Bid Item Description Units
Estimated
Quantity Unit Price Total Price
% of Total
Bid Price Unit Price Total Price
% of Total
Bid Price Unit Price Total Price
% of Total
Bid Price Unit Price Total Price
% of Total
Bid Price Unit Price Total Price
% of Total
Bid Price Unit Price Total Price
% of Total
Bid Price
Base Bid Items - Locations 1 Through 11
1 Mobilization LS 1 9,000.00 $ 9,000.00 $ 1.06% 55,000.00 $ 55,000.00 $ 6.06% 37,500.00$ 37,500.00$ 3.95% 21,000.00$ 21,000.00$ 1.93% 80,000.00$ 80,000.00$ 7.34% 379,533.00$ 379,533.00$ 23.76% 2 Traffic Control System LS 1 13,000.00 $ 13,000.00 $ 1.53% 39,000.00 $ 39,000.00 $ 4.30% 29,000.00$ 29,000.00$ 3.05% 30,500.00$ 30,500.00$ 2.81% 30,000.00$ 30,000.00$ 2.75% 82,698.00$ 82,698.00$ 5.18% 3 Pedestrian and Bicyclist Safety LS 1 7,000.00 $ 7,000.00 $ 0.82% 12,000.00 $ 12,000.00 $ 1.32% 3,750.00$ 3,750.00$ 0.39% 30,500.00$ 30,500.00$ 2.81% 20,000.00$ 20,000.00$ 1.84% 30,250.00$ 30,250.00$ 1.89% 4 Water Pollution Control LS 1 7,000.00 $ 7,000.00 $ 0.82% 6,500.00 $ 6,500.00 $ 0.72% 1,875.00$ 1,875.00$ 0.20% 8,900.00$ 8,900.00$ 0.82% 10,000.00$ 10,000.00$ 0.92% 9,438.00$ 9,438.00$ 0.59% 5 Project Information Sign EA 2 2,800.00 $ 5,600.00 $ 0.66% 1,100.00 $ 2,200.00 $ 0.24% 2,637.50$ 5,275.00$ 0.56% 2,300.00$ 4,600.00$ 0.42% 6,000.00$ 12,000.00$ 1.10% 3,025.00$ 6,050.00$ 0.38% 6 Construction Survey and Staking LS 1 10,000.00 $ 10,000.00 $ 1.18% 62,500.00 $ 62,500.00 $ 6.89% 13,800.00$ 13,800.00$ 1.45% 38,000.00$ 38,000.00$ 3.50% 40,000.00$ 40,000.00$ 3.67% 8,784.60$ 8,784.60$ 0.55% 7 Concrete Removal SF 24773 3.75 $ 92,898.75 $ 10.95% 5.00 $ 123,865.00 $ 13.66% 5.10$ 126,342.30$ 13.31% 9.00$ 222,957.00$ 20.53% 7.00$ 173,411.00$ 15.92% 11.76$ 291,330.48$ 18.24% 8 Remove Striping or Thermoplastic Pavement Markings SF 3232 8.00 $ 25,856.00 $ 3.05% 8.00 $ 25,856.00 $ 2.85% 4.49$ 14,511.68$ 1.53% 8.00$ 25,856.00$ 2.38% 5.00$ 16,160.00$ 1.48% 8.47$ 27,375.04$ 1.71% 9 6" & 8" Concrete Curb & Gutter, City Std. 301 & 302 LF 499 130.00 $ 64,870.00 $ 7.64% 64.50 $ 32,185.50 $ 3.55% 240.93$ 120,224.07$ 12.66% 76.00$ 37,924.00$ 3.49% 90.00$ 44,910.00$ 4.12% 77.14$ 38,492.86$ 2.41% 10 Concrete Access Ramp per Specified Detail SF 13235 15.00 $ 198,525.00 $ 23.39% 12.00 $ 158,820.00 $ 17.51% 15.04$ 199,054.40$ 20.97% 14.00$ 185,290.00$ 17.06% 18.00$ 238,230.00$ 21.86% 14.75$ 195,216.25$ 12.22% 11 Concrete Cross Gutters, Spandrel, and Curb, City Std. 311, 312 & 318 SF 8344 20.00 $ 166,880.00 $ 19.66% 15.50 $ 129,332.00 $ 14.26% 18.40 $ 153,529.60 $ 