2024 Pavement Management
Award of Contract and Update
Department of Public Works
August 27, 2024
1 Outline
2 Recent Work
Budget and Funding
Project Details
PEI Presentation
Recent Paving
3 • FY21/22 project completed in August 2023
• Completion delayed by rain
• $1,414,000
• Digouts: Main, Harbor, Beach, Pacific, South Bay, Coral, San Jacinto
• Preston Lane (2023)
• Quintana Road (2023)
• Bike Path (2023)
• Harbor Street (2023)
• Park Lot Rehab (2024)
Recent Paving
4 • Targeted/small contract work – Maintenance Division $180k • Radcliffe neighborhood (2024)
• Greenwood, Bolton, Laurel, Cuesta (2024)
• Jamaica, Panorama, Island, Tide (2024)
• Maintenance Division (ongoing)
• Routine/weekly pothole repair and digout/skinpatch work as requested
Current Budget and Project
5 Pavement Management Project: 3 years of budget
• FY22/23, FY23/24, FY24/25
• Remaining: $5,037,669
Benefits to consolidating budgets:
• Higher paving budgets mean better pricing
• Mobilization
• More efficient for staff
Project Funding
6 • Where does the money come from?
• Measure Q/E
• ARPA
• SB1
• Reserves
Project Details
7 Construction
• Bid: July 18th to August 15th
• Engineer’s Estimate: $4,641,309
• Bidders: 3
• Low Bid: $3,023,108
• Bidder: Souza Construction, San Luis Obispo
Project Details
8 How were roads chosen?
• Critical point management

CITY OF MORRO BAY

CITY COUNCIL MEETING

PAVEMENT MANAGEMENT PROGRAM
UPDATE
August 27, 2024
9 •Pavement 101
•Pavement management principles
•Assessment findings
•Funding needs
• Recommendations

PRESENTATION GOALS
10 PAVEMENT 101
11 12
What Determines a Pavement Section?
Pavement Deterioration Cycle
PAVEMENT 101
13 Asphalt concrete deteriorates in two ways:

Pavement Deterioration
Oxidizing effects of sun and water Fatigue from heavy wheel loads PAVEMENT 101
The Impact of Sun and Water
PAVEMENT 101
15 The Impact of Heavy Loads
PAVEMENT 101
16 17
Block
Cracking
Alligator
Cracking
Transverse or
Longitudinal
Cracking
Weathering or
Raveling
Common Pavement Distresses
Evaluating Pavement: the PCI
PAVEMENT 101
18 100 – 91 = Excellent
90 – 71 = Good
70 – 51 = Fair/ At Risk
50 – 31 = Poor
30 – 0 = Failed
Developed by the U. S. Army Corp of Engineers
during World War II and standardized by ASTM, the
PCI is an objective and rational basis for
determining pavement condition and establishing
maintenance priorities.

City of Morro Bay’s Network Avg. PCI
60 • Alligator cracking
• Block cracking
• Distortions
• Longitudinal / transverse cracking
• Patches / utility cuts
• Rutting / depressions
• Weathering / raveling
Evaluating Common Pavement Distresses
PAVEMENT 101
19 PCI = 100
Excellent 100-91
PAVEMENT 101
PCI = 85
Good 90-71
PAVEMENT 101
PCI = 70
Fair 70-51
PAVEMENT 101
PCI = 60
Fair 70-51
PAVEMENT 101
PAVEMENT 101
PCI = 51
Fair 70-51
PCI = 38
Poor 50-31
PAVEMENT 101
PCI = 28
Failed 30-0
PAVEMENT 101
PCI = ?
PAVEMENT 101
27 PAVEMENT MANAGEMENT PRINCIPLES
28 Applying the RIGHT TREATMENT
to the RIGHT PAVEMENT
at the RIGHT TIME
using the RIGHT MATERIALS

PAVEMENT PRESERVATION
29 Pavement Preservation Timing

PAVEMENT PRESERVATION
30 Cape Seal / TMO
Overlay

PAVEMENT PRESERVATION
Pavement Management Strategies
31 •Best-First “Top Down” Management
•Worst-First “Bottom Up” Management
• Critical-Point Management
Pavement Management Strategies
Critical Point Management

PAVEMENT PRESERVATION
32 Critical-Point-Management
selects streets before they
deteriorate and need the
next most expensive
treatment.

Cape Seal / TMO
Overlay
Pavement Condition vs.

Maintenance / Rehabilitation Cost

PAVEMENT PRESERVATION
33 PCI
Range
Treatment
Category
Cost Range
(per SY)
90-71 Light
Maintenance
$6.18 to
$8.40
70-51 Heavy
Maintenace
$26.00 to
$28.00
70-51 Light
Rehabilitation
$58.50 to
$64.40
50-26 Heavy
Rehabilitation
$130.00 to
$210.00
25-0 Reconstruction $195.00 to
$266.00
Cape Seal / TMO
Overlay

ASSESSMENT FINDINGS
34 City of Morro Bay System Data
•System Size
 53.5 centerline miles
 8,653,830 square feet of pavement
•System-wide average weighted PCI of 60
•Replacement value of $206,987,000

ASSESSMENT FINDINGS
35 Maintained Road System

ASSESSMENT FINDINGS
36 Functional
Classificati
on
Centerline
Miles
Pavement
Area
(SqFt)
Percent
Of
System
2024
Average
PCI
Arterial 6.95 1,389,605 16.06% 66
Collector 12.13 2,223,870 25.70% 61
Residential 34.75 5,040,355 58.24% 58
Totals 53.77 8,653,830 100.00% 60
Maintained Road System

ASSESSMENT FINDINGS
37 Functional
Classification
Percent
Of
System
2020
Average
PCI
2022
Average
PCI
2024
Average
PCI
Arterial 16.06% 68 65 66
Collector 25.70% 66 62 61
Residential 58.24% 66 62 58
Totals 100.00% 66 63 60

ASSESSMENT FINDINGS
38 39
40 41

FUNDING NEEDS
42 Five Year PCI Trend Using Future Treatment Costs

BUDGET NEEDS
43 78
60 65
60 53
48 45
50 55
60 65
70 75
80 85
2024 2025 2026 2027 2028 2029
PCI Range
Year
5 Year Projections
(S1) System Needs
$56.5M/Yr 1,
$2.1M/Yr 2-5 Avg.
(S2) Increase PCI by 5
Avg. $7.5M/Yr
(S3) Maintain PCI
Avg. $4.5M/Yr
(S4) Current Funding
Avg. $1.36M/Yr
(S5) Zero Budget

PEI RECOMMENDATIONS
44 • Continue to update the Pavement Management System
• Develop Multi-Year Pavement Expenditure Plan
• Critical Point - Maintenance and Rehabilitation
• Focus limited funding to preserve critical assets
• Leverage limited funds with grants (Matching Funds) on Grant Eligible Streets (Arterials)
• STIP, Complete Streets, Safe Routes to Schools
• Consider additional funding sources
Refuse Impact Fees, Utility Impact Fees, Sales Tax, Parcel Tax QUESTIONS?