to herein.

Employment Eligibility; Subcontractors, Sub-subcontractors and Consultants. To the same extent and under the same conditions as Contractor, Contractor shall require all of its subcontractors, sub-subcontractors and consultants performing any part of the Work or of this Contract to make the same verifications and comply with all requirements and restrictions provided for herein.

Employment Eligibility; Failure to Comply. Each person executing this Contract on behalf of Contractor verifies that he or she is a duly authorized officer of Contractor, and understands that any of the following shall be grounds for the City to terminate the Contract for cause: (1) failure of Contractor or its subcontractors, sub-subcontractors or consultants to meet any of the requirements provided for herein; (2) any misrep resentation or material omission concerning compliance with such requirements; or (3) failure to immediately remove from the Work any person found not to be in compliance with such requirements.

ARTICLE 34 DEBARMENT OF CONTRACTORS AND SUBCONTRACTORS
Contractors or subcontractors may not perform work on a public works project with a subcontractor who is ineligible to perform work on a public project pursuant to Labor Code section 1777.1 or 1777.7. Any contract on a public works project entered into between a contractor and a debarred subcontractor is void as a matter of law. A debarred subcontractor may not receive any public money for performing work as a subcontractor on a public works contract. Any public money that is paid, or may have been paid to a debarred subcontractor by a contractor on the project shall be returned to the City. The Contractor shall be responsible for the payment of wages to workers of a debarred subcontractor who has been allowed to work on the project. 




 





Page 216 of 396 ends

38077.00180\29080232.10

-72- 00 72 13 – GENERAL CONDITIONS

ARTICLE 35 LABOR/EMPLOYMENT SAFETY
The Contractor shall comply with all applicable laws and regulations of the federal, state, and local government, including Cal/OSHA requirements and requirements for verification of employees’ legal right to work in the United States.

The Contractor shall maintain emergency first aid treatment for his employees which complies with the Federal Occupational Safety and Health Act of 1970 (29 U.S.C. § 651 et seq.), and California Code of Regulations, Title 8, Industrial Relations Divis ion 1, Department of Industrial Relations, Chapter 4. The Contractor shall ensure the availability of emergency medical services for its employees in accordance with California Code of Regulations, Title 8, Section 1512.

The Contractor shall submit the Illness and Injury Prevention Program and a Project site specific safety program to the City prior to beginning Work at the Project site. Contractor shall maintain a confined space program that meets or exceeds th e City Standards. Contractor shall adhere to the City’s lock out tag out program.

ARTICLE 36 INSURANCE
The Contractor shall obtain, and at all times during performance of the Work of Contract, maintain all of the insurance described in this Article. Contractor shall not commence Work under this Contract until it has provided evidence satisfactory to the City that it has secured all insurance required hereunder. Contractor shall not allow any subcontractor to commence work on any subcontract until it has provided evidence satisfactory to the City that the subcontractor has secured all insurance required unde r this Article. Failure to provide and maintain all required insurance shall be grounds for the City to terminate this Contract for cause. Contractor shall furnish City with original certificates of insurance and endorsements effective coverage required by this Contract on forms satisfactory to the City. The certificates and endorsements for each insurance policy shall be signed by a person author ized by that insurer to bind coverage on its behalf, and shall be on forms acceptable to the Cit y. All certificates and endorsements must be received and approved by the City before Work commences.

A. Additional Insureds; Waiver of Subrogation . The City, its elected and appointed officials, officers, attorneys, agents employees and volunteers shall be named as Additional Insureds on Contractor’s All Risk policy and on Contractor’s and its subcontractors’ policies of Commercial General Liability and Automobile Liability insurance using, for Contractor’s policy/ies of Commercial General Liability insurance, ISO CG forms 20 10 and 20 37 (or endorsements providing the exact same coverage, including completed operations), and, for subcontractors’ policies of Commercial General Liability insurance, ISO CG form 20 38 (or endorsements providing the exact same coverage). Notwithstanding the minimum limits set forth in this Contract for any type of insurance coverage, all available insurance proceeds in excess of the specified minimum limits of coverage shall be available to the parties required to be na med as Additional Insureds hereunder.

Contractor and its insurance carriers shall provide a Waiver of Subrogation in favor of those parties.

B. Workers’ Compensation Insurance . The Contractor shall provide workers’ compensation insurance for all of the employees engaged in Work under this Contract, on or at the Site, and, in case of any sublet Work, the Contractor shall require the subcontractor similarly to provide workers’ compensation insurance for 




 





Page 217 of 396 ends

38077.00180\29080232.10

-73- 00 72 13 – GENERAL CONDITIONS

all the latter’s employees as prescribed by State law. Any class of employee or employees not covered by a subcontracto r’s insurance shall be covered by the Contractor’s insurance. In case any class of employees engaged in work under this Contract, on or at the Site, is not protected under the Workers’ Compensation Statutes, the Contractor shall provide or shall cause a subcontractor to provide, adequate insurance coverage for the protection of such employees not otherwise protected. The Contractor is required to secure payment of compensation to his employees in accordance with the provisions of section 3700 of the Labor Code.

The Contractor shall file with the City certificates of his insurance protecting workers. Company or companies providing insurance coverage shall be acceptable to the City, if in the form and coverage as set forth in the Contract Documents.

C. Employer’s Liability Insurance. Contractor shall provide Employer’s Liability Insurance, including Occupational Disease, in the amount of at least one million dollars ($1,000,000.00) per person per accident. Contractor shall provide City with a certificate of Employer’s Liability Insurance. Such insurance shall comply with the provisions of the Contract Documents. The policy shall be endorsed, if applicable, to provide a Borrowed Serva nt/Alternate Employer Endorsement and contain a Waiver of Subrogation in favor of the City.

D. Commercial General Liability Insurance. Contractor shall provide “occurrence” form Commercial General Liability insurance coverage at least as broad as the most current ISO CGL Form 00 01, including but not limited to, premises liability, contractual liability, products/completed operations, personal and advertising injury which may arise from or out of Contractor’s operations, use, and management of the Site, or the performance of its obligations hereunder. The policy shall not contain any exclusion contrary to this Contract including but not limited to endorsements or provisions limiting coverage for (1) contractual liability (including but not limited to ISO CG 24 26 or 21 39); or (2) cross-liability for claims or suits against one insured against anothe r. Policy limits shall not be less than $1,000,000 per occurrence for bodily injury, personal injury and property damage.

If Commercial General Liability Insurance or other form with a general aggregate limit is used, either the general aggregat e limit shall apply separately to this project/location or the general aggregate limit shall be twice the required occurrence limit. Defense costs shall be paid in addition to the limits.

1. Such policy shall comply with all the re quirements of this Article. The limits set forth herein shall apply separately to each insured against whom claims are made or suits are brought, except with respect to the limits of liability.

Further the limits set forth herein sh all not be construed to relieve the Contractor from liability in excess of such coverage, nor shall it limit Contractor’s indemnification obligations to the City, and shall not preclude the City from taking such other acti ons available to the City under other provisions of the Contract Documents or law.

2. All general liability policies provided pursuant to the provisions of this Article shall comply with the provisions of the Contract Documents.

3. All general liability policies shall be written to apply to all bodily injury, including death, property damage, personal injury, owned and non-owned 




 





Page 218 of 396 ends

38077.00180\29080232.10

-74- 00 72 13 – GENERAL CONDITIONS

equipment, blanket contractual liability, completed operations liability, explosion, collapse, under-ground excavation, removal of lateral support, and other covered loss, however occa sioned, occurring during the policy term, and shall specifically insure the performance by Contractor of that part of the indemnification contained in these General Conditions relating to liability for injury to or death of persons and damage to property.

4. If the coverage contains one or mo re aggregate limits, a minimum of 50% of any such aggregate limit must remain available at all times; if over 50% of any aggregate limit has been paid or reserved, the City may require additional coverage to be purchased by Contractor to restore the required limits. Contractor may combine primary, umbrella, and as broad as possible excess liability coverage to achieve the total limits indicated above. Any umbrella or excess liability policy sh all include the additional insured endorsement described in the Contract Documents.

5. All policies of general liability insurance shall permit and Contractor does hereby waive any right of subrogation which any insurer of Contractor may acquire from Contractor by virtue of the payment of any loss.

E. Automobile Liability Insurance . Contractor shall provide “occurrence” form Automobile Liability Insurance at least as broad as ISO CA 00 01 (Any Auto) in the amount of, at least, one million dollars ($1,000,000) per accident for bodily injury and property damage. Such insurance shall provide coverage with respect to the ownership, operation, maintenance, use, loading or unloading of any auto owned, leased, hired or borrowed by Contractor or for which Contractor is responsible, in a form and with insurance companies acce ptable to the City. All policies of automobile insurance shall permit and Contractor does hereby waive any right of subrogation which any insurer of Contractor may acquire from Contractor by virtue of the payment of any loss.

F. Builder’s Risk [“All Risk”] Not applicable.

G. Pollution Liability Coverage. Not applicable.

H. Contractor shall require all tiers of sub-contractors working under this Contract to provide the insurance required under this Article unless otherwise agreed to in writing by City. Contractor shall make certain that any and all subcontractors hired by Contractor are insured in accordance with this Contract. If any subcontractor’s coverage does not comply with the foregoing provisions, Contractor shall indemnify and hold the City harmless from any damage, loss, cost, or expense, including attorneys’ fees, incurred by the City as a result thereof.

ARTICLE 37 FORM AND PROOF OF CARRIAGE OF INSURANCE
A. Any insurance carrier providing insurance coverage required by the Contract Documents shall be admitted to and author ized to do business in the State of California unless waived, in writing, by the City’s Risk Manager. Carrier(s) shall have an A.M. Best rating of not less than an A:VII. Insurance deductibles or self- insured retentions must be declared by th e Contractor. At the election of the City the Contractor shall either 1) reduce or eliminate such deductibles or self-insured 




 





Page 219 of 396 ends

38077.00180\29080232.10

-75- 00 72 13 – GENERAL CONDITIONS

retentions, or 2) procure a bond which guarantees payment of losses and related investigations, claims administration, and defense costs and expenses. If umbrella or excess liability coverage is used to me et any required limit(s) specified herein, the Contractor shall provide a “follow form” endorsement satisfactory to the City indicating that such coverage is subject to the same terms and conditions as the underlying liability policy.

B. Each insurance policy required by this Co ntract shall be endorsed to state that: (1) coverage shall not be suspended, voided, reduced or cancelled except after thirty (30) days prior written notice by certified mail, return receipt requested, has been given to the City; and (2) any failure to comply with reporting or other provisions of the policies, including breaches of warranti es, shall not affect coverage provided to the City, its officials, officers, agents, employees, and volunteers.

C. The Certificates(s) and policies of insura nce shall contain or shall be endorsed to contain the covenant of the insurance carrier(s) that it shall provide no less than thirty (30) days written notice be given to the City prior to any material modification or cancellation of such insurance. In the event of a material modification or cancellation of coverage, the City may terminate the Contract or stop the Work in accordance with the Contract Documents, unless the City receives, prior to such effective date, another properly executed original Certificate of Insurance and original copies of endorsements or cert ified original policies, including all endorsements and attachments thereto evidencing coverage’s set forth herein and the insurance required herein is in full force and effect. Contractor shall not take possession, or use the Site, or commence operations under this Contract until the City has been furnished original Certificat e(s) of Insurance and certified original copies of endorsements or policies of insurance including all endorsements and any and all other attachments as requir ed in this Article. The original endorsements for each policy and the Certif icate of Insurance shall be signed by an individual authorized by the insurance carrier to do so on its behalf.

D. The Certificate(s) of Insurance, policie s and endorsements shall so covenant and shall be construed as primary, and the City’s insurance and/or deductibles and/or self-insured retentions or self-insured programs shall not be construed as contributory.

E. City reserves the right to adjust the monetary limits of insurance coverages during the term of this Contract including any extension thereof if, in the City’s reasonable judgment, the amount or type of insurance carried by the Contractor becomes inadequate.

F. Contractor shall report to the City, in addition to the Contractor’s insurer, any and all insurance claims submitted by the Contractor in connection with the Work under this Contract.

ARTICLE 38 TIME FOR COMPLETION AND LIQUIDATED DAMAGES
A. Time for Completion/Liquidated Damages. Time is of the essence in the completion of the Work. Work shall be commenced within ten (10) Days of the date stated in the City’s Notice to Proceed and shall be completed by Contractor specified in the Contract Documents. The City is under no obligation to consider 




 





Page 220 of 396 ends

38077.00180\29080232.10

-76- 00 72 13 – GENERAL CONDITIONS

early completion of the Project; and the Contract completion date shall not be amended by the City’s receipt or acceptance of the Contractor’s proposed earlier completion date. Furthermore, Contractor shall not, under any circumstances, receive additional compensation from the City (including but not limited to indirect, general, administrative or other forms of overhead costs) for the period between the time of earlier completion proposed by the Contractor and the Contract completion date. If the Work is not completed as stated in the Contract Documents, it is understood that the City will suffer damage. In accordance with Government Code section 53069.85, being impractical and infeasible to determine the amount of actual damage, it is agreed that Contractor shall pay to the City as fixed and liquidated damages, and not as a penalty, the sum stipulated in the Contract for each calendar day of delay until the Work is fully completed as determined by the City. Contractor and its surety shall be liable for any liquidated damages. Any money due or to become due the Contractor may be retained to cover liquidated damages.

B. Inclement Weather. Contractor shall abide by the Engineer’s determination of what constitutes inclement weather. Time extensions for inclement weather shall only be granted when the Work stopped during inclement weather is on the critical path of the Project schedule. The Contractor shall implement measures and make contingencies as may be required to protect the Work and to all allow Work to proceed during wet or inclement weather to prevent delay or stoppage.

Extension of Time Due to Weather Delays: The City and Contractor mutually agree that excusable delay events associated with the occurrence of inclement weather will be based only on conditions that were not foreseeable at the time the Contract was entered into. The Contractor’s construction schedule shall include an allowance for the following schedule of expected weather delay days. If the Contractor encounters fewer inclement weather days per month or in total than shown below, then the City has the right to use the unencountered balance of days as an offset against any other claims for excusable delays or Owner-caused delays. Actual inclement weather days must prevent work on critical activities for 50 percent or more of the Contractor’s scheduled work day. All Contractor claims for excusable delay due to excessive inclem ent weather shall be for critical path work only and must be supported by a Time Impact Analysis as described in Article

42. No additional compensation will be granted for an excusable delay.

Month Calendar Days
January 6
February 6
March 7
April 4
May 3
June 1
July 0
August 1
September 2
October 2
November 3
December 5
Total Annual Inclement Weather Days 40






 





Page 221 of 396 ends

38077.00180\29080232.10

-77- 00 72 13 – GENERAL CONDITIONS

C. Extension of Time. Contractor shall not be charged liquidated damages because of any delays in completion of the Work due to unforeseeable causes beyond the control and without the fault or negligence of Contractor (or its subcontractors or suppliers). Contractor shall within five (5) Days of identifying any such delay notify the City in writing of causes of delay. The City shall ascertain the facts and extent of delay and grant extension of time for completing the Work when, in its judgment, the facts justify such an extension. Time extensions to the Project shall be requested by the Contractor as they occu r and without delay. No delay claims shall be permitted unless the event or occurrence delays the completion of the Project beyond the Contract completion date.

D. No Damages for Reasonable Delay. The City’s liability to Contractor for delays for which the City is responsible shall be limited to only an extension of time unless such delays were unreasonable under the circumstances. In no case shall the City be liable for any costs which are borne by the Contractor in the regular course of business, including, but not limited to, home office overhead and other ongoing costs. Damages caused by unreasonable City delay, including delays caused by items that are the responsibility of the City pursuant to Government Code section 4215, shall be based on actual costs only, no proportions or formulas shall be used to calculate any delay damages.

ARTICLE 39 SCHEDULE OF VALUES, COST BREAKDOWN AND PERIODIC ESTIMATES Contractor shall furnish on forms Approved by the City:

A. When requested by the Engineer, and wit hin ten (10) Days of Notice to Proceed with the Contract, the Contractor shall provide a Schedule of Values consisting of a detailed estimate giving a complete br eakdown of the Contract price for each lump sum bid item in the Contract.

B. A monthly itemized estimate of Work done for the purpose of making progress payments. In order for the City to consider and evaluate each progress payment application, the Contractor shall subm it a detailed measurement of Work performed and a progress estimate of the value thereof before the tenth (10th) Day of the following month.

C. Contractor shall submit, with each of its payment requests, an adjusted list of actual quantities, verified by the Engineer, for unit price items listed, if any, in the Bid Form.

D. Following the City’s Acceptance of the Work, the Contractor shall submit to the City a written statement of the final quantities of unit price items for inclusion in the final payment request.

E. The City shall have the right to adjust an y estimate of quantity and to subsequently correct any error made in any estimate for payment.

Contractor shall certify under penalty of perjury, that all cost breakdowns and periodic estimates accurately reflect the Work on the Project.





 





Page 222 of 396 ends

38077.00180\29080232.10

-78- 00 72 13 – GENERAL CONDITIONS

ARTICLE 40 PROGRESS ESTIMATES AND PAYMENT
A. By the tenth (10th) Day of the following calendar month, Contractor shall submit to Engineer a payment request which shall set forth in detail the value of the Work done for the period beginning with the date work was first commenced and ending on the end of the calendar month for which the payment request is prepared.

Contractor shall include any amount earned for authorized extra work. From the total thus computed, a deduction shall be made in the amount of five percent (5%) for retention, except where the City has adopted a finding that the Work done under the Contract is substantially complex, and then the amount withheld as retention shall be the percentage specified in the Notice Inviting Bids. From the remainder a further deduction may be made in accordance with Section B below. The amount computed, less the amount withheld for retention and any amounts withheld as set forth below, shall be the amount of the Contractor’s payment request.

B. The Contractor shall provide an up dated project schedule with each payment request.

C. The City may withhold a su fficient amount or amounts of any payment or payments otherwise due to Contractor, as in his judgment may be necessary to cover:

1. Payments which may be past due an d payable for just claims against Contractor or any subcontractors for labor or materials furnished in and about the performance of work on the Project under this Contract.

2. Defective work not remedied.

3. Failure of Contractor to make proper payments to his subcontractor or for material or labor.

4. Completion of the Contract if there is a reasonable doubt that the Work can be completed for balance then unpaid.

5. Damage to another contractor or a third party.

6. Amounts which may be due the City for claims against Contractor.

7. Failure of Contractor to keep the re cord (“as-built”) drawings up to date.

8. Failure to provide update on cons truction schedule as required herein.

9. Site cleanup.

10. Failure to comply with Contract Documents.

11. Liquidated damages.

12. Legally permitted penalties.

D. The City may apply such withheld amount or amounts to payment of such claims or obligations at its discretion with the exception of subsections (B)(1), (3), and (5) of this Article, which must be retained or applied in accordance with applicable law. 




 





Page 223 of 396 ends

38077.00180\29080232.10

-79- 00 72 13 – GENERAL CONDITIONS

In so doing, the City shall be deemed the agent of Contractor and any payment so made by the City shall be considered as a payment made under contract by the City to Contractor and the City shall not be liable to Contractor for such payments made in good faith. Such payments may be made without prior judicial determination of claim or obligations. The City will render Contractor a proper accounting of such funds disbursed on behalf of Contractor.

E. Upon receipt, the Engineer shall review the payment request to determine whether it is undisputed and suitable for payment. If the payment request is determined to be unsuitable for payment, it shall be returned to Contractor as soon as practicable but not later than seven (7) Days after receipt, accompanied by a document setting forth in writing the reasons why the payment request is not proper. The City shall make the progress payment within 30 calendar days after the receipt of an undisputed and properly submitted payment request from Contractor, provided that a release of liens and claims has been received from the Contractor pursuant to Civil Code section 8132. The number of days available to the City to make a payment without incurring interest pursuant to this paragraph shall be reduced by the number of days by which the Engineer exceeds the seven (7) Day requirement.

