Land Development
Process

CITY COUNCIL STUDY SESSION
MARCH 10, 2026
Outline
Pre
-
Development
1 7
2 3
4 5
6 Entitlement Process
Building & Construction
Public Works
Business License
Economic Development
Q & A
Site Selection / Zoning Verification
1 Property Owner Rights
2 •
Review and Analysis by Development Review Team (DRT)
⚬
Internal & external depts., divisions, & other agencies i.e., EMWD, SCE, MVU, etc.
•
Comments Issued
3 Pre-Development Process
Pre
-
Application / Preliminary Review

Entitlement Process & Approvals
Formal Application(s) Submittal
1 2
Review and Analysis by Development Review Team
3 4
5 California Environmental Quality Act (CEQA) Compliance Tribal Consultation
Community Outreach
•
Plng
., Bldg., Econ.

Dev’t
., Fire, Land
Dev’t
., Parks, MVU, Special Districts, etc.
•
Other agencies, i.e., EMWD

Entitlement Process & Approvals
Discretionary Approval / Public Hearing
6 7
8 Administrative Approval
Vested Rights
•
Recommendation
•
Findings
•
Conditions of Approval

Building Permitting & Construction

UNSAFE STRUCTURE

UNSAFE ELECTRICAL WIRES
•
Ensure residential, industrial, & commercial building & energy code compliance for both State and local •
Code compliance is necessary to protect life & property investment Building Permitting & Construction
4 5
6 Plan Review
-
Ensure code compliance with both State and Local codes and structural integrity
1 2
3 Contractor Verification
-
Confirm proper licensing / credentials
Permit Issuance
-
Authorize construction to begin
Inspections
-
For code compliance & built to approved plans
Certificate of Occupancy
Stop Work Notice
-
Enforcement actions for violations i.e., work without
permits, deviations from approved plans
Public Works
Land Development
1 2
Transportation
3 4
Construction and Permits
Electric Utility
•
Engineering standards
•
Infrastructure requirements
•
State and federal regulations (i.e., stormwater, floodplains, etc.) •
Traffic study
•
Road configuration
•
Traffic control during construction
•
Inspections
•
Service
•
Infrastructure requirements
Other Agencies
1 •
If not within MVU service area = Southern California Edison 2 Water and Sewer
•
Eastern Municipal Water District
•
Box Springs Mutual Water Company
3 Flood Control
•
Riverside County Flood Control and Conservation District Electricity
Applicant
may
be
required
to
coordinate
with
other
agencies
for
:
4 Other agencies such as:
•
Waste Management
,

RCALUC (ALUC), RCA (MSHCP), LAFCO, WRCOG (TUMF)
Business Licensing
Required for all businesses
1 2
3 Licenses valid Jan. 1
-
Dec. 31
Renewal Required Annually
Prorated for new businesses
Quality of Life
•
Market City’s image
•
Showcase assets and
opportunities
•
Attract talent and investments
Business Attration
•
Regional and Neighborhood Service
⚬
Retail and Service
•
Job Centers
⚬
Business Park
⚬
Corporate Investment
Business Retention
•
Keep successful
exsisting

businesses
•
Assist in expansion efforts
•
Connect with resources
Workforce Development
•
Talent pipeline
•
Hiring events
•
Skills training
•
Career coaching
•
Educational connections
Economic Development
Initiatives

What Affects Development?

•
Exsisting Non
-
Conforming use
•
Dust, noise, pavement condition
impacts at a gateway intersection
•
Visual blight
•
Unsafe air pollution to surrounding
residential neighborhood / medical
offices
Case Study: Robertson’s Ready Mix
•
Robertson’s new batch plant is screened by a 32' façade wall that replicates a tilt -
up building
Case Study: Relocation To Industrial Zone

Case Study: Former Site on Day St.
•
The former Robertson’s site on Day Street was cleared and ready for commercial development •
Aggressive marketing to attract
quality tenants
•
Master planned project was 86%
pre
-
released
•
Hotels
⚬
Residence Inn
⚬
Holiday Inn Express
•
22k sq. ft. retail & restaurants
Case Study: The Quarter – Commercial Project

Case Study: Under Construction

Case Study: End Result

Questions?

THANK YOU