ATT 1 - FY 22-23 Annual Compliance Report for Development Impact Fees

Mountain View City Council
December 5, 2023

Document
ATT 1 - FY 22-23 Annual Compliance Report for Development Impact Fees
Meeting
December 5, 2023
Body
Mountain View City Council
Pages
23
Original file
333 KB
Text extracted from the city's file for reading and search. Open the original on legistar1.granicus.com. That file is the official record.

Attachment 1
Finance and Administrative Services Department

DATE: November 7, 2023

TO: City Council

FROM: Elliot Young, Senior Financial Analyst
Grace Zheng, Assistant Finance and Administrative
Services Director
Derek Rampone, Finance and Administrative Services Director

VIA: Kimbra McCarthy, City Manager

SUBJECT: Fiscal Year 2022-23 Annual Compliance Report for Development Impact Fees

BACKGROUND

California Government Code (CGC) Section 66006(b)(1)(A -H) requires local agencies, within 180 days after the last day of each fiscal year, to make available to the public certain information for the fiscal year. CGC Section 66006(b)(2) requires the information be made available to the public at least 15 days prior to City Council consideration of the report.

This report discusses various fees, including the Citywide Transportation Impact Fee, Housing Impact (HI) Fee, Rental Housing Impact (RHI) Fee, North Bayshore Development Impact Fees for Transportation, Sewer, and Water (NBS Development Impact Fees) (including transportation, water, and sewer), Water Development Impact Fee, and Sewer Development Impact Fee. CGC Section 66001(d)(1) requires local agencies to make findings with respect to fees and investment earnings remai ning unexpended, whether committed or uncommitted, for the fifth year following receipt of the first fee deposited and every five years thereafter.

Although the City is required to make these findings every five years after the first fee is deposited, t he City reports findings when required or provides the information on an annual basis, after the initial reporting, to make this requirement easier to administer. There are currently four different five -year finding cycles, and this year’s report has no r equired findings.

For ease of administration, this report provides information on those fees that have had an initial five-year findings report, which are the HI, RHI, NBS Development Impact Fee—Transportation, and Sewer Development Impact Fees.

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 2 of 23 ends

ANALYSIS

1. Citywide Transportation Impact Fund

Description of the Type of Fee—CGC Section 66006(b)(1)(A):

On September 25, 2018, the City Council adopted Ordinance 8.18, adding Chapter 43 to the City Code to enact a Transportation Impact Fee on Citywide Development, which became effective on November 24, 2018. The purpose of the fee is to fund new Citywide multi - modal transportation improvements required under the Congestion Management Program (CMP). The CMP is managed by the Santa Clara Valley Transportation Authority (VTA), pursuant to State law.

Amount of Fee—CGC Section 66006(b)(1)(B):

Type FY 2022-23 FY 2023-24

Single-Family, attached or detached (net new dwelling unit)

$5,364

$6,120
Multi-Family (net new dwelling unit) $3,004 $3,428
Hotels and Motels (net new guest room) $3,317 $3,785
Service and Retail Commercial (SF, net new floor area) $5.72 $6.53 Office, R&D, Industrial (SF, net new floor area) $5.72 $6.53 Low Trip-Generating Uses (a.m. and p.m. peak-hour trips) $3,100 $3,537

Beginning and Ending Balances, Amount of Fees Collected, and Interest Earned —CGC Section 66006(b)(1)(C and D):

Beginning Balance, July 1, 2022 $869,051
Citywide Transportation Impact Fees $1,089,604
Investment Earnings 48,358
Total Unaudited Revenues $1,137,962
Total Unaudited Expenditures -0-
Unexpended/Available Balance, June 30, 2023 $2,007,013

During Fiscal Year 2022-23, there were $1.1 million in fees deposited, $48,358 in investment earnings, and no expenditures. As of June 30, 202 3, there is an unexpended/available balance of $ 2.0 million . A transportation -related capital project, 2020 -21 Street Resurfacing/Slurry Seal , P roject 21 -01, previously funded by these fees, is listed in the following section, and the funds will be expended over the life of the capital project.

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 3 of 23 ends

Identification of Each Public Improvement on Which Fees Were Expended in Fiscal Year 2022-23—CGC Section 66006(b)(1)(E) (dollars in thousands):

The table below shows active project(s) that have been partially or fully funded by Citywide Transportation Impact (CTI) Fees.

Total
Project
Cost
FY 2022-23
CTI
Expenditures
Life to Date
(LTD) CTI
Expenditures

Total CTI
Funding
% of Project
Funded by
CTI Fee
20-21 Street
Resurfacing/
Slurry Seal
(21-01) $3,783 $131

$267

$156 4.1%

Identification of Approximate Date by Which Construction Will Commence Once Sufficient Funds have been Collected—CGC Section 66006(b)(1)(F):

Construction for the 2020-21 Street Resurfacing/Slurry Seal project commenced in summer 2023 and is expected to be completed fall/winter 2023. Expenditures in the project to date are for project management and design.

Description of Each Interfund Transfer or Interfund Loan Made from the Fund —CGC Section 66006(b)(1)(G):

No CTI Fees were expended during Fiscal Year 2022-23.

