Rengstorff Avenue Complete Streets Study, Project 25-39 August 31, 2026
ATTACHMENT 1
Table 1: Project Scope, Schedule and Status
Task Name Description Schedule Status
Existing Conditions and
Background Review
Identify study goals, review
background documents and
collect data to develop
alternatives.
November 2025 – February
2026 Complete
Alternative
Development and
Analysis
Develop conceptual alternatives
based on existing conditions
analysis and public feedback
from round 1 outreach.
March 2026 – August 2026 Underway
Outreach and
Community
Engagement
Develop the outreach plan, seek
feedback on existing travel
patterns, issues and potential
improvements.
Round 1: February 2026 Complete
Seek feedback on two planning-
level concept alternatives. Round 2: August 2026 Underway Preferred Alternative
and Cost Estimate
Refine the concept alternatives
to a preferred alternative based
on the screening criteria and
feedback from BPAC, CTC, and
the community, and develop a
cost estimate.
September 2026 – February
2027 Not Started
Draft and Final Plan
Prepare a draft and final report
including the study
recommendation, cost estimate,
and implementation strategies.
March 2027 – April/May
2027 Not Started
Committee/Council
Review
Prepare and present materials
for BPAC, CTC and Council
meetings
August 2026 (BPAC, CTC)
January 2027 (BPAC)
February 2027 (CTC)
April/May 2027 (Council)
Underway