ATT 2 - Active CIP Projects with Bicycle and Pedestrian Improvements

Mountain View City Council
April 3, 2023

Document
ATT 2 - Active CIP Projects with Bicycle and Pedestrian Improvements
Meeting
April 3, 2023
Body
Mountain View City Council
Pages
6
Original file
182 KB
Text extracted from the city's file for reading and search. Open the original on legistar1.granicus.com. That file is the official record.

Active CIP Projects with Bicycle and Pedestrian Improvements Attachment 2

Page 1 of 6 ends

Project Title (CIP #) Bike/Pedestrian Element Status
Anticipated
Construction Timeline Comments
East Whisman Area Transit-
Oriented Development
Improvements, Phase II: Ellis
Street Improvements,
Project 16-48
• High visibility crosswalk and
shortened crosswalks.
• Multi-use path on the west side
of Ellis Street between Fairchild
Drive and Manila Avenue.

Design Begin: Fall 2023
Complete: Spring 2024

Shoreline Boulevard Interim
Bus Lane and Utility
Improvements, Design and
Construction, Projects 16-58
& 18-43
• Widened sidewalks
• Protected Bike Lanes
• Protected intersections and
Middlefield, Terra Bella, and Pear
Design Begin: Early 2024
Complete: Summer
2025

Shoreline Boulevard at
Highway 101 Bicycle and
Pedestrian Bridge, Projects
16-60 and 20-38
• Two-way cycle track and walkway
bridge between Terra Bella and
Pear Avenue over Highway 101.

Preliminary Design Begin: Spring 2025.

Complete: Spring 2026

Shoreline/Church-Latham
Intersection Signal
Improvements, Projects 17-
27, 19-27, 20-27, 21-27

• Protected left turn phases to
eliminate vehicles/pedestrian
conflicts.
• Reconstruct median for more
available crosswalk area.

Design Begin: Fall 2023
Complete: Summer
2024
Partially funded with
Vehicle License Fee –
2010 Measure B
funds

Stierlin Road Bicycle and
Pedestrian Improvements,
Project 17-41
• Protected intersection
• Buffered Bike Lane
• High visibility crosswalks
• Mid-block pedestrian crossing
• Improved lighting, traffic calming
Design Begin: Summer 2023
Complete: Winter 2024

Funded by Federal
grant.

Pending Caltrans E-76
approval
Active CIP Projects with Bike and/or Pedestrian Improvements

Page 2 of 6 ends

Project Title (CIP #) Bike/Pedestrian Element Status
Anticipated
Construction Timeline Comments
Rengstorff Avenue Grade
Separation, Projects 17-37 &
18-44 (Preliminary
Engineering and
Environmental), 22-27 (Final
Design and ROW)
• Class IV bikeways on Rengstorff
between Stanford and Central
Expressway
• Bike/ped overcrossing between
Rengstorff Park and west side of
Rengstorff Avenue
• Widened sidewalks
Final Design Begin: Early 2025
Complete: 2027
Measure B funded.
(pending construction
funding availability).

Rengstorff/Latham Signal
Improvements, Projects 18-
27 and 22-15

• Protected left turn phases to
eliminate vehicles/pedestrian
conflicts.
• High visibility crosswalks.
• Bike enhancements include
green bike skip boxes
approaching along Rengstorff,
and a bike crossing at the
intersection along the west side
of Rengstorff.

Design Begin: Fall 2023
Complete:

Summer2024
Partially funded with
Vehicle License Fee –
2010 Measure B
funds
Bernardo Avenue
Undercrossing, Project 18-69

• Bike/ped undercrossing of
Caltrain rail and Central
Expressway
• Bicycle access improvements
within 500 feet of approaches
Preliminary Design
and Environmental
Clearance
Begin: 2025
Complete: 2027
Measure B funded.

Caltrain is project
lead for design and
construction.

Collaboration
between Mountain
View, Sunnyvale,
VTA, Caltrain and
County.

Charleston Road Corridor
Improvements, Project 19-34
• Dedicated Bus Lane
• Widened Sidewalk
• Protected bike lanes
• Protected Intersections
Design Begin: Early 2024
Complete: Fall 2025

Active CIP Projects with Bike and/or Pedestrian Improvements

Page 3 of 6 ends

Project Title (CIP #) Bike/Pedestrian Element Status
Anticipated
Construction Timeline Comments
Street Reconstruction
Project, Project 19-48, (Park
Drive, Sonia Way, Park Court)
• High visibility crosswalks Design Complete Begin: Summer 2023 Complete: Early 2024

Cross Culvert Removal (Dana
Street between Oak Street
and Franklin Street), Project
19-49
• High visibility crosswalks
• ADA-compliant curb ramps.

Design Begin: Early 2024
Complete: summer
2024

El Monte Corridor
Improvements, Projects 19-
61 (Study), 21-38 (Design and
Construction)
• Complete streets study.
• New and enhanced crosswalks
with lighting, striping, and
signage.
• Enhanced bike facility.
• ADA compliant curb ramps.

Preliminary Design
and Environmental
Clearance
Begin: Winter 2025
Complete: 2026

Study to BPAC, CTC
and council prior to
summer 2023

SR 237/Middlefield Road
Interchange Improvements,
Project 19-65
• ADA-compliant curb ramps
• High visibility crosswalks
• Class IV bikeways on Middlefield
Road between Ferguson Drive
and SR 237 eastbound on- and
off-ramps.