Amount of Refunds Made—CGC Section 66006(b)(1)(H):

No refunds were made from this fund.

Findings for Amounts Remaining Unexpended—CGC Section 66001(d)(1):

The first Citywide Transportation Impact Fee was deposited June 10, 2019 and, in accordance with CGC Section 66001(d)(1), the City is required to make all findings as of June 30, 2024, the end of the fifth year fo llowing deposit of the first fee into the Citywide Transportation Impact Fund.

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 4 of 23 ends

2. Housing Impact Fund

Description of the Type of Fee—CGC Section 66006(b)(1)(A):

On January 8, 2002, the Council adopted Ordinance 01.02, amending Chapter 36 of the City Code, allowing for a nonresidential HI Fee to be imposed on all net new gross floor area for nonresidential development projects on a per -square-foot basis. The fee was adopted by resolution on October 30, 2001, with an effective date of January 14, 2002, and is adjusted annually based on the Consumer Price Index for the San Francisco -Oakland-San Jose area for the previous year. The HI fees and any investment earnings shall be used to increase and improve the supply of affordable housing to moderate- and lower-income households.

Amount of Fee—CGC Section 66006(b)(1)(B):

Type FY 2022-23 FY 2023-24
Commercial/Entertainment/Hotel/Retail
First 25,000 SF $1.65/net SF $2.00/net SF
25,000+ SF $3.27/net SF $3.50/net SF
High-Tech/Industrial/Office
First 10,000 SF $15.28/net SF $16.00/net SF
10,000+ SF $30.57/net SF $33.00/net SF

Beginning and Ending Balances, Amount of Fees Collected, and Interest Earned —CGC Section 66006(b)(1)(C and D):

Beginning Balance, July 1, 2022 $41,244,721
Housing Impact Fees $5,000,000
Capital Project Refunds 1,606,272
Investment Earnings 1,106,554
Other Revenue 123,361
Total Unaudited Revenues 7,836,187
Total Unaudited Expenditures (5,947,010)
Unexpended Balance 43,133,898
Reserved by City Council for
Affordable Housing Projects:

(25,194,860)
Available Balance, June 30, 2023 $17,939,038

During Fiscal Year 2022-23, there were $5.0 million in fees deposited, $1.6 million of capital project refunds, $1.1 million of investment earnings, $123,361 of other revenue , and $5.9 million in expenditures, which includes $5.0 million transfer to the Local Housing Trust Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 5 of 23 ends

Fund. As of June 30, 2023, there is an unexpended balance of $43.1 million, $25.2 million of which has been reserved for the projects below:

Charities Housing project at 1265 Montecito Avenue—$15.2 million

Danco Communities project at 96 West El Camino Real—$8.0 million

Mountain View Lot 12 project—$2.0 million

Identification of Each Public Improvement on Which Fees Were Expended in Fiscal Year 2022-23—CGC Section 66006(b)(1)(E) (dollars in thousands):

The table below shows active project(s) that have been partially or fully funded by Housing Impact (HI) Fees.

Total
Project
Cost

FY 2022-23 HI
Expenditures
Life to Date
(LTD) HI
Expenditures

Total HI
Funding
% of Project
Funded by
HI Fee
Lease/Purchase of
Evelyn Lot
(19-69) $15,041 $ 11,038

$11,189

$15,041 100.0%
Administration of
HI Program and
Fees (1) N/A 281

N/A

N/A 100.0%
$11,319 $ 11,189 $15,041
_____________________
(1) Administration costs are annual costs.

Identification of Approximate Date by Which Construction will Commence Once Sufficient Funds Have Been Collected—CGC Section 66006(b)(1)(F):

The City completed the purchase of the Evelyn Lot property in 2023.

Description of Each Interfund Transfer or Interfund Loan Made from the Fund —CGC Section 66006(b)(1)(G):

During Fiscal Year 2022-23, a $5 million transfer was made to the Local Housing Trust Fund.

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 6 of 23 ends

Amount of Refunds Made—CGC Section 66006(b)(1)(H):

During Fiscal Year 2022-23, a $1.6 million capital project refund was made to this fund from the project listed below and referenced in CGC Section 66006(b)(1)(F) above:

19-69—Lease/Purchase of Evelyn Lot

Findings for Amounts Remaining Unexpended—CGC Section 66001(d)(1):

The first HI Fee was deposited February 13, 2003 and, in accordance with CGC Section 66001(d)(1), the City is required to make its next five -year required finding as of June 30, 2023. As of June 30, 2023, this fund has the unexpended balance of $17.9 million. The next reporting is due on June 30, 2028. As previously mentioned, for ease of reporting after the initial five-year finding, the City provides information on an annual basis.

(A) Identify the purpose to which the fee is to be put.

The HI funds will be used to fund additional moderate- and lower-income housing in Mountain View, including the affordable housing project at 1265 Montecito Avenue, and eventually on affordable developments on Parking Lot 12 and the former VTA Park and Ride Lot on Evelyn Avenue and Pioneer Way and 96 West El Camino Real.

(B) Demonstrate a reasonable relationship between the fee and the purpose for which it is charged.

