May 24, 2022
Agenda Item No. 3
TO:

HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM:

David A. Webb, Public Works Director - 949-644-3311, [email protected] PREPARED BY:

Tom Sandefur, Assistant City Engineer, [email protected] PHONE:
949-644-3321
TITLE:

Cliff Drive Clubhouse Rehabilitation – Notice of Completion for Contract No. 8695-1 (20F13) ABSTRACT:

On October 26, 2021, the City Council awarded Contract No. 8695-1, Cliff Drive Clubhouse Rehabilitation, to A2Z Construct, Inc. The project consisted of replacing the exterior of the building, painting, wood patching and repair, installing a new pathway to the building, adding a new water fountain, replacing the wall behind the sidewalk at the park, and removing an interfering tree. The work is now substantially complete and staff requests City Council acceptance and closeout of the contract.

RECOMMENDATION:
a) Accept the completed work and authorize the City Clerk to file a Notice of Completion for the project; b) Authorize the City Clerk to release the Labor and Materials Bond 65 days after Notice of Completion has been recorded in accordance with applicable portions of the Civil Code; and c) Release the Faithful Performance Bond one year after acceptance by the City Council.

DISCUSSION:

Overall Contract Cost/Time Summary
Award Contract Amount
Final Cost at
Completion
Total Contract Change Amount
Percent Contract Cost Change
$ 185,750.00
$ 181,378.75
$ -4,371.25
-2.4%
Allowed Contract Time (days)
40 Actual Time
Under (-) or Over (+)
+7

The work necessary for the completion of this contract consisted of replacing the exterior siding of the building, wood patching and repair, painting, installing a new pathway to the building, adding a new water fountain, replacing the wall behind the sidewalk at the park, removing an interfering tree, and other incidental items to complete the work in place as required by the contract documents.

The contract has now been completed to the satisfaction of the Public Works and Recreation and Senior Services Departments. A summary of the construction cost is as follows:

Original Bid Amount:
$
185,750.00
Actual Cost of Bid Items Constructed:
$
175,750.00
Total Change Orders:
$
16,128.75
Applied Liquidated Damages
$
-10,500.00
Final Contract Cost:
$
181,378.75
Changes to the contract cost included replacing several rotted support posts and additional concrete repairs. The seven day delay in contract completion resulted in the contractor incurring $10,500 in liquidated damages.

A summary of the project schedule is as follows:

Estimate Start of Construction per Annual Baseline Schedule February 28, 2022
Actual Start of Construction per Notice to Proceed
January 10, 2022
Actual Substantial Construction Completion Date
April 15, 2022
FISCAL IMPACT:

Funds for the construction contract were expended from the following Capital Improvement budget account:

Account Description
Account Number
Amount
FFP: Parks/Community Centers
56201-980000-20F13
$
181,378.75
Total:
$
181,378.75
The City’s Facilities Financing Plan (FFP) fund is used to fund improvements and replacements of public buildings throughout the city.

ENVIRONMENTAL REIEW:

On October 26, 2021, City Council found this project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301(a) (minor interior or exterior alterations involving such things as partitions and plumbing) of the CEQA Guidelines, California Code of Regulations, Title 14, Chapter 3, because this project results in no expansion of an existing use.

NOTICING:

The agenda item has been noticed according to the Brown Act (72 hours in advance of the meeting at which the City Council considers the item).

ATTACHMENT:

Attachment A – Location Map
3-3
3-1
Cliff Drive Clubhouse Rehabilitation – Notice of Completion for Contract No. 8695-1 (20F13)
May 24, 2022

Page 3 ends

CITY OF CITY OF

CITY OF

CITY OF
City Council Staff Report COUNCIL STAFF REPORT City Council Staff Report COUNCIL STAFF REPORT NEWPORT BEACH NEWPORT BEACH City Council Staff Report COUNCIL STAFF REPORT
City Council Staff Report COUNCIL STAFF REPORT

NEWPORT BEACH

NEWPORT BEACH

← All documents from this meeting