ATT 2 - Evaluation of Proposed Council FY 2025-27 Work Plan Projects

Mountain View City Council
April 22, 2025

Document
ATT 2 - Evaluation of Proposed Council FY 2025-27 Work Plan Projects
Meeting
April 22, 2025
Body
Mountain View City Council
Pages
9
Original file
765 KB
Text extracted from the city's file for reading and search. Open the original on legistar1.granicus.com. That file is the official record.

Evaluation of Proposed FYs 25-27 Council Work Plan Projects Legend:

Fiscal Impact: = < $0.5 Million, = $0.5 to $1 Million, = Over $1 Million Staff Resources:

Page 1 of 9 ends

PROJECT STRATEGIC

PRIORITY FISCAL IMPACT STAFF

RESOURCES

DEPENDENCY/

NOTES PROJECT DURATION

EXISTING PROJECT

1. Stevens Creek Trail
Extension

Execute funding agreement(s)
with City of Sunnyvale and begin
conceptual engineering design
and feasibility for the trail
extension into Sunnyvale.

Mobility &
Connectivity

Expands the
multimodal
network,
offering safe
alternatives to
vehicle trips
.

No additional
funding needed in
2-year period

Funding
appropriated in CIP’s
18-39 and 20-50
($6.25 Million)

Significant long-
term
implementation cost
Lead Dept.:

Public Works

Obtained
Measure B grant
funding from VTA
($4.8 million), in
partnership with
City of
Sunnyvale.

Drafting of
funding
agreement
between cities
has begun.
18-24 Months

EXISTING PROJECT

2. Low- and Middle-Income
Home Ownership Strategy

Create a strategy to identify how
the City can support low- and
moderate-income
homeownership, including
identifying funding support,
utilizing City properties,
partnership opportunities, and
addressing City barriers to
condominium development.

Intentional
Development &
Housing
Options

Supports a
range of housing
options.

Cost:

$50,000

Lead Dept.:

Housing

Supporting:

Community
Development

Housing Element
Program 1.6
(DUO
Subdivisions) is
related, but not
dependent. This
program has a
deadline of
December 31,
2026.
12-18 Months

Timing is proposed to
align with Housing
Element Program 1.6.

Attachment 2
Evaluation of Proposed FYs 25-27 Council Work Plan Projects Legend:

Fiscal Impact: = < $0.5 Million, = $0.5 to $1 Million, = Over $1 Million Staff Resources:

Page 2 of 9 ends

EXISTING PROJECT

3. R3 Zoning Code Update

Complete the update of R3
zoning district development
standards to increase diversity
of housing types, establish
design standards consistent with
the community's vision, and
encourage neighborhood-
serving uses in alignment with
the Housing Element and State
Law.

Intentional
Development &
Housing
Options

Introduces
contemporary
building types
and higher
densities,
increasing
housing
development
opportunities.

No additional
funding needed

Funding
appropriated in CIP
20-67 ($2,197,000)
Lead Dept.:

Community
Development

This project
includes Housing
Element Program

1.3 a, c, e, and h,
with a deadline
of December 31,
2025. Majority of
the
R3 Zoning
Code Update is
discretionary, not
dependent.
9-12 Months

This project is
significantly underway.

NEW PROJECT

4. End of Natural Gas Flow by
2045

Adopt a resolution to end the
flow of natural gas by 2045 and
identify the legal pathways,
electrical grid improvements,
and community resiliency work
necessary to support this goal.

Sustainability &
Climate
Resiliency

Supports
decarbonization
goals.

No additional
funding needed in
2-year period

Significant long-
term
implementation cost
Lead Dept.:

City Manager’s
Office

Supporting:

Public Works,
Community
Development,
Community
Services, Finance

Efforts identified
in the
Decarbonization
Strategy will
contribute to the
ability to end the
flow of natural
gas.
18-24 Months

Evaluation of Proposed FYs 25-27 Council Work Plan Projects Legend:

Fiscal Impact: = < $0.5 Million, = $0.5 to $1 Million, = Over $1 Million Staff Resources:

Page 3 of 9 ends

EXISTING PROJECT

5. Community for All Action
Plan

Update the current Race, Equity,
and Inclusion Action Plan to
communicate current and
identify upcoming initiatives in a
new Community for All Action
Plan: Supporting Diversity,
Equity, and Inclusion; develop
and implement a
communications strategy to
build community awareness of
the Plan.