A reasonable relationship exists between the HI Fees and the purpose for which said fees were charged as demonstrated by the Jobs -Housing Nexus Study (Nexus Study), dated November 2012, and prepared by Keyser Marston Associates, Inc. The Nexus Study demonstrates that a reasonable relationship exists between the need for affordable housing and the impacts of new commercial office development within the City. A reasonable relationship also exists between the fee’s use and the impacts of new commercial and office development because the developments will create new jobs. The Nexus Study demonstrates that some of the new jobs created w ould be filled by lower-income workers in need of affordable housing. This type of affordable housing continues to be in short supply within Mountain View. The HI Fee will be used to help increase the supply of affordable housing in the City to meet the increased need generated by new commercial and office developments.

(C) Identify all sources and amounts of funding anticipated to complete financing of incomplete improvements (dollars in millions).

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 7 of 23 ends

1265 Montecito Avenue
$16.0 City of Mountain View HI Funds

18.0 County of Santa Clara Measure A

31.08 Tax Credit Equity

9.51 Conventional Loan

0.82 FHLB – Affordable Housing Program

5.48 Contributed Developer Fee

0.88 Deferred Developer Fee

5.47 Fee Waivers

1.46 Deferred Interest from City and County
$88.70 Total Funding

(D) Designate the approximate dates on which the funding referred to in Subparagraph (C) is expected to be deposited into the appropriate account or fund.

The 1265 Montecito Avenue project will be developed and managed by Charities Housing. This project will be funded by the City’s Housing Notice of Funding Availability (NOFA) (HI) funds and County of Santa Clara Measure A funds as well as low-income housing tax credits and a permanent loan. The HI funds detailed above have been deposited into the fund and were reserved for this project by the City Council. None of the outside funding sources will be deposited into the City’s account.

All outside funding sour ces will sign loan agreements with the developer and will disburse loan proceeds by reimbursing the developer during the construction phase.

The development was approved by City Council on December 6, 2022.

3. Rental Housing Impact Fund

Description of the Type of Fee—CGC Section 66006(b)(1)(A):

On December 11, 2012, Council adopted Resolution No. 17748 , allowing for an RHI Fee to be imposed on all new market -rate rental housing developments , effective February 9, 2013. With Council approval, a developer may pay the fee or choose an equivalent alternative to the fee that may include construction of affordable housing units, dedication of land, or other equivalent options. The RHI Fee and any investment earnings shall be used for increasing and improving the supply of moderate- to very low-income rental housing.

On February 13, 2018, Council adopted Resolution No. 18196, which rescinded the RHI Fee effective April 28, 2018. State legislation, AB 1505, restored the ability for cities to implement inclusionary housing for rentals in response to Palmer/Sixth Street Properties, L.P. v. City of Los Angeles, which had caused cities, including Mountain View, to suspend their rental inclusionary housing programs. AB 1505 went into effect January 1, 2018, and the City resumed its inclusionary housing program on rentals. As the fee is not due until Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 8 of 23 ends

occupancy of the project, and to ensure collection of the RHI fee on projects approved or project applications deemed complete before April 28, 2018, the City reinstated the fee for these projects on June 19, 2018, with the adoption of Resolution No. 18922. All such projects have paid the RHI Fee, and the RHI Fee was eliminated in Fiscal Year 2021-22 as of August 22, 2021. The City will continue to report the RHI Fees annually until they are fully spent.

Amount of Fee—CGC Section 66006(b)(1)(B):

For Fiscal Year 2021-22, the fee was $19.82 per net new habitable square foot and was eliminated as of August 22, 2021.

Beginning and Ending Balances, Amount of Fees Collected, and Interest Earned —CGC Section 66006(b)(1)(C and D):

Beginning Balance, July 1, 2022 $3,287,203
Rental Housing Impact Fees $ -0-
Investment Earnings 66,736
Total Unaudited Revenues 66,736
Total Unaudited Expenditures -0-
Unexpended Balance 3,353,939
Reserved by City Council for
Affordable Housing Projects:

(888,000)
Available Balance, June 30, 2023 $2,465,939

During Fiscal Year 2022-23, there were $ 66,736 of investment earnings, and $888,000 reserved for housing projects . As of June 30, 202 3, there is an unexpended balance of $3.4 million, $888,000 of which is reserved for the Crestview Hotel Conversion Project.

Identification of Each Public Improvement on Which Fees were Expended in Fiscal Year 2022-23—CGC Section 66006(b)(1)(E):

No RHI Fees were expended during Fiscal Year 2022-23.

Identification of Approximate Date by Which Construction will Commence Once Sufficient Funds Have Been Collected—CGC Section 66006(b)(1)(F):

The RHI funds will be used to increase and improve the supply of moderate - to very low- income rental housing when a new rental housing project is in the development pipeline.

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 9 of 23 ends

Description of Each Interfund Transfer or Interfund Loan Made from the Fund—CGC Section 66006(b)(1)(G):

No Interfund Transfers or Interfund Loans were made from this fund.

Amount of Refunds Made—CGC Section 66006(b)(1)(H):

No refunds were made from this fund.