16.17% 20.00 $ 166,880.00 $ 15.36% 16.00 $ 133,504.00 $ 12.25% 29.83 $ 248,901.52 $ 15.59% 12 Concrete Sidewalks, City Std. 320 SF 2126 14.00 $ 29,764.00 $ 3.51% 9.50 $ 20,197.00 $ 2.23% 16.90$ 35,929.40$ 3.78% 9.00$ 19,134.00$ 1.76% 14.00$ 29,764.00$ 2.73% 11.85$ 25,193.10$ 1.58% 13 Remove and Replace Pull Box (Type 6 or 6E) EA 41 800.00 $ 32,800.00 $ 3.86% 925.00 $ 37,925.00 $ 4.18% 753.13$ 30,878.33$ 3.25% 3,300.00$ 135,300.00$ 12.46% 2,800.00$ 114,800.00$ 10.54% 643.50$ 26,383.50$ 1.65% 14 Adjust Pull Boxes to Grade EA 1 1,500.00 $ 1,500.00 $ 0.18% 515.00 $ 515.00 $ 0.06% 284.38$ 284.38$ 0.03% 1,100.00$ 1,100.00$ 0.10% 950.00$ 950.00$ 0.09% 605.00$ 605.00$ 0.04% 15 Pedestrian Push Button EA 2 4,000.00 $ 8,000.00 $ 0.94% 7,500.00 $ 15,000.00 $ 1.65% 1,314.63$ 2,629.26$ 0.28% 7,600.00$ 15,200.00$ 1.40% 6,500.00$ 13,000.00$ 1.19% 13,665.00$ 27,330.00$ 1.71% 16 Roadside Sign, Post, and Anchor EA 3 350.00 $ 1,050.00 $ 0.12% 400.00 $ 1,200.00 $ 0.13% 875.00$ 2,625.00$ 0.28% 410.00$ 1,230.00$ 0.11% 650.00$ 1,950.00$ 0.18% 423.50$ 1,270.50$ 0.08% 17 Install 12" Thermoplastic Limit Line SF 2010 3.00 $ 6,030.00 $ 0.71% 3.50 $ 7,035.00 $ 0.78% 9.09$ 18,270.90$ 1.92% 3.50$ 7,035.00$ 0.65% 4.50$ 9,045.00$ 0.83% 3.63$ 7,296.30$ 0.46% 18 Install Thermoplastic Pavement Marking "STOP" SF 69 15.00 $ 1,035.00 $ 0.12% 17.00 $ 1,173.00 $ 0.13% 17.25$ 1,190.25$ 0.13% 18.00$ 1,242.00$ 0.11% 20.00$ 1,380.00$ 0.13% 18.15$ 1,252.35$ 0.08% 19 Install 24" Yellow Thermoplastic Continental Crosswalk SF 1008 6.00 $ 6,048.00 $ 0.71% 6.75 $ 6,804.00 $ 0.75% 8.63$ 8,699.04$ 0.92% 7.00$ 7,056.00$ 0.65% 4.50$ 4,536.00$ 0.42% 7.26$ 7,318.08$ 0.46% 20 Fog Seal SF 9942 3.00 $ 29,826.00 $ 3.51% 0.75 $ 7,456.50 $ 0.82% 1.39$ 13,819.38$ 1.46% 1.00$ 9,942.00$ 0.92% 0.56$ 5,567.52$ 0.51% 1.82$ 18,094.44$ 1.13% 21 Paint Curb Red LF 114 5.00 $ 570.00 $ 0.07% 5.75 $ 655.50 $ 0.07% 4.60$ 524.40$ 0.06% 6.00$ 684.00$ 0.06% 3.00$ 342.00$ 0.03% 6.05$ 689.70$ 0.04% Additive Bid Items - Locations 12 and 13
22 Traffic Control System LS 1 7,500.00 $ 7,500.00 $ 0.88% 25,000.00 $ 25,000.00 $ 2.76% 5,800.00$ 5,800.00$ 0.61% 6,800.00$ 6,800.00$ 0.63% 5,000.00$ 5,000.00$ 0.46% 13,112.00$ 13,112.00$ 0.82% 23 Pedestrian and Bicyclist Safety LS 1 7,500.00 $ 7,500.00 $ 0.88% 10,500.00 $ 10,500.00 $ 1.16% 2,500.00$ 2,500.00$ 0.26% 6,800.00$ 6,800.00$ 0.63% 2,000.00$ 2,000.00$ 0.18% 7,260.00$ 7,260.00$ 0.45% 24 Construction Survey and Staking LS 1 7,000.00 $ 7,000.00 $ 0.82% 38,500.00 $ 38,500.00 $ 4.24% 2,500.00$ 2,500.00$ 0.26% 6,700.00$ 