Cities Index.
ATT 3 - Proposal from Murrieta Development Company, Inc.

Murrieta City Council
July 1, 2025

Document
ATT 3 - Proposal from Murrieta Development Company, Inc.
Meeting
July 1, 2025
Body
Murrieta City Council
Pages
3
Original file
571 KB
Text extracted from the city's file for reading and search. Open the original on murrieta.legistar1.com. That file is the official record.

To: Contact: CITY OF MURRIETA JEFFREY J. HITCH, PE
7591_CITY OF MURRIETA_11004 HAYES AVE_EMERGENCY BRIDGE

REPLACE
Project Name: Bid Number: 7591
Fax: Murrieta, CA 92562
Address: ONE TOWN SQUARE Phone: (951) 304-2489
Project Location: IVY STREET & HAYES AVENUE, MURRIETA, CA Bid Date: 6/11/2025 Total Price Unit Price Unit Item Description Item # Estimated Quantity

GENERAL CONDITIONS
$5,300.00 $5,300.00 1.00 LS MOBILIZATION
$7,330.00 $7,330.00 1.00 LS BOND COSTS FOR PROJECT
$8,205.00 $8,205.00 1.00 EACH POTHOLE EXISTING UTILITIES PRIOR TO DEMO OF

EXISTING BRIDGE
$5,220.00 $5,220.00 1.00 LS DEVELOP CONSTRUCTION WATER
$26,055.00 Total Price for above GENERAL CONDITIONS Items:

STORM DRAIN IMPROVEMENT PLANS
$21,940.00 $21,940.00 1.00 EACH DEMO & REMOVE EXISTING WOOD BRIDGE & PREPARE

FOR NEW RCB BOX
$133,650.00 $4,860.00 27.50 LF INSTALL 14'W X 7'H PRECAST REINFORCED CONCRETE BOX PER CALTRANS D80
$101,250.00 $50,625.00 2.00 EACH STD. DWG. D84 HEADWALLS WALLS PER DETAIL ON SHEET 2
$31,584.00 $987.00 32.00 LF PARAPET WALLS PER DETAIL ON SHEET 2 $9,856.00 $308.00 32.00 LF CUTOFF WALL UNDER RCB ASSUME 1' THK W#4 AT 18" OC
$33,440.00 $1,045.00 32.00 LF CONCRETE BARRIER TYPE 836 PER CALTRANS B11-80 MODIFIED TO 26"
TALL
$15,180.00 $506.00 30.00 LF TUBULAR HANDRAILINGS PER CALTRANS STD PLAN B11- 51 $37,488.00 $284.00 132.00 LF STD. DWG. A77L1 MIDWEST GUARDRAIL SECTION $90,882.00 $243.00 374.00 TON STD. DWG. 446A RIP RAP PAD PER CITY OF MURRIETA $34,075.00 $23.50 1,450.00 SF CONSTRUCT FULL DEPTH PAVEMENT SECTION PER DETAIL 3 ON SHEET 2
· PER DRTAIL MDC IS BIDDING A PAVING
SECTION OF 6"AC OVER 12" CAB
$24,112.00 $8.00 3,014.00 SF 2" MILL & OVERLAY PER DETAILS ON PLANS $3,820.00 $3,820.00 1.00 LS RE-STRIPE CENTER LINE PER PLANS $4,470.00 $4,470.00 1.00 LS TRAFFIC CONTROL - EXCLUDES ENGINEERED TRAFFIC CONTROL PLAN. BASED OFF EXISTING ROAD CLOSURE
FOR ENTIRE DURATION. ONLY PROVIDING FLAGGERS

FOR ACCESS TO EXISTING HOME OWNERS

Page 1 of 3 ends

$541,747.00 Total Price for above STORM DRAIN IMPROVEMENT PLANS Items:
$567,802.00 Total Bid Price:

Notes:
• MDC GENERAL NOTES:
· BID INCLUDES (1) MOVE IN. ADDITIONAL MOBILIZATION S WILL BE BILLED AT THE UNIT PRICE FOR MOBILIZATION. · A MINIMUM OF 2,000LF FULLY GRADED AND SURVEYED IS REQUIRED PRIOR TO MOBILIZATION OF A PRODUCTION CREW · SEWER PLUGGING AND PUMPING FOR CONSTRUCTION PHASE RELEASES IS EXCLUDED. · 5 BY STAKING IS TO BE PROVIDED FOR CENTER LINE AND ELEVATION OF RISER LOCATION FOR ALL APPURTENANCES (NOT CURB