Preliminary Design Begin: Summer 2024
Complete: Spring 2025
Measure B funded
design. Pending right-
of-way and
construction funding
Miramonte Avenue
Pavement Improvements,
Project 20-01

• Class II bike lanes on Miramonte
between Cuesta and Hans
• Two-way Class IV bike lane on
northbound Miramonte between
Hans and Castro.
• Bulb-out and led-enhanced
crosswalk system at Hans
Avenue.

Design Begin: Early 2024
Complete: Fall 2024

Follows Miramonte
Utility Replacement
Project, currently
under construction
Active CIP Projects with Bike and/or Pedestrian Improvements

Page 4 of 6 ends

Project Title (CIP #) Bike/Pedestrian Element Status
Anticipated
Construction Timeline Comments
Annual Traffic Studies/NTMP
Improvements/Bicycle
Counts, Project 20-15
• NTMP Study Outreach/postcard
survey step of
guidelines
TBD Latham Street to CTC
in April; Central
Avenue postcard
survey in March
Castro Street Curb Ramp,
Project 20-30
• Replace curb ramps in Downtown
section of Castro Street
Design Begin: Summer 2023
Complete: Fall 2023

Plymouth Street/Space Park
Realignment, Project 20-40

• High visibility crosswalks
• Two-way bikeway on Shoreline
Boulevard between
Plymouth/Space Park and Pear
Avenue
• Class II bikeways on Plymouth
between Joaquin and Shoreline
Design Begin: Fall 2023
Complete: Fall 2025
Construction to
proceed in three
phases: 1) tree
removal, 2) building
demolition, 3) street
realignment
El Camino Real Pavement
Resurfacing/Bike and
Pedestrian Improvements,
Project 20-60
• Bike lanes
• Mid-block pedestrian crossings
• Replace curb ramps
Design Complete Begin: Fall 2023
Complete: Spring 2024
Caltrans project
Street Resurfacing (Leong
Drive and Fairchild Drive),
Project 21-01
• Bike lanes Design Begin: Summer 2023
Complete: Early 2024
Measure B funded.

Annual Sidewalk and Curb
Repairs, Project 21-06
• Repair sidewalks and install 9
curb ramps throughout the City
Design Begin: Summer 2023
Complete: Fall 2023

Street Lane Line and Legend
Repainting, Project 21-12

• High visibility crosswalks around
City of Mountain View schools
Design Begin: Fall 2023
Complete: Early 2024

SB-1 Streets Project (Velarde,
Pamela, Bay, Doverton,
Katrina, Fairbrook), Project
21-30
• High visibility crosswalks Design Begin: Spring 2023
Complete: Early 2024
Includes 100 – 300
blocks of Castro
Street
Active CIP Projects with Bike and/or Pedestrian Improvements

Page 5 of 6 ends

Project Title (CIP #) Bike/Pedestrian Element Status
Anticipated
Construction Timeline Comments
Transit Center Grade
Separation and Access
Project, Project 21-35

• Shared-use path underneath the
Evelyn Avenue ramp to Shoreline
• Bike/ped undercrossings
between northside of Central
Expressway and Transit Center
and Downtown.
• Bikeways and high-visibility
crosswalks within project limits
Design Begin: Early 2025
(pending funding
availability).

Complete: 2026
Measure B funded.

Bicycle/Pedestrian
Improvements (Shoreline
Blvd from Wright Avenue to
Villa Street), Project 21-37

• Reconstruct bicycle and
pedestrian pathway on east side
of Shoreline Blvd.
• ADA-compliant curb ramps
• Pathway lighting
Design Begin: Fall 2023
Complete: Early 2024
$2M grant funding by
One Bay Area Grant
Program.

Grant Road and Sleeper
Avenue Intersection
Improvements (Design and
Construction)
- including 9 other
intersections, Project 21-39
Grant/Sleeper:
• Installation of a Pedestrian
Hybrid Beacon (PHB)
• High-visibility crosswalk across
the southern leg of Grant Road
with left turn restriction from
Sleeper Avenue.
• Bike improvement crossing Grant
• New and enhanced crosswalk
striping and signage. ADA
compliant curb ramps.
9 Other Intersections:
• High-visibility crosswalks.
• LED-enhanced signs.
• Rectangular Rapid-Flashing
Beacons.
• Other enhancements.

Design Begin: Spring 2024
Complete: Early 2025

Active CIP Projects with Bike and/or Pedestrian Improvements

Page 6 of 6 ends

Project Title (CIP #) Bike/Pedestrian Element Status
Anticipated
Construction Timeline Comments
California Complete Streets
Pilot, Project 21-40
• Vehicle lane reduction from four
lanes to three lanes
• Parking-protected bike lanes
• Bulb-outs, midblock crossings,
protected intersection
treatments and enhanced
lighting
Design Begin: Fall 2023
Complete: Early 2024
Showers to Shoreline
Blvd
Crittenden Lane
Reconstruction, Project 21-
41 • Bike facilities
• ADA-compliant curb ramps
Design Begin: Fall 2024
Complete: Summer
2025
Pending completion
of the South Bay Salt
Ponds Restoration
project. Measure B
funded