Attachment 2

Page 1 of 7 ends

Active CIP Projects with Bike and Pedestrian Improvements

Project Title (#CIP) Bike/Pedestrian Element Status Anticipated Construction Timeline Comments
East Whisman Area
Transit-Oriented
Development
Improvements, Phase II:

Ellis Street Improvements
(16-48)
• Pavement resurfacing
• High visibility crosswalk and
shortened crosswalks.
• Multi-use path on the west side of
Ellis Street between Fairchild Drive
and Manila Avenue.

Design Begin: Spring 2025
Complete: Spring 2026
Scope adjustment due to
Google project rescheduling.

Shoreline Boulevard Bus
Lane and Utility
Improvements
(16-58 and 18-43)
• Pavement resurfacing
• New Class IV protected bike lanes
• New sidewalk
• Protected Intersections at
Middlefield, Terra Bella, and Pear
Avenue

Design Phase 1
Begin: May 2025
Complete: Summer
2026

Charleston Road
Improvements
(16-59 and 19-34)
• Pavement resurfacing
• New Class IV protected bike lanes
• New sidewalk
• Protected intersections at Landings
Ave and Alta Ave

Design Begin: Summer 2025
Complete: Summer
2026
Alta Avenue to Salado Drive
Shoreline Boulevard at
Highway 101 Bicycle and
Pedestrian Bridge
(16-60 and 20-38)

• Two-way cycle track and walkway
bridge between Terra Bella and
Pear Avenue over Highway 101.

On Hold Pending progress of North
Bayshore development.

Shoreline/Church/Latham
Intersection Signal
Improvements
(17-27, 19-27, 20-27 and
21-27)
• Protected left turn phases to
eliminate vehicles/pedestrian
conflicts.
• Reconstruct median for more
available crosswalk area.

Construction Begin: Summer 2024
Complete: Early 2025
Partially funded with Vehicle
License Fee—2010 Measure
B funds.

Page 2 of 7 ends

Project Title (#CIP) Bike/Pedestrian Element Status Anticipated Construction Timeline Comments
Rengstorff Avenue Grade
Separation
(17-37, 22-27)
• Pavement reconstruction
• Class IV bike lanes on Rengstorff
between Stanford and Central
Expressway
• ADA compliant sidewalk and
pathway
• Bike/pedestrian overcrossing
between Rengstorff Park and the
west side of Rengstorff Avenue
• High visibility crosswalks

Design Begin: 2026 (pending
funding availability)
Complete: 2028
Measure B funded.

Stierlin Road Bicycle and
Pedestrian Improvements
(17-41)
• Protected intersection
• Buffered Bike Lane
• High visibility crosswalks
• Mid-block pedestrian crossing
• Improved lighting, traffic calming

Design Begin: Fall 2024
Complete: Spring 2025
Funded by federal grant.

Includes Shoreline Boulevard
between Montecito Avenue
and West Middlefield Road.

Rengstorff/Latham Signal
Improvements
(18-27 and 22-15)

• Protected left turn phases to
eliminate vehicles/pedestrian
conflicts.
• High visibility crosswalks.
• Bike enhancements include green
bike skip boxes approaching along
Rengstorff, and a bike crossing at
the intersection along the west
side of Rengstorff.

Begin: Fall2024
Complete: Spring 2025
Partially funded with Vehicle
License Fee—2010 Measure
B funds.

Stevens Creek Trail
Extension
(18-39, 20-50)

• Trail extension from
Dale/Heatherstone to Remington

Preliminary Begin: TBD
Complete: TBD

Page 3 of 7 ends

Project Title (#CIP) Bike/Pedestrian Element Status Anticipated Construction Timeline Comments
Colony Street Connection
to Permanente Creek Trail
(18-48)
• Trail connection and access at
Colony Street
• Bike/pedestrian overcrossing over
Permanente Creek

Construction Complete: Spring 2024
Transit Center Grade
Separation and Access
Project
(18-65 and 21-35)
• Bike/pedestrian undercrossings
between northside of Central
Expressway and Transit Center and
Downtown.
• Bikeways and high-visibility
crosswalks within project limits.

Design Begin: TBD Measure B funded.

