Report to City Council
ID: 26-0377 Page 1
TO: Mayor and City Council
FROM: Melissa Walker, Public Works Director/City Engineer AGENDA DATE: October 6, 2026
TITLE: AUTHORIZATION OF ADDITIONAL CONTINGENCY TO
THE CORNERSTONECC CONTRACT TO INSTALL
ELECTRIC VEHICLE CHARGERS AT THE MORENO
VALLEY CIVIC CENTER AMPHITHEATER (REPORT
OF: PUBLIC WORKS) (DISTRICT 1)
TITLE SUMMARY: Authorization Of Additional Contingency To The CornerstoneCC Contract To Install Electric Vehicle Chargers At The Moreno Valley Civic Center Amphitheater, Project Number 805 0081
DISTRICT: District 1
Recommendation(s)
That the City Council:
1. Authorize the City Manager to increase the CornerstoneCC contract contingency amount for Project 805 0081 by $29,841.20 to a total amount of $179,047.20 (original authorized contract amount of $149,206 plus 20% contingency). Funded by the Moreno Valley Electric Utility’s Restricted Assets Fund (6011);
2. Authorize a change order to the purchase order amount for CornerstoneCC for Project Number 805 0081 to the total amount of $179,047.20, once the construction change order has been executed by all parties; and
3. Authorize the City Manager or his designee to execute any subsequent construction change orders to the Contract with CornerstoneCC that are necessary to complete the ID: 26-0377 Page 2
project, including issuing additional purchase orders, up to the annual project budget as previously approved by the City Council, subject to the approval of the City Attorney.
SUMMARY
The intent of this report is to recommend approval of an additional 20% of contingency, which will add $29,841.20 to cover anticipated construction costs resulting from field conditions associated with the construction of electric vehicle chargers at the Moreno Valley Civic Center Amphitheater. The additional contingency amount will increase the total contract to $179,047.20. The project is funded by Moreno Valley Electric (MVU) restricted fund balance and has been approved in the Fiscal Year 2025/2026 Adopted Capital Improvement Plan.
DISCUSSION
As the City expands its electric fleet, several capital improvement projects are needed to support vehicle charging infrastructure. The Electric Vehicle (EV) Charging Project at the Moreno Valley Civic Center Amphitheater will install EV chargers in the Amphitheater parking to provide charging solutions for the City’s electric fleet to accommodate the growing number of EV owners in the community.
The initial agreement with CornerstoneCC was approved for $149,206 to fund the project’s construction costs. During construction, utility lines were discovered in locations that differed from those shown on the as-built plans. Additionally, an existing drain line conflicted with the proposed transformer location. As a result, the transformer was relocated several feet to avoid the drain line, which required additional materials and increased construction costs.
The additional work also included replacing deteriorated Americans with Disabilities Act (ADA) and EV parking signs and restriping the accessible EV charging stalls to improve the condition and visibility of the signs and pavement markings.
These improvements, in coordination with the EV charger installation, will enhance the condition and appearance of the parking area and facilitate the project’s completion.
ALTERNATIVES
1. Approve and authorize the recommended actions as presented in this staff report.
This will allow for the timely construction of the EV charging stations in the Moreno Valley Civic Center Amphitheater parking lot. Staff recommends this alternative.
2. Do not approve and authorize the recommended actions as presented in this staff report. This alternative will delay the timely construction of this project and slow the growth of electric vehicle charging infrastructure in the City. Staff does not recommend this alternative.
FISCAL IMPACT
The EV Charger Project is included in the Fiscal Year 2025/2026 and 2026/2027 Adopted ID: 26-0377 Page 3
Capital Improvement Plan Budget and is funded by the Moreno Valley Electric Utility’s Restricted Asset Fund (6011). The fund has sufficient budget to cover the $29,841.20 increase in construction costs without impacting the General Fund.
NOTIFICATION
Posting of the Agenda.
PREPARATION OF STAFF REPORT
Prepared By: Department Head Approval:
Giovanny Felix Melissa Walker, P.E.
Assistant Electrical Engineer Public Works Director/City Engineer Concurred By:
Jason Niccoli, P.E.
Electric Utility Division Manager
CITY COUNCIL GOALS
Public Facilities and Capital Projects: Ensure that needed public facilities, roadway improvements, and other infrastructure improvements are constructed and maintained.
CITY COUNCIL STRATEGIC PRIORITIES
1. Economic Development
2. Public Safety
3. Library
4. Infrastructure
5. Beautification, Community Engagement, and Quality of Life
6. Youth Programs
Objective 4.6: Advance the development of a well-connected and balanced citywide transportation network that serves all modes.
Objective 4.7: Demonstrate innovative and industry leading transportation systems.
ID: 26-0377 Page 4
Report Approval Details
Document
Title:
STAFFREPORT_PW_MVU_AMPHITHEATER_EV_CO.docx
Attachments: - Location Map.pdf
Final Approval
Date:
Sep 30, 2026