F. A payment request shall be considered pr operly executed if funds are available for payment of the payment request and payment is not delayed due to an audit inquiry by the financial officer of the City.

ARTICLE 41 SECURITIES FOR MONEY WITHHELD
Pursuant to section 22300 of the Public Contract Code of the State of California, Contractor may request the City to make retention payments dire ctly to an escrow agent or may substitute securities for any money withheld by the City to ensure performance under the contract. At the request and expense of Contractor, securities equivalent to the amount withheld shall be deposited with the City or with a state or federally chartered bank as the escrow agent who shall return such securities to Contractor upon satisfactory completion of the contract. Deposit of securities with an escrow agent shall be subject to a written agreement substantially in the form provided in section 22300 of the Public Contract Code.

ARTICLE 42 CHANGES AND EXTRA WORK.

A. Contract Change Orders.

1. The City, without invalidating the Co ntract, may order changes in the Work consisting of additions, deletions or other revisions, and the Contract Price and Contract Time shall be adjusted accordingly. Except as otherwise provided herein, all such changes in the Work shall be authorized by Change Order, and shall be performed under the applicable conditions of the Contract Documents. A Change Order signed by the Contractor indicates the Contractor's agreement therewith, including any adjustment in the Contract Price or the Contract Time, and the full and final settlement of all costs (direct, indirect and over head) related to the Work authorized by the Change Order.

2. Contractor shall promptly execute changes in the Work as directed in writing by the City even when the parties have not reached agreement on 




 





Page 224 of 396 ends

38077.00180\29080232.10

-80- 00 72 13 – GENERAL CONDITIONS

whether the change increases the scope of Work or affects the Contract Price or Contract Time. All claims for additional compensation shall be presented in writing. No claim will be considered after the Work in question has been completed unless a written Change Order has been issued or a timely written notice of claim has been made by Contractor.

3. Whenever any change is made as pr ovided for herein, such change shall be considered and treated as though originally included in the Contract, and shall be subject to all terms, cond itions, and provisions of the original Contract.

4. Contractor shall not be entitled to claim or bring suit for damages, whether for loss of profits or otherwise, on account of any decrease or omission of any item or portion of Work to be done.

5. No dispute, disagreement, or failure of the parties to reach agreement on the terms of the Change Order shall relieve the Contractor from the obligation to proceed with performanc e of the work, including Additional Work, promptly and expeditiously.

6. Contractor shall make available to the City any of the Contractor’s documents related to the Project immediately upon request of the City, as set forth in Article 52.

7. Any alterations, extensions of time , Additional Work, or any other changes may be made without securing consent of the Contractor’s surety or sureties.

B. Contract Price Change.

1. Process for Determining Adjustments in Contract Price. a. Owner Initiated Change. The Co ntractor must submit a complete cost proposal, including any change in the Contract Price or Contract Time, within seven (7) Days after receipt of a scope of a proposed change order initiate d by the City, unless the City requests that proposals be submitted in less than seven (7) Days. b. Contractor Initiated Change. The Contractor must give written notice of a proposed change order required for compliance with the Contract Documents within seven (7) Days of discovery of the facts giving rise to the proposed change order.
c. Whenever possible, any changes to the Contract amount shall be in a lump sum mutually agreed to by the Contractor and the City. d. Price quotations from the Cont ractor shall be accompanied by sufficiently detailed supporting documentation to permit verification by the City, including but not limit ed to estimates and quotations from subcontractors or material suppliers, as the City may 




 





Page 225 of 396 ends

38077.00180\29080232.10

-81- 00 72 13 – GENERAL CONDITIONS

reasonably request. Contractor shall certify the accuracy of all Change Order Requests under penalty of perjury.
e. If the Contractor fails to submit a complete cost proposal within the seven (7) Day period (or as requested), the City has the right to order the Contractor in writing to commence the Work immediately on a time and materials basis and/or issue a lump sum change to the Contract Price and/or Contra ct Time in accordance with the City’s estimate. If the change is issued based on the City's estimate, the Contractor will waive its right to dispute the action unless within fifteen (15) Days following completion of the added/deleted work, the Contractor presents written proof that the City’s estimate was in error.

2. Unit Price Change Orders.
a. When the actual quantity of a Unit Price item is found to vary from the Bid Form, compensation for the change in quantity will be calculated by multiplying the actual quantity by the Unit Price. This calculation may result in either an additive or deductive Final Change Order pursuant to the Co ntract Documents. Contractor shall immediately inform the Engineer when the actual quanities vary from estimated quantities.
b. No Mark up for Overhead and Pr ofit. Because the Contract Unit Prices provided in the Bid Form include Overhead and Profit as determined by Contractor at the time of Bid submission, no mark up or deduction for Overhead and Profit will be included in Unit Price Change Orders.
c. Bid items included on the Bid Fo rm may be deducted from the Work in their entirety without any negotiated extra costs.
d. Contractor acknowledges that unit quantities are estimates and agrees that the estimated unit quantities listed on the Bid Form will be adjusted to reflect the actual unit quantities which may result in an adjustment to the Contract Unit Prices. Such an adjustment will be made by execution of a final additive or deductive Change Order following Contractor’s completion of the Work. Upon notification, Contractor’s failure to respond within seven (7) Days will result in City’s issuance of a unit quantity adjustment to the Contract Unit Prices and/or Contract Time in accordance with the Contract Documents.

3. Lump Sum Change Orders. Compensation for Lump Sum Change Orders shall be limited to expenditures necessitated specifically by the Additional Work, and shall be segregated as follows:
a. Labor. The costs of labor will be th e actual cost for wages prevailing locally for each craft or type of worker at the time the Additional Work is done, plus employer payments of payroll taxes and 




 





Page 226 of 396 ends

38077.00180\29080232.10

-82- 00 72 13 – GENERAL CONDITIONS

insurance, health and welfare, pe nsion, vacation, apprenticeship funds, and other direct costs resulting from Federal, State or local laws, as well as assessment or benefits required by lawful collective bargaining agreements. The use of a labor classification which would increase the Additional Work cost will not be permitted unless the Contractor establishes the necessity for such new
classifications. Labor costs fo r equipment operators and helpers shall be reported only when such costs are not included in the invoice for equipment rental.
b. Materials. The cost of material s reported shall be at invoice or lowest current price at which such materials are locally available in the quantities involved, plus sale s tax, freight, and delivery.

Materials costs shall be based upon supplier or manufacturer’s invoice. If invoices or other satisfactory evidence of cost are not furnished within fifteen (15) Days of delivery, then the City shall determine the materials cost, at its sole discretion.
c. Tool and Equipment Use. Costs for the use of small tools, which are tools that have a replacement value of $1,000 or less, shall be considered included in the Overhead and Profit mark-ups established below. Regardless of ownership, the rates to be used in determining equipment use costs shall not exceed listed rates prevailing locally at equipment rent al agencies, or distributors, at the time the Work is performed.

4. Time and Materials Change Orders.
a. General. The term Time and Materials means the sum of all costs reasonably and necessarily incurred and paid by Contractor for labor, materials, and equipment in the proper performance of Additional Work. Except as otherwise may be agreed to in writing by the City, such costs shall be in amounts no higher than those prevailing in the locality of the Project, and shall include only the following items.
b. Timely and Final Documentation.
i. T&M Daily Sheets. Contractor must submit timesheets, materials invoices, records of equipment hours, and records of rental equipment hours to the City’s Representative for an approval signature each day Additional Work is performed.

Failure to get the City’s Representative’s approval signature each Day shall result in a waiver of Contractor’s right to claim these costs. The City’s Representative’s signature on time sheets only serves as verification that the Work was performed and is not indicati ve of City’s agreement to Contractor’s entitlement to the cost.
ii. T&M Daily Summary Sheets. All documentation of incurred costs (“T&M Daily Summary Sheets”) shall be submitted by 




 





Page 227 of 396 ends

38077.00180\29080232.10

-83- 00 72 13 – GENERAL CONDITIONS

Contractor within three (3) Days of incurring the cost for labor, material, equipment, and special services as
Additional Work is performed. Contractor’s actual costs shall be presented in a summary table in an electronic
spreadsheet file by labor, material, equipment, and special services. Each T&M Daily Summary Sheet shall include
Contractor’s actual costs incurred for the Additional Work performed that day and a cumulative total of Contractor’s actual costs incurred for the Additional Work. Contractor’s failure to provide a T&M Daily Summary Sheet showing a
total cost summary within three (3) Days but within five (5) Days of performance of the Work will result in the
Contractor’s otherwise allowable overhead and profit being reduced by 50% for that port ion of Additional Work which was not documented in a timely manner. Contractor’s
failure to submit the T&M Daily Summary Sheet within five (5) Days of performance of the Work will result in a total waiver of Contractor’s right to claim these costs.
iii. T&M Total Cost Summary Sheet. Contractor shall submit a T&M Total Cost Summary Sheet, which shall include total actual costs, within seven (7) Days following completion of City approved Additional Work. Contractor’s total actual cost shall be presented in a summary table in an electronic spreadsheet file by labor, material, equipment, and special services. Contractor’s failure to submit the T&M Total Cost Summary Sheet within seven (7) Days of completion of the Additional Work will result in Contractor’s waiver for any reimbursement of any costs associated with the T&M
Summary Sheets or the performance of the Additional Work. c. Labor. The Contractor will be paid the cost of labor for the workers used in the actual and direct performance of the Work. The cost of labor will be the sum of the actual wages paid (which shall include any employer payments to or on behalf of the workers for health and welfare, pension, vacation, and similar purposes) substantiated by timesheets and certified payroll for wages prevailing for each craft or type of workers performing the Additional Work at the time the Additional Work is done, and the labor surcharge set forth in the Department of Transportation publication entitled Labor Surcharge and Equipment Rental Rates , which is in effect on the date upon which the Work is accomplished and which is a part of the Contract.

The labor surcharge shall constitu te full compensation for all payments imposed by Federal, State, or local laws and for all other payments made to, or on behalf of, the workers, other than actual wages.
i. Equipment Operator Exception. Labor costs for equipment operators and helpers shall be paid only when such costs are not included in the invoice for equipment rental.





 





Page 228 of 396 ends

38077.00180\29080232.10

-84- 00 72 13 – GENERAL CONDITIONS

ii. Foreman Exception. The labor costs for foremen shall be proportioned to all of their a ssigned work and only that applicable to the Additional Wo rk shall be paid. Indirect labor costs, including, without limitation, the superintendent, project manager, and other labor identified in the Contract Documents will be considered Overhead.
d. Materials. The cost of materi als reported shall be itemized at invoice or lowest current price at which materials are locally available and delivered to the Project site in the quantities involved, plus the cost of sales tax, freight, delivery, and storage. i. Trade discounts available to the purchaser shall be credited to the City notwithstanding the fact that such discounts may not have been taken by Contractor.
ii. For materials secured by othe r than a direct purchase and direct billing to the purchaser, the cost shall be deemed to be the price paid to the actual supplier as determined by the City’s Representative.
iii. Payment for materials from so urces owned wholly or in part by the purchaser shall not exceed the price paid by the purchaser for similar materials from said sources on
Additional Work items or th e current wholesale price for such materials delivered to the Project site, whichever price is lower.
iv. If, in the opinion of the City’s Representative, the cost of materials is excessive, or Contractor does not furnish
satisfactory evidence of the cost of such materials, then the cost shall be deemed to be the lowest current wholesale price for the total quantity concerned delivered to the Project site less trade discounts.
v. The City reserves the right to furnish materials for the Additional Work and no Claim shall be allowed by
Contractor for costs of such materials or Indirect Costs or profit on City furnished materials.
e. Equipment.
i. Rental Time. The rental time to be paid for equipment on the Project site shall be the time the equipment is in
productive operation on the Additional Work being
performed and, in addition, shall include the time required to move the equipment to the loca tion of the Additional Work and return it to the original location or to another location requiring no more time than that required to return it to its original location; except that moving time will not be paid if 




 





Page 229 of 396 ends

38077.00180\29080232.10

-85- 00 72 13 – GENERAL CONDITIONS

the equipment is used on other than the Additional Work, even though located at the site of the Additional Work. (a) Rental Time Not Allowed. Rental time will not be
allowed while equipment is inoperative due to
breakdowns.
(b) Computation Method. The following shall be used in computing the rental time of equipment on the
Project site.
(i) When hourly rates are paid, any part of an
hour less than 30 minutes of operation shall
be considered to be 1/2-hour of operation,
and any part of an hour in excess of 30
minutes will be considered one hour of
operation.
(ii) When daily rates are paid, any part of a day
less than 4 hours operation shall be
considered to be 1/2-day of operation, and
any part of an hour in excess of 4 hours will
be considered one day of operation.
ii. Rental Rates. Contractor will be paid for the use of equipment at the lesser of (i) the actual rental rate, or (ii) the rental rate listed for that equipment in the California Department of Transportati on publication entitled Labor Surcharge and Equipment Rental Rates , which is in effect on the date upon which the Contract was executed. Such rental rates will be used to compute payments for equipment whether the equipment is under Contractor’s control through direct ownership, leasing, renting, or another method of acquisition. The rental rate to be applied for use of each item of equipment shall be the rate (i.e., daily, monthly) resulting in the least total cost to the City for the total period of use. If it is deemed necessary by Contractor to use equipment not listed in the publication, an equitable rental rate for the equipment will be established by the City’s Representative. Contractor may furnish cost data which might assist the City’s Representative in the establishment of the rental rate.
iii. Contractor-Owned Equipment.
(a) For Contractor-owned equipment, the allowed
equipment rental rate will be limited to the monthly
equipment rental rate using a utilization rate of 173
hours per month.





 





Page 230 of 396 ends

38077.00180\29080232.10

-86- 00 72 13 – GENERAL CONDITIONS

(b) For Contractor-owned equipment, the rental time to
be paid for equipment on th e Site shall be the time
the equipment is in productive operation, unless, in
the instance of standby time, the equipment could be
actively used by Contractor on another project, then
City shall pay for the entirety of the time the
equipment is on Site. It shall be Contractor’s burden
to demonstrate to the City that the equipment could
be actively used on another project.
(i) All equipment shall, in the opinion of the
City’s Representative, be in good working
condition and suitable for the purpose for
which the equipment is to be used.
(ii) Before construction equipment is used on
the Additional Work, Contractor shall plainly
stencil or stamp an identifying number
thereon at a conspicuous location, and shall
furnish to the City’s Representative, in
duplicate, a description of the equipment and
its identifying number and the scheduled
Additional Work activities planned.
(iii) Unless otherwise specified, manufacturer’s
rating and manufacturer approved
modifications shall be used to classify
equipment for the determination of
applicable rental rates. Equipment which
has no direct power unit shall be powered by
a unit of at least the minimum rating
recommended by the manufacturer.
f. Special Services. Special work or services are defined as that Additional Work characterized by extraordinary complexity, sophistication, or innovation or a combination of the foregoing attributes which are unique to the construction industry. i. Invoices for Special Services. When the City’s
Representative and Contractor determine that a special
service is required which cannot be performed by the forces of Contractor or those of any of its Subcontractors, the special service may be performed by an entity especially skilled in the Additional Work. Invoices for special services based upon the current fair market value thereof may be accepted without complete itemization of labor, material, and equipment rental costs, after validation of market values by the City’s Representative.
ii. Discount and Allowance. All invoices for special services will be adjusted by deducting all trade discounts offered or 




 





Page 231 of 396 ends

38077.00180\29080232.10

-87- 00 72 13 – GENERAL CONDITIONS

available, whether the discounts were taken or not. In lieu of Overhead and Profit specified herein, a total allowance not to exceed fifteen percent (15%) for Overhead and Profit will be added to invoices for Special Services.
iii. When the City determines, in its sole discretion, that competitive bidding is necessary for certain special
services, Contractor shall solicit competitive bids for those special services.
g. Excluded Costs. Th e term Time and Material shall not include any of the following costs or any othe r home or field office overhead costs, all of which are to be considered administrative costs covered by Contractor’s allowance for Overhead and Profit.
i. Overhead Cost. Payroll costs and other compensation of Contractor’s officers, executives, principals, general
managers, engineers, architects, estimators, attorneys, auditors, accountants, purchasing and contracting agents, timekeepers, clerks, and ot her personnel employed by
Contractor whether at the Site or in Contractor’s principal office or any branch office, material yard, or shop for general administration of the Additional Work;
ii. Office Expenses. Expenses of Contractor’s principal and branch offices;
iii. Capital Expenses. Any part of Contractor’s capital expenses, including interest on Contractor’s capital
employed for the Additional Work and charges against
Contractor for delinquent payments;
iv. Negligence. Costs due to the negligence of Contractor or any Subcontractor or Supplier, or anyone directly or
indirectly employed by any of them or for whose acts any of them may be liable, including without limitation the
correction of Defective Work, disposal of materials or
equipment wrongly supplied, and making good any damage
to property;
v. Other. Other overhead or ge neral expense costs of any kind and the cost of any item not specifically and expressly included in the Contract Documents;
vi. Small Tools. Cost of small to ols valued at less than $1,000 and that remain the property of Contractor;
vii. Administrative Costs. Cost s associated with the preparation of Change Orders (whether or not ultimately authorized), cost estimates, or the preparation or filing of Claims; 




 





Page 232 of 396 ends

38077.00180\29080232.10

-88- 00 72 13 – GENERAL CONDITIONS

viii. Anticipated Lost Profits. Expenses of Contractor associated with anticipated lost profits or lost revenues, lost income or earnings, lost interest on earnings, or unpaid retention; ix. Home Office Overhead. Costs derived from the
computation of a “home office overhead” rate by application of the Eichleay, Allegheny , burden fluctuation, or other similar methods;
x. Special Consultants and Attorneys. Costs of special consultants or attorneys, whether or not in the direct employ of Contractor, employed for services specifically related to the resolution of a Claim, dispute, or other matter arising out of or relating to the performance of the Additional Work. h. Overhead, Profit and Other Char ges. The mark-up for overhead (including supervision) and profit on work added to the Contract shall be according to the following:
i. “Net Cost” is defined as consisting of costs of labor, materials, and tools and equipment only excluding overhead and profit. The costs of ap plicable insurance and bond premium will be reimbursed to the Contractor and
subcontractors at cost only, without mark-up. Contractor shall provide City with documentation of the costs, including, but not limited to, payroll records, invoices, and such other information as City may reasonably request.
ii. For Work performed by the Contractor’s forces, the added cost for overhead and profit shall not exceed fifteen percent (15%) of the Net Cost of the Work.
iii. For Work performed by a subcontractor, the added cost for overhead and profit shall not exceed fifteen percent (15%) of the subcontractor’s Net Cost of the Work to which the Contractor may add five percent (5%) of the subcontractor’s Net Cost.
iv. For Work performed by a sub-subcontractor, the added cost for overhead and profit shall not exceed fifteen percent (15%) of the sub-subcontractor’s Net Cost for Work to which the subcontractor and general contractor may each add an additional five percent (5%) of the Net Cost of the lower tier subcontractor.
v. No additional mark-up will be allowed for lower tier subcontractors, and in no case shall the added cost for overhead and profit payable by City exceed twenty-five
percent (25%) of the Net Cost as defined herein, of the party that performs the Work.





 





Page 233 of 396 ends

38077.00180\29080232.10

-89- 00 72 13 – GENERAL CONDITIONS

5. All of the following costs are included in the markups for overhead and profit described above, and Contractor shall not receive any additional compensation for: Submittals, drawings, field drawings, Shop Drawings, including submissions of drawin gs; field inspection; General Superintendence; General administ ration and preparation of cost proposals, schedule analysis, Change Orders, and other supporting documentation; computer services; reproduction services; Salaries of project engineer, supe rintendent, timekeeper , storekeeper, and secretaries; Janitorial services; Small tools, incidentals and consumables; Temporary On-Site facilities (Offices, Telephones, High Speed Internet Access, Plumbing, Electrical Power, Lighting; Platforms, Fencing, Water), Jobsite and Home office overhead or other expenses; vehicles and fuel used for work otherwise included in the Contract Documents; Surveying; Estimating; Protection of Work; Handling and disposal fees; Final Cleanup; Other Incidental Work; Related Warranties; insurance and bond premiums.