Community for
All

Supports
ongoing
diversity, equity,
and inclusion
throughout the
community.

No additional
funding needed

Lead Dept.:

City Manager’s
Office

This project will
replace the
current
Race,
Equity and
Inclusion Action
Plan which is
substantively
completed.
18-24 Months

EXISTING PROJECT

6. Citywide Broadband
Network

Develop a Citywide Fiber
Network conceptual design.

Community for
All

Increases
equitable access
to broadband
citywide.

Cost:

$75,000

Potentially
significant long-term
implementation cost
Lead Dept.:

City Manager’s
Office

A needs
assessment and
gap analysis was
shared at a
Council Study
Session on
February 26,
2025. This
project follows
direction
provided at that
meeting.
18-24 Months

Evaluation of Proposed FYs 25-27 Council Work Plan Projects Legend:

Fiscal Impact: = < $0.5 Million, = $0.5 to $1 Million, = Over $1 Million Staff Resources:

Page 4 of 9 ends

EXISTING PROJECT

7. Smart Water Meters

Establish an implementation
plan to procure and install smart
water meters, and associated
technology infrastructure,
citywide to allow for remote
collection of water meter data
and improve customer leak
detection. Depending on
selected rollout plan, begin
installation.

Sustainability &
Climate
Resiliency

Improves water
use efficiency by
providing real-
time
information to
customers.

No additional
funding needed

Funding
appropriated in CIP
23-45
($10.3 Million)

Longer-term
implementation
costs anticipated

Lead Dept.:

Public Works

Supporting:

Finance

City obtained
Valley Water
grant of
approximately
$9.3 million for
project.

City has
completed a
Request for
Proposal and is
currently
selecting a
consultant team.
24+ Months

EXISTING PROJECT (Deferred)

8. 2026 City Charter
Amendment

Identify routine clean up
amendments to the City Charter
and place an amendment on the
2026 ballot. Identify, potentially
through Charter Commission,
other more substantive
amendments for consideration
in future election cycle (e.g.,
2028).

Organizational
Strength &
Good
Governance

Modernizes the
City Charter.

Cost:

$100,000

Lead Dept.:

City Manager’s
Office

Supporting:

City Clerk’s
Office, Finance

None.
12-18 Months

This project timeline
would coincide with 2026
election deadlines.

Evaluation of Proposed FYs 25-27 Council Work Plan Projects Legend:

Fiscal Impact: = < $0.5 Million, = $0.5 to $1 Million, = Over $1 Million Staff Resources:

Page 5 of 9 ends

NEW PROJECT

9. 2026 Revenue Measure

Develop a revenue measure and
place it on the 2026 ballot.

Organizational
Strength &
Good
Governance

Supports the
City’s fiscal
health to allow
for enhanced
services.

Cost:

$250,000

Lead Dept.:

City Manager’s
Office

Supporting:

City Clerk’s
Office, Finance

None.
12-18 Months

This project timeline
would coincide with 2026
election deadlines.

EXISTING PROJECT (Deferred)

10. City Code Clean-Up

Review and make periodic
amendments to the Municipal
Code in a phased approach to
remove contradictory,
unenforceable, or otherwise
outdated sections.

Organizational
Strength &
Good
Governance

Enhances clarity,
updates
procedures, and
achieves
compatibility
with State Law.

No additional
funding needed

Lead Depts.:

City Manager’s
Office,
Community
Development,
Public Works,
Community
Services

These code
clean-ups will
occur in phases
as City staff
prepare other
coordinated code
updates and are
anticipated to
occur throughout
the work plan
timeline.
18-24 Months

Evaluation of Proposed FYs 25-27 Council Work Plan Projects Legend:

Fiscal Impact: = < $0.5 Million, = $0.5 to $1 Million, = Over $1 Million Staff Resources:

Page 6 of 9 ends

NEW PROJECT

11. Citywide Objective Design
Standards

Create citywide objective design
standards for new development
to increase transparency on
community design expectations
and streamline project review.

Phase 1 of this effort would
focus on multi-family and mixed-
use development types to
maximize the benefit to housing
and affordable housing
production, including alignment
with the R3 Zoning Code Update
and select precise plans with
significant housing development
potential.

Intentional
Development &
Housing
Options

Streamlines new
developments
and facilitates
alignment with
the City's vision.

