DATE:

June 28, 2022
CATEGORY:

Consent
DEPT.:

Public Works

TITLE: Stierlin Road Bicycle and Pedestrian
Improvements, Project 17-41— Approve
Plans and Specifications, and Authorize
Bidding

RECOMMENDATION

1. Approve plans and specifications for Sti erlin Road Bicycle and Pedestrian Improvements, Project 17-41, and authorize staff to advertise the project for bids.

2. Authorize the City Manager or designee to award the construction contract to the lowest responsible bidder if the bid is within the project budget.

BACKGROUND

The Stierlin Road corridor provides a critical first -/last-mile link between the Mountain View Transit Center and the North Bayshore employment area. The importance of this corridor was established in the 2014 Shoreline Corridor Study, which identified several projects designed to increase the use of nonautomotive modes of transportation and support the planned growth of North Bayshore, the Transit Center, and downtown Mountain View (see Figure 1).

Figure 1: Project Location and Overview

Stierlin Road Bicycle and Pedestrian Improvements, Project 17-41— Approve Plans and Specifications, and Authorize Bidding June 28, 2022

Page 2 of 5 ends

On April 30, 2019 , Council authorized a professional services agreement with TJKM Transportation Co nsultants for Stier lin Road Bicycle and Pedestrian Improvements, Project 17-41. On May 11, 2021, Council adopted a Resolution of Local Support and authorized the filing of the Safe and Seamless Mobi lity Quick-Strike Grant for construction funding for this project. On June 23, 2021, the Metropolitan Transportation Commission (MTC) approved a Federal funding grant aw ard of $4,007,000 for project construction. A key requirement to receiving the grant is the timely use of the funds to avoid forfeiture. The City must advertise the project for construction before fall 2022 and begin construction by early 2023 .

On August 25, 2021, staff presented the project to the Bicycle/Pedestrian Advisory Committee , at which time the public an d the Committee provided comments and generally supported the project.

ANALYSIS

The project will install bicycle and pedestrian improvements along Stierlin Road, Central Avenue, and Shoreline Boulevard. Improvements include:

• Green-backed sharrows o n Stierlin Road , between Washington Street and Windmill Park Lane/Wright Avenue , and Class II bike lanes on the Stierlin Road slip ramp to Shoreline Boulevard;

• Traffic-calming and pedestrian improvements on Central Avenue and Sti erlin Road, including bulb-outs, high-visibility crosswalks, pedestrian and street lighting improvements, a midblock raised crossing, and speed humps;

• Class IV protected bikeways on Shoreline Boulevard from Montecito Avenue to south of Middlefield Road (see Figure 2);

• Protected intersection at Shoreline Boulevard and Montecito Avenue/Stierlin Road (see Figure 3); and

• A pedestrian -activated midblock crossing on Shoreline Boulevard adjacent to the Bailey Park Plaza (Safeway) Shopping Center.

Stierlin Road Bicycle and Pedestrian Improvements, Project 17-41— Approve Plans and Specifications, and Authorize Bidding June 28, 2022

Page 3 of 5 ends

Figure 2: Shoreline Boulevard Configuration

Figure 3: Protected Intersection at Montecito Avenue/Stierlin Court and North Shoreline Boulevard

Plans and specifications for the project are complete and available for review in the Public Works Department. If the City Council approves the recommended actions, and a responsive bid within the project budget is received, construction is estimated to b egin in early 2023 after project clearance is received by Caltrans, which serves as the grant administrator. This will meet the Federal grant schedule requirements.

Stierlin Road Bicycle and Pedestrian Improvements, Project 17-41— Approve Plans and Specifications, and Authorize Bidding June 28, 2022

Page 4 of 5 ends

ENVIRONMENTAL CLEARANCE

This project has been determined to be categorically exempt as a Class 1, Minor Alteration of Existing Facilities , and Class 4, Minor Alteration of Land , in accordance with the California Environmental Quality Act (CEQA) Guidelines. The categorical exemptions will be filed for the project after Council approval of the plans and specifications.

FISCAL IMPACT

Stierlin Road Bicycle and Pedestrian Improvements, Project 17 -41, is currently funded with $278,000 from the Construction and Conveyance Tax Fund and $371,700 from the Shoreline Regional Park Community Fund . The reimbursable grant funding of $4,007,000 will be appropriated to Project 17 -41 as part of the Fiscal Year 2022 -23 Capital Improvement Program (CIP), scheduled to be adopted by Council on Ju ne 28, 2022 . With the grant funding , the total project budget will be $4,656,700.

The estimated project cost is as follows:

Construction (including contingency) $3,600,000
Consultant Services 190,000
City Project Management 110,000
Construction Inspection and Testing 45,000
Outreach, Printing, and Miscellaneous 18,000
Project Contingency 400,000

Subtotal $4,363,000

City Administration 284,000

TOTAL PROJECT COST ESTIMATE: $4,647,000

There is sufficient funding for the project.

ALTERNATIVES

1. Do not approve plans and specifications and defer the project , relinquishing the grant funding.

2. Provide other direction.

Stierlin Road Bicycle and Pedestrian Improvements, Project 17-41— Approve Plans and Specifications, and Authorize Bidding June 28, 2022

Page 5 of 5 ends

PUBLIC NOTICING—Agenda posting.

Prepared by:

Robert Gonzales
Principal Civil Engineer/Civil Infrastructure

Reviewed by:

Edward Arango
Assistant Public Works Director/
City Engineer
Approved by:

Dawn S. Cameron
Public Works Director

Audrey Seymour Ramberg
Assistant City Manager/
Chief Operating Officer

RG/TS/1/CAM
956-06-28-22CR
202040

cc: APWD—Arango, PCE —Gonzales, CTE, PCE —Shah, SMA —Goedicke, Doan, PA —Li, File (17-41), [email protected]