6. For added or deducted Work by subcon tractors, the Contractor shall furnish to the City the subcontractor’s signed detailed record of the cost of labor, material and equipment, including the subcontractor markup for overhead and profit. The same requirement shall apply to sub-subcontractors

7. For added or deducted work furn ished by a vendor or supplier, the Contractor shall furnish to the City a detailed record of the cost to the Contractor, signed by such vendor or supplier.

8. Any change in the Work involvin g both additions and deletions shall indicate a net total cost, including subcontracts and materials. Allowance for overhead and profit, as specified herein, shall be applied if the net total cost is an increase in the Contract Pr ice; overhead and profit allowances shall not be applied if the net total cost is a deduction to the Contract Price.

The estimated cost of deductions shall be based on labor and material prices on the date the Contract was executed.

9. Contractor shall not reserve a right to assert impact costs, extended job site costs, extended overhead, constr uctive acceleration and/or actual acceleration beyond what is stated in the Change Order for Work. No claims shall be allowed for impact, extended overhead costs, constructive acceleration and/or actual accelerati on due to a multiplicity of changes and/or clarifications. The Contractor may not change or modify the City’s change order form in an attempt to reserve additional rights.

10. If the City disagrees with the proposal submitted by Contractor, it will notify the Contractor and the City will provide its opinion of the appropriate price and/or time extension. If the Cont ractor agrees with the City, a Change Order will be issued by the City. If no agreement can be reached, the City shall have the right to issue a unilateral Change Order setting forth its determination of the reasonable addi tions or savings in costs and time attributable to the extra or deleted work. Such determination shall become final and binding if the Contractor fail s to submit a claim in writing to the City within fifteen (15) Days of the issuance of the unilateral Change Order, 




 





Page 234 of 396 ends

38077.00180\29080232.10

-90- 00 72 13 – GENERAL CONDITIONS

disputing the terms of the unilateral Change Order, and providing such supporting documentation for its position as the City may require.

C. Change of Contract Times.

1. The Contract Times may only be changed by a Change Order.

2. All changes in the Contract Price and/or adjustments to the Contract Times related to each change shall be included in Contractor’s COR pursuant to this Article. No cost or time will be allowed for cumulative effects of multiple changes. All Change Orders must st ate that the Contract Time is not changed or is either increased or decreased by a specific number of days.

Failure to include a change to time shall waive any change to the time unless the parties mutually agree in writing to postpone a determination of the change to time resulting from the Change Order.

3. Notice of the amount of the request for adjustment in the Contract Times with supporting data shall be delivered within seven (7) Days after such start of occurrence, unless City’s Repr esentative allows an additional period of time to ascertain more accurate data in support of the request.

No extension of time or additional compensation shall be given for a delay if the Contractor failed to give noti ce in the manner and within the time prescribed.

4. City may elect, at City’s sole discretio n, to grant an extension in Contract Times, without Contractor’s request, because of delays or other factors.

5. Use of Float and Critical Path.
a. Float is for the benefit of the Project. Float shall not be considered for the exclusive use or benefit of either the City or the Contractor. b. Contractor shall not be entitled to compensation, and City will not compensate Contractor, for delays which impact early completion.

Any difference in time between the Contractor’s early completion and the Contract Time shall be considered a part of the Project float.

6. Contractor’s entitlement to an extensio n of the Contract Times is limited to a City-caused extension of the critical path, reduced by the Contractor’s concurrent delays, and established by a proper time impact analysis. No time extension shall be allowed unless, and then only to the extent that, the City-caused delay extends the critical path beyond the previously approved Contract Time. If approved, the increase in time required to complete the Work shall be added to the Contract Time.
a. Contractor shall not be entitled to an adjustment in the Contract Price or Contract Times for delays within the control of Contractor.

Delays attributable to and within the control of a Subcontractor or Supplier shall be deemed to be delays within the control of Contractor.





 





Page 235 of 396 ends

38077.00180\29080232.10

-91- 00 72 13 – GENERAL CONDITIONS

b. If Contractor is delayed in the performance or progress of the Work by fire, flood, epidemic, abno rmal weather conditions (as determined by the City), Acts of God, acts or failures to act of utility owners not under the control of City, or other causes not the fault of and beyond control of City and Contractor, then Contractor shall be entitled to an time extension when the Work stopped is on the critical path. Such a non-compensable adjustment shall be Contractor’s sole and exclusive remedy for such delays. Contractor must submit a timely request in accordance with the requirements of this Article.
c. Utility-Related Delays.
i. Contractor shall immediately notify in writing the utility owner and City’s Representative of its construction schedule and any subsequent changes in the construction schedule which will affect the time available for protection, removal, or relocation of utilities. Requests for extensions of time arising out of utility relocation or repair delays shall be filed in accordance with this Article.
ii. Contractor shall not be enti tled to damages or additional payment for delays attributable to utility relocations or alterations if correctly located, as noted in the Contract Documents or by the Underground Service Alert survey.

7. Content for Requests for Contract Extension. Contractor’s justification for entitlement shall be clear and complete citing specific Contract Document references and reasons on which Contractor’s entitlement is based. At a minimum, each request for a time extension must include:
a. Each request for an extension of Contract Time must identify the impacting event, in narrative form , providing a description of the delay event and sufficient justification as to why the Contractor is entitled to a time extension. Contractor must demonstrate that the delay arises from unforeseeable causes beyond the control and without the fault or negligence of both Contractor and any Subcontractors or Suppliers, or any other persons or organizations employed by any of them or for whose acts any of them may be liable, and that such causes in fact lead to performance or completion of the Work, or specified part in question, beyond the corresponding Contract Times, despite Contractor’s reasonable and diligent actions to guard against those effects.
b. Each request for an extension of Contract Time must include a time impact analysis in CPM format, using the Contemporaneous Impacted As-Planned Schedule Analysis to calculate the impact of the delay event.

8. No Damages for Reasonable Delay.





 





Page 236 of 396 ends

38077.00180\29080232.10

-92- 00 72 13 – GENERAL CONDITIONS

a. City’s liability to Contractor for delays for which City is responsible shall be limited to only an extension of time unless such delays were unreasonable under the circumstances. In no case shall City be liable for any costs which are borne by the Contractor in the regular course of business, including, but not limited to, home office overhead and other ongoing costs.
b. City and City’s Representative, and the officers, members, partners, employees, agents, consultants, or subcontractors of each of them, shall not be liable to Contractor for any claims, costs, losses, or damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute resolution costs) sustained by Contractor on or in connection with any other project or anticipated project.

9. Contractor’s failure, neglect, or refusal to comply with the requirements of the Contract Documents, or any portion thereof, shall bar Contractor’s request for extensions of the Contract Times. Such failure, neglect, or refusal prejudices City’s and City’s Representative’s ability to recognize and mitigate delay, and such failure, neglect, or refusal prevent the timely analysis of requests for extensions of Contract Times, and whether such extensions may be warranted. Contractor hereby waives all rights to extensions of Contract Times due to delays or accelerations that result from or occur during periods of time for which Contractor fails, neglects, or refuses to fully comply with the requirements of this Article.

10. Contractors submission of daily cons truction reports and schedule updates in accordance with these Contract Documents is required for the evaluation of the merits of time extension request. Failure of the Contractor to submit daily construction reports and schedul e updates shall constitute a waiver of its right to seek a time extension or additional compensation.

ARTICLE 43 FINAL ACCEPTANCE AND PAYMENT
A. Final Inspection. Upon written notice from Contractor that the entire Work is complete, the Engineer will promptly make a final inspection and will notify Contractor in writing of all particulars in which this inspection reveals that the Work is incomplete or defective. Contractor shall immediately take such measures as are necessary to complete such Work or remedy such deficiencies.

B. Final Acceptance. After Contractor has, in the opinion of the Engineer, satisfactorily completed all corrections identified during the final inspection and has delivered, in accordance with the Cont ract Documents, all maintenance and operating instructions, schedules, guaran tees, bonds, certificates or other evidence of insurance, certificates of inspection, marked-up record documents (as- builts), and other documents required by the Contract Documents, the City shall execute and file with the County in whic h the Project is located a Notice of Completion, constituting final acceptance and completion of the Project, except as may be expressly noted.





 





Page 237 of 396 ends

38077.00180\29080232.10

-93- 00 72 13 – GENERAL CONDITIONS

C. Final Payment.

1. Application for Payment. Upon exec ution of the Notice of Completion, Contractor may make application for final payment following the procedure for progress payments. The final application for payment shall be accompanied (except as previously delivered) by: all documentation called for in the Contract Documents, including but not limited to a fully completed Conditional Waiver and Release on Final Payment

2. City’s Review of Application and Acce ptance. If, on the basis of the City’s observation of the Work during cons truction and final inspection, and review of the final Application for Payment and accompanying documentation as required by the Contract Documents, the City is satisfied that the Work has been completed and Contractor has satisfied all other requirements for final payment, the City will process the final payment appllication. Otherwise, the City will return the payment application to Contractor, indicating in writing the reasons for refusing to recommend final payment, in which case Contractor shall make the necessary corrections and resubmit the application for payment.

3. Payment Becomes Due. Within sixty (60) Days after the presentation to the City of the proper and complete final application for payment and accompanying documentation, the amount recommended by the Engineer, less any sum the City is entitled to set off pursuant to the Contract Documents, will become due and will be paid by the City to Contractor.

D. Waiver of Claims. The making and acceptance of final payment will constitute a waiver of all Claims by Contractor agai nst the City other than those previously made in accordance with the requirements herein and expressly acknowledged by the City in writing as still unsettled.

ARTICLE 44 OCCUPANCY
The City reserves the right to occupy or utilize any portion of the Work at any time before completion, and such occupancy or use shall not constitute acceptance of any part of Work covered by this Contract.This use shall not relieve the Contractor of its responsibilities under the Contract.

ARTICLE 45 INDEMNIFICATION
To the fullest extent permitted by law, Contract or shall immediately defend (with counsel of the City’s choosing), indemnify and hold harmless the City, officials, officers, agents, employees, and representatives, and each of them from and against:

A. Any and all claims, demands, causes of action, costs, expenses, injuries, losses or liabilities, in law or in equity, of every kind or nature whatsoever, but not limited to, injury to or death, including wrongful death, of any person, and damages to or destruction of property of any person, arising out of, related to, or in any manner directly or indirectly connected with the Work or this Contract, including claims made by subcontractors for nonpayment, including without limitation the payment of all consequential damages and attorney’s fees and other related costs and 




 





Page 238 of 396 ends

38077.00180\29080232.10

-94- 00 72 13 – GENERAL CONDITIONS

expenses, however caused, regardless of whether the allegations are false, fraudulent, or groundless, and regardless of any negligence of the City or its officers, employees, or authorized volu nteers (including pa ssive negligence), except the sole negligence or willful misconduct or active negligence of the City or its officials, officers, employees, or authorized volunteers.

B. Contractor’s defense and in demnity obligation herein includes, but is not limited to damages, fines, penalties, attorney’s fees and costs arising from claims under the Americans with Disabilities Act (ADA) or other federal or state disability access or discrimination laws arising from Contractor’s Work during the course of construction of the improvements or after the Work is complete, as the result of defects or negligence in Contractor’s construction of the improvements.

C. Any and all actions, proc eedings, damages, costs, ex penses, fines, penalties or liabilities, in law or equity, of every ki nd or nature whatsoever, arising out of, resulting from, or on account of the violation of any governmental law or regulation, compliance with which is the responsibility of Contractor; D. Any and all losses, expenses, damages (including damages to the Work itself), attorney’s fees, and other costs, including all costs of defense which any of them may incur with respect to the failure, neglect, or refusal of Contractor to faithfully perform the Work and all of Contractor’s obligations under the agreement. Such costs, expenses, and damages shall include all costs, including attorney’s fees, incurred by the indemnified parties in any lawsuit to which they are a party.

Contractor shall immediately defend, at Contra ctor’s own cost, expense and risk, with the City Council’s choosing, any and all such aforesaid suits, actions or other legal proceedings of every kind that may be brought or instituted against th e City, its officials, officers, agents, employees and representatives. Contractor shall pay and satisfy any judgment, award or decree that may be rendered against the City, it s officials, officers, employ ees, agents, employees and representatives, in any such suit, action or other legal proceeding. Contractor shall reimburse the City, its officials, officers, agents, employees and representatives for any and all legal expenses and costs incurred by each of them in connection therewith or in enforcing the indemnity herein provided. The only limitations on this provision shall be those imposed by Civil Code section 2782.

ARTICLE 46 PROCEDURE FOR RESOLVING DISPUTES
Contractor shall timely comply with all notices and requests for changes to the Contract Time or Contract Price, including but not limited to all requirements of Article 42, Changes and Extra Work, as a prerequisite to filing any claim governed by this Article. The failure to timely submit a notice of delay or notice of change, or to timely request a change to the Contract Price or Contract Time, or to timely provide any other notice or request required herein shall constitute a waiver of the right to further pursue the claim under the Contract or at law.

A. Intent. Effective January 1, 1991, Section 20104 et seq., of the California Public Contract Code prescribes a process utilizing informal conferences, non-binding judicial supervised mediation, and judicial arbitrat ion to resolve disputes on construction claims of $375,000 or less. Effective Ja nuary 1, 2017, Section 9204 of the Public Contract Code prescribes a process for negotiation and mediation to resolve disputes on construction claims. The intent of this Article is to implement Sections 20104 et seq. 




 





Page 239 of 396 ends

38077.00180\29080232.10

-95- 00 72 13 – GENERAL CONDITIONS

and Section 9204 of the California Public Contract Code. This Article shall be construed to be consistent with said statutes.

B. Claims. For purposes of this Article, “Claim” means a separate demand by the Contractor, after a change order duly requested in accordance with Article 42 “Changes and Extra Work” has been denied by the City, for (A) a time extension, (B) payment of money or damages arising from Work done by or on behalf of the Contractor pursuant to the Contract, or (C) an amount the payment of which is disputed by the City. Claims governed by this Arti cle may not be filed unless and until the Contractor completes all procedures for giving notice of delay or change and for the requesting of a time extension or change order, including but not necessarily limited to the procedures contained in Article 42, Changes and Extra Work, and Contractor’s request for a change has been denied in wh ole or in part. Claims governed by this Article must be filed no later than the da te of final payment. The claim shall be submitted in writing to the City and shall include on its first page the following in 16 point capital font: “THIS IS A CLAIM.” Furthermore, the claim shall include the documents necessary to substantiate the claim. Nothing herein is intended to extend the time limit or supersede notice requirements otherwise provided by contract for the filing of claims, including all requirements pertaining to compensation or payment for extra Work, disputed Work, and/or changed conditions. Failure to follow such contractual requirements shall bar any claims or subsequent lawsuits for compensation or payment thereon.

C. Supporting Documentation. The Contractor shall submit all claims in the following format:

1. Summary of claim merit and price, reference Contract Document provisions pursuant to which the claim is made

2. List of documents relating to claim:

Specifications
Drawings
Clarifications (Requests for Information)
Schedules
Other

3. Chronology of events and correspondence

4. Analysis of claim merit

5. Analysis of claim cost

6. Time Impact Analysis in CPM format
D. City’s Response. Upon receipt of a claim pursuant to this Article, City shall conduct a reasonable review of the claim and, withi n a period not to exceed 45 Days, shall 




 





Page 240 of 396 ends

38077.00180\29080232.10

-96- 00 72 13 – GENERAL CONDITIONS

provide the Contractor a written statement identifying what portion of the claim is disputed and what portion is undisputed. Any payment due on an undisputed portion of the claim will be processed and made within 60 Days after the City issues its written statement.

1. If the City needs approval from its gove rning body to provide the Contractor a written statement identifying the disputed portion and the undisputed portion of the claim, and the City’s governing body does not meet within the 45 Days or within the mutually agreed to extension of time following receipt of a claim sent by registered mail or certified mail, return receipt requested, the City shall have up to three Days following the next duly publicly noticed meeting of the City’s governing body after the 45-Day period, or extension, expires to provide the Contractor a written statement identifying the disputed portion and the undisputed portion.

2. Within 30 Days of receipt of a claim, the City may request in writing additional documentation supporting the claim or relating to defenses or claims the City may have against the Contractor. If additional information is thereafter required, it shall be requested and provided pursuant to th is subdivision, upon mutual agreement of City and the Contractor. The City’s written response to the claim, as further documented, shall be submitted to the Contractor within 30 Days (if the claim is less than $15,000, within 15 Days) after receipt of the further documentation, or within a period of time no greater than that taken by the Contractor in producing the additional information or requested documentation, whichever is greater.

E. Meet and Confer. If the Contractor disputes the City’s written response, or the City fails to respond within the time prescribed, the Contractor may so notify the City, in writing, either within 15 Days of receipt of the City’s response or within 15 Days of the City’s failure to respond within the time prescribed, respectively, and demand in writing an informal conference to meet and confer for settlement of the issues in dispute. Upon receipt of a demand, the City shall schedule a meet and confer conference within 30 Days for settlement of the dispute.

F. Mediation. Within 10 business Days following the conclusion of the meet and confer conference, if the claim or any portion of the claim remains in dispute, the City shall provide the Contractor a written statement identifying the portion of the claim that remains in dispute and the portion that is undisputed. Any payment due on an undisputed portion of the claim shall be processed and made within 60 Days after the City issues its written statement. Any disputed portion of the claim, as identified by the Contractor in writing, shall be submitted to nonbinding mediation, with the City and the Contractor sharing the associated cost s equally. The City and Contractor shall mutually agree to a mediator within 10 business Days after the disputed portion of the claim has been identified in writing, unless the parties agree to select a mediator at a later time.

1. If the parties cannot agree upon a mediat or, each party shall select a mediator and those mediators shall select a qualified ne utral third party to mediate with regard to the disputed portion of the claim. Each party shall bear the fees and costs charged by its respective mediator in co nnection with the selection of the neutral mediator.





 





Page 241 of 396 ends

38077.00180\29080232.10

-97- 00 72 13 – GENERAL CONDITIONS

2. For purposes of this section, medi ation includes any nonbinding process, including, but not limited to, neutral evaluation or a dispute review board, in which an independent third party or board assists the parties in dispute resolution through negotiation or by issuance of an evaluation. Any mediation utilized shall conform to the timeframes in this section.

3. Unless otherwise agreed to by the City an d the Contractor in writing, the mediation conducted pursuant to this section shall excuse any further obligation under Public Contract Code Section 20104.4 to mediate after litigation has been commenced.

4. The mediation shall be held no earlier than the date the Contractor completes the Work or the date that the Contractor last performs Work, whichever is earlier. All unresolved claims shall be considered jointly in a single mediation, unless a new unrelated claim arises after mediation is completed.

G. Procedures After Mediation. If following the mediation, the claim or any portion remains in dispute, the Contractor must file a claim pursuant to Chapter 1 (commencing with Section 900) and Chapter 2 (commencing with Section 910) of Part 3 of Division 3.6 of Title 1 of the Government Code prior to initiating litigation. For purposes of those provisions, the running of the period of time within which a claim must be filed shall be tolled from the time the Contractor submits his or her written claim pursuant to subdivision (a) until the time the claim is denied, including any period of time utilized by the meet and confer conference.

H. Civil Actions. The following procedures are estab lished for all civil actions filed to resolve claims of $375,000 or less:

1. Within 60 Days, but no earlier than 30 Days, following the filing or responsive pleadings, the court shall submit the matter to non-binding mediation unless waived by mutual stipulation of both parties or unless mediation was held prior to commencement of the action in accordance with Public Contract Code section 9204 and the terms of this Contract. Th e mediation process shall provide for the selection within 15 Days by both parties of a disinterested third person as mediator, shall be commenced within 30 Days of the submittal, and shall be concluded within 15 Days from the commencement of the mediation unless a time requirement is extended upon a good cause showing to the court.

