11 - An Amendment Authorizing Staff to Extend the Time to Complete Construction for One-Unit and Two-Unit Family Dwellings - PowerPoint

Newport Beach City Council
March 8, 2022

Document
11 - An Amendment Authorizing Staff to Extend the Time to Complete Construction for One-Unit and Two-Unit Family Dwellings - PowerPoint
Meeting
March 8, 2022
Body
Newport Beach City Council
Pages
7
Text extracted from the city's file for reading and search. Open the original on ecms.newportbeachca.gov. That file is the official record.

Amendment to
NBMC IS-n2-na,
City Council Meetng
March 08, 2022
Seimone Jurjis, Community Development
Department Director
Tonee Thai, Acting Chief Building Official
,�
March 8, 2022
Item No. 11
_ ,V,W PO\
cc\ FO V7%

Background
Ordinance No. 2019-8, sets a three-year time limit to
complete construction of one -unit and two -unit family dwellings.

Approximately 165 building permits are expected to be
subject to the three-year time limit in June 2022.

After June, it is estimated that an average of 25 projects per month would be subject to the three-year time limit for completion.

Current Workflow
Ordinance No. 2010-2
3 -YEAR TIME

EXTENSION
NEEDED

HEARING OFFICER
Hear 1St & 2nd extension
request. May grant up to 180
days extension.

CITY COUNCIL HEAR

ANY ADDITIONAL

EXTENSION

What Happened?
COV/D-79 disrupted the construction industry
Impacts and Delays:
• General Building Materials: OK
• Specialized Orders: 1— 2 Months
• Door / Windows: 5 - 7 Months
• Appliances: 10 —14 Months
• Skilled Labor: Very Limited (many left the industry)

Number of Permits by Age
80 75
70 N
a -j
E 50
L
o 40 36
32 = 30
z
20 12
10 5 3
0 M
3 4 5 6 7 8 9
Age of Permits in Years

Proposed Workflow

HEARING OFFICER
Hear 2nd & 3rd extension
3 -YEAR TIME request. May grant up to 180
EXTENSION days extension.

NEEDED

BUILDING OFFICIAL
Ministerially grant 15t extension
request up to 365 days.

CITY COUNCIL HEAR

ANY ADDITIONAL

EXTENSION

Questions and Discussion
City Council Meeting
March 08, 2022
Tonee Thai, Acting Chief Building Official
Email: [email protected]
Phone: 949-718-1867