Bernardo Avenue
Undercrossing Feasibility
Study
(18-69)
• Bike/pedestrian undercrossing of
Caltrain rail and Central
Expressway
• Bicycle access improvements
within 500’ of approaches
Preliminary
Design and
Environmental
Begin: 2025
Complete: 2027
Measure B funded. Caltrain
is project lead for design and
construction. Collaboration
between Mountain View,
Sunnyvale, VTA, Caltrain and
the County.

Street Reconstruction
(19-48)
• Pavement reconstruction
• New sidewalk
Construction Complete: Spring 2024 Park and Sonia Drive, 300’ of Sewer Rehab added to
scope.

Cross Culvert Removal
(19-49)
• High visibility crosswalks
• ADA-compliant curb ramps.
• Removal of existing cross culverts.

Design Begin: Spring 2025
Complete design: Early
2026
Dana Street between Oak
Street and Franklin Street
El Monte Corridor
Improvements
(19-61 and 21-38)
• Complete Streets Study
• New and enhanced crosswalks
with lighting, striping, and signage.
• Enhanced bike facility.
• ADA compliant curb ramps.

Design Begin: Summer 2025
Complete: Spring 2026

Page 4 of 7 ends

Project Title (#CIP) Bike/Pedestrian Element Status Anticipated Construction Timeline Comments
SR 237/Middlefield Road
Interchange
Improvements
(19-65)
• ADA-compliant curb ramps
• High visibility crosswalks
• Class IV bikeways on Middlefield
Road between Ferguson Drive and
SR 237 eastbound on- and off-
ramps.

Preliminary
Design
Begin: 2026
Complete: TBD
Measure B funded.

Miramonte Avenue
Pavement Improvements
(20-01)
• Class II bike lanes on Miramonte
between Cuesta and Hans
• Two-way Class IV bike lane on
northbound Miramonte between
Hans and Castro.
• Bulb-out and led-enhanced
crosswalk system at Hans Avenue.

Design Begin: Summer 2024
Complete: Early 2025
Miramonte Avenue (Cuesta
to Castro).

Annual Traffic
Studies/NTMP
Improvements/Bicycle
Counts
(20-15)

• Traffic calming devices on
neighborhoods streets
On-Going NA
Castro Street Curb Ramp,
(20-30)
• Replace curb ramps in downtown
section of Castro Street

Design Begin: Summer 2024
Complete: Spring 2025

Plymouth Street/Space
Park Realignment
(20-40)
• New roadway pavement
• High visibility crosswalks
• Two-way bikeway on Shoreline
Boulevard between
Plymouth/Space Park and Pear
Avenue
• Class II bikeways on Plymouth
between Joaquin and Shoreline.

Design (Phase
3)
Phases 2 & 3 Begin:

Summer 2025
Complete: Summer
2026
Construction to proceed in
three phases:
1) tree removal (completed),
2) building demolition
(construction summer 2024),
3) street realignment
(design)

Page 5 of 7 ends

Project Title (#CIP) Bike/Pedestrian Element Status Anticipated Construction Timeline Comments
Castro Pedestrian Mall
(23-49)
• Pavement resurfacing
• High visibility crosswalks
Design Begin: Fall 2025
Complete: Spring 2025

El Camino Real Pavement
Resurfacing Bike and
Pedestrian Improvements
(20-61 and 22-29)
• Pavement resurfacing
• Bike lanes
• Mid-block pedestrian crossings
• Replace curb ramps

Construction Complete: Spring 2025 Caltrans project.

Street Resurfacing
(21-01)
• Pavement resurfacing
• Bike lanes

Construction Complete in March
2024
Measure B funded. Leong
Drive and Fairchild Drive.

SB-1 Streets Project
(21-30)
• Pavement resurfacing
• High visibility crosswalks.

Construction Complete: Spring 2024 Velarde, Pamela, Bay, Doverton, Katrina,
Fairbrook.

Bicycle/Pedestrian
Improvements
(21-37)
• Reconstruct bicycle and pedestrian
pathway on east side of Shoreline
Blvd.
• ADA-compliant curb ramps
• Pathway lighting
•
Design Begin: Fall 2024
Complete: Summer
2025
$2M grant funding by One
Bay Area Grant Program.

