Active CIP Projects with Bicycle and Pedestrian Improvements Attachment 2
Project Title (CIP #) Bike/Pedestrian Element Status
Anticipated
Construction Timeline Comments
East Whisman Area Transit-
Oriented Development
Improvements, Phase II: Ellis
Street Improvements,
Project 16-48
• High visibility crosswalk and
shortened crosswalks.
• Multi-use path on the west side
of Ellis Street between Fairchild
Drive and Manila Avenue.
Design Begin: Fall 2023
Complete: Spring 2024
Shoreline Boulevard Interim
Bus Lane and Utility
Improvements, Design and
Construction, Projects 16-58
& 18-43
• Widened sidewalks
• Protected Bike Lanes
• Protected intersections and
Middlefield, Terra Bella, and Pear
Design Begin: Early 2024
Complete: Summer
2025
Shoreline Boulevard at
Highway 101 Bicycle and
Pedestrian Bridge, Projects
16-60 and 20-38
• Two-way cycle track and walkway
bridge between Terra Bella and
Pear Avenue over Highway 101.
Preliminary Design Begin: Spring 2025.
Complete: Spring 2026
Shoreline/Church-Latham
Intersection Signal
Improvements, Projects 17-
27, 19-27, 20-27, 21-27
• Protected left turn phases to
eliminate vehicles/pedestrian
conflicts.
• Reconstruct median for more
available crosswalk area.
Design Begin: Fall 2023
Complete: Summer
2024
Partially funded with
Vehicle License Fee –
2010 Measure B
funds
Stierlin Road Bicycle and
Pedestrian Improvements,
Project 17-41
• Protected intersection
• Buffered Bike Lane
• High visibility crosswalks
• Mid-block pedestrian crossing
• Improved lighting, traffic calming
Design Begin: Summer 2023
Complete: Winter 2024
Funded by Federal
grant.
Pending Caltrans E-76
approval
Active CIP Projects with Bike and/or Pedestrian Improvements
Project Title (CIP #) Bike/Pedestrian Element Status
Anticipated
Construction Timeline Comments
Rengstorff Avenue Grade
Separation, Projects 17-37 &
18-44 (Preliminary
Engineering and
Environmental), 22-27 (Final
Design and ROW)
• Class IV bikeways on Rengstorff
between Stanford and Central
Expressway
• Bike/ped overcrossing between
Rengstorff Park and west side of
Rengstorff Avenue
• Widened sidewalks
Final Design Begin: Early 2025
Complete: 2027
Measure B funded.
(pending construction
funding availability).
Rengstorff/Latham Signal
Improvements, Projects 18-
27 and 22-15
• Protected left turn phases to
eliminate vehicles/pedestrian
conflicts.
• High visibility crosswalks.
• Bike enhancements include
green bike skip boxes
approaching along Rengstorff,
and a bike crossing at the
intersection along the west side
of Rengstorff.
Design Begin: Fall 2023
Complete:
Summer2024
Partially funded with
Vehicle License Fee –
2010 Measure B
funds
Bernardo Avenue
Undercrossing, Project 18-69
• Bike/ped undercrossing of
Caltrain rail and Central
Expressway
• Bicycle access improvements
within 500 feet of approaches
Preliminary Design
and Environmental
Clearance
Begin: 2025
Complete: 2027
Measure B funded.
Caltrain is project
lead for design and
construction.
Collaboration
between Mountain
View, Sunnyvale,
VTA, Caltrain and
County.
Charleston Road Corridor
Improvements, Project 19-34
• Dedicated Bus Lane
• Widened Sidewalk
• Protected bike lanes
• Protected Intersections
Design Begin: Early 2024
Complete: Fall 2025
Active CIP Projects with Bike and/or Pedestrian Improvements
Project Title (CIP #) Bike/Pedestrian Element Status
Anticipated
Construction Timeline Comments
Street Reconstruction
Project, Project 19-48, (Park
Drive, Sonia Way, Park Court)
• High visibility crosswalks Design Complete Begin: Summer 2023 Complete: Early 2024
Cross Culvert Removal (Dana
Street between Oak Street
and Franklin Street), Project
19-49
• High visibility crosswalks
• ADA-compliant curb ramps.
Design Begin: Early 2024
Complete: summer
2024
El Monte Corridor
Improvements, Projects 19-
61 (Study), 21-38 (Design and
Construction)
• Complete streets study.
• New and enhanced crosswalks
with lighting, striping, and
signage.
• Enhanced bike facility.
• ADA compliant curb ramps.
Preliminary Design
and Environmental
Clearance
Begin: Winter 2025
Complete: 2026
Study to BPAC, CTC
and council prior to
summer 2023
SR 237/Middlefield Road
Interchange Improvements,
Project 19-65
• ADA-compliant curb ramps
• High visibility crosswalks
• Class IV bikeways on Middlefield
Road between Ferguson Drive
and SR 237 eastbound on- and
off-ramps.