FACE STAKING)
· SURVEY CUT SHEETS ARE TO BE PROVIDED TO MDC FOREMA N PRIOR TO EXCAVATION. · OVER-EXCAVATION AND RECOMPACTION OF UNSUITABLE SOI LS IS EXCLUDED. · PROPOSAL ASSUMES THAT ALL TRENCHES CAN BE EXCAVATE D WITH A CAT 345 EXCAVATOR (OR EQUIVALENT). IF EXCESSIVE HARD DIG CONDITIONS ARE ENCOUNTERED, ABOVE PRICING IS SUBJECT TO CHANGE. · CLEARING, GRUBING, AND REMOVALS OTHER THAN AS SHOW N IS EXCLUDED. · ALL EXCAVATIONS WILL BE BACKFILLED TO 0.5' +/- FRO M EXISTING GRADES. · BID INCLUDES SELECT BACKFILL IN THE PIPE ZONE ONLY (PER GOVERNING AGENCY AND/OR MANUFACTURER'S SPECIFICATIONS).

REMAINING BACKFILL MATERIAL SHALL BE NATIVE SOIL. IN THE EVENT NATIVE SOIL CANNOT BE USED, EXTRA CHARGES TO PROCESS SOIL WILL APPLY.
· SCREENING OF BACKFILL IS EXCLUDED (UNLESS SPECIFIC ALLY INDICATED IN THE PROPOSAL LINE ITEMS). · PROPOSAL EXCLUDES EXPORT OF EXCESS UTILITY SPOILS. MDC WILL SPREAD OUR EXCESS SPOILS ONSITE. · HANDLING AND / OR DISPOSAL OF HAZARDOUS MATERIALS IS EXCLUDED. · ASPHALT / BASE REMOVAL AND / OR PLACEMENT, GRINDIN G, OR OVERLAY, PERMANENT OR TEMPORARY, IS EXCLUDED (UNLESS SPECIFIED IN PROPOSAL LINE ITEMS).
· DRILLING, BLASTING, AND ROCK REMOVAL IS EXCLUDED.
· CATHODIC PROTECTION IS EXCLUDED. MDC WILL COAT A ND WRAP ALL BELOW GRADE STEEL BOLTS AND DUCTILE IRON FITTINGS. · BID IS BASED ON UNOBSTRUCTED ACCESS TO ALL WORK AR EAS. · OWNER / GC TO PROVIDE AND PAY FOR A CONSTRUCTION W ATER SOURCE. · DUST CONTROL WILL BE PROVIDED ONLY UNTIL BACKFILL OPERATION IS COMPLETE. NO WEEKEND DUST CONTROL IS INCLUDED. · DEWATERING, WATER CONTROL, AND NON-CONVENTIONAL EX CAVATION OF SATURATED MATERIAL IS EXCLUDED. · FIELD ENGINEERING AND STAKING IS EXCLUDED.
· UTILITY RELOCATION AND / OR UTILITY BRACING IS EXC LUDED (UNLESS SPECIFICALLY INCLUDED IN PROPOSAL LINE ITEMS). · ALL CURB MARKINGS FOR SEWER AND WATER TO BE DONE B Y OTHERS. · CATCH BASIN FILTERS ARE EXCLUDED (OTHER THAN AS SH OWN) · VIDEO INSPECTION OF PIPELINES IS EXCLUDED UNLESS S PECIFICALLY NOTED IN PROPOSAL. · PROPERTY LINE CLEAN OUTS & BACK WATER VALVES ARE E XCLUDED. · ALL LANDSCAPE AND IRRIGATION REPLACEMENT IS EXCLUD ED. · UTILITY DEMOLITION IS EXCLUDED
· RETAINING WALLS AND BLOCK WALLS OF ANY KIND ARE EX CLUDED. · ALL NECESSARY TREE REMOVALS BY OTHERS.
· EXISTING STREET CLEAN UP OF ANY KIND IS EXCLUDED.
· WALL DRAINS AND UNDERDRAINS ARE EXCLUDED.
