From: SCG SE Region Redlands Utility Request
To: Planning Notices_DG
Cc: SCG SE Region Redlands Utility Request
Subject: 4/29/26- Change of Zone (PEN24-0155), Conditional Use Permit (PEN24-0154) Date: Wednesday, April 29, 2026 9:41:33 AM
Attachments: Change of Zone (PEN24-0155) - Conditional Use Permit (PEN24-0154).pdf Warning: External Email – Watch for Email Red Flags!
Hello,
Regarding: Change of Zone (PEN24-0155), Conditional Use Permit (PEN24-0154) SoCalGas Distribution does have facilities in the area. Please include a note to have the developer contact 811 / USA at DigAlert | Utility Locating California | Underground Wire & Cable Locator prior to any excavation / demolition activities so we can Locate & Mark out our facilities. Any excavation activity within ten (10) feet of our High-Pressure facilities will require a SoCalGas employee standby.
If the Developer needs new gas service, please have them contact our Builder Services group to begin the application process as soon as practicable, at https://www.socalgas.com/for-your-business/builder-services .
To avoid delays in processing requests and notifications, please have all Franchise correspondence sent to our Utility Request inbox.
Utility Request Contact Information by Region
Southeast Region – Redlands
For requests in the southeastern areas of Los Angeles County, Riverside County, San Bernardino County, and Imperial County, please contact:
[email protected]
Southeast Region – Anaheim
For all of Orange County and the southern portions of Los Angeles County, please send Map and/or Will Serve Letter requests to:
AtlasRequests/[email protected]
Northwest Region – Compton HQ
For West and Central Los Angeles County, please direct Map Requests and Will Serve Letters to:
[email protected]
Northwest Region – Chatsworth
For requests from the northernmost parts of Los Angeles County extending up to Visalia, San Luis Obispo, Fresno, and Tulare, please contact:
[email protected] Transmission
For Transmission-related requests, please contact:
[email protected]
New Business
For new gas service, please contact our Builder Services group to begin the application process:
https://www.socalgas.com/for-your-business/builder-services Project Notification Requirements
Minor Street Improvement Projects
(Chip Seal, Slurry Seal, Grind & Overlay)
Please notify SoCalGas (SCG) a minimum of four (4) months prior to the start of pavement work to allow sufficient time to conduct required leak surveys and any necessary repairs.
Major Street Improvement Projects
Projects including, but not limited to:
Excavations greater than 9 inches
Street widening
Installation of new curbs and gutters
Bus pads
Traffic signals
Street realignments
Grade separations
AND
Pipeline Projects
Including:
Storm drain
Water and sewer lines
Electrical
Telecommunications
Please provide signed and approved design plans showing all SCG facilities clearly identified:
4–6 months prior to construction for potential relocation of SCG medium‑pressure facilities.
9–12 months prior to construction for potential relocation of SCG high‑pressure facilities.
This time is required to review plans and design any necessary modifications to conflicting SCG facilities.
Coordination & Relocation Requests
Please keep SCG informed of:
Pre‑construction meetings
Construction schedules
Project phasing updates
This information allows SCG to coordinate and schedule any required work.
Potholing may be required to determine whether conflicts exist between proposed improvements and existing SCG facilities.
If SCG facilities are in conflict and relocation is required, requests must be submitted in writing and include the following:
A signed “Notice to Owner” on official City, County, and/or company letterhead.
Project name, number, and responsible title.
Project address, location, anticipated start date, parameters, and full scope of work.
A Thomas Guide page and/or Google Maps screenshot clearly highlighting the project area.
Requestor company’s contact name, title, phone number, email address, and any additional relevant information.
Thank you,
Josh Rubal
Lead Planning Associate
Distribution Planning & Project Management (Franchise)
Redlands HQ - Southeast Region
Office: (213) 231-7978
Email: [email protected]