Findings for Amounts Remaining Unexpended—CGC Section 66001(d)(1):

The first RHI Fee was deposited February 12, 2013 and, in accordance with CGC Section 66001(d)(1), the City is required to make its next five -year required finding as of June 30, 2023. As of June 30, 2023, this fund has an unexpended balance of $2.5 million. The next reporting is due June 30, 2028. As previously mentioned, for ease of reporting after the initial five-year finding, the City provides information on an annual basis.

(A) Identify the purpose to which the fee is to be put.

The RHI Fees will be used to fund additional moderate- and lower-income housing in Mountain View.

(B) Demonstrate a reasonable relationship between the fee and the purpose for which it is charged.

A reasonable relationship exists between the RHI Fees and their use to develop affordable housing as demonstrated by the Nexus -Based Affordable Housing Fee Analysis, dated September 29, 2011, and the memorandum entitled “Draft Technical Memorandum,” dated November 29, 2012, and prepared by Economic and Planning Systems, Inc. (together the “Nexus Study”). The Nexus Stud y demonstrated that to fully mitigate the impacts of new rental housing development on the need for affordable housing, a RHI Fee on new market -rate rental development would be needed.

The Nexus Study demonstrates that a reasonable relationship exists be tween the need for affordable housing and the deleterious impacts of new market -rate rental housing development within the City. A reasonable relationship also exists between the fee’s use and the impacts of new market -rate rental housing development.

Development of new rental housing results in more residents living in the City. The residents who move into new rental housing developments will increase the demand for services provided by the public and private sectors. Some of the public - and Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 10 of 23 ends

private-sector employees needed to meet the needs of the new City residents earn incomes that only allow these employees to afford housing for moderate low -, very low-, and extremely low-income households. This type of affordable housing is in very short supply wit hin Mountain View and other available housing subsidies are inadequate to meet the need created by new rental housing developments. The RHI Fee will be used to help increase the supply of affordable housing in the City to meet the increased need generated by new rental housing developments.

(C) Identify all sources and amounts of funding anticipated to complete financing of incomplete improvements (dollars in millions).

Crestview Hotel
$7.4 CDBG/HOME

0.9 City of Mountain View RHI Funds

0.8 Federal Grants
$9.1 Total Funding

(D) Designate the approximate dates on which the funding referred to in Subparagraph (C) is expected to be deposited into the appropriate account or fund.

The Crestview Hotel project will be developed by Jamboree Housing. On January 26, 2021, the City of Mountain View partnered with the County of Santa Clara to convert the Crestview Hotel into residential units to meet various housing needs and priorities, serving extremely low - and low -income households. This project was funded by the City’s Community Development Block Grant (CDBG) and HOME funds, the County of Santa Clara Measure A funds, and the California Department of Housing and Community Development Project Homekey funds. The City sources of funding have been reserved for this project by the City Council. All outside funding sources will sign loan and regulatory agreements with the developer and will disburse loan proceeds by reimbursing the developer during the rehabilitation process. The project is expected to be completed by April 2024.

4. North Bayshore Development Impact Funds

Description of the Type of Fee—CGC Section 66006(b)(1)(A):

The North Bayshore Precise Plan (NBPP), adopted November 25, 2014, identified significant transportation and water and sewer utility improvements necessary to accommodate the anticipated development. An important component of funding for the required infrastructure improvements to support this development is a development impact fee.

Environmental Planning Systems prepared the City’s North Bayshore Development Impact Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 11 of 23 ends

Fee Nexus Study, dated February 3, 2016, with technical assistance from Fehr+Peers (transportation consultants) and Shaaf & Wheeler (consulting civil engineers). On February 23, 2016, the City Council considered the North Bayshore Development Impact Fee Nexus Study and adopted the NBS Development Impact Fees with an effective date of April 23 , 2016. The fees in effect during Fiscal Year 2022-23 and the fees approved by City Council for Fiscal Year 2023-24 are detailed below.

Amount of Fee—CGC Section 66006(b)(1)(B):

FY 2022-23 FY 2023-24
Hotel:

Transportation (Guest Rooms) $2,415 $2,756
Water (Guest Rooms) $4,743 $5,412
Sewer (Guest Rooms) $854 $974
Office/R&D:

Transportation (SF net new gross floor area) $27.11 $30.93 Water (SF net new gross floor area) $7.66 $8.74
Sewer (SF net new gross floor area) $1.43 $1.63
Retail:

Transportation (SF net new gross floor area) $2.83 $3.23 Water (SF net new gross floor area) $0.01 $0.01
Sewer (SF net new gross floor area) $0.95 $1.08

Each type of improvement (transportation, water, and sewer) has a specific fee and is posted to a separate subfund in accordance with development impact fee requirements.

Below are separate reportings of the three NBS Development Impact fees by subfund:

a. North Bayshore Development Impact Fund—Transportation

Beginning and Ending Balances, Amount of Fees Collected, and Interest Earned —CGC Section 66006(b)(1)(C and D):

Beginning Balance, July 1, 2022 $14,741,366
Transportation: North Bayshore Development
Impact Fees

$ -0-
Capital Project Refunds 32,429
Investment Earnings 577,013
Total Unaudited Revenues 609,442
Total Unaudited Expenditures (385,000)
Unexpended/Available Balance, June 30, 2023 $14,965,808

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 12 of 23 ends

During Fiscal Year 202 2-23, there were no fees deposited, $32,429 in capital project refunds, $155,782 in investment earnings, and $ 385,000 in expenditures. As of June 30, 2023, there is an unexpended/available balance of $ 15 million. Transportation -related capital projects previously funded by these fees are listed in the following section , and the funds will be expended over the life of the capital project.