· PROPOSAL EXCLUDES REMOVAL OR DISPOSAL OF ANY UNFOR SEEABLE SUBSURFACE DEBRIS, STRUCTURES OR OTHERWISE UNSUITABLE MATERIALS. EXCLUDES HANDLING OR REMEDIATION OF HAZARDOUS MATERIALS. · DETOURS, ACCESS ROADS, PLATING, FENCING, RESTRIPIN G, SIGNAL LOOP REPLACEMENT, TRAFFIC CONTROL & TRAFFIC CONTROL PLAN PREPARATION OF ANY KIND IS EXCLUDED (EXCEPT WHERE SPECIFICALLY INCLUDED IN THE PROPOSAL). ·
TRASH DUMPSTERS ARE TO BE PROVIDED BY THE OWNER / GC.
· ALL ITEMS OF WORK NOT SPECIFICALLY MENTIONED IN TH IS PROPOSAL ARE EXCLUDED. · IF NO PHASING IS PROVIDED AT THE TIME OF THIS BID, WE ARE ASSUMING THAT TESTING & VIDEO CAN BE DONE IN 2,500LF INCREMENTS. IF INCREMENTS OF LESS THAT 2,500LF ARE REQUIRED, ADDITIONAL CHARGES MAY APPLY. · A MINIMUM OF 10 MANHOLES MUST BE PROVIDED FOR 1ST RAISE PER MOBILIZATION AND A MINIMUM OF 20 MANHOLES MUST BE PROVIDED FOR FINAL RAISE PER MOBILIZATION. ADDTIONAL CHARGES WILL APPLY IF THESE MINIMUM QUANTITIES ARE NOT AVAILABLE AT TIME OF MOVE-IN.
· A MINIMUM OF 2O VALVE CANS MUST BE PROVIDED PER MO BILIZATION FOR VALVE CAN RAISES OR ADDITIONAL CHARGES MAY APPLY.
· EXCLUDES ALL V-DITCHES
·
THIS PROPOSAL IS GOOD FOR THIRTY (30) DAYS (FORCE MAJEURE NOT WITHSTANDING) • THIS PROPOSAL IS BASED OFF HAYES_BRIDGE_REPLACEMENT_PLAN_DRAFT_052225 (95% BID SET) • TRAFFIC CONTROL IS BASED OFF EXISTING STREET CLOSURE BY THE CITY OF MURRIETA. MDC ONLY INCLUDED COST FOR FLAGGMEN TO HELP EXISTING HOME OWNERS. ANYTHING ADDITIONAL REQUIRED WILL COME AT A COST TO THE CITY. • UNLESS OTHERWISE SPECIFIED ON THE PROPOSAL, PRICING IS BASED OFF OF ONE PHASE OF TESTING AND CHLORINATION. IF MULTIPLE PHASES OF CHLORINATION ARE REQUIRED ADDITIONAL COSTS FOR TIE-INS, CREW / SUBCONTRACTOR MINIMUMS AND LAB FEES WILL APPLY. • VALVE RISERS WILL NOT BE CUT DOWN UNTIL THE BASE SECTION HAS BEEN PLACED AND GRADED. MDC REQUIRES A MINIMUM OF 5 WORKING DAYS' NOTICE TO SCHEDULE CUTTING VALVE RISERS TO GRADE. SLIP CANS ARE TO BE PULLED UP BY THE PAVING CONTRACTOR AS ASPHALT IS BEING PLACED.
• UNLESS SPECIFICALLY NOTED ON THE PROPOSAL, ALL BOLLARDS AROUND APPURTENANCES ARE EXCLUDED. THIS EXCLUSION IS DUE TO THE AMBIGUITY IN LOCATION AND INCONSISTENT INTERPRETATION OF SPECIFICATIONS. IF BOLLARDS ARE REQUIRED, THEY WILL BE BILLED ON A UNIT PRICE BASIS OF $750 PER BOLLARD.

Page 2 of 3 ends

ACCEPTED:

The above prices, specifications and conditions are satisfactory and hereby accepted.

Buyer:

Signature:

Date of Acceptance:

CONFIRMED:

Murrieta Development Inc.

Authorized Signature:

Estimator: Zach Carlson
(951) 719-1680
[email protected]

Page 3 of 3 ends