6,700.00$ 0.62% 5,000.00$ 5,000.00$ 0.46% 1,331.00$ 1,331.00$ 0.08% 25 Concrete Removal SF 2725 3.75 $ 10,218.75 $ 1.20% 8.50 $ 23,162.50 $ 2.55% 6.03$ 16,431.75$ 1.73% 9.00$ 24,525.00$ 2.26% 8.00$ 21,800.00$ 2.00% 13.47$ 36,705.75$ 2.30% 26 Remove Striping or Thermoplastic Pavement Markings SF 538 8.00 $ 4,304.00 $ 0.51% 8.00 $ 4,304.00 $ 0.47% 4.49$ 2,415.62$ 0.25% 8.00$ 4,304.00$ 0.40% 5.00$ 2,690.00$ 0.25% 8.47$ 4,556.86$ 0.29% 27 6" & 8" Concrete Curb & Gutter, City Std. 301 & 302 LF 199 130.00 $ 25,870.00 $ 3.05% 59.00 $ 11,741.00 $ 1.29% 153.77$ 30,600.23$ 3.22% 76.00$ 15,124.00$ 1.39% 90.00$ 17,910.00$ 1.64% 103.71$ 20,638.29$ 1.29% 28 Concrete Access Ramp per Specified Detail SF 2189 15.00 $ 32,835.00 $ 3.87% 13.50 $ 29,551.50 $ 3.26% 17.65$ 38,635.85$ 4.07% 15.00$ 32,835.00$ 3.02% 18.00$ 39,402.00$ 3.62% 21.86$ 47,851.54$ 3.00% 29 Concrete Sidewalks, City Std. 320 SF 288 20.00 $ 5,760.00 $ 0.68% 18.00 $ 5,184.00 $ 0.57% 19.79$ 5,699.52$ 0.60% 9.00$ 2,592.00$ 0.24% 14.00$ 4,032.00$ 0.37% 22.30$ 6,422.40$ 0.40% 30 Roadside Sign, Post, and Anchor EA 4 350.00 $ 1,400.00 $ 0.16% 400.00 $ 1,600.00 $ 0.18% 805.00$ 3,220.00$ 0.34% 410.00$ 1,640.00$ 0.15% 650.00$ 2,600.00$ 0.24% 1,139.22$ 4,556.88$ 0.29% 31 Install 12" Thermoplastic Limit Line SF 80 3.00 $ 240.00 $ 0.03% 3.50 $ 280.00 $ 0.03% 9.09$ 727.20$ 0.08% 3.50$ 280.00$ 0.03% 4.50$ 360.00$ 0.03% 3.63$ 290.40$ 0.02% 32 Install Thermoplastic Pavement Marking "STOP" SF 88 15.00 $ 1,320.00 $ 0.16% 17.00 $ 1,496.00 $ 0.16% 17.25$ 1,518.00$ 0.16% 18.00$ 1,584.00$ 0.15% 20.00$ 1,760.00$ 0.16% 18.15$ 1,597.20$ 0.10% 33 Install 24" Yellow Thermoplastic Continental Crosswalk SF 660 6.00 $ 3,960.00 $ 0.47% 6.75 $ 4,455.00 $ 0.49% 8.63$ 5,695.80$ 0.60% 7.00$ 4,620.00$ 0.43% 4.50$ 2,970.00$ 0.27% 7.26$ 4,791.60$ 0.30% 34 Fog Seal SF 7800 3.00 $ 23,400.00 $ 2.76% 0.75 $ 5,850.00 $ 0.64% 1.77$ 13,806.00$ 1.45% 1.00$ 7,800.00$ 0.72% 0.56$ 4,368.00$ 0.40% 1.82$ 14,196.00$ 0.89% 35 Paint Curb Red LF 39 5.00 $ 195.00 $ 0.02% 5.75 $ 224.25 $ 0.02% 4.60$ 179.40$ 0.02% 6.00$ 234.00$ 0.02% 3.00$ 117.00$ 0.01% 6.05$ 235.95$ 0.01% 848,755.50 $ 100.00% 907,067.75 $ 100.00% 949,441.76 $ 100.00% 1,086,168.00 $ 100.00% 1,089,558.52 $ 100.00% 1,597,048.59 $ 100.00%
PEDESTRIAN SAFETY ENHANCEMENTS PROJECT
CITY PROJECT NO. 22-454 (CIP 13044)
BIDS OPENED: 2/5/25 @2:00 PM
TVR Construction Engineering CT&T Construction
TOTAL BID PRICE
LC Paving & Sealing Inc. Alfaro Communications Construction Gentry General Engineering Aster Construction Services