Identification of Each Public I mprovement on Which Fees Were Expended in Fiscal Year 2022-23—CGC Section 66006(b)(1)(E) (dollars in thousands):

The table below shows active project(s) that have been partially or fully funded by North Bayshore Development Impact—Transportation Fees.

Total
Project
Cost

FY 2022-23
Expenditures

LTD
Expenditures

Total NBS—
Transportation
Funding
% of Project
Funded by NBS—
Transportation
Acquisition Plymouth
Street Realignment
(18-70)

$28,540

$69

$28,540

$13,370

46.8%
NB Shoreline Blvd/101
Off-Ramp
Realignment,
Design (19-59)

6,785

338

2,121

6,785

100.0%
Shoreline at 101
Ped/Bike
Overcrossing,
Construction (20-38)

17,917

-0-

-0-

3,848

21.5%
Landings Frontage Road
(Landings to
Permanente
Creek)(22-28)

3,420

-0-

-0-

2,790

81.6%
TOTAL $407 $30,661 $26,793

Identification of Approximate Date by Which Construction Will Commence Once Sufficient Funds Have Been Collected—CGC Section 66006(b)(1)(F):

The Acquisition of Real Property for the Plymouth Street Realignment (18 -70) project was approved as a midyear Fiscal Year 2017 -18 Capital Improvement Project and partially funded with $13,369,650 from the NBS Develop ment Impact Fund. Negotiations began in summer 2017, and the Purchase and Sale Agreement was signed with Google LLC (Google) on February 14, 2018. Escrow closed on August 26, 2021 and the project was closed June 2023.

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 13 of 23 ends

The NB Shoreline Blvd/101 Off-Ramp Realignment, Design (19-59) project was fully funded from the NBS Development Impact Fund. Project design began in August 2019 and should be complete by winter 2023.

The Shoreline at 101 Ped/Bike Overcrossing, Construction (20 -38), project was adopted with the 2019-20 Capital Improvement Program (CIP) and partially funded with $3,848,000 from the NBS Development Impact Fund. This project is part of the Shoreline Corridor Study and will construct a bicycle and pedestrian bridge parallel and adjacent to Sh oreline Boulevard over U.S. 101. Preliminary project design began in summer 2018 and is temporarily on hold until spring/summer 2024 pending developer project application.

Landings Frontage Road (Landings to Permanente Creek), Project 22-28, was adopted with the Fiscal Year 2021 -22 CIP and partially funded with $2,790,000 from the NBS Development Impact Fund. This project will be designed and constructed by the development at 1860 -2159 Landings Drive (800,000 square foot office building). The project is currently on hold by the developer.

Description of Each Interfund Transfer or Interfund Loan Made from the Fund—CGC Section 66006(b)(1)(G):

During Fiscal Year 2022-23, a $385,000 Interfund Transfer was made to Capital Projects for the project listed below and referenced in CGC Section 66006(b)(1)(F) above:

19-59—NB Shoreline Blvd/101 Off-Ramp Realignment

Amount of Refunds Made—CGC Section 66006(b)(1)(H):

During Fiscal Year 2022-23, a $32,429 capital project refund was made to this fund from the project listed below and referenced in CGC Section 66006(b)(1)(F) above:

18-70—Acquisition of Real Property for the Plymouth Street Realignment

Findings for Amounts Remaining Unexpended—CGC Section 66001(d)(1):

The first NBS Development Impact Fee for transportation was deposited in September 2014 and, in accordance with CGC Section 66001(d)(1), the City is required to make its next five- year required finding as of June 30, 2025. However, the City is providing information as of June 30, 2023 regarding the unexpended balance of $15 million. As previously mentioned, for ease of reporting after the initial five -year finding, the City provides information on an annual basis.

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 14 of 23 ends

(A) Identify the purpose to which the fee is to be put.

The purpose of this fee is to provide revenue that the City can use to help mitigate the impact new development will have on the existing transportation. Fee revenue will be used as a funding source for transportation improvements in the City and specifically the Shoreline Regional Park Community, particularly those improvements that will need to be made in North Bayshore to facilitate the growth in daily service population.

(B) Demonstrate a reasonable relationship between the fee and the purpose for which it is charged.

A reasonable relationship exists between the fee and the purpose for which said fees are charged. New development in North Bayshore will contribute an additional burden to Mountain View’s transportation and utility infrastructure. Fe e revenues that are collected from this new development will be spent to directly offset this burden by increasing the capacity of the existing transportation infrastructure as well as construction of new infrastructure to accommodate the projected growth.

(C) Identify all sources and amounts of funding anticipated to complete financing of incomplete improvements.

The current unexpended/available balance of $ 15 million in the NBS Development Impact Fund—Transportation will be programmed into future transportation-related projects in the North Bayshore Area.

(D) Designate the approximate dates on which the funding referred to in Subparagraph (C) is expected to be deposited into the appropriate account or fund.