2. If the matter remains in dispute, the case shall be submitted to judicial arbitration pursuant to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, notwithstanding Section 1114.11 of that code. The Civil Discovery Act of 1986 (Article 3 (commencing with Section 2016) of Chapter 3 of Title 3 of Part 4 of the Code of Civil Procedure) shall apply to any proceeding brought under this subdivision consistent with the rules pertaining to judicial arbitration. In addition to Chapter 2.5 (commencing with Section 1141.10) of Title 3 of Part 3 of the Code of Civil Procedure, (A) arbitrators shall, when possible, be experienced in construction law, and (B) any party appealing an arbitration award who does not obtain a more favorable judg ment shall, in addition to payment of costs and fees under that chapter, also pa y the attorney’s fees on appeal of the other party.





 





Page 242 of 396 ends

38077.00180\29080232.10

-98- 00 72 13 – GENERAL CONDITIONS

I. Government Code Claims. In addition to any and all contract requirements pertaining to notices of an d requests for compensation or payment for extra Work, disputed Work, construction claims and/or changed conditions, the Contractor must comply with the claim procedures set forth in Government Code Sections 900, et seq. prior to filing any lawsuit against the City. Such Government Code claims and any subsequent lawsuit based upon the Government Code claims shall be limited to those matters that remain unresolved after all procedures pertaining to extra Work, disputed Work, construction claims, and/or changed conditions have been followed by Contractor. If no such Government Code claim is submitted, or if the prerequisite contractual requirements are not satisfied, no action against the City may be filed. A Government Code claim must be filed no earlier than the date the Work is completed or the date the Contractor last performs Work on the Project, whichever occurs first. A Government Co de claim shall be inclusive of all unresolved claims unless a new unrelated claim arises after the Government Code claim is submitted.

J. Non-Waiver. The City’s failure to respond to a claim from the Contractor within the time periods described in this Article or to otherwise meet the time requirements of this Article shall result in the claim being deemed rejected in its entirety.

ARTICLE 47 CITY’S RIGHT TO TERMINATE CONTRACT
A. Termination for Cause by the City:

1. In the sole estimation of the City, if the Contractor refuses or fails to prosecute the Work or any separable part thereof with such diligence as will insure its completion within the time specified by the Contract Documents, or any extension thereof, or fails to complete such Work within such time, or if the Contractor should be adjudged a bankrupt, or if it should make a general assignment for the benefi t of its creditors, or if a receiver should be appointed on account of its insolvency, or the Contractor or any of its subcontractors should violate any of the provisions of this Contract, the City may serve written notice upon the Contractor and its Surety of the City's intention to terminate this Contract. This notice of intent to terminate shall contain the reasons for such intention to terminate this Contract, and a statement to the effect that the Contractor's right to perform this Contract shall cease and terminate upon the expiration of ten (10) calendar days unless such violations have ceased an d arrangements satisfactory to the City have been made for correction of said violations.

2. In the event that the City serves such written notice of termination upon the Contractor and the Surety, the Surety shall have the right to take over and perform the Contract. If the Surety does not: (1) give the City written notice of Surety's intention to take over and commence performance of the Contract within 15 calendar days of the City's service of said notice of intent to terminate upon Surety; and (2) ac tually commence performance of the Contract within 30 calendar days of th e City's service of said notice upon Surety; then the City may take over the Work and prosecute the same to completion by separate contract or by any other method it may deem advisable for the account and at the expense of the Contractor. 




 





Page 243 of 396 ends

38077.00180\29080232.10

-99- 00 72 13 – GENERAL CONDITIONS

3. In the event that the City elects to obtain an alternative performance of the Contract as specified above: (1) the City may, without liability for so doing, take possession of and utilize in completion of the Work such materials, appliances, plants and other property belonging to the Contractor that are on the site and reasonably necessary for such completion (A special lien to secure the claims of the City in the event of such suspension is hereby created against any property of Contractor taken into the possession of the City under the terms hereof and such lien may be enforced by sale of such property under the direction of the City Council without notice to Contractor.

The proceeds of the sale after deducting all expenses thereof and connected therewith shall be credited to Contractor. If the net credits shall be in excess of the claims of the City against Contractor, the balance will be paid to Contractor or Contractor’s legal representatives.); and (2) Surety shall be liable to the City for any cost or other damage to the City necessitated by the City securing an alternate performance pursuant to this Article.

B. Termination for Convenience by the City:

1. The City may terminate performance of the Work called for by the Contract Documents in whole or, from time to time, in part, if the City determines that a termination is in the City's interest.

2. The Contractor shall terminate all or any part of the Work upon delivery to the Contractor of a Notice of Termination specifying that the termination is for the convenience of the City, the extent of termination, and the Effective Date of such termination.

3. After receipt of Notice of Termination , and except as directed by the City's Representative, the Contractor shall, regardless of any delay in determining or adjusting any amount s due under this Termination for Convenience clause, immediately proceed with the following obligations:
a. Stop Work as specified in the Notice.
b. Complete any Work specified in th e Notice of Termination in a least cost/shortest time manner while still maintaining the quality called for under the Contract Documents.
c. Leave the property upon which the Contractor was working and upon which the facility (or facilities) forming the basis of the Contract Document is situated in a safe and sanitary manner such that it does not pose any threat to the public health or safety. d. Terminate all subcontracts to the extent that they relate to the portions of the Work terminated.
e. Place no further subcontracts or orders, except as necessary to complete the continued portion of the Contract.





 





Page 244 of 396 ends

38077.00180\29080232.10

-100- 00 72 13 – GENERAL CONDITIONS

f. Submit to the City's Representa tive, within ten (10) calendar days from the Effective Date of the Notice of Termination, all of the usual documentation called for by the Contract Documents to
substantiate all costs incurred by the Contractor for labor, materials and equipment through the Effective Date of the Notice of Termination. Any documentation substantiating costs incurred by the Contractor solely as a result of the City's exercise of its right to terminate this Contract pursuant to this clause, which costs the contractor is authorized under the Contract documents to incur, shall: (1) be submitted to and received by the Engineer no later than 30 calendar days after the Effective Date of the Notice of Termination; (2) describe the costs incurred with particularity; and (3) be conspicuously identified as “Termination Costs occasioned by the City's Termination for Convenience.”

4. Termination of the Contract shall not relieve Surety of its obligation for any just claims arising out of or relating to the Work performed.

5. In the event that the City exercises its right to terminate this Contract pursuant to this clause, the City shall pay the Contractor, upon the Contractor's submission of the documentation required by this clause and other applicable provisions of the Contract Documents, the following amounts:
a. All actual reimbursable costs incurred according to the provisions of this Contract.
b. A reasonable allowance for profit on the cost of the Work performed, provided Contractor establishes to the satisfaction of the City's Representative that it is reasonably probable that Contractor would have made a profit had the Contract been completed and provided further, that the profit allowed shall in no event exceed fifteen (15%) percent of the costs.
c. A reasonable allowance for Contractor's administrative costs in determining the amount payable due to termination of the Contract under this Article.

C. Notwithstanding any other provision of this Article, when immediate action is necessary to protect life and safety or to reduce significant exposure or liability, the City may immediately order Contractor to cease Work on the Project until such safety or liability issues are addressed to the satisfaction of the City or the Contract is terminated.

ARTICLE 48 WARRANTY AND GUARANTEE OF WORK
A. Contractor hereby warrants that materials and Work shall be completed in conformance with the Contract Documents and that the materials and Work provided will fulfill the requirements of this Warranty. Contractor hereby agrees to repair or replace, at the discretion of the City, any or all Work that may prove to be defective in its workmanship, materials furnished, methods of installation or fail to 




 





Page 245 of 396 ends

38077.00180\29080232.10

-101- 00 72 13 – GENERAL CONDITIONS

conform to the Contract Document requirements together with any other Work which may be damaged or displaced by su ch defect(s) within a period of one (1) year from the date of the Notice of Completion of the Project without any expense whatever to the City, ordinary wear and tear and unusual abuse and neglect excepted. Contractor shall be required to promptly repair or replace defective equipment or materials, at Contractor’s option. All costs associated with such corrective actions and testing, incl uding the removal, replacement, and reinstitution of equipment and materials necessary to gain access, shall be the sole responsibility of the Contractor.

B. For any Work so corrected, Contractor’s obligation hereunder to correct defective Work shall be reinstated for an addition al one (1) year period, commencing with the date of acceptance of such corrected Work. The reinstatement of the one (1) year warranty shall apply only to that portion of work that was corrected.

Contractor shall perform such tests as City may require to verify that any corrective actions, including, without limitation, re design, repairs, and replacements comply with the requirements of the Contract. In the event of Contractor’s failure to comply with the above-mentioned conditions withi n ten (10) calendar days after being notified in writing of required repairs, to the reasonable satisfaction of the City, the City shall have the right to correct and replace any defective or non-conforming Work and any work damaged by such work or the replacement or correction thereof at Contractor’s sole expense. Contractor shall be obligated to fully reimburse the City for any expenses incurred hereunder immediately upon demand.

C. In addition to the warranty set forth in this Article, Contractor shall obtain for City all warranties that would be given in normal commercial practice and assign to City any and all manufacturer’s or installer’s warranties for equipment or materials not manufactured by Contractor and provided as part of the Work, to the extent that such third-party warranties are assignable and extend beyond the warranty period set forth in this Article. Contractor shall furnish the City with all warranty and guarantee documents prior to final Acceptance of the Project by the City as required.

D. When specifically indicated in the Cont ract Documents or when directed by the Engineer, the City may furnish materials or products to the Contractor for installation. In the event any act or failure to act by Contractor shall cause a warranty applicable to any materials or products purchased by the City for installation by the Contractor to be voided or reduced, Contractor shall indemnify City from and against any cost, expense, or other liability arising therefrom, and shall be responsible to the City for the co st of any repairs, replacement or other costs that would have been covered by the warranty but for such act or failure to act by Contractor.

E. The Contractor shall remedy at it s expense any damage to City-owned or controlled real or personal property.

F. The City shall notify the Contractor, in writing, within a reasonable time after the discovery of any failure, defect, or dama ge. The Contractor shall within ten (10) calendar days after being notified comm ence and perform with due diligence all necessary Work. If the Contractor fails to promptly remedy any defect, or damage; 




 





Page 246 of 396 ends

38077.00180\29080232.10

-102- 00 72 13 – GENERAL CONDITIONS

the City shall have the right to replace, repair or otherwise remedy the defect, or damage at the Contractor’s expense.

G. In the event of any emergency constituti ng an immediate hazard to health, safety, property, or licensees, when caused by Work of the Contractor not in accordance with the Contract requirements, the City may undertake at Contractor’s expense, and without prior notice, all Work necessary to correct such condition.

H. Acceptance of Defective Work.

1. If, instead of requiring correction or removal and replacement of Defective Work, the City prefers to accept it, City may do so. Contractor shall pay all claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects, attorneys, and other professionals and all court or arbitration or other dispute re solution costs) attributable to City’s evaluation of and determination to accept such Defective Work and for the diminished value of the Work.

2. If any acceptance of defective work occurs prior to release of the Project Retention, a Change Order will be issued incorporating the necessary revisions in the Contract Documents with respect to the Work, and City shall be entitled to an appropriate decrease in the Contract Price, reflecting the diminished value of Work and all costs incurred by City.

3. If the Project Retention is held in an escrow account as permitted by the Contract Documents, Contractor will promptly alert the escrow holder, in writing, of the amount of Retention to be paid to City.

4. If the acceptance of Defective Work occurs after release of the Project Retention, an appropriate amount will be paid by Contractor to City.

I. City May Correct Defective Work.

1. If Contractor fails within a reasonable time after written notice from City’s Representative to correct Defective Work, or to remove and replace rejected Work as required by City, or if Contractor fails to perform the Work in accordance with the Contract Documents, or if Contractor fails to comply with any other provision of the Contract Documents, City may, after seven (7) Days’ written notice to Contractor, correct, or remedy any such deficiency.

2. In connection with such corrective or remedial action, City may exclude Contractor from all or part of the Site, take possession of all or part of the Work and suspend Contractor’s services related thereto, take possession of Contractor’s tools, appliances, construction equipment and machinery at the Site, and incorporate in the Work all materials and equipment stored at the Site or for which City has paid Contractor but which are stored elsewhere. Contractor shall allow City and City’s Representative, and the agents, employees, other contractors, and consultants of each of them, access to the Site to enable City to exercise the rights and remedies to correct the Defective Work.





 





Page 247 of 396 ends

38077.00180\29080232.10

-103- 00 72 13 – GENERAL CONDITIONS

3. All claims, costs, losses, and damages (including but not limited to all fees and charges of engineers, architects , attorneys, and other professionals and all court or arbitration or other dispute resolution costs) incurred or sustained by City correcting the Defective Work will be charged against Contractor, and a Change Order will be issued incorporating the necessary revisions into the Contract Documents with respect to the Work; and City shall be entitled to an appropriate decrease in the Contract Price.

4. Such claims, costs, lo sses and damages will include, but not be limited to, all costs of repair, or replacement of work of others destroyed or damaged by correction, removal, or replacement of Defective Work.

5. If the Change Order is executed after all payments under the Contract have been paid by City and the Project Rete ntion is held in an escrow account as permitted by the Contract Documents, Contractor will promptly alert the escrow holder, in writing, of the amount of Retention to be paid to City.

6. If the Change Order is executed after release of the Project Retention, an appropriate amount will be paid by Contractor to City.

7. Contractor shall not be allowed an extension of the Contract Times because of any delay in the performanc e of the Work attributable to City correcting Defective work.

J. Nothing in the Warranty or in the Cont ract Documents shall be construed to limit the rights and remedies available to City at law or in equity, including, but not limited to, Code of Civil Procedure section 337.15.

ARTICLE 49 DOCUMENT RETENTION & EXAMINATION
A. In accordance with Government Code section 8546.7, records of both the City and the Contractor shall be subject to exam ination and audit by the State Auditor General for a period of three (3) years after final payment.

B. Contractor shall make available to the City any of the Contractor’s other documents related to the Project immediately upon request of the City.

C. In addition to the State Auditor rights ab ove, the City shall have the right to examine and audit all books, estimates, records, contracts, documents, bid documents, subcontracts, and other data of the Co ntractor (including computations and projections) related to negotiating, pricing, or performing the modification in order to evaluate the accuracy and completeness of the cost or pricing data at no additional cost to the City, for a period of four (4) years after final payment.

ARTICLE 50 SEPARATE CONTRACTS
A. The City reserves the right to let other co ntracts in connection with this Work or on the Project site. Contractor shall permit other contractors reasonable access and storage of their materials and execution of their work and shall properly connect and coordinate its Work with theirs.





 





Page 248 of 396 ends

38077.00180\29080232.10

-104- 00 72 13 – GENERAL CONDITIONS

B. To ensure proper execution of its subs equent Work, Contractor shall immediately inspect work already in place and shall at once report to the Engineer any problems with the Work in place or discrepancies with the Contract Documents.

C. Contractor shall ascertai n to its own satisfaction the scope of the Project and nature of any other contracts that have been or may be awarded by the City in prosecution of the Project to the end that Contractor may perform this Contract in the light of such other contracts, if any. Nothing herein contained shall be interpreted as granting to Contractor excl usive occupancy at site of the Project.

Contractor shall not cause any unnecessary hindrance or delay to any other contractor working on the Project. If simultaneous execution of any contract for the Project is likely to cause interference with performance of some other contract or contracts, the Engineer shall deci de which Contractor shall cease Work temporarily and which contractor shall continue or whether work can be coordinated so that contractors may proc eed simultaneously. The City shall not be responsible for any damages suffered or for extra costs incurred by Contractor resulting directly or indirectly from award, performance, or attempted performance of any other contract or contracts on the Project site.

ARTICLE 51 NOTICE AND SERVICE THEREOF
All notices shall be in writing and either served by personal delivery or mailed to the other party as designated in the Bid Forms. Written notice to the Contractor shall be addressed to Contractor’s principal place of business unless Contractor designates another address in writing for service of notice. Notice to City shall be addressed to the City as designated in the Notice Inviting Bids unless City designates another address in writing for service of notice. Notice shall be effective upon receipt or five (5) calendar da ys after being sent by first class mail, whichever is earlier. Notice given by facsimile shall not be effective unless acknowledged in writing by the receiving party.

ARTICLE 52 NOTICE OF THIRD PARTY CLAIMS
Pursuant to Public Contract Code section 9201, the City shall provide the Contractor with timely notification of the receipt of any third-party claims relating to the Contract. The City is entitled to recover reasonable costs incurred in providing such notification.

ARTICLE 53 STATE LICENSE BOARD NOTICE
Contractors are required by law to be licensed and regulated by the Contractors’ State License Board which has jurisdiction to investigate complaints against contractors if a complaint regarding a patent act or omission is filed within four (4) years of the date of the alleged violation. A complaint regarding a latent act or omission pertai ning to structural defects must be filed within ten (10) years of the date of the alleged violation. Any questions concerning a contractor may be referred to the Registrar, Contractors’ State License Board, P.O. Box 26000, Sacramento, California 95826.

ARTICLE 54 INTEGRATION
A. Oral Modifications Ineffective. No oral order, objection, direction, claim or notice by any party or person shall affect or modify any of the terms or obligations contained in the Contract Documents.





 





Page 249 of 396 ends

38077.00180\29080232.10

-105- 00 72 13 – GENERAL CONDITIONS

B. Contract Documents Represent Entire Contract. The Contract Documents represent the entire agreement of the City and Contractor.

ARTICLE 55 ASSIGNMENT OF CONTRACT
Contractor shall not assign, transfer, convey, sublet or otherwise dispose of the rights or title of interest of any or all of this contract without the prior written consent of the City. Any assignment or change of Contractor’s name of legal entity without the written consent of the City shall be void.

Any assignment of money due or to become due un der this Contract shall be subject to a prior lien for services rendered or Material supplied for performance of Work called for under the Contract Documents in favor of all persons, firms, or corporations rendering such services or supplying such Materials to the extent that clai ms are filed pursuant to the Civil Code, the Code of Civil Procedure or the Government Code.

ARTICLE 56 CHANGE IN NAME AND NATURE OF CONTRACTOR’S LEGAL ENTITY Should a change be contemplated in the name or nature of the Contractor’s legal entity, the Contractor shall first notify the City in order that proper steps may be taken to have the change reflected on the Contract and all related documents. No change of Contractor’s name or nature will affect City’s rights under the Contract, including but not limited to the bonds.

ARTICLE 57 ASSIGNMENT OF ANTITRUST ACTIONS
Pursuant to Public Contract Code section 7103.5 , in entering into a public works contract or subcontract to supply goods, services, or materials pursuant to a public works contract, Contractor or subcontractor offers and agrees to assign to th e City all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 USC, Section 15) or under the Cartwright Act (Chapter 2 (commencing with Section 16700) of Part 2 of Division 7 of the Business and Professions Code), arising from th e purchase of goods, services, or materials pursuant to this contract or any subcontract. This assignment shall be made and become effective at the time the City tenders final payment to the Contractor, without further acknowledgment by the parties.

ARTICLE 58 PROHIBITED INTERESTS
No City official or representative who is authorized in such capacity and on behalf of the City to negotiate, supervise, make, accept, or approve, or to take part in negotiating, supervising, making, accepting or approving any engineering, inspection , construction or material supply contract or any subcontract in connection with construction of the project, shall be or become directly or indirectly interested financially in the Contract.

ARTICLE 59 CONTROLLING LAW
Notwithstanding any subcontract or other contract with any subcontractor, supplier, or other person or organization performing any part of th e Work, this Contract shall be governed by the law of the State of California excluding any choice of law provisions.

ARTICLE 60 JURISDICTION; VENUE
Contractor and any subcontractor, supplier, or ot her person or organization performing any part of the Work agrees that any action or suits at law or in equity arising out of or related to the 




 





Page 250 of 396 ends

38077.00180\29080232.10

-106- 00 72 13 – GENERAL CONDITIONS

bidding, award, or performance of the Work sha ll be maintained in the Superior Court of Santa Clara County, California, and expressly consent to the jurisdiction of said court, regardless of residence or domicile, and agree that said court shall be a proper venue for any such action.

