SEQUENCING OF SUBSEQUENT APPROVALS
Estimated Project Sequencing
1. PG&E Temporary Power Coordination
2. Demolition/Grading Permit Submittal (with related investigations)
3. Demolition/Grading Permit Work Start
4. Development Agreement, PD
and Tentative Parcel Map Approval
5. Design Review Submittal
6. Foundation/Underground Permit Submittal
7. Structure/MEPS Permit Submittal
8. Full Building Permit Submittal
9. Design Review Approval
10. Foundation/Underground Permit Work Start
11. City Parcels Close of Escrow
12. Initial CCR review by City
13. Preliminary Public Report Application
14. Preliminary DRE Public Report
15. Final Map
16. Structure/MEPS Permit Work Start
17. Finalize TOT Agreement
18. Fee Credit Submittals
19. Full Building Permit
20. Construction Commencement
21. Conditional or Final Public Report for Condominium
22. Final DRE Report
23. Parking Agreement
24. Fund Affordable Housing Equivalent
-
Methodist Housing
25. Condo Deposits and Sales
26. Complete Construction
27. Temporary Occupancy
28. Final Occupancy
29. TOT Revenue Sharing begins
30. TOT Revenue Sharing ends