The funds will be deposited into a new ca pital improvement project when approved and appropriated by Council.

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 15 of 23 ends

b. North Bayshore Development Impact Fund—Water

Beginning and Ending Balances, Amount of Fees Collected, and Interest Earned —CGC Section 66006(b)(1)(C and D):

Beginning Balance, July 1, 2022 $5,100,525
Water: North Bayshore Development Impact
Fees

$ -0-
Capital Project Refunds 2,885
Investment Earnings 229,654
Total Unaudited Revenues 232,539
Total Unaudited Expenditures (984,000)
Unexpended/Available Balance, June 30, 2023 $4,349,064

During Fiscal Year 2022-23, there were no fees deposited, $2,885 in capital project refunds, $229,654 in investment earnings, and $984,000 in expenditures. As of June 30, 2023, there is an unexpend ed/available balance of $ 4.3 million. Water infrastructure -related capital projects, previously funded by these fees, are listed in the following section, and the funds will be expended over the life of the capital project.

Identification of Each Public Improvement on Which Fees Were Expended in Fiscal Year 2022-23—CGC Section 66006(b)(1)(E) (dollars in thousands):

The table below shows active project(s) that have been partially or fully funded by North Bayshore Development Impact—Water Fee.

Total
Project
Cost

FY 2022-23
Expenditures

LTD
Expenditures
Total
NBS—
Water
Funding
% of Project
Funded by
NBS—
Water
Miscellaneous Water
Main/Service Line
Replacement (17-21)

$3,509

$582

$3,509

$ 28

0.6%
Shoreline Boulevard
Interim Bus Lane and
Utility Improvements,
Construction (18-43)

$16,402

684

3,118

1,414

8.6%
Water & Sewer Main
Replacement 101
at Two Locations,
Construction (20-41)

$19,779

3,949

5,760

5,971

30.2%
Total $5,215 $12,387 $7,413

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 16 of 23 ends

Identification of Approximate Date by Which Construction Will Commence Once Sufficient Funds Have Been Collected—CGC Section 66006(b)(1)(F):

The Annual Water Main/Service Line Replacement project (17-21) was adopted in Fiscal Year 2016-17. On March 9, 2021, the City Council approved transferring the balance of the 2020-21 Annual Water Main/Service Line Replacement project to this capital project, including the North Bayshore Development Impact—Water Fee funding of $28,000. These funds were used to complete the Rock Street and Spring Street Water Main Replacement.

Project design began in summer 2018 and was completed in spring 2021. Project construction began in November 2021 and was completed as of June 2023.

The Shoreline Boulevard Interim Bus Lane and Utility Improvements, Construction (18 -43) project was approved with the Fiscal Year 2017 -18 budget , and construction began in March 2021. The project will construct the interim reversible bus lane along with bicycle and pedestrian improvements along Shoreline Boulevard from Middlefield Road to Pear Avenue, including impr ovements to replace water and sewer mains along Shoreline Boulevard from Middlefield Road to south of U.S. 101. The construction phase is under way and estimated to be complete in 2024.

The Water & Sewer Main Replacement 101 at Two Locations, Construction (20-41) project was adopted with the 2019 -20 CIP and partially funded with $5,627,000 from NBS Development Impact—Water funds. In Fiscal Year 2020 -21, $640,000 of this funding was returned as a capital project refund (and replaced with Wastewater Debt P roceeds), reducing the funding from NBS Development Impact —Water funds to $4,987,000. This project will construct the replacement of a new water and sewer main to cross under U.S. 101 south of Shoreline Boulevard as well as a new water main under U.S. 101 at Macon Avenue to improve water service reliability to North Bayshore. Construction for the Macon Avenue water pipeline began in May 2020 and was completed and accepted by the City Council in December 2020. Construction for the water and sewer lines crossing U.S. 101 is in the bidding phase and anticipated to be completed at the end of 2024.

Description of Each Interfund Transfer or Interfund Loan Made from the Fund—CGC Section 66006(b)(1)(G):

During Fiscal Year 2022-23, a $984,000 Interfund Transfer was made to Capital Projects for the project listed below and referenced in CGC Section 66006(b)(1)(F) above:

At two locations, Water and Sewer Main Replacement Crossing U.S. 101, Construction, Project 20-41.

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 17 of 23 ends

Amount of Refunds Made—CGC Section 66006(b)(1)(H):

During Fiscal Year 2022-23, a $2,885 capital project refund was made to this fund from the project listed below and referenced in CGC Section 66006(b)(1)(F) above:

17-21—Annual Water Main/Service Line Replacement

Findings for Amounts Remaining Unexpended—CGC Section 66001(d)(1):

The first NBS Development Impact Fee for water improvements was deposited February 28, 2017 and, in accordance with CGC Section 66001(d)(1), the City is required to make all findings as of June 30, 2022, the end of the fifth year following deposit of the first fee into the NBS Development Impact Fund—Water.

(A) Identify the purpose to which the fee is to be put.

The purpose of this fee is to provide revenue that the City can use to help mitigate the impact new development will have on the existing utility infrastructure. Fee revenue will be used as a funding source for utility improve ments in the City and specifically the Shoreline Regional Park Community, particularly those improvements that will need to be made in North Bayshore to facilitate the growth in the community.

