Attachment 3

ACTIVE CIP PARK PROJECTS

LL/4/PWK
979-03-25-25Att3 Page 1 of 2
Project Title (CIP No.) Project Scope Status Anticipated Construction Timeline
Comments
All-Inclusive Playground (18-36) Magical Bridge designed playground for children of all
abilities.

Construction Begin: Summer 2023
Complete: Spring 2025

Additional Shade
Structures: Summer 2025
Combined with Rengstorff
Park Maintenance and
Tennis Building, Project
21-48. Park opened to Public
on 1/25/2025
Rengstorff Park—Aquatics Center
Replacement, Design and
Construction (18-38)
New Aquatics Center building,
new recreational and lap pools,
and site amenities.

Construction Begin: April 2022
Complete: Spring 2025
Pools open for lap swim on
March 3, 2025.

Grand Opening Ceremony
scheduled for March 29,
2025.

Shoreline Play Structure Replacement
(20-55)
Replacement boat-themed
play structure at Shoreline at
Mountain View.

Design Begin: Fall 2025
Complete: Summer 2026
Scope expanded to address
ADA access along pathway.

Timeline impacts from
sensitive environmental
conditions.

1720 Villa Park, Design (21-61)

New mini-park. Design Begin: Summer 2025
Complete: Spring 2026

Pickleball Court Preliminary Study and
Design, (23-36)
Study and design of park sites
to add four to 12 pickleball
courts.

In Study Phase Begin Study: Fall 2023
Complete Study: Fall 2025

San Rafael Avenue Park, Design and
Construction (24-36)

New 2.4-acre park. Preliminary Design

Begin: Fall 2027
Complete: Fall 2028
915 San Rafael Avenue
demolition in summer 2025.

Shoreline Lake Cove and Hill
Landscaping (24-37)
New landscape area between
the pathway and lake shore on
the north side of the
Boathouse at Shoreline Lake.

Design Begin: Summer 2026
Complete: Fall 2026

LL/4/PWK
979-03-25-25Att3 Page 2 of 2
Project Title (CIP No.) Project Scope Status Anticipated Construction Timeline
Comments
Monta Loma Playground Renovations,
Construction (25-38)
Construction but will likely
include pour in place surface
replacement, addition of a
shade structure, and potential
replacement of the
playground. Other elements
may be built dependent on
feedback from the community.

Pending staff
resources
Pending staff resources
Eagle Park Pool Improvements (25-38) Include a full deck replacement, replastering of
the pool, new pool lights,
removal of the 3M diving
board and relocation of the
1M diving board.

Pending staff
resources
Pending staff resources