Pickleball Court
Construction Strategy
Brian Crawford, Senior Program Manager
July 2, 2024
Received After Agenda Printed
6/18/2024 - Regular Meeting
AGENDA ITEM 24
Presentation
2 • Design & Build as many pickleball courts as possible. • Funding: $400,000 in ARPA Related Funds
• Funds need to be expended or applied to construction
c
ontracts by December 31, 2024
Pickleball Court Project Overview
3 • Tennis Community Feedback:
• Don’t convert existing courts to Pickleball
• Don’t locate pickleball courts next to tennis courts
• Pickleball Community Feedback:
• Prefer more courts, central location
• Social game with tournaments
Parks & Recreation Commission Recap
4 • Existing Park
• Prefer parking and restroom facilities
• Relatively even grade
• Minimal drainage issues (high point of park)
• Minimal CEQA (California Environmental Quality Act) Issues Location Criteria
5 Possible Locations
6 Option 1: Two Courts
7 Option 2: Four Courts
8 Option 3: Tennis Court Conversion
NOT RECOMMENDED
9 • Design: Put likely locations into design as soon as possible o Need understanding of costs
o Most of design can be duplicated for multiple locations • Construction:
o Cooperative purchasing for public works projects
o Job Order Contracting proposals
Strategies
10 QUESTIONS & COMMENTS