ARTICLE 61 LAWS AND REGULATIONS
A. Contractor shall give al l notices and comply with all laws, ordinances, rules and regulations bearing on conduct of work as indicated and specified. If Contractor observes that drawings and specifications are at variance therewith, it shall promptly notify the Engineer in writing and any necessary changes shall be adjusted as provided for in this Contract for changes in work. If Contractor performs any work knowing it to be contrary to such laws, ordinances, rules and regulations, and without such notice to the Engineer, it shall bear all costs arising therefrom.

B. Contractor shall be responsible for familiarity with the Americans with Disabilities Act (“ADA”) (42 U.S.C. § 12101 et seq.). The Work will be performed in compliance with ADA regulations.

ARTICLE 62 PATENTS
Contractor shall hold and save the City, officials, officers, employees, and authorized volunteers harmless from liability of any nature or kind of claim therefrom including costs and expenses for or on account of any patented or unpatented invention, article or appliance manufactured, furnished or used by Contractor in the performance of this contract.

ARTICLE 63 OWNERSHIP OF CONTRACT DOCUMENTS
All Contract Documents furnished by the City ar e City property. They are not to be used by Contractor or any subcontractor on other work nor shall Contractor claim any right to such documents. With exception of one complete set of Contract Documents, all documents shall be returned to the City on request at completion of the Work.

ARTICLE 64 NOTICE OF TAXABLE POSSESSORY INTEREST
In accordance with Revenue and Taxation Code section 107.6, the Contract Documents may create a possessory interest subject to personal property taxation for which Contractor will be responsible.

ARTICLE 65 SURVIVAL OF OBLIGATIONS
All reresentations, indemnifications, warranties, and guarantees made in, required by, or given in accordance with the Contract Documents, as well as all continuing obligations indicated in the Contract Documents, will survive final payment, completion, and acceptance of the Work or termination or completion of the Contract or termination of the services of Contractor.






 





Page 251 of 396 ends

38077.00180\29080232.10

-107- 00 73 13 – SPECIAL CONDITIONS

00 73 13 – SPECIAL CONDITIONS

1.1 Project Manager
A For purposes of this Project, the Project Manager shall be: Mike Serpa, Senior Public Works Lead.

1.2 Location of the Project.

A The Project is located at various locations throughout the City.

B The general location of the Project is shown on Exhibit B – Si te List. Additional areas of work (not exceeding 25% quantity for any one bid item) may be added at the discretion of the Project Manager.

1.3 Status of the Project Area and Rights-of-Way.

A City, at its expense, will provide all rights-of-way or permits, or both, covering the crossing of private property and public and private rights-of-way necessary for the permanent Work; provided, however, Contractor shall, at its expense, obtain any bonds or insurance policies or pay any fees and enter into any agreements required by a controlling authority, e.g., Caltrans or Southern Pacific Railroad Company, before Contractor enters upon any property or righ t-of-way under the jurisdiction of any such controlling authority for the purpose of performing Work.

B City has acquired or is negotiating to ac quire any rights-of-way, or both, necessary for the permanent Work.

C If such permits are required, all operations of Contractor shall conform to the restrictions, regulations, and requirements set forth in said permits, copies of which will be included in the Contract Documents.

D Contractor may be required, as a condition for receiving final payment, to obtain, and provide City’s Representative with copies of, executed damage releases from the owners of public and private proper ty whose property has been damaged by the Work. The damage releases will be on a form provided by City.

E Contractor shall, also, as a condition for receiving final payment, obtain, and provide City’s Representative with copies of, executed damage releases from the owners of certain public and private pr operty or areas which have been crossed by the Work or otherwise affected by the Work. The damage releases will be on a form provided by City.

1.4 Site Data.

Not used.

1.5 Pre-Purchased or Pre-Negotiated Material.

Not used.





 





Page 252 of 396 ends

38077.00180\29080232.10

-108- 00 73 13 – SPECIAL CONDITIONS

1.6 Designation of City’s Representative.

A Unless otherwise modified by City, City’s Representative shall be Michael Serpa, Senior Public Works Lead.

1.7 Project Retention
In accordance with Public Contract Code § 7201, City will withhold 5% of each progress payment as retention on the Project.

1.8 Liquidated Damages Due to Contractor Delay.

A Time is of the essence. Should Contractor fail to complete all or any part of the Work within the time specified in the Contract Documents, City will suffer damage, the amount of which is difficult, if not impossible, to ascertain and, pursuant to the authority of Government Code section 53069.85, City shall therefore be entitled to Two Hundred ($250) per Day as liquidated damages for each Day or part thereof that actual completion extends beyond the time specified.

B Liquidated damages may be deducted fr om progress payments due to Contractor, Project retention or may be collected directly from Contractor, or from Contractor's surety. These provisions for liquidated damages shall not prevent City, in case of Contractor's default, from terminating the Contractor.

1.9 Utility Outages – Notices to Residents.

A Should Contractor’s operations requ ire interruption of any utility service, Contractor shall notify City at least ten (10) Days prior to the scheduled outage.

Contractor will notify all impacted residents on a form provided by City at least seven (7) Days prior to the scheduled outage.

B Contractor shall be responsible for provid ing, at its cost, any temporary utility or facilities necessitated by the utility outage.

1.10 Schedule Constraints.

A Contractor shall schedule to have first orde r of work to complete locations in Exhibit B – Site List.

B Contractors shall schedule to have the second order of work to complete locations yet to be determined and as may be provided to the contractor as received by the City.

1.11 Safety Programs.

Not used.

1.12 Coordination with Other Contractors.

Not used.

END OF SPECIAL CONDITIONS





 





Page 253 of 396 ends

38077.00180\29080232.10

-109- 00 73 13 – SPECIAL CONDITIONS






 





Page 254 of 396 ends

38077.00180\29080232.10

-110- 01 00 00 – GENERAL REQUIREMENTS

01 00 00 – GENERAL REQUIREMENTS
PART 1 GENERAL

1.1 DESCRIPTION
A. The work to be done is maintenance ty pe work and consists, in general, of the removal and replacement of existing port land cement concrete curb & gutters, sidewalks, driveway approaches, accessible ramps, asphalt replacement adjacent to portland cement concrete work, flat work, and tree root barriers, as required.

B. The majority of the work consists of removal and replacement of portland cement concrete curb & gutter and sidewalk where drainage problems exist or where displacements may become a public safety hazard. The improvements will be replaced over existing base material in most cases (approximately 50% of sidewalk replacement locations). When it is necessary to remove pavement adjacent to the lip of the gutter, replacement of asphalt concrete pavement twelve (12) inches out from new gutter lip will be completed by the Contractor.

C. Contractor shall complete all work in conformance with Sections 39, 73, 92 and 94 of the State of California, Department of Transportation, Standard Specifications 2022.

PART 2 (NOT USED)
PART 3 EXECUTION

3.1 LAYOUT OF WORK AND QUANTITY SURVEYS
A. General. The Contractor shall utilize a properly licensed surveyor to perform all layout surveys required for the control and completion of the Work, and all necessary surveys to compute quantities of Work performed.

City and/or the Engineer of Record has established primary control to be used by the Contractor for establishing lines and grades required for the Work.

Primary control consists of benchmarks and horizontal control points in the vicinity of the Work.A listing and identification of the primary control is provided on the Drawings. Before beginning any layout work or construction activity, the Contractor shall check and verify primary control, and shall advise the City Representative of any discrepancies.

B. Quantity surveys. The Contractor shall perform such surveys and computations as are necessary to determine quantities of Work performed or placed during each progress payment period, and shall perform all surveys necessary for theCity Representative to determine final quan tities of Work in place. The City Representative will determine final quantities based upon the survey data provided by the Contractor, and the design lines and grades. If requested by the City Representative, the Contractor shall prov ide an electronic copy of data used for quantity computations.





 





Page 255 of 396 ends

38077.00180\29080232.10

-111- 01 00 00 – GENERAL REQUIREMENTS

All surveys performed for measurement of final quantities of Work and material shall be subject to approval of City’s Representative. Unless waived by City’s Representative in each specific case, quantity surveys made by the Contractor shall be made in the presence of City’s Representative.

C. Surveying

1. Accuracy. Degree of accuracy shal l be an order high enough to satisfy tolerances specified for the Work and the following:
(a) Right-of-way and alignment of tangents and curves shall be within

0.1 foot.
(b) Structure points shall be set within 0.01 foot, except where operational function of the specia l features or installation of metalwork and equipment require closer tolerances. When formwork has been placed and is ready for concrete, the Contractor shall check the formwork for conformance with the drawings and to ensure that the forms are sufficiently within the tolerance limits for the completed work.
(c) Cross-section points shall be loca ted within 0.1 foot, horizontally and vertically.
(d) Aerial Mapping shall meet Na tional Mapping Standards for 2- foot contour intervals.

D. Records. Survey data shall be recorded in accordance with recognized professional surveying standards. Origin al field notes, computations, and other surveying data shall be recorded on electronic data collectors or in standard field books and must be of sufficient quality to enable the Contractor to prepare accurate record drawings as required by the Contract Documents.

E. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required for surveys for the layout of work and quantity surveys shall be included in the Schedule of Pay Items for items of work requiring the surveys. No additional compensation shall be made to the Contractor for this Work.

3.2 SCHEDULE
A. Estimated Schedule. Within 21 Days after the issuance of the Notice of Award, Contractor shall prepare a Project schedule and shall submit this to the Engineer for Approval. The receipt or Approval of any schedules by the Engineer or the City shall not in any way relieve the Contractor of its obligations under the Contract Documents. The Contractor is fully responsible to determine and provide for any and all staffing and resources at levels which allow for good quality and timely completion of the Project. Contractor’s failure to incorporate all elements of Work required for the performance of the Cont ract or any inaccuracy in the schedule shall not excuse the Contractor from performing all Work required for a completed Project within the specified Contract time pe riod. If the required schedule is not 




 





Page 256 of 396 ends

38077.00180\29080232.10

-112- 01 00 00 – GENERAL REQUIREMENTS

received by the time the first payment under the Contract is due, Contractor shall not be paid until the schedule is received, reviewed and accepted by the Engineer.

B. Schedule Contents. The schedule sha ll indicate the beginning and completion dates of all phases of construction; critic al path for all critical, sequential time related activities; and “float time” for all “slack” or “gaps” in the non-critical activities.

The schedule shall clearly identify all staffing and other resources which in the Contractor’s judgment are needed to complete the Project within the time specified for completion. The overall Project Schedule duration shall be within the Contract time.

C. Weather Allowance. The schedule sha ll allow adequate time for inclement weather.

D. Schedule Updates. Contractor sha ll continuously update its construction schedule. Contractor shall submit an updated and accurate construction schedule to the Engineer monthly when requested to do so by Engineer. Contractor shall also submit schedules showing a three we ek detailed look-ahead at bi-weekly meetings conducted with the City. The Engineer may withhold progress payments or other amounts due under the Contract Documents if Contractor fails to submit an updated and accurate construction schedule.

3.3 TEMPORARY FIELD OFFICE
Not used.

3.4 PROTECTION OF WORK AND PROPERTY
A. All traffic detector loops, fences, walls, culverts, monuments, or other obstructions (except property line monuments within five (5) feet of the centerline of the mains) which are removed, damaged, or destroyed in the course of the Work, shall be replaced or repaired to the original cond ition at no additional cost to City.

Contractor shall be responsible for the cost to repair, replace, relocate, and replacement of utilities whether or not those obstructions have been shown on the Plans, unless otherwise stated herein. It is then the Contractor’s responsibility to employ at its expense a Licensed Land Surveyor to restore all property line monuments located more than five (5) feet from the centerline of the mains, which are destroyed or obliterated. Property lin e monuments located within five (5) feet of the centerline of the mains will be replaced by the City at no expense to the Contractor, provided the City is notified at least 48 hours before the property line monuments are damaged.

B. Contractor shall provide such heat, co vering, and enclosures as are necessary to protect all Work, materials, equipment, appliances, and tools against damage by weather conditions.

C. Contractor shall take adequate precauti ons to protect existing sidewalks, curbs, pavements, utilities, and other adjoining property and structures, and to avoid damage thereto, and Contractor shall repair any damage thereto caused by the Work operations. Contractor shall:





 





Page 257 of 396 ends

38077.00180\29080232.10

-113- 01 00 00 – GENERAL REQUIREMENTS

1. Enclose the working area with a substantial barricade, and arrange work to cause minimum amount of inconvenience and danger to the public.

2. Provide substantial barricades around any shrubs or trees indicated to be preserved.

3. Deliver materials to the Project si te over a route designated by the Engineer.

4. Provide any and all dust control re quired and follow the Applicable air quality regulations as appropriate. If the Contractor does not comply, the City shall have the immediate authority to provide dust control and deduct the cost from payments to the Contractor.

5. Confine Contractor’s apparatus, the storage of materials, and the operations of its workers to limits requ ired by law, ordinances, permits, or directions of the Engineer. Contract or shall not unreasonably encumber the Project site with its materials.

6. Take care to prevent disturbing or covering any survey markers, monuments, or other devices marking property boundaries or corners. If such markers are disturbed by accident , they shall be replaced by a civil engineer or land surveyor acceptable to the City, at no cost to the City.

7. Ensure that existing facilities, fences and other structures are all adequately protected and that, upon completion of all Work, all facilities that may have been damaged are restored to a condition acceptable to the City.

8. Preserve and protect from injury all buildings, pole lines and all direction, warning and mileage signs that have been placed within the right-of-way.

9. At the completion of work each day, leave the Project site in a clean, safe condition.

10. Comply with any approved stage cons truction and traffic control plans.

Access to residences and businesses shall be maintained at all times, unless otherwise permitted in writing by the City.

11. Cover and or protect work and project site as may be required to prevent or mitigate schedule delay and to allow work to proceed during wet weather or wet conditions.

D. These precautionary measures will apply continuously and not be limited to normal working hours. Full compensation for the Work involved in the preservation of life, safety and property as above specified shall be considered as included in the prices paid for the various contract items of Work, and no additional allowance will be made therefore.

E. Should damage to persons or property occur as a result of the Work, Contractor shall be responsible for proper investigat ion, documentation, including video or 




 





Page 258 of 396 ends

38077.00180\29080232.10

-114- 01 00 00 – GENERAL REQUIREMENTS

photography, to adequately memorialize an d make a record of what transpired.

The City shall be entitled to inspect and copy any such documentation, video, or photographs.

3.5 SITE CONDITIONS SURVEYS
A. Work Included.

Contractor shall conduct thorough pre-co nstruction and post-construction site condition surveys of the entire project area. Site Conditions surveys shall include written documentation of the conditions fo und, as well as photographs and video recordings of the area within at least 80 feet of any construction area and staging area. The written notes, photographs, an d video shall be suitable for forensic purposes to resolve any damage claims that may arise as a result of construction.

B. Submittals.

1. Written documentation of site cond ition survey at pre-construction and post-construction.

2. Photographs as described herein of pre-construction and post-construction conditions.

3. Video recordings as described herein of pre-construction and post- construction conditions.

4. Submittals shall be made within three days of the surveys. All post- construction data shall be submitted prior to the final project inspection.

C. Site Condition Written Documentation.

Written documentation shall include the time, date, and conditions under which the site survey was made. The documentation shall note the condition of structures, pavement, sidewalks, utilities, fences, and etc. within the work areas.

D. Photographs & Video Recording.

1. General – Prior to starting Work, Contractor shall provide a video recording of the project site. Contract shall take enough photographs during each site survey to provide a record of conditions existing prior to construction and conditions after construction. Pre- construction video and photographs shall be taken prior to any construction or mobilization of equipment, but not more that one week prior to actual start of work. The pre-construction photographs may be staged at different times to match the progression of the Work.

2. The photographs shall document exis ting damage to public and private facilities, both prior to and after construction. Conditions to be documented include, but are not limited to: sidewalk cracks, broken curbs, separated property walls, improvements within pu blic right-of-ways, access roads used, utility covers and markings, signs, pavement striping, pavement, 




 





Page 259 of 396 ends

38077.00180\29080232.10

-115- 01 00 00 – GENERAL REQUIREMENTS

unique or unusual conditions, adjace nt driveways, landscaping, survey markers, and any feature directed by the Engineer. Private property that is adjacent to the public right-of-way shall be documented to the extent visible from the public right-of-way.

3. Photographs shall include items to indi cate scale, as needed. In particular, scales or other items shall be laid next to close ups of structural cracks and other damaged areas being recorded. Scaling shall also be used to document elevation differences, as needed.

4. One set of color prints and the preconstruction site video shall be submitted. Additional sets shall be available for reviewing in settling any construction disputes. A set of photos shall also be furnished in electronic format. The resolution shall be at least equal to 7 mega-pixels. All photos shall be documented as to time an d date taken, photographer, project number, location, and orientation. Documentation shall include a brief description of objects photographed.

E. Video Recording.

1. Video recordings shall document the co nditions of the entire area affected by construction, as well as nearby st ructures and facilities. The general documentation requirements for videos are the same as for photographs.

Video recorders shall accurately and continuously record the time and date.

2. Video recordings shall include an audio portion made simultaneously during the videoing. The audio recording shall describe the location, time, orientation, and objects being recorded. Special commentary shall be provided for unusual conditions or damage noted.

3. Video equipment shall be capable of producing high resolution images and shall have zoom capabilities.

4. Video recordings shall provide an overall picture of the sites and shall provide detailed images of damaged areas. Video shall extend to the maximum height of structures.

5. The Engineer shall have the right to reject any audio video recordings submitted with unintelligible audio, uncontrolled pan or zoom, or of poor quality. Video recordings shall be repeated when rejected.

6. Video recordings shall be submitted with labels indicating the project, date, recorder, and other pertinent informati on. Recordings shall be submitted on standard DVDs in a standard format.

F. Timing.

Contractor shall provide written notice of the time scheduled for the site conditions survey and the place it is to begin. Contractor shall obtain the Engineer’s concurrence prior to beginning the condition survey. The Engineer reserves the right to cancel the survey due to weather conditions or other problems. Videoing 




 





Page 260 of 396 ends

38077.00180\29080232.10

-116- 01 00 00 – GENERAL REQUIREMENTS

shall be done during times of good visibility and no videoing or photography shall be done during peri ods of visible precipitation or when standing water obscures pavement. Contractor shall provide the Engineer with an opportunity to have a representative present when taking th e photos and provide guidance during photographing.

G. Site Surveyor.

The site condition surveyor(s) shall be ex perienced in construction and potential damage concerns. The site condition surveyor(s) shall be familiar with the photography and video equipment being used.

H. Field Quality Control.

Prior to submitting videos and photograph s, the Contractor shall spot check the photos and videos in the field to insure they accurately reflect the actual conditions and to insure they are correctly labeled.

I. Soils Compaction Testing.

1. All soils compaction testing will be done by a licensed geotechnical engineer furnished by the City. Soils compaction testing will be done for all footings and foundations prior to placement of rebar or concrete.

2. For pipeline construction, soil compaction testing will be done at 100-foot intervals or as ordered by the project soils/geotechnical report at the bottom of the trench prior to placement of pi pe bedding; at the top of the pipe bedding above the pipe; every two vertic al feet of trench backfill or as otherwise ordered by the project soils/geotechnical report; at the top of the trench backfill, which sould be the bottom of the pavement section; and at the top of the aggregate base prior to pavement construction.

3.6 SUBMITTAL REQUIREMENTS FOR MANUALS AND RECORD DRAWINGS A. General. The Contractor shall furnish all materials and perform all Work required for furnishing submittals to City in accordance with Contract Documents. The Contractor shall submit Project Record Drawings, Technical Manual, Spare Parts, and other required items within 5 days following completion of project construction, and prior to Contractors request for Project Acceptance.