Cost:

$350,000

Lead Dept.:

Community
Development

Supporting:

Public Works,
Community
Services

Project would
require updates
to Zoning
Ordinance and
Precise Plans.
24+ Months

Evaluation of Proposed FYs 25-27 Council Work Plan Projects Legend:

Fiscal Impact: = < $0.5 Million, = $0.5 to $1 Million, = Over $1 Million Staff Resources:

Page 7 of 9 ends

NEW PROJECT

12. Pedestrian Mall Vacant
Storefront Activation
Program

Develop and implement vacant
storefront display and pop-up
program guidelines including
both requirements and
incentives for storefront
maintenance and aesthetics.

Economic
Vitality

Supports a
walkable,
visually
pleasant, and
vibrant
downtown.

Cost:

$300,000

For program
development and
ongoing operation.

Lead Dept.:

Community
Development

Supporting:

Public Works

Related to
Economic Vitality
Strategy actions
1C. 1, 2, 3, and 8.
12-18 Months

Project start would be
delayed due to staffing
vacancy in Economic
Development.

NEW PROJECT

13. Pavement Condition Index
(PCI) increase to 71

Develop a strategy to set
pavement project priorities,
determine the pace for
accelerated investment, and
identify the tradeoffs for shifting
limited unrestricted funds in
order to achieve and maintain a
PCI of 71, while continuing to
prioritize both scheduled
pavement projects and active
transportation projects.
1 Livability &
Quality of Life

Enhances
roadway
experience for
all modes of
transportation.

No additional
funding needed in
2-year period

Funding
appropriated in CIP
25-01
($2.153 Million)

Significant long-
term
implementation cost
Lead Dept.:

Public Works

Strategy may
result in
decisions that
impact other
transportation
projects with
unrestricted
funding and/or
utility project
coordination.
12-18 Months

1 One-time funding of $1 Million for the Fiscal Year 2025-26 Budget is proposed to be allocated to pavement and active transportation projects.

Evaluation of Proposed FYs 25-27 Council Work Plan Projects Legend:

Fiscal Impact: = < $0.5 Million, = $0.5 to $1 Million, = Over $1 Million Staff Resources:

Page 8 of 9 ends

NEW PROJECT

14. City Policy/Template
Updates

Update Council Policies and
standard City templates and
documents to assist in
streamlining regular business
operations.

Organizational
Strength &
Good
Governance

Improves
organizational
efficiency and
consistency.

No additional
funding needed

Lead Dept.:

City Manager’s
Office

Supporting:

Community
Development,
Finance

This work will be
done by City staff
throughout the
work plan cycle. 18-24 Months

NEW PROJECT

15. City Volunteer Framework

Create a framework to support
opportunities for volunteer
organizations to work with the
City.

Organizational
Strength &
Good
Governance

Facilitates
collaboration
with volunteer
organizations on
initiatives of
mutual interest.

No additional
funding needed

Dept. Lead:

Community
Services

None.

18-24 Months

Evaluation of Proposed FYs 25-27 Council Work Plan Projects Legend:

Fiscal Impact: = < $0.5 Million, = $0.5 to $1 Million, = Over $1 Million Staff Resources:

Page 9 of 9 ends

EXISTING PROJECT

16. Pickleball Solution

Include in the Pickleball
Feasibility study a portion of
Cuesta Annex (as suggested by
the Pickleball Club), a portion of
Cuesta Park (as presented to the
Parks and Recreation
Commission), and City-owned
property on San Rafael Avenue
for the development of
permanent pickleball courts;
expedite completion of the
Feasibility Study and location
selection and development of
permanent pickleball courts;
explore private/public
partnerships for the
development of pickleball
facilities; and explore the
possibility of a modest
expansion of pickleball hours at
Rengstorff Park in the interim
during the development of
permanent facilities.

Livability &
Quality of Life

Provide a fun,
and accessible,
way for all ages
to stay active.

Cost:

TBD

No additional
funding needed for
the recommended
scope for a modest
increase in hours at
Rengstorff Park as
an interim solution
and to include
Cuesta Annex and
City property on
San Rafael Avenue
to the Pickleball
Feasibility Study for
construction of
permanent
pickleball courts

Significant cost for
construction of
permanent courts,
to be funded from
the Parkland Fund,
which will be
appropriated when
the pickleball facility
site is selected.

Lead Dept.:

Community
Services

Supporting:

Public Works

Related to
current pickleball
feasibility study
underway
addressing long-
term options,
along with
interim solutions
in place.
12-18 Months