(B) Demonstrate a reasonable relationship between the fee and the purpose for which it is charged.

A reasonable relationship exists between the fee and the purpose for which said fees are charged. New development in North Bayshore will contribute an additional burden to Mountain View’s utility infrastructure. Fee revenues that are collected from this new development will be spent to directly offset this burden by increasing the capacity of the existing utility infrastructure as well as construction of new infrastructure to accommodate the projected growth.

(C) Identify all sources and amounts of funding anticipated to complete financing of incomplete improvements.

The current unexpended balance of $ 4.4 million in the NBS Development Impact Fund—Water will be programmed into future water -related project s in the No rth Bayshore Area.

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 18 of 23 ends

(D) Designate the approximate dates on which the funding referred to in Subparagraph (E) is expected to be deposited into the appropriate account or fund.

The funds will be deposited into a new capital improvement project when approved and appropriated by Council.

c. North Bayshore Development Impact Fund—Sewer

Beginning and Ending Balances, Amount of Fees Collected, and Interest Earned —CGC Section 66006(b)(1)(C and D):

Beginning Balance, July 1, 2022 $1,535,711
Sewer: North Bayshore Development Impact
Fees

$ -0-
Capital Project Refunds 27,358
Investment Earnings 39,493
Total Unaudited Revenues 66,851
Total Unaudited Expenditures (769,000)
Unexpended/Available Balance, June 30, 2023 $833,562

During Fiscal Year 202 2-23, there were no fees deposited, $27,358 in capital project refunds, $39,493 in investment earnings, and $769,000 in expenditures. As of June 30, 2023, there is an unexpended/available balance of $833,562. Sewer infrastructure-related capital projects previously funded by these fees are listed in the following section, and the funds will be expended over the life of the capital project.

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 19 of 23 ends

Identification of Each Publi c Improvement on Which Fees Were Expended in Fiscal Year 2022-23—CGC Section 66006(b)(1)(E) (dollars in thousands):

The table below shows active project(s) that have been partially or fully funded by North Bayshore Development Impact—Sewer Fees.

Total
Project
Cost

FY 2022-23
Expendi-
tures

LTD
Expendi-
tures
Total
NBS—
Sewer
Funding
% of Project
Funded by
NBS—
Sewer
Shoreline Boulevard
Interim Bus Lane and
Utility Improvements,
Construction (18-43)

$16,402

$684

$3,118

$269

1.6%
Miscellaneous Storm/
Sanitary Sewer Main
Replacement (20-22)

1,649

-0-

-0-

132

8.0%
Water and Sewer Main
Replacement Crossing
U.S. 101 (at South of
Shoreline Boulevard
and Macon Avenue),
Construction (20-41)

19,779

3,949

5,760

769

3.9%
Interceptor Force Trunk
Rehab, Construction,
Phase II (20-42)

3,410

2,492

2,735

222

6.5%
TOTAL $7,125 $11,613 $1,392

Identification of Approximate Date by Which Construction will Commence Once Sufficient Funds Have Been Collected—CGC Section 66006(b)(1)(F):

Shoreline Boulevard Interim Bus Lane and Utility Improvements, Phase I Construction, Project 18-43, was approved with the Fiscal Year 2017 -18 budget, and construction began in March 2021. The status of this project is identified in the North Bayshore Development Impact—Water section of this report.

The annual Miscellaneous Storm/Sanitary Sewer Main Replacement , Project 20-22, was adopted with the 2019-20 CIP and partially funded with $132,000 from NBS Development Impact—Sewer funds. The portion of the project funded by NBS Development Impact - Sewer funds will be proposed to be returned to the fund in the upcoming CIP budget process.

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 20 of 23 ends

Water and Sewer Main Replacement Crossing U.S. 101, Construction, Project 20-41, South of Shoreline B oulevard and Macon Avenue, was adopted with the 2019 -20 CIP and is partially funded with $769,000 from NBS Development Impact —Sewer funds. The status of this project is identified in the North Bayshore Development Impact —Water section of this report.

Interceptor Force Trunk Rehab, Construction, Phase II, Project 20-42, was adopted with the 2019-20 CIP and was partially funded with $222,000 from NBS Development Impact — Sewer funds. This project will rehabilitate approximately 1,090’ of a 42” interceptor force trunk main just downstream of the Shoreline Sewage Pump Station and rehabilitate an existing manhole adjacent to Michaels at Shoreline Restaurant. Project construction began in fall 2021 and has been completed.

Description of Each Interfund Transfer or Interfund Loan Made from the Fund—CGC Section 66006(b)(1)(G):

During Fiscal Year 2022-23, a $769,000 transfer was made to Capital Projects for the Water and Sewer Main Replacement Crossing U.S. 101 (at South of Shoreline Boulevard and Macon Avenue), Construction (20-41), project.

Amount of Refunds Made—CGC Section 66006(b)(1)(H):

No refunds were made from this fund.

Findings for Amounts Remaining Unexpended—CGC Section 66001(d)(1):

The first NBS Development Impact Fee for sewer improvements was deposited February 28, 2017 and, in accordance with CGC Section 66001(d)(1), the City is required to make all findings as of June 30, 2022, the end of the fifth year following deposit of the first fee into the NBS Development Impact Fund—Sewer.

