Attachment 1
-1-
CITY OF MOUNTAIN VIEW
RESOLUTION NO.
SERIES 2022
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF MOUNTAIN VIEW
ADOPTING A LIST OF PROJECTS FOR FUNDING TO BE ALLOCATED DURING FISCAL YEAR 2022-23 FROM SENATE BILL 1—
THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and signed into law by the Governor in April 2017 in order to address the significant mu lti-modal transportation funding shortfalls Statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of our City are aware of the projects proposed for funding in our community and which projects have been completed each fiscal year; and
WHEREAS, the City must adopt by resolution a project or list of projects proposed to receive funding from the Road Maintenance and Rehabilitation Account (RMRA) created by SB 1 which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and
WHEREAS, the City will receive an estimated $1.3 million to $1.6 million in RMRA funding in Fiscal Year 2022-23 from SB 1; and
WHEREAS, this is the sixth year in which the City is receiving SB 1 funding that will enable the City to continue essential road maintenance and rehabilitation projects, safety improvements, repairing and replacing aging bridges, and increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and
WHEREAS, the City has undergone a robust public process to ensure public input into our community’s transportation priorities/projects list; and
WHEREAS, the City used a Pavement Management System to develop the SB 1 projects list to ensure revenues are being used on the most high -priority and cost-effective projects that also meet the community’s priorities for transportation investment; and
WHEREAS, the funding from SB 1 will help the City maintain and rehabilitate streets and add active transportation infrastructure in the City’s Moffett/Whisman Road Neighborhood Area this year and hundreds of similar projects into the future; and
-2-
WHEREAS, the 2018 California Statewide Local Streets and Roads Needs Assessment found that the City’s streets and roads are in good condition, and this revenue will help the City increase the overall quality of our road system and over the next decade will maintain our streets and roads in good condition; and
WHEREAS, the SB 1 project s list and overall investment in our local streets and roads infrastructure with a focus on basic maintenance and safety, investing in complete streets infrastructure, and using cutting -edge technology, materials, and practices will have significant positive City and community benefits Statewide;
NOW, THEREFORE, BE IT RESOLVED by the City Council of the City of Mountain View as follows:
1. The foregoing recitals are true and correct.
2. The following list of projects will have funding added in-part or solely with Fiscal Year 2022-23 Road Maintenance and Rehabilitation Account revenues.
Project Description
SB 1 Streets Project , Project 2 4-03—This project purposes to install asphalt concrete overlays, raise utilities and monuments, install pavement markings and markers, and /or apply slurry seal to selected street surfaces. Active transportation improvements or enhancements , such as installing high-visibility crosswalks and new bike lanes or enhancements of existing bike lanes , where feasible, will be integrated into each street segment.
Resurfacing and/or Slurry Seal Project Locations
• Moffett/Whisman Road Neighborhood Area Street Segments
Amount of Funds to be Allocated
• $1.3 million to $1.6 million in RMRA funds
Project Design and Construction Schedule
• August 2023—July 2024
Estimated Useful Life
• 10 years
– – – – – – – – – – –