ATTACHMENT 1
Capital Projects Bid Results (2017 – 2023)

Listed below are the bid results for City capital projects with construction costs over $1 million categorized by type of project. 2023 information is for bids opened through May 2023.

Project Name
Bid
Year
#
Bidders
Engineer’s
Estimate Low Bid
#
Subs*
New Buildings
Rengstorff Aquatics Center 2021 3 $21,342,000 $21,804,000 23 Building Renovations
Library Space Modifications 2017 5 2,600,000 2,371,000 5 Fire Station 4 Restroom Renovation 2022 6 1,550,000 1,596,000 5 Recycling Building Retrofit 2022 2 500,000 1,122,000 4
Parks
Evandale Park 2019 5 950,000 1,019,000 6
Wyandotte Park 2019 5 1,700,000 1,609,000 3
Fayette Park 2020 11 1,500,000 1,507,000 3
Mora Park 2021 8 1,200,000 1,118,000 2
Pyramid Park 2021 3 3,625,000 3,758,389 3
Fayette Park 2022 4 1,475,000 1,644,000 7
Sylvan Park Trellis Replacement/
Sand Volleyball Court 2022 6 1,264,000 1,180,000 2
Magical Playground and Rengstorff
Tennis/Maintenance Building 2023 1 7,820,000 10,819,000 13 Utilities
Citywide Trash Capture 2017 2 1,300,000 1,377,000 1
Annual Water/Sewer Mains
Replacement 2018 5 4,200,000 5,188,000 0
Leong Water/Sewer Mains 2019 4 6,170,000 4,838,000 1
Sewage Pump Station Repairs 2019 1 3,400,000 3,495,000 2 Water Main Crossing 101 at Macon 2019 6 2,182,000 1,848,000 1 Annual Water Main Replacement 2021 8 3,250,000 2,428,000 0 Interceptor Trunk Main 2021 3 2,500,000 2,486,000 4
ATTACHMENT 1
Project Name
Bid
Year
#
Bidders
Engineer’s
Estimate Low Bid
#
Subs*
Miramonte Water/Sewer Mains
Replacement 2022 4 3,400,000 2,888,000 2
Annual Water/Sewer Mains
Replacement 2023 1 5,200,000 5,785,000 1
Street Resurfacing and Reconstruction
16-17 Street Resurfacing 2017 3 1,350,000 1,306,000 4
Hackett/Wagner Reconstruction 2017 9 1,400,000 1,344,000 2 17-18 Street Resurfacing 2018 4 1,448,000 1,381,000 3
18-19 Street Resurfacing 2019 3 1,650,000 1,858,000 4
Middlefield Road Improvements 2020 4 1,550,000 1,194,000 3 Leong/Fairchild Reconstruction 2023 3 1,900,000 2,056,000 4 Park/Sonia Reconstruction 2023 1 2,700,000 2,633,000 4
Other Infrastructure Projects
Grant/Phyllis/Martins Intersection
Improvements 2018 3 1,239,000 1,333,000 5
Whisman Transit-Oriented
Development (TOD) Improvements 2018 6 1,134,000 1,350,000 7 Castro/Moffett/Central
Intersection Improvements 2019 6 1,240,000 1,375,000 3
Shoreline Bus Lane and Utility
Improvements 2020 6 11,500,000 14,482,000 6
Shoreline Lake Improvements 2021 5 2,100,000 2,142,000 3 * Number of subcontractors (subs) for the lowest responsive responsible bidder.