Update: Children’s Library
Expansion Project
Brian Crawford, Senior Program Manager
March 19, 2024
Received After Agenda Printed
03/19/2024 - Regular Meeting
City Manager - Administrative Update
2 • June 2023: Design contract awarded to SVA
• July & August 2023: Stakeholder Visioning Workshops
• September – November 2023: Refine Preliminary Design & Overall Budget
• January 2024: City Council confirms Expansion Project is a priority • SVA is now working on schematic design and construction cost estimate
Progress Recap
3 THE FOLLOWING SLIDES CONTAIN
CONCEPTUAL DRAWINGS AND ARE
SUBJECT TO CHANGE
4 DRAFT
5 DRAFT
6 7
DRAFT
8 DRAFT
9 • April – July 2024: Design Development
• July – November 2024: Construction Documents & Plan Check • November 2024 – February 2025: Bidding & Contracts
• March 2025: Start of Construction
Next Steps
10 QUESTIONS & COMMENTS