B. Technical Manuals.

1. The Contractor shall submit technical operation and maintenance information for each item of mechanical, electrical and instrumentation equipment in an organized manner in the Technical Manual. It shall be written so that it can be used and understood by City’s operation and maintenance staff.

2. The Technical Manual shall be subdiv ided first by specification section number; second, by equipment item; and last, by "Category." The Contractor shall furnish to City four (4) identical Technical Manuals. Each 




 





Page 261 of 396 ends

38077.00180\29080232.10

-117- 01 00 00 – GENERAL REQUIREMENTS

set shall consist of one or more volu mes, each of which shall be bound in a standard binder.

C. Spare Parts List - The Contractor shall fu rnish to City six (6) identical sets of spare parts information for all mechanical, el ectrical, and instrumentation equipment.

The spare parts list shall include the current list price of each spare part. The spare parts list shall include those spare parts which each manufacturer recommends be maintained by City in inventory. Each manufacturer or supplier shall indicate the name, address, and telephone number of its nearest outlet of spare parts to assist City in ordering. The Contractor shall cross-reference all spare parts lists to the equipment numbers designated in the Contract Documents. The spare parts lists shall be bound in standard size, 3-ring binder.

D. Record Drawings

1. The Contractor shall maintain one record set of Drawings at the Site. On these, it shall mark all Project conditions, locations, configurations, and any other changes or deviations which may vary from the information represented in the original Contract Documents, including buried or concealed construction and utility feat ures which are revealed during the course of construction. Special attention shall be given to recording the horizontal and vertical location of all buried utilities that differ from the locations indicated, or which were not indicated on the Contract Drawings.

Said record drawings shall be supplemented by any detailed sketches as necessary or directed to fully indicate the Work as actually constructed.

These master record drawings of the as-built conditions, including all revisions made necessary by Addenda and Change Orders shall be maintained up-to-date during the progress of the Project. Red ink shall be used for alterations and notes. Notes shall identify relevant Change Orders by number and date.

2. For all Projects involving the installa tion of any pipeline, Contractor shall survey and record the top of the pipe at a minimum of every 100 linear feet, and at each bend, recording both the horizontal and vertical locations.

3. Record drawings shall be accessible to City’s Representative at all times during the construction pe riod. The record drawings shall be kept up to date and will be checked by the City prior to each progress payment.

Failure on the Contractor’s part to keep record drawings current could result in withholding partial payment.

4. Upon Completion of the Project and as a condition of final acceptance, the Contractor shall finalize and deliver a complete set of Record Drawings to City’s Representative. The information submitted by the Contractor will be assumed to be correct, and the Contractor shall be responsible for, and liable to City, for the accuracy of such information, and for any errors or omissions which may or may not appear on the Record Drawings.

E. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete the Manuals and Record 




 





Page 262 of 396 ends

38077.00180\29080232.10

-118- 01 00 00 – GENERAL REQUIREMENTS

Drawings shall be included in Contractor’s bid and distributed in the Schedule of Pay. No additional compensation shall be made to the Contractor for this Work.

3.7 MATERIALS
A. Materials to be Furnished by the Contractor

1. Inspection of Materials. Materials furnished by the Contractor which will become a part of the Project shall be subject to inspection at any one or more of the following locations, as determined by City’s Representative: at the place of production or manufacture, at the shipping point, or at the site of the Work. To allow sufficient time to provide for inspection, the Contractor shall submit to City’s Representative, at the time of issuance, copies of purchase orders or ot her written instrument confirming procurement of the materials, including drawings and other pertinent information, covering materials on which inspection will be made.

2. No later than fourteen (14) Days prior to manufacture of material, Contractor shall inform City’s Representative, in writing, the date the material is to be manufactured.

3. Contractors Obligations. The inspection of materials at any of the locations specified above or the waiving of the inspection thereof shall not impact whether the materials and equipment conform to the Contract Documents.

Contractor will not be relieved from furnishing materials meeting the requirements of the Contract Documents due to City’s inspection or lack of inspection of the equipment or materials. Acceptance of any materials will be made only after materials are installed in the Project.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to accommodate City’s testing efforts, including any travel required by Contractor’s forces, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items related to the materials requiring testing. No additional compensation shall be made to the Contractor for this Work.

3.8 LOCAL CONDITIONS AND REQUIREMENTS
A. Access to Work and Haul Routes

1. General. All work on the rights-of-way necessary for access to the Site shall be performed by the Contractor. Contractors anticipated Haul Routes shall be in compliance with the City's approved Truck Routes available from the Engineer.

2. Access, Damage, Restoration. The Contractor shall make his own investigation of the condition of available public or private roads and of clearances, restrictions, bridge-load limits, permit or bond requirements, and other limitations that affect or may affect transportation and ingress or egress at the Site.





 





Page 263 of 396 ends

38077.00180\29080232.10

-119- 01 00 00 – GENERAL REQUIREMENTS

3. The Contractor shall maintain and repair any damage arising out of Contractor’s operations to all roads used during construction of the Project, and upon completion of all Work, but prior to final acceptance, the roads shall be restored to their original condition. Prior to using any road for access to the Site, the Contractor shall conduct a photograph and/or video survey of the roadway with a copy submitted to City’s Representative.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items.

No additional compensation shall be made to the Contractor for this Work.

B. Power. Contractor shall provide at it s own expense all necessary power required for operations under the contract. The Co ntractor shall provide and maintain in good order such modern equipment and inst allations as shall be adequate in the opinion of the Engineer to perform in a safe and satisfactory manner the Work required by the contract.

C. Construction Water.

1. Construction water shall not be used for purposes other than those required to satisfactorily complete the contract.

2. Construction recycled water will be made available to the contractor from one of three fill locations within the city limits. If there is a need for construction recycled water during construction, the contractor shall apply for a city construction recycled water meter at the city hall finance counter prior to the beginning of work. A security deposit of $2,000 is required for the construction water me ter from which the meter rental fee and cost of water will be deducted. if the rental fee and the water costs exceed the $2,000.00 deposited, an invoice will be issued to the contractor for payment.

3. Construction potable water will only be made available to the contractor if it can be demonstrated that recycled water cannot be used for the construction activities. potable water will be made available from existing city fire hydrant(s) nearest the propos ed construction site as approved by the engineer, or by such other means as may be expressly approved in writing by the engineer. If there is a need for water during construction, the contractor shall apply for a city construction water meter at the city hall finance counter prior to the beginning of work. a security deposit of $2,000 is required for the construction water meter from which the meter rental fee and cost of water will be deducted. If the rental fee and the water costs exceed the $2,000.00 deposited, an invoice will be issued to the contractor for payment.

4. All required water, all work and materials required for obtaining, pumping, transporting and applying and otherwise disposing of said water shall be in an approved manner and shall be performed by, and at the expense of the contractor and no extra or separate compensation will be made thereof. 




 





Page 264 of 396 ends

38077.00180\29080232.10

-120- 01 00 00 – GENERAL REQUIREMENTS

D. Operation of Existing Water Facilities

1. The Contractor shall not operate any of the existing water systems, including pumps, motors, valves, and hydrants, but shall contact the City two (2) working days in advance with a list and location of the water system facilities that will require operating, opening, stopping, or closure by the City.

2. At the option of the Engineer, the Contractor may be permitted to operate valves for the purpose of making connections to existing mains. The City will perform all notification to existing customers regarding temporary loss of service.

3. Contractor shall submit a request on City’s standard form for any shut-down of existing water facilities.

E. Construction at Existing Utilities

1. General. Where the Work to be performed crosses or otherwise interferes with water, sewer, gas, or oil pipelines ; buried cable; or other public or private utilities, the Contractor shall perform construction in such a manner so that no damage will result to either public or private utilities. It shall be the responsibility of the Contractor to determine the actual locations of, and make accommodates to maintain, all utilities.

2. Permission, Notice and Liability. Before any utility is taken out of service, permission shall be obtained by the Contractor from the owner. The owner, any impacted resident or business owner and the City Representative will be advised of the nature and duration of the utility outage as well as the Contractor’s plan for providing temporary utilities if required by the owner.

The Contractor shall be liable for all damage which may result from its failure to maintain utilities during the progress of the Work, and the Contractor shall indemnify City as required by the Contract Documents from all claims arising out of or connected with damage to utilities encountered during constr uction; damages resulting from disruption of service; and injury to persons or damage to property resulting from the negligent, accidental, or intentional breaching of utilities.

3. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items.

No additional compensation shall be made to the Contractor for this Work.

F. Traffic Control

1. General. Contractor shall abide by traffic control plans approved by the City.

2. Protections. Roads subject to interf erence by the Work shall be kept open or suitable temporary passages through the Work shall be provided and maintained by the Contractor. The Co ntractor shall provide, erect, and 




 





Page 265 of 396 ends

38077.00180\29080232.10

-121- 01 00 00 – GENERAL REQUIREMENTS

maintain all necessary barricades, suitable and sufficient flasher lights, flag persons, danger signals, and signs, and shall take all necessary precautions for the protection of the Work and the safety of the public. No construction work along public or private roads may proceed until the Contractor has proper barricades, flasher lights, flag persons, signals, and signs in place at the construction site.

3. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items.

No additional compensation shall be made to the Contractor for this Work.

G. Cleaning Up

1. Contractor at all times shall keep premises free from debris such as waste, rubbish, and excess materials and equi pment. Contractor shall not store debris under, in, or about the premis es. Contractor shall also clean all asphalt and concrete areas to the degree necessary to remove oil, grease, fuel, or other stains caused by Contractor operations or equipment, including all USA markings. The use of water, resulting in mud on streets, will not be permitted as substitute for sweeping or other methods. Dust control may require having a water tr uck onsite for the duration of the project, and/or use of temporary hoses and pipelines to convey water.

2. Contractor shall fully clean up the site at the completion of the Work. If the Contractor fails to immediately clean up at the completion of the Work, the City may do so and the cost of such clean up shall be charged back to the Contractor.

3.9 ENVIRONMENTAL QUALITY PROTECTION
A. Environmental Conditions
Not used.

B. Landscape and Vegetation Preservation

1. General. The Contractor shall exercise care to preserve the natural landscape and vegetation, and shall conduct operations so as to prevent unnecessary destruction, scarring, or defacing of the natural surroundings in the vicinity of the Work.

2. Damage and Restoration. Movement of crews and equipment within the rights-of-way and over routes provided for access to the Work shall be performed in a manner to prevent damage to property. When no longer required, construction roads shall be restored to original contours.

3. Upon completion of the Work, and following removal of construction facilities and required cleanup, land used for construction purposes and not required for the completed installation shall be scarified and regraded, 




 





Page 266 of 396 ends

38077.00180\29080232.10

-122- 01 00 00 – GENERAL REQUIREMENTS

as required, so that all surfaces are left in a condition that will facilitate natural revegetation, provide for proper drainage, and prevent erosion.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to complete this Work, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items.

No additional compensation shall be made to the Contractor for this Work.

C. Protected Species

1. General. If, in the performance of the Work, evidence of the possible occurrence of any State or Federally listed threatened or endangered plant or animal is discovered, the Contractor shall notify the City Representative immediately, giving the location and nature of the findings. Written confirmation of the evidence, location and nature of the findings shall be forwarded to City within 2 Days.

2. Procedures. The Contractor shall immediately cease all construction activities in the immediate area of the discovery to the extent necessary to protect the endangered plant or animal.

If directed by the City Representative, Contractor will refrain from working in the immediate area, suspend the Work in its entirety, or alter its performance to ensure full compliance with all applicable permits, laws and regulations. Any City directed changes to the Work as a result of a siting will be pursuant to the Contract Documents.

3. False Siting. Any costs or delays incurred by City or the Contractor due to unreasonable or false notification of an endangered plant or animal will be borne by the Contractor.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to comply with this paragraph, shall be included in Contractor’s bi d and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

D. Preservation of Historica l and Archeological Resources

1. General. If, in the performance of the Work, Contractor should unearth cultural resources (for example, human remains, animal bones, stone tools, artifacts and/or midden deposits) throug h excavation, grading, watering or other means, the Contractor notify the
Construction/Archeological Monitor and/or the City Representative immediately, giving the location and nature of the findings. Written confirmation of the evidence, location and nature of the findings shall be forwarded to the Construction/Archeological Monitor and/or City within 2 Days.





 





Page 267 of 396 ends

38077.00180\29080232.10

-123- 01 00 00 – GENERAL REQUIREMENTS

2. Procedures. The Contractor shall immediately cease all construction activities in the immediate area of the discovery to the extent necessary to protect the cultural resource.

If directed by the City Representative, Contractor will refrain from working in the immediate area, suspend the Wo rk in its entirety, or re-sequence and/or alter its performance to ensure full compliance with all applicable permits, laws and regulations. Should the presence of cultural resources be confirmed, the Contractor will assist the City Representative and the Construction/Archeological Monitor in the preparation and implementation of a data recovery plan. The Contra ctor shall provide such cooperation and assistance as may be necessary to preserve the cultural resources for removal or other disposition. Any City directed changes to the Work as a result of the cultural resource will be pursuant to the Contract Documents.

3. Contractor’s Liability. Should Contractor, without permission, injure, destroy, excavate, appropriate, or remove any cultural resource on or adjacent to the Site, it will be subject to disciplinary action, arrest and penalty under applicable law. The Contractor shall be principally responsible for all costs of mitigation and/or restoration of cultural resources related to the unauthorized actions identified above. Contractor shall be required to pay for unauthorized damage and mitiga tion costs to cultural resources (historical and archeological resources) as a result of unauthorized activities that damage cultural resources and shall indemnify City pursuant to the Contract Documents.

4. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to comply with this paragraph, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

E. Dust and Pollution Control

1. Contractor shall provide all nece ssary material, equipment and labor to prevent and control the emission of dust and any other potential pollutant on site. Contractor shall remove construction caused debris from streets and sidewalks as directed by the Engineer.

2. Contractor shall not discharge in to the atmosphere from any source smoke, dust or other air contaminants in violation of the law, rules, and regulations of the governing agency.

3. Cost. Unless otherwise called for by the Contract Documents, the cost of all material, equipment, and labor required to comply with this paragraph, shall be included in Contractor’s bid and distributed in the Schedule of Pay Items. No additional compensation shall be made to the Contractor for this Work.

F. Management of Storm, Surface and Other Waters





 





Page 268 of 396 ends

38077.00180\29080232.10

-124- 01 00 00 – GENERAL REQUIREMENTS

1. Storm water, surface water, groundwater, and nuisance, or other waters may be encountered at various times du ring construction of the Project.

Federal and State laws require the City and its contractors to manage such waters pursuant to the requirements of California State Water Resources Control Board Order Number 2009-0009-DWQ, the Federal Clean Water Act, and the California Porter Cologne Water Quality Control Act.

Contractor acknowledges that it has investigated the risk arising from such waters in conjunction with the Projec t, has prepared its Bid accordingly, and assumes any and all risks and liabilities arising therefrom.

2. The Contractor shall keep itself and all subcontractors, staff, and employees fully informed of and in compliance with all local, state and federal laws, rules and regulations that may impact, or be implicated by the performance of the Work including, without limitation, all applicable provisions of the City’s ordinances regulating discharges of storm water; the Federal Water Pollution Control Act (33 U.S.C. § 1251 et seq.); the California Porter-Cologne Water Quality Control Act (Water Code § 13000 et seq.); and any and all regulations, policies, or permits issued pursuant to any such authority. These include, but are not limited to the San Francisco Bay Regional Water Quality Control Board Order No. R2-2015- 0049 (NPDES Permit No. CAS 612008), and State Water Resources Control Board Order No. 2010-0014-DWQ, Order No. 2009-0009-DWQ, and Order No. 2012-0006-DWQ, and any amendment or renewal thereof (“Construction General Permit”). Contractor must perform all construction operations in such a manner as to comply, and ensure all subcontractors to comply, with all applicable Federal, State, and local laws, orders, and regulations concerning the control and abatement of water pollution; and all terms and conditions of any applicable permits issued for the Project. In the event there is a conflict between Federal, State, and local laws, regulations, and requirements, the most stringent shall apply.

3. Compliance with Construction Gene ral Permit. Contractor must comply with all aspects of the Construction General Permit, State Water Resources Control Board (State Board) Water Quality Order No. 2009-0009-DWQ, as amended by Order Nos. 2010-0014-DWQ and 2012-0006-DWQ, and any amendment or renewal thereof (NPDES CAS000002), for all projects that involve construction on or disturbance of one acre or more of land or which are part of a larger common plan of development or sale. (a) Permit registration. Unless otherwise specified in the Special Conditions, Contractor must prepare the Notice of Intet for coverage under the Construction General Permit and all Permit Registration Documents (PRDs), including but not limited to the Storm Water Pollution Prevention Plan (SWPPP), as those terms are defined in the Construction General Permit. Contractor must coordinate submittal of all PRDs with th eCity’s Legally Responsible Person and/or Authorized Signatory, as those terms are defined in the Construction General Permit. The Contractor must submit the PRDs, including the SWPPP to the City Representative for review not less than fifteen (15) Days prior to the start of on- site 




 





Page 269 of 396 ends

38077.00180\29080232.10

-125- 01 00 00 – GENERAL REQUIREMENTS

construction work. City will file the Notice of Intent and PRDs and pay the filing fee.
(b) Before any Construction General Permit related documents may be submitted to the State Board or implemented on the Project site, they must first be reviewed and accepted by City. Acceptance by the City does not relieve the Contractor from ensuring such documents comply with all lawsapplicable laws, regulations, and orders.
(c) Contractor must ensure that the SWPPP is developed by a Qualified SWPPP Developer and implemented by a Qualified SWPPP Practitioner as those terms are defined in the Permit.

Contractor must implement the SWPPP and all other provisions of the Construction General Permit , including the monitoring and reporting requirements, preparing and submitting all reports, plans, inspections, and monitoring info rmation in compliance with the Construction General Permit. The SWPPP must include industry standard requirements for water quality control including but not be limited to the following:
(1) Sediment and erosion control measures to manage
sediment and erosion including vegetative practices,
structural control, silt fences, straw dikes, sediment controls or operator controls as appropriate.Storm water
management measures shall be instituted as required,
including velocity dissipaters, and solid waste controls shall address controls for building materials and offsite tracking of sediment.
(2) Wastewater and storm water management controls to divert offsite surface flows around the Project site and to divert surface flows within the Project area away from areas of open earth or stockpiles of building and other materials.

Wastewater from general construction activities, such as drain water collection, aggregate processing, concrete
batching, drilling, grouting, or other construction operations, shall not enter flowing or dry watercourses without having met the authorized non-storm water discharge requirements listed in State Board Water Quality Order No. 2009-0009- DWQ, Section III.C., including proper notification to the Regional Water Board.
(3) Pollution prevention measures including methods of
dewatering, unwatering, excavating, or stockpiling earth and rock materials which include prevention measures to control silting and erosion, and which will intercept and settle any runoff of sediment-laden waters.
(4) Turbidity prevention measur es for prevention of excess turbidity including, but are not restricted to, intercepting 




 





Page 270 of 396 ends

38077.00180\29080232.10

-126- 01 00 00 – GENERAL REQUIREMENTS

ditches, settling ponds, gravel filter entrapment dikes, flocculating processes, recirculation, combinations thereof, or other approved methods that are not harmful to aquatic life. All such wastewaters discharged into surface waters, shall contain the least concentration of settleable material possible, and shall meet all conditions of section 402, the National Pollutant Discharge Elimination System (NPDES) permit.
(5) Overall construction site ma nagement measures to address changes at the Project site as the Project moves through different phases and changes that account for rainy and dry season management practices.
(6) Pollution control measures and construction activity methods that will prevent entrance, or accidental spillage, of solid matter, contaminants, debris, or other pollutants or wastes, into streams, flowing or dry watercourses, lakes, wetlands, reservoirs, or underground water sources. Such pollutants and wastes include, but are not restricted to:
refuse, garbage, cement, sanitary waste, industrial waste, hazardous materials, radioactive substances, oil and other petroleum products, aggregate processing, tailings, mineral salts, and thermal pollution.
(7) Control measures for stockpiled or deposited materials prohibiting the stockpile or de posit of excavated materials, or other construction materials, near or on stream banks, lake shorelines, or other watercourse perimeters where they can be washed away by high water or storm runoff, or can, in any way, encroach upon the watercourse.
(8) Develop and implement a Ra in Event Action Plan (REAP), if required, that must be designed and implemented to
protect all exposed portions of the site 48 hours prior to any likely precipitation event.
(9) Monitoring, reporting and record keeping, as necessary to achieve compliance with applicable Permit requirements, including but not limited to annual reports and rain event reports.
(d) City retains the right to procur e and maintain coverage under the Construction General Permit for the Project site if the Contractor fails to draft a SWPPP or other Construction General Permit related document, or fails to proceed in a manner that is satisfactory to City.