Shoreline Blvd from Wright
Avenue to Villa Street.

Grant Road and Sleeper
Avenue Intersection
Improvements
(21-39)
Grant/Sleeper:
• Installation of a Pedestrian Hybrid
Beacon (PHB).
• High-visibility crosswalk across the
southern leg of Grant Road with
left turn restriction from Sleeper
Avenue.
• Bike improvement crossing Grant
Road.
• New and enhanced crosswalk
striping and signage. ADA
compliant curb ramps.

Design
(Phase 1)

Phase 1
Begin: Fall 2024
Complete: Spring 2025
Construction to proceed in
two phases:
1) Grant/Sleeper,
Sleeper/Franklin, and Dale
Heatherstone, 2) seven
other intersections.

Page 6 of 7 ends

Project Title (#CIP) Bike/Pedestrian Element Status Anticipated Construction Timeline Comments
Nine Intersections:
• High-visibility crosswalks.
• LED-enhanced signs.

California Complete
Streets
(21-40)
• Pavement resurfacing (slurry seal).
• Vehicle lane reduction from four
lanes to three lanes.
• Parking-protected bike lanes.
• Bulb-outs, midblock crossings,
protected intersection treatments
and enhanced lighting.

Design Begin: Summer 2024
Complete: Summer
2025
Showers to Shoreline
Boulevard.

Crittenden Lane and
North Shoreline Boulevard
Reconstruction
(21-41)

• Pavement resurfacing.
• Bike facilities.
• ADA-compliant curb ramps.
• High visibility crosswalks.

Design Begin: Early 2025
Complete: Spring 2026

Annual Street
Maintenance
(22-01)
• Class IV bikeways between Moffett
and Bernardo.
• Pavement resurfacing
• High visibility crosswalks

Design Begin: Summer 2025
Complete: Early 2026
Middlefield Road Complete
Streets.

Grant funded.

Concrete Sidewalk/Curb
Repairs
(22-02, 23-02)

• Sidewalk and curb repairs Design Begin: Spring 2025
Complete: Fall 2025

SB1 Streets Project
(22-03 and 23-03)
• Pavement resurfacing
• High visibility crosswalks
Design Begin: Spring 2025
Complete: Fall 2025

Biennial Installation of
ADA Curb Ramps
(22-04, 24-04)
• ADA compliant curb ramps
• High visibility crosswalks
On hold TBD Awaiting completion of the
ADA Self-Evaluation and
Transition Plan for priority
locations.

Page 7 of 7 ends

Project Title (#CIP) Bike/Pedestrian Element Status Anticipated Construction Timeline Comments
Terra Bella Avenue
Bikeway Feasibility Study
(22-30)

• Assess feasibility of on-street
bikeway

Study NA
Stevens Creek Trail Bridge
Over Central Expressway
and Evelyn Avenue Deck
Replacement and Painting
(22-35)

• Deck replacement of
bike/pedestrian bridge over Evelyn
and Central Expressway
On hold TBD Awaiting available Project
Manager.

Annual Street
Maintenance
(23-01, 24-01)

• Street resurfacing
• High visibility crosswalks
Design Begin: Spring 2025
Complete: Fall 2025

MTC Mobility Hub Pilot
(23-27)
• Bike room improvements at the
Transit Center

Design Begin: Spring 2024
Complete: Fall 202.

Street Reconstruction
(23-31)
• Pavement reconstruction
• Bike lanes
• High visibility crosswalks
On hold Begin: Fall 2025
Complete: Summer
2026
Miramonte Avenue (Castro
to El Camino Real).

Awaiting available Project
Manager.

SB1 Streets Project
(24-03)
• Pavement resurfacing
• Bikeways on Moffett Boulevard
• High visibility crosswalks

Design Begin: Fall 2025
Complete: Fall 2026
Moffett Complete Street
Street Reconstruction
(24-28)
• Pavement reconstruction
• High visibility crosswalks

On hold TBD Awaiting available Project
Manager.

Cross Culvert Removal and
Storm Drain Extension
(24-30)
• Removal of cross culverts
• New ADA curb ramps
• High visibility crosswalks

On hold TBD Awaiting Available Project
Manager