(A) Identify the purpose to which the fee is to be put.

The purpose of this fee is to provide revenue that the City can use to help mitigate the impact new development will have on the existing utility infrastructure. Fee revenue will be used as a funding source for utility improvements in the City and specifi cally the Shoreline Regional Park Community, particularly those improvements that will need to be made in North Bayshore to facilitate the growth in the community.

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 21 of 23 ends

(B) Demonstrate a reasonable relationship between the fee and the purpose for which it is charged.

A reasonable relationship exists between the fee and the purpose for which said fees are charged. New development in North Bayshore will contribute an additional burden to Mountain View’s utility infrastructure. Fee revenues that are collected from this new development will be spent to directly offset this burden by increasing the capacity of the existing utility infrastructure as well as construction of new infrastructure to accommodate the projected growth.

(C) Identify all sources and amount s of funding anticipated to complete financing of incomplete improvements.

The current unexpended balance of $833,562 in the NBS Development Impact Fund— Sewer will be programmed into future sewer -related projects in the North Bayshore Area.

(D) Designate the approximate dates on which the funding referred to in Subparagraph (C) is expected to be deposited into the appropriate account or fund.

The funds will be deposited into a new capital improvement project when approved and appropriated by Council.

5. Sewer Development Impact Fund

Description of the Type of Fee—CGC Section 66006(b)(1)(A):

This fee is assessed as a condition for new developments in order to mitigate a future deficiency in specific areas beyond the planned capacity of the sewer system.

Amount of Fee—CGC Section 66006(b)(1)(B):

The fee is the developer’s contribution for their proportional share of the required infrastructure improvements due to the developer’s project exceeding the capacity of the sewer system anticipated in the 2030 General Plan and is required as a condition of development.

Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 22 of 23 ends

Beginning and Ending Balances, Amount of Fees Collected, and Interest Earned —CGC Section 66006(b)(1)(C and D):

Beginning Balance, July 1, 2022 $466,020
Sewer Development Impact Fees $201,619
Investment Earnings 13,054
Total Unaudited Revenues 214,674
Total Unaudited Expenditures -0-
Unexpended/Available Balance, June 30, 2023 $680,694

During Fiscal Year 2022-23, there were $201,619 in fees deposited, $13,054 in investment earnings, and no expenditures. As of June 30, 202 3, there is an unexpended/available balance of $680,694.

Identification of Each Public Improvement on Which Fees Were Expended in Fiscal Year 2022-23—CGC Section 66006(b)(1)(E):

No Sewer Development Impact Fees were expended during Fiscal Year 2022-23 for sewer- related capital improvements.

Identification of Approximate Date by Which Construction will Commence Once Sufficient Funds Have Been Collected—CGC Section 66006(b)(1)(F):

When it is necessary to increase the capacity of the system and a sewer infrastructure improvement project is adopted for the specific areas of the City in which fees have been collected, the fees collected for the specific area will be utilized for project funding.

Description of Each Interfund Transfer and Interfund Loan Made from the Fund —CGC Section 66006(b)(1)(G):

No Interfund Transfers or Interfund Loans were made from this fund.

Amount of Refunds Made—CGC Section 66006(b)(1)(H):

No refunds were made from this fund.

Findings for Amounts Remaining Unexpended—CGC Section 66001(d)(1):

The first Sewer Development Impact Fee was deposited November 14, 2013 and, in accordance with CGC Section 66001(d)(1), the City is required to make its next five -year required finding as of June 30, 2024. However, the City is providing information as of Fiscal Year 2022-23 Annual Compliance Report for
Development Impact Fees
November 7, 2023

Page 23 of 23 ends

June 30, 2023, regarding the unexpended balance of $ 680,694. As previously mentioned, for ease of reporting after the initial five -year finding, the City provides information on an annual basis.

(A) Identify the purpose to which the fee is to be put.

The fee will be used to mitigate a future deficiency in specific areas beyond the planned capacity of the sewer system.

(B) Demonstrate a reasonable relationship between the fee and the purpose for which it is charged.

A reasonable relationship exists between the fee and the purpose for which said fees are charged. The fee is charged as a condition of new development when a project exceeds the capacity of the sewer system anticipated in the 2030 General Plan. The funds generated from this fee will be used to mitigate the impacts to the sewer system caused by the new development project.

(C) Identify all sources and amounts of funding anticipated to complete financing of incomplete improvements.

The current unexpended/available balance of $ 680,694 in the Sewer Development Impact Fund will be programmed into future sewer projects.

(D) Designate the approximate dates on which the funding referred to in Subparagraph (C) is expected to be deposited into the appropriate account or fund.

The funding will be transferred to Capital Projects when identified and approved by the City Council.

CONCLUSION

The development impact funds discussed in this report comply with the requirements of CGC Section 66001 for annual reporting regarding the collection and use of development fees.

EY-GZ-DR/1/FIN
575-11-07-23M

cc: APWD—Arango, APWD—Au, APWD—Skinner, HD, SMA—Goedicke, SMA—Doan