City reserves the right to implement its own SWPPP at the Project site, and hire additi onal contractors to maintain compliance.

Whether Contractor has adequately maintained compliance with the Construction General Permit shall be City’s sole determination.

In the event that Contractor has failed or is unable to maintain 




 





Page 271 of 396 ends

38077.00180\29080232.10

-127- 01 00 00 – GENERAL REQUIREMENTS

compliance with the Construction General Permit, any costs or fines incurred by City in implementing a SWPPP, or otherwise
maintaining compliance with the Construction General Permit shall be paid by the Contractor.

4. For those Work sites where construction activity results in the disturbance of less than one acre of total land area and/or do not need coverage under the Construction General Permit, the Contractor shall be responsible for preparing and implementing construction industry best management practices to eliminate or reduce the discharge of pollutants from construction sites, such as the best management practices set forth in the CASQA Construction BMP Handbook.

5. In addition to compliance with the Pe rmit, Contractor shall comply with the lawful requirements of any applicab le municipality, district, drainage district, flood control district, and other local agencies regarding discharges of storm water, surface water, groundwater or other nuisance waters off of the Project site.

6. Contractor violations.
(a) Failure to implement the SWPPP or otherwise comply with the Construction General Permit or local state and federal laws is a violation of this Contract. Notwithstanding any other indemnity contained in this Agreement, Contractor agrees to indemnify, defend – with counsel acceptable to the City – and hold harmless the City, its officials, officers, agents, employees and authorized volunteers from and against any and all claims, demands, losses or liabilities of any kind or nature wh ich the City, its officials, officers, agents, employees and authorized volunteers may sustain or incur for noncompliance with the laws, regulations, and ordinances listed above, arising out of or in connection with the Work, except for liability resulting from the sole established negligence, willful misconduct or active negligence of the City, its officials, officers, agents, employees or authorized volunteers.
(b) City reserves the right to defend any enforcement action or civil action brought against the City for Contractor’s failure to comply with any applicable water quality law, regulation, or policy.

Contractor hereby agrees to be bound by, and to reimburse the City for the costs associated with, any enforcement action and/or settlement reached between the City and any relevant enforcement entity.
(c) City may seek damages from Contractor for delay in completing the Contract in accordance with the Contract Documents, caused by Contractor’s failure to comply with the the laws, regulations and policies described in this Article, or any other relevant water quality law, regulation, order, or policy.





 





Page 272 of 396 ends

38077.00180\29080232.10

-128- 01 00 00 – GENERAL REQUIREMENTS

(d) If noncompliance with any relevant law, regulation or permit, order, or policy occurs, the Contractor shall report this to the City Representative immediately, with the specific information submitted in writing within 2 Days. Consistent violations of applicable Federal, State, or local laws, orders, regulations, or Water Quality Standards may result in City stopping all site activity until compliance is ensured. The Contractor shall not be entitled to any change in Contract Price or Contract Times, claim for damage, or additional compensation by reason of such a work stoppage. Corrective measures required to bring activities into compliance shall be at the Contractor's expense.

7. Oil storage tanks management.
(a) Storage tank placement. All oil or other petroleum product (hereinafter referred to collectively as oil) storage tanks shall be placed at least 20 feet from streams, flowing or dry watercourses, lakes, wetlands, reservoirs, and any other water source. (b) Storage area dikes. Storage areas shall be diked at least 12 inches high or graded and sloped to permit safe containment of leaks and spills equal to the capacity of all tanks and/or containers located within each area, plus a sufficient amount of freeboard to contain the 25-year rainstorm.
(c) Diked area barriers. Diked areas shall have an impermeable barrier at least 10 mils thick. Areas used for refueling operations shall have an impermeable liner at least 10 mils thick buried under 2 to 4 inches of soil.
(d) Spill Prevention Control and Countermeasure Plan (SPCC). Where the location of a construction site is such that oil from an accidental spillage could reasonably be expected to enter into or upon the navigable waters of the United St ates or adjoining shorelines, and the aggregate storage of oil at the site is over 1,320 gallons or a single container has a capacity in excess of 660 gallons, the Contractor shall prepare an SPCC Plan. The Contractor shall submit the SPCC Plan to the Engineer at least 30 days prior to delivery or storage of oil at the site. The Plan must have been reviewed and certified by a registered professional engineer in accordance with 40 C.F.R., part 112

8. Underground tank prohibition. The Contractor shall not use underground storage tanks.

9. Construction safety standards. The Contractor shall comply with the sanitation and potable water requirements of Section 7 of United States Bureau of Reclamation's publication “Reclamation Safety And Health Standards.”

10. Other Permits.





 





Page 273 of 396 ends

38077.00180\29080232.10

-129- 01 00 00 – GENERAL REQUIREMENTS

(a) Other permits applicable to the Project are listed in the Special Conditions. The Contractor shall obtain all other necessary licenses and permits.
(b) Monitoring. The Contractor is required to conduct monitoring in order to meet the requirements of the permits, which may include sampling, testing and inspections.
(c) Recordkeeping. The Contractor shall retain all records and data required by the permits for the time specified in the contract.

11. Cost. Except as specified herein, the cost of complying with this section shall be included in the Schedule of Pay Items for work which necessitate the water pollution prevention measures required by this paragraph.

END OF GENERAL REQUIREMENTS






 





Page 274 of 396 ends

38077.00180\29080232.10

-130- 01 20 00 – MEASUREMENT AND PAYMENT

01 20 00 – MEASUREMENT AND PAYMENT

11. Payment

11.1 Payment shall be per unit specified and shall be considered full compensation for furnishing all materials, equipment, labor, safety, traffic controls, cleanup and all work incidental thereto.

Bid Item 1 – Administration of Diversion of Waste Recyclable Materials. This work includes completion of a construction and demolition (C&D) Debris Management Plan using the City's Green Halo on-line application and providing weigh tickets listing the descriptions and quantities of all materials recycled to the City Project Manager. Actual removal and recycling of materials is to be included in the payment of bid items 2, 3, 4, 5. 6A, 6B, 6C and 8.

Bid item 2 (Remove and Replace 4” Sidewalk)
Bid Item 3 (Remove and Replace 6” Driveway Approach)
Bid Item 4 (Remove and Replace Curb and Gutter),
The contract price paid per Square Foot for “Remove and Replace 4“ Sidewalk ”, shall include full compensation for furnishing all traffic control, mobilization, labor, materials, tools, equipment, and incidentals, and for doing all the work to removing and installing concrete flatwork to the nearest joint, complete in place, including furnishing and placement of Class 2 aggregate base and concrete, furnishing, placement, and removal of forming, sawcutting and removal of sawcut material, doweling into existing curb or sidewalk, excavation, subgrade preparation, hauling and disposal of all unsuitable aggregate base, asphalt concrete, concrete and material, compaction of aggregate base and subgrade, weakened plane joints and score lines, tree root removal and protection, coordination with the private property owner, compaction, aggregate base, and concrete, existing surfaces restoration, tree root inspection, protection and removal, as shown on the latest City of Milpitas Standard Drawings, as specified in the State Standard Specifications, and these Technical Provisions, and as directed by Project Manager and no additional compensation shall be allowed therefor. Contractor is advised to closely review City of Milpitas Standard Details provided in Exhibit C.

Bid Item 5 –Removal of Park Strip Improvements: This work includes traffic control, mobilization, breaking up, loading, hauling and disposing of portland cement concrete, asphalt, brick or other materials. The contract price paid per Square Foot for “Removal of Park Strip Improvements”, shall include full compensation for furnishing all traffic control, mobilization, labor, materials, tools, equipment, and incidentals, and for doing all the work to removing and installing concrete, asphalt, brick or other materials in areas such as park strips where new portland cement concrete is not to be installed. This work shall also include saw cutting and removal of sawcut material, tree root removal and protection, coordination with the private property owner, compaction, aggregate base, and concrete, existing surfaces restoration, tree root inspection, protection and backfilling and smoothing out topsoil to a plane even with top-of- curb and top- of-sidewalk and as directed by Project Manager and no additional compensation shall be allowed therefor.

Bid Item 6A – 6C - Depressed Curb Ramps: This work occurs at various locations per 




 





Page 275 of 396 ends

38077.00180\29080232.10

-131- 01 20 00 – MEASUREMENT AND PAYMENT

Caltrans Standard Detail A88A provided in Exhibit C and in conformance with ADA requirements and shall include full compensation for furnishing all traffic control, mobilization, labor, materials, tools, equipment, and incidentals, and for doing all the work to removing and installing curb ramp, curb and gutter, sidewalk and base, encompassing 4’ minimum of sidewalk, curb and gutter and base on each side of the new ramp up to the nearest score line or weakened plane joint or as shown on the plans, whichever is furthest, complete in place, including furnishing and placement of Class 2 aggregate base, curb and gutter, curb ramp, sidewalk and detectable warning surface, furnishing, placement, and removal of forming, sawcutting and removal of sawcut material, doweling into existing curb or sidewalk, excavation, subgrade preparation, hauling and disposal of all unsuitable aggregate base, asphalt concrete, concrete and material, compaction of aggregate base and subgrade, weakened plane joints and score lines, tree root removal and protection, coordination with the private property owner, compaction and compressive testing of subgrade, aggregate base, and concrete, existing surfaces restoration, tree root inspection, protection and removal, as shown on the Contract Drawings, the latest City of Milpitas Standard Drawings, as specified in the State Standard Specifications, and these Technical Provisions, and as directed by the Engineer and no additional compensation shall be allowed.

The City Project Manager shall determine the type of ramp to be installed at each location.

Work shall include all improvements within ramp boarders (including adjacent curb & gutter) as shown on detail A88A, assuming planter width ranging 4.5' to 5.0'. Payment shall be on per each basis. Depressed curb ramps shall be poured monolithically with adjacent curb and gutter, retaining curbs, etc. Hardscape in planter strip adjacent to curb ramps shall be removed to limits specified by City Project Manager prior to installation of ramp, and shall be paid per bid item 5.

The detectable warning surface shall typically be dark gray, however the detectable warning service shall be federal yellow within 600’ from a school building or school grounds, or along established Safe Routes to Schools.

Bid Item 7 - Root Barriers: Payment shall be made per linear foot of root barrier installation.

Payment shall include traffic control, mobilization, excavating the required trench, and the furnishing of all labor, materials, tools, and equipment required to root prune, apply dressing, and install root barrier complete and in place.

Bid Item 8 - Asphalt Replacement: Payment shall be measured and paid per the theoretical weight, measured in tons. The contract price paid per Ton for “Asphalt Replacement” shall include full compensation for furnishing all mobilization, traffic control, labor, materials, tools, equipment and incidentals and for doing all the work involved in furnishing and placing hot mix asphalt, complete in place, including sawcutting, compaction, spreading, overexcavation, removal of spoils, protect all existing utility covers, crack sealing, tack coat, paint binder as specified in the Contract Documents, State Standard Specifications and these Technical Provisions and as directed by the Project Manager and no additional compensation shall be allowed therefor.

The theoretical weight will be calculated based upon the individual asphalt replacement areas marked by the City, multiplied by the depth, multiplied by the weight of asphalt in lb/cubic feet (assume 148 lbs/cubic foot), all divided by 2000. Any and all removal and replacement done outside of the areas marked by the City or to depths greater than the required 6 inches will not be included in the quantity calculation.






 





Page 276 of 396 ends

38077.00180\29080232.10

-132- 01 20 00 – MEASUREMENT AND PAYMENT

Contractor is required to coordinate construction City Project Manager a minimum of 48 hours in advance.

Payment shall be made for only those items shown on the bid schedule. Any item of work that is not shown on bid schedule, but is required by these specifications shall be considered as incidental and full compensation for same shall be made as considered included in the payment for the bid items.

In general, contract prices and payments for all bid items shall include, but not be limited to, full compensation for all necessary materials, labor, tools, equipment, traffic control, and incidentals to do all the work involved, complete and in place, as shown on the plans, as specified in the specifications and as directed by the City Project Manager.

No adjustment in the contract prices for Bid Item 1 – Administration of Diversion of Waste Recyclable Materials, Bid item 2 (Remove and Replace 4” Sidewalk), Bid Item 3 (Remove and Replace 6” Driveway Approach), Bid Item 4 (Remove and Replace Curb and Gutter), Bid Item 5 - Removal of Park Strip Improvements, Bid Item 6A – 6C - Depressed Curb Ramps, Bid Item 7 - Root Barriers or Bid Item 8 - Asphalt Replacement shall be made for increases or decreases of more than 25 percent of the quantities.

END OF MEASUREMENT AND PAYMENT SECTION






 





Page 277 of 396 ends

38077.00180\29080232.10

-133- 01 31 00 – NOTICE TO PROCEED

01 31 00 – NOTICE TO PROCEED

The Contractor shall accomplish the followin g items prior to being issued a Notice to Proceed:

1. Attend City Pre-Construction Meeting with the Project Manager. Attendees shall include the Contractor, Contractor's Superintendent, and all Subcontractors.

2. Obtain favorable City review of Contract or’s Construction Base-Line Schedule, which shall be completed in accordance with the requirements of the Contract Documents.

3. Obtain favorable City review of Contractor’s Water Pollution Control Plan, and/or De- Water Operations Plan (if applicable) which shall be completed in accordance with these Contract Documents.

4. Obtain favorable City review of Contractor’s Traffic Control/Staging Plan completed in accordance with these Contract Documents.

5. Obtain favorable City review of Contractor’s Construction Sequence/Work Plan completed in accordance with these Contract Documents.

Upon completion of these items, and any other requirements as may be specified elsewhere in these Contract Documents, the Engineer will issue a Notice to Proceed to the Contractor. This Notice will establish the first chargeable day of the Contract. However, the City shall start charging contract days 21 calendar days following the date of the Contractor’s receipt of the Notice of Award letter, regardless of the Contractor's progress in completing all the items specified above and/or elsewhere within the Contract Documents. The Contractor shall notify the Project Manager of its intent to begin work at least 24-hours prior to beginning work by calling (408) 586-2634. Once work begins , notification must be made only if work is delayed or suspended.

END OF NOTICE TO PROCEED






 





Page 278 of 396 ends

38077.00180\29080232.10

-134- 01 33 00 – LIST OF SUBMITTALS

01 33 00 – LIST OF SUBMITTALS

Refer to the General Conditions, Technical Provisions, and elsewhere within the Contract Documents regarding the Submittal requirements and required Submittals for this Work. The list of submittals shall include, but is not limited to the following:

Item Description Time for City Review
(Working Days)

1. Project Schedule 5

2. USA Tag & Number 2

3. Traffic Control Plan 5

4. Hot Mix Asphalt Mix Design 2

5. Concrete Mix Design 2

6. Detectable Warning Surface 2

7. Class 2 Aggregate Base 2

8. Root Barrier 2
.

END OF LIST OF SUBMITTALS






 





Page 279 of 396 ends

38077.00180\29080232.10

-135- 02 00 00 – TECHNICAL PROVISIONS

02 00 00 – TECHNICAL PROVISIONS

1. Materials

1.1 PORTLAND CEMENT CONCRETE:

Portland Cement Concrete shall be Class A concrete have one (1") inch maximum combined aggregate grading, conforming to Section 90-

1.02C(4)(d) of the Standard Specifications. Concrete shall contain not less than six (6) sacks (564 pounds) of cementitious material per cubic yard.

1.2 PORTLAND CEMENT:

All cement used shall be of one brand and shall conform to A.S.T.M. C150 Type II Supplementary Cementitious Materials shall conform to Section 90-

1.02B(3). Results of certified tests made by recognized testing laboratory shall be furnished by the cement manufacturer on request of the Project Manager.

1.3 AGGREGATES:

Aggregates for portland cement concrete shall conform to Section 90-2.02C of the State of California, Department of Transportation, Standard Specifications 2022.

Combined aggregate grading shall conform to the one (1") inch maximum requirements of Section 90-1.02C(4)(d) of the State of California, Department of Transportation, Standard Specifications latest edition.

1.4 WATER:

Water for washing aggregates and for mi xing portland cement concrete shall conform to Section 90-1.02D of the State of California, Department of Transportation, Standard Specifications latest edition.

1.5 ADMIXTURES:

No admixtures, accelerators, or retarders shall be allowed without the express approval of the Project Manager.

1.6 EXPANSION JOINTS:

Expansion joints shall consist of prepar ed strips of three-eighths (3/8") inch thick premolded joint filler conforming to the specifications of A.S.T.M.

Designation: D-1751.

1.7 CURING:

All portland cement concrete surfac es shall be cured using a portland cement concrete curing compound No. 4 or 5 meeting the requirements of State of California, Department of Transportation, Standard Specifications Section 90- 1.03B(3)(b) of the latest edition of the State of California Standard Specifications.

1.8 HOT MIX ASPHALT (HMA) REPLACEMENT:

This work shall conform to Section 39, HOT MIX ASPHALT, Section 92, ASPHALTS, and Section 94, ASPHALTIC EMULSIONS of the State of California, Department of 




 





Page 280 of 396 ends

38077.00180\29080232.10

-136- 02 00 00 – TECHNICAL PROVISIONS

Transportation, Standard Specifications latest edition, with the exceptions noted in these Provisions. The HMA shall be ½" Type A with PG 64-10,

Asphalt Materials:
x Aggregate Grading - Hot mix asphalt (HMA ) shall be produced at a central mixing plant. Aggregate for the final lift or top lift shall be a ½ inch maximum, specified in Section 39-1.02E, "Aggregate," of the State Standard Specifications. For intermediate courses, aggregate shall conform to the ¾ inch maximum.

x Asphalt Binder - Asphalt Bi nder to be mixed with the aggregate shall conform to the provisions of Section 92, “Asphalts”, of the State Standard Specifications and shall be paving asphalt Performance Grade PG 64-10 in conformance to Section 92-1.02(B) of the State Standard Specifications, unless otherwise directed by the Engineer.

3. Paint Binder (Tack Coat) - Liquid emulsion SS-1 shall be in conformance with Section 94, “Asphaltic Emulsions”, of the State Standard Specifications. No fog seal will be required.

The work shall include sawcutting and/or grinding of asphalt, removal of asphalt and affected subgrade and replacement of asphalt as specified in these Provisions and as directed by the City Project Manager.

1.9 CERTIFICATES OF COMPLIANCE:

Contractor shall furnish to the City Project Manager a Certificate of Compliance signed by the manufacturer of the plant mix portland cement concrete and Hot Mix Asphalt.

Certificate of Compliance shall state that the portland cement concrete and asphaltic cement concrete furnished complies in all respects with the requirements of the specifications. A Certificate of Compliance shall be furnished with each lot of material delivered to the work and the lot so certified shall be clearly identified in the Certificate.

2. Traffic Control and Pedestrian Safety

2.1 The Contractor shall provide traffic control in the form of placing warning signs, markers and devices in accordance with the California MUTCD (latest edition) and as required by the C i t y Project Manager. When necessary to provide for public safety or convenience, either for vehicles, pedestrians or bicyclist, the Contractor shall provide flaggers as necessary. Duri ng non-work hours, the Contractor shall post signs and warning devices to safely direct pedestrians and bicyclist around the work are. See Traffic Control Specifications for additional requirements.