Preliminary Design Begin: Summer 2024
Complete: Spring 2025
Measure B funded
design. Pending right-
of-way and
construction funding
Miramonte Avenue
Pavement Improvements,
Project 20-01
• Class II bike lanes on Miramonte
between Cuesta and Hans
• Two-way Class IV bike lane on
northbound Miramonte between
Hans and Castro.
• Bulb-out and led-enhanced
crosswalk system at Hans
Avenue.
Design Begin: Early 2024
Complete: Fall 2024
Follows Miramonte
Utility Replacement
Project, currently
under construction
Active CIP Projects with Bike and/or Pedestrian Improvements
Project Title (CIP #) Bike/Pedestrian Element Status
Anticipated
Construction Timeline Comments
Annual Traffic Studies/NTMP
Improvements/Bicycle
Counts, Project 20-15
• NTMP Study Outreach/postcard
survey step of
guidelines
TBD Latham Street to CTC
in April; Central
Avenue postcard
survey in March
Castro Street Curb Ramp,
Project 20-30
• Replace curb ramps in Downtown
section of Castro Street
Design Begin: Summer 2023
Complete: Fall 2023
Plymouth Street/Space Park
Realignment, Project 20-40
• High visibility crosswalks
• Two-way bikeway on Shoreline
Boulevard between
Plymouth/Space Park and Pear
Avenue
• Class II bikeways on Plymouth
between Joaquin and Shoreline
Design Begin: Fall 2023
Complete: Fall 2025
Construction to
proceed in three
phases: 1) tree
removal, 2) building
demolition, 3) street
realignment
El Camino Real Pavement
Resurfacing/Bike and
Pedestrian Improvements,
Project 20-60
• Bike lanes
• Mid-block pedestrian crossings
• Replace curb ramps
Design Complete Begin: Fall 2023
Complete: Spring 2024
Caltrans project
Street Resurfacing (Leong
Drive and Fairchild Drive),
Project 21-01
• Bike lanes Design Begin: Summer 2023
Complete: Early 2024
Measure B funded.
Annual Sidewalk and Curb
Repairs, Project 21-06
• Repair sidewalks and install 9
curb ramps throughout the City
Design Begin: Summer 2023
Complete: Fall 2023
Street Lane Line and Legend
Repainting, Project 21-12
• High visibility crosswalks around
City of Mountain View schools
Design Begin: Fall 2023
Complete: Early 2024
SB-1 Streets Project (Velarde,
Pamela, Bay, Doverton,
Katrina, Fairbrook), Project
21-30
• High visibility crosswalks Design Begin: Spring 2023
Complete: Early 2024
Includes 100 – 300
blocks of Castro
Street
Active CIP Projects with Bike and/or Pedestrian Improvements
Project Title (CIP #) Bike/Pedestrian Element Status
Anticipated
Construction Timeline Comments
Transit Center Grade
Separation and Access
Project, Project 21-35
• Shared-use path underneath the
Evelyn Avenue ramp to Shoreline
• Bike/ped undercrossings
between northside of Central
Expressway and Transit Center
and Downtown.
• Bikeways and high-visibility
crosswalks within project limits
Design Begin: Early 2025
(pending funding
availability).
Complete: 2026
Measure B funded.
Bicycle/Pedestrian
Improvements (Shoreline
Blvd from Wright Avenue to
Villa Street), Project 21-37
• Reconstruct bicycle and
pedestrian pathway on east side
of Shoreline Blvd.
• ADA-compliant curb ramps
• Pathway lighting
Design Begin: Fall 2023
Complete: Early 2024
$2M grant funding by
One Bay Area Grant
Program.
Grant Road and Sleeper
Avenue Intersection
Improvements (Design and
Construction)
- including 9 other
intersections, Project 21-39
Grant/Sleeper:
• Installation of a Pedestrian
Hybrid Beacon (PHB)
• High-visibility crosswalk across
the southern leg of Grant Road
with left turn restriction from
Sleeper Avenue.
• Bike improvement crossing Grant
• New and enhanced crosswalk
striping and signage. ADA
compliant curb ramps.
9 Other Intersections:
• High-visibility crosswalks.
• LED-enhanced signs.
• Rectangular Rapid-Flashing
Beacons.
• Other enhancements.
Design Begin: Spring 2024
Complete: Early 2025
Active CIP Projects with Bike and/or Pedestrian Improvements
Project Title (CIP #) Bike/Pedestrian Element Status
Anticipated
Construction Timeline Comments
California Complete Streets
Pilot, Project 21-40
• Vehicle lane reduction from four
lanes to three lanes
• Parking-protected bike lanes
• Bulb-outs, midblock crossings,
protected intersection
treatments and enhanced
lighting
Design Begin: Fall 2023
Complete: Early 2024
Showers to Shoreline
Blvd
Crittenden Lane
Reconstruction, Project 21-
41 • Bike facilities
• ADA-compliant curb ramps
Design Begin: Fall 2024
Complete: Summer
2025
Pending completion
of the South Bay Salt
Ponds Restoration
project. Measure B
funded