2.2 Contractor shall not unnecessarily interfere with use of any roadway, walkway or other facility for vehicular or pedestrian traffic. Before beginning any interference and only with City's prior concurrence, Contractor may provide detour or temporary bridge for traffic to pass around or over the interference, which Contractor shall maintain in satisfactory condition as long as interference continues. Unless otherwise provided in the Contract Documents, Contractor shall bear the cost of these temporary facilities.

3. Construction Methods

3.1 SUBGRADE PREPARATION (Portland Cement Concrete & Asphaltic Concrete):

The existing material shall be excavated to the required depth per the City of Milpitas 




 





Page 281 of 396 ends

38077.00180\29080232.10

-137- 02 00 00 – TECHNICAL PROVISIONS

Standard Details or Caltrans Standard Plans as provided in Exhibit C, as is applicable.

The finished subgrade immediately prior to placing subsequent material thereon shall have a relative compaction of ninety (90%) percent for a depth of 0.5 foot as determined by State of California Test Me thod No.216. The subgrade shall be smooth and true to the required grade. Immediately prior to the placing of cushion for portland cement concrete, the subgrade shall be thoroughly saturated with water. Ponded water shall not be permitted.

3.2 CUSHION:

The base material underlying existing sidewalk, curb and gutter or other portland cement concrete improvements is considered acceptable for this work. The Contractor will be required to bring the material to the proper grade and to consolidate by watering. The City Project Manager will determine when the required moisture content has been obtained. If additional cushion material is required due to grade changes, base material uncontaminated by native soil from other locations or ¾" Class 2 aggregate base may be used.

3.3 FORMS:

Forms shall be smooth on the side placed next to the portland cement concrete, and shall have a true smooth upper edge and shall be sufficiently rigid to withstand the pressure and tamping of fresh portland cement concrete without distortion. Timber forms shall be free from warping of deformation.

All forms shall be thoroughly cleaned and coated with form oil to prevent the portland cement concrete from adhering to them.

The depth of forms for back of curbs shall be equal to the full depth of the curb. The depth of face forms for portland cement concrete curbs shall be equal to the full face height of the curb. The gap between the bottom of the form and the subgrade shall not exceed 1 inch. Forms shall be set carefully to alignment and grade and shall be held rigidly in place by stakes, spreaders, or clamps, and shall be braced so that no displacement will occur during the working of the portland cement concrete. For other than short radius curves, timber forms shall be nominal two (2") inch stock.

All concrete placement shall be confined and no neat (earth confined) placement shall be allowed. When allowed by the City Project Manager, concrete may be placed neatly against asphaltic concrete.

3.4 PLACEMENT:

All portland cement concrete shall be used while fresh and before it has taken an initial set. Retempering any partially hardened portland cement concrete with additional water shall not be permitted.

Where pavement or surfacing is to be placed around or adjacent to manholes, drop inlets, or catch basins, which will be located within traffic lanes, such structures shall not be constructed to final grade until after the pavement or surfacing has been placed around these locations.

Portland cement concrete shall be poured co ntinuously between joints and brought to the required section as the work progresses.






 





Page 282 of 396 ends

38077.00180\29080232.10

-138- 02 00 00 – TECHNICAL PROVISIONS

3.5 JOINTS (CURB AND GUTTER):

Expansion joints shall be installed at each side of structures and at the ends of curb returns. Weakened plane joints shall be constructed at ten (10') foot maximum intervals.

Weakened plane joints shall be cut to a minimum depth of one and one-fourth (1-1/4") inch with a tool that leaves corners rounded and insures a free movement of the portland cement concrete at the joint. The joint shall have a minimum width of one-eighth (1/8th) inch and shall not exceed one-fourth (1/4") inch.

3.6 JOINTS (SIDEWALK):

Expansion joints shall be constructed at all returns and opposite expansion joints in adjacent curb. Where curb is not adjacent, expansion joints shall be constructed at intervals of sixty (60') foot maximum intervals and opposite weakened plane joints in adjacent curb. Joints shall be constructed at right angle to the line of curb and to the same depth and width as for curb and gutter.

Score lines shall be constructed at five (5') foot intervals at right angle to the line of curb.

For sidewalk eight (8') feet or over in width, a score line parallel to the line of curb shall be constructed midway between back of curb and back of walk.

Score line shall be made with a scoring to ol which will make a rounded line of uniform width and depth of one-fourth (1/4") inch. A score line parallel to the face of curb shall be constructed six (6") inches from the face of the curb.

3.7 TOLERANCE:

The top and face of the curb and gutter, the flowline of the curb and gutter, and the surface of the sidewalk shall not vary more than one-fourth (1/4") inch for the edge of an eight (8') foot straight edge when placed against the surface, except at grade changes or curves.

3.8 FINISH:

Fresh portland cement concrete shall be st ruck off and compacted until a layer of mortar has been brought to the surface. The surf ace shall be finished to grade and cross section with a float, troweled smooth, and finished with a broom. The finish and texture of the portland cement concrete shall be approved by the Project Manager. Portland cement concrete adjacent to expansion joints shall be finished with an edger tool.

Brooming shall be transverse to the line of traffic.

3.9 HMA PLACEMENT:

All asphalt replacement area fi nish surfaces must be smooth, uniform and match existing grades. Application of asphalt and asphaltic emulsion must be neat, with surrounding areas kept clean. Asphalt replacement thickness shall be 6 inches. W h e n a n asphalt concrete plug is needed, it shall be a minimum of 12” wide from the new concrete. T h e H M A s h a ll be placed in two lifts with the top lift no less than 1-3/4 inches thick. Any broken edges of existing pavement shall be sawcut immediately prior to paving. Tack coat shall be placed on the vertical edges of both the existing HMA and concrete prior to the base course paving and again prior to the paving of the surface course.

4. Tree Roots & Tree Damage

4.1 Contractor shall notify the City Project Ma nager of any roots discovered which are larger 




 





Page 283 of 396 ends

38077.00180\29080232.10

-139- 02 00 00 – TECHNICAL PROVISIONS

than two inches in diameter. No root larger than 2 inches in diameter shall be removed without expressed permission from the City Project Manager. Where work occurs adjacent to or over tree roots, the roots shall be removed to a minimum depth of six inches (6") below the bottom or side of the new portland cement concrete. Root removal shall be achieved by mechanical root pruning, supersonic air tool root pruning, or approved equal. Cuts on tree roots and barks or skins or cuts on trees shall be treated with an acceptable sealer and growth inhibitor such as Tre-hold.

Excavation in an area where roots are present shall not cause the tearing or ripping of tree roots. Roots must first be cleanly severed prior to continuing with the excavation or tunneled around to prevent damage to the root. Tree roots shall not remain exposed to drying out. Root ends shall be covered with soil or burlap and kept moist until the final backfill or grade is established.

The following guidelines shall be followed whenever tree roots with a diameter of two inches or greater are encountered during the Contractor’s trenching or grading activities:

1. Trenches shall be hand dug within a tree canopy zone to avoid damage to the tree roots.

2. Upon uncovering, immediately cover the root with a board or burlap and keep it moist.

3. Backfill the exposed root area with soil as soon as the work has been completed.

4. If the tree becomes damaged, cut the damaged root clean with a saw and immediately wrap the root end with plastic secured with tape.

Payment for this work shall be considered as included in the price for removal and replacement.

5. Root Barrier

5.1 Linear root barriers shall be used when concre te hardscape is placed within six feet (6') of any tree in any direction. Eighteen-inch root barriers shall be used when tree is located adjacent to new curb and gutter. All root barriers shall be made of high density, high impact plastic, shall have a minimum thickness of 0.085" and shall be installed according t o m a n u f a c t u r e r ' s s p e c i f i c a t i o n s . Per Standard Detail No. 448 (refer to Exhibit C), root barrier is to be “Biobarrier” root barrier by R e e m a y o r e q u i v a l e n t . The length of the root barrier shall extend five times the diameter of the tree trunk each direction measured from the centerline of the tree's trunk or, entire length of repair, whichever is less. Contractor is required to provide a product submittal for the City to review.

6. Removal of Park Strip Improvements

6.1 At various locations it will be necessary to remove existing concrete improvements made by property owners in the public right of way. If such removals are necessary, the limit of removal shall be sawcut to full depth of the existing concrete. After removal and construction of the new concrete facilities, the remaining area shall be backfilled with topsoil approved by the City Project Manager.

7. Existing Improvements





 





Page 284 of 396 ends

38077.00180\29080232.10

-140- 02 00 00 – TECHNICAL PROVISIONS

7.1 Prior to any underground e xcavation, the Contractor shall contact Underground Services Alert (USA) 811 a minimum of 48 hours prior to the beginning of each excavation.

The Contractor shall notify USA at 1-800-227-2600 to locate and mark existing subsurface utilities within the Contractor’s project site. The Contractor shall also be responsible for contacting private utility companies for the review of their as-built records for their underground utilities.

The Contractor shall have the responsibility to contact directly all agencies that do not participate in USA program to arrange for the location and mark-out of their utilities. The California Department of Transportation (Caltrans) is an example of such an agency that does not participate in the USA program.

Unmarked Utilities: As required by law, should the Contractor find utilities during excavation that were unmarked by the USA locate process, that Contractor shall immediately notify Underground Services Alert (USA) 811 of the find and request they respond.

The following utilities have facilit ies within the limits of work:

PG&E Gas/Electrical
City of Milpitas Water, Recycled Water, Storm Drain, and Sanitary Sewer lines; Street light, Traffic Signal, and Fiber Optics
AT&T Telephone/Fiber Optics
Verizon Telephone/Fiber Optics
Zayo Telephone/Fiber Optics
Comcast Cable TV/ Fiber Optics
Air Products Nitrogen Gas
Protection and repair of damage of laterals and appurtenances shall be the responsibility of the Contractor.

In the event that water services, fire hydrants, storm drain pipes, city fiber optics, or other appurtenances are broken or damaged, the Contractor shall immediately notify the Engineer.

The Contractor shall be required to repair, at their own expense, such damage in a manner satisfactory to the Engineer, or City forces may repair such damage at the Contractor's expense.

In the event damage is done to any gas, electric, cable TV, fiber optics, or telephone facility by the Contractor, the Contractor shall immediately notify the respective utility company. The utility company at the Contractor’s expense shall make repairs.

7.2 Where irrigation systems , landscaping, fences, mailboxes, signs, and other improvements exist adjacent to the work, the Contractor shall use reasonable caution to 




 





Page 285 of 396 ends

38077.00180\29080232.10

-141- 02 00 00 – TECHNICAL PROVISIONS

ensure that no damage is caused. If damage to these improvements does occur, the Contractor shall replace in kind or with an acceptable substitute, at his expense.

When repairs to sidewalks and driveways adjacent to property line occur, there may be instances where on-site flat work (driveways and walkways) on private property will:

1. Interfere with the repair of existing public improvements.

2. Be incompatible with the new sidewalk, curb and gutter grades.

3. Be out of repair to the extent that th e hardscape is hazardous to pedestrian traffic.

4. Present a restriction to the street tree's natural growing space.

In these situations, it may become necessary for the City's Contractor to remove and replace portions of the on-site flat work. The costs for the removal and replacement of private portland cement concrete improvements will be paid at contract unit prices. The costs for removal and replacement of private improvements other than portland cement concrete and/or asphalt will be negotiated on a case-by-case basis with the City Project Manager. On-site removal and replacement will be only as directed by the City Project Manager, and no extension of quantities will be allowed without prior approval.

8. Cleanup and Backfilling

8.1 The construction area shall be kept neat and safe. Forms shall be removed from the edge of portland cement concrete within two (2) days and be kept in neat piles, not scattered about, and nails in boards shall be turned under, bent over, or removed.

Removed nails shall be cleaned up and removed from site.

After forms are removed, portland cement concrete edges shall be backfilled and raked smooth with clean and suitable topsoil. Said topsoil material shall also be used to backfill and bring to an acceptable grade area where portland cement concrete or other paving material is removed but not replaced.

The Contractor shall clean all areas occupied by him/her in connection with the work, and the entire area shall be left in a neat, clean and presentable condition, within seven days of completion. All asphalt replacement shall be completed, brought to finish grade with asphaltic concrete within thirty (30) calendar days of removal.

Upon removal of forms, all edges of concrete are to be backfilled. When the edge is lip of gutter, backfill material will be compacted class II aggregate base or asphalt concrete.

Any residue left from said cutting operations shall be cleaned and removed per the nonpoint source pollution control best management practices. All cleanup shall be performed as required by the City Project Manager.

City streets within the project site, including those of the Contractor’s truck haul route shall be swept daily and immediately following all operations.

9. Work Areas





 





Page 286 of 396 ends

38077.00180\29080232.10

-142- 02 00 00 – TECHNICAL PROVISIONS

9.1 The City Project Manager, whenever possible, will arrange the work so that all of the work required to be done in a section of the City will be scheduled continuously. Work identified with a location to be determined may or may not be arranged to be completed with other work.

The majority of work items will occur on various residential streets throughout the City with parking on either side of the street and a 25 miles per hour speed limit. All other work will occur on arterial / collector streets. These streets include, but are not limited to:

x Jacklin Road
x N. Milpitas Blvd
x N. Able Street
x Dixon Road
x Escuela Parkway

9.2 The Contractor shall conduct operations and schedule cleanup to cause the least possible obstruction and inconvenience to traffic, pedestrians, cyclists and adjacent property owners. All work areas shall be swep t clean at the end of each day's work and at other times when directed by the City Project Manager. A mobile street sweeper shall be used wherever practical and dust shall be suppressed to the satisfaction of the City Project Manager.

9.3 The Contractor shall protect open excavati ons, trenches, and such during construction with fences, covers, and railings as required, together with signs, lights, and other warning devices sufficient to maintain safe pedestrian, bicycle and vehicular traffic to the satisfaction of the Project Manager. No open excavations will be allowed over Saturday or Sunday.

9.4 Damage done by the Contractor during the cour se of the work to adjacent City, public or private property shall be repaired in kind, or as directed by the City Project Manager, at the Contractor's expense. This includes the repair of traffic loop detectors, striping, signing, curb markings, etc. Loop detectors must be repaired within one week of the damage.

9.5 The work of restoration, including backfilling, repair of existing systems (irrigation, etc.), transitioning to existing improvements and cleanup, at each location, shall be diligently pursued to completion and no location shall the work be left partially completed for more than seven working days.

9.6 The City Project Manager shall have the ri ght to limit the amount of removed concrete which may be opened or partly opened at any time. No more than 300 feet of removed concrete shall be left open at any one time.

9.7 All excavations must be backfilled or properly delineated for pedestrian / vehicle traffic at the end of each workday.

9.8 Spillage resulting from hauling operations al ong or across any public traveled way shall be removed immediately by the Contractor at his expense.

10. TRAFFIC CONTROL






 





Page 287 of 396 ends

38077.00180\29080232.10

-143- 02 00 00 – TECHNICAL PROVISIONS

10.11 Contractor shall maintain access to all driveways except when actually doing construction within the driveway boundaries, at which time partial access will be maintained unless alternate arrangements can be made with the property owners or tenants in advance. If the driveway to any garage or parking area is to be closed for construction work, prior written approval must be obtained from the property owners and the Project Manager. Notice shall be posted by the Contractor 72 hours in advance stating the approximate time the driveway will be closed and reopened.

10.12 The Contractor shall supply, place, and maintain all necessary traffic control devices during construction in accordance with the applicable requirements of the City of Milpitas, the California Manual of Uniform Traffic Control Devices, and the traffic control plans approved by the City.

10.13 Signs to be used for traffic control shall conform to the requirements of the California Manual of Uniform Traffic Control Devices. Signs that are attached to existing poles shall not cause any damage to the poles when they are attached or removed. All of the hardware that is used when attaching signs to existing poles shall be completely removed from the poles when the signs are removed. If a construction sign is required in an area where it cannot be attached to an existing pole, it shall be attached to a 4" x 4" wooden pole. The distance from the ground su rface to the bottom of the sign shall be seven (7) feet.

10.14 A flag-type high level warning device with three or more flags shall be used for each direction of traffic affected, generally placed within the taper area.

10.15 Flashing arrow boards sha ll be Type A or Type II as described in Section 6F.56 of the California Manual of Uniform Traffic Control Devices. Flashing arrow boards are required for lane shifts and reductions and may be required for nighttime work.

10.16 Dated "No Parking Tow Away" signs shall be posted a minimum of 72 hours in advance of all work requiring that cars not be parked on the street. Date and time of work shall be written on signs in two-inch-high letters with a ¼-inch felt black marker. Signs shall be posted 50 feet on center and removed immediately after the work is completed. The Contractor must notify the City Project Manager with locations of posting to verify seventy-two (72) hour notice.

10.17 Traffic Control Plans. A traffic control plan consistent with the following generally applicable conditions must be approved by the Public Works Department prior to the pre- construction meeting. The Contractor shall submit traffic control plans to the City Project Manager for approval five (5) working days prior to the pre-construction meeting. All cost and expense for traffic control shall be included in the bid prices for various bid items and no special compensation shall be allowed.

x Traffic control plans will include a schedule of construction showing each phase of work and the anticipated method of handling traffic for each phase. Traffic control plans will include a scaled drawing of the street, lane configuration, parking, sidewalk, work area, and the location of signs and cones, etc., to warn, direct, and guide the traffic. For all major intersections, the traffic control plan shall reflect actual (not typical) intersection layout and indicate islands, medians, lane lines, bike lanes, nearby driveways, and note all pavement and lane widths. 




 





Page 288 of 396 ends

38077.00180\29080232.10

-144- 02 00 00 – TECHNICAL PROVISIONS

x In general, Contractor shall maintain all vehicular, pedestrian, and bike movements.

No total closure of any arterial or collector street will be permitted. City may allow closure of local residential streets but Contractor shall always maintain local and emergency access.

x The Contractor shall maintain one lane of traffic in each direction at all times on all streets. The clear width of the lane shall be a minimum of 10 feet.

x A minimum four feet clear sidewalk shall be maintained unless the work makes closure unavoidable, in which case the sidewalk may be closed while working, subject to the approval of the Project Manager. However, an alternate pedestrian facility must be provided for the duration of the closure. At intersections, work will be permitted at one corner at a time so pedestrian movements can be maintained through the intersection.

10.18 Work shall not restrict visibility of any traffic control device.

10.19 The Contractor shall not remove the barricad es in the street at any given location until the asphalt concrete patching adjacent to the gutter has been done and a hazard to bicycles, pedestrians and motorists no longer exists.

10.20 The Contractor shall place barricades 50 feet on center at the gutter joints and provide one working flasher for each barricade and shall insure that each flasher is maintained in working condition while in use. The Contractor shall not remove the barricades in the street at any given location until the asphalt concrete patching adjacent to the gutter has been done and the hazard to bicyclists and motorists no longer exist.

10.21 No work will be permitted within 1500 feet of school grounds until after 9:30 a.m. on school days. Other special restrictions may be required at heavily used school crossings or school commute routes beyond 1500 feet from the school grounds as deemed necessary for student safety by the City Project Manager.

10.22No closure of lanes on arterial and collector streets will be permitted between the hours of 7 and 9 a.m. and 3:30 and 7 p.m.

10.23 If work will impact transit stops or transit routes, Contractor shall be required to contact Santa Clara Valley Transportation Authority or other affected transit companies to address relocation of facilities or rerouting of buses prior to submitting traffic control plan.

Traffic control plan should indicate what actions are being taken with regard to transit services.

10.24 Any work within 150 feet of any signalized intersection should be coordinated with the Traffic Signal Technician (Matt Garcia) at (408) 690-3625.

10.25 All signs and other warning devices shall be provided by the Contractor and shall become his property after completion of the Contract. The cost of providing, installing and maintaining signs, lights, caution tape, delineators, flares, barricades and other facilities as directed by the Project Manager for the convenience and direction of public traffic shall be included in the prices paid for the various items of work involved in the 




 





Page 289 of 396 ends