Cities Index.
SS3 - Early Look FY 2023_2024 CIP - PowerPoint

Newport Beach City Council
March 28, 2023

Document
SS3 - Early Look FY 2023_2024 CIP - PowerPoint
Meeting
March 28, 2023
Body
Newport Beach City Council
Pages
23
Text extracted from the city's file for reading and search. Open the original on ecms.newportbeachca.gov. That file is the official record.

March 28, 2023
Agenda Item No. SS3
Early Look
Fiscal Year 2023-24
Capital Improvement Program
City Council Study Session
March 28, 2023

City Council Goals for Allocation to CIP
✓ Budget Focuses Resources on Maintaining or
Replacing our Existing Infrastructure to keep it in
Good Working Condition
✓ Includes $6,000,000 baseline General Fund
Investment towards Citywide Infrastructure
Maintenance & Repair
✓ Includes $2,500,000 for Facility Maintenance Master
Plan projects.
✓ Includes $1,000,000 for Parks Maintenance Master
Plan projects.

How New Projects are Selected for the CIP
Identified & Scheduled through City Master Plans
• Facility Finance Plan
• Facility Maintenance & Management Plan
• Harbor Master Plan
• Pavement Management Plan
• Water Master Plan
• Sewer Master Plan
Identified/Requested by Community, Council or
City Department Staff
Developed to Support City Council Goals and Objectives
Required by Federal, State Law or Legal Action

Significant Projects Recently Completed — $38M
➢ Fire Station No. 2
➢ East Coast Highway Pavement Rehabilitation
➢ Jamboree Road Pavement Rehabilitation
➢ Assessment District 111 and Underground
District 22 — Phase 2
➢ Assessment District 113
➢ Via Lido Soud and Nord Pavement Rehabilitation
➢ Balboa Boulevard Median Improvements
➢ Dog Park Refurbishment
➢ 2021-22 City Bridge Maintenance
➢ 2021-22 Traffic Signal Rehabilitation
OF
�9e o�v
,

Significant Projects Under Construction - $44M
➢ Junior Lifeguard Facility
➢ Sunset View Park & Superior Pedestrian Bridge
➢ Balboa Boulevard and Newport Coast Dr
Pavement Rehabilitation
➢ West Irvine Terrace & Balboa Island Water
Main Replacement
➢ 16t" Street Pump Station Upgrades and Backup
Generator
➢ Water Transmission Main Valve Replacement
➢ Peninsula Tidegate Improvement Project
➢ Gateway Park Landscape Improvements

FY 2022-23 CIP = $103.4 Milli
Preliminary FY 2023-24 CIP
Tentative Total f*j
$29.0 Million
$43.3 Million
r

72.3 Million
New Funding
Re -budget* from
FY 2022-2.'--"
Some Possible Large Re -budget Projects - $30.4 Million • Library Lecture Hall
• Newport Bay Water Wheel
• Newport Coast Pickleball Courts
• Balboa Blvd/Newport Blvd Pvmt.
• City Yard Fueling/Transfer Station
• Balboa Island Drainage Imp.
d??
*Assumed Re -budget on July 1, 2023

FACILITIES [New proposed funding]
➢ 15t" Street Restroom Replacement
Rebudgeting - $16, 000 for a total of $866, 000
➢ Facilities Maintenance Master Plan (FMMP)
Rebudgeting - $900, 000 for a total of $3, 400, 000
TOTAL FACILITIES (News)
$275007000
$3,350,000
FFP
19AIA19
FFP - Major Facilities Finance Plan FMMP - Facilities Capital Maintenance Program

STREETS & DRAINAGE [New proposed funding]
➢ Alleys Reconstruction (AD 111)
Rebudgeting - $580, 000 for a total of $980, 000
➢ Balboa Island Street & Drainage Improvements
(Collins Island Bridge)
Rebudgeting - $68, 000 for a total of $1, 468, 000
➢ Concrete Replacement Program (Dover/Mariners)
Rebudgeting - $50, 000 for a total of $1, 050, 000
➢ East Coast Hwy Pavement Rehab
(Jamboree Road to MacArthur Blvd.)
➢ Landscape Enhancement Program
(Ocean Boulevard, Newport Blvd, 38t" Street, WCH Shoulder) Rebudgeting - $550, 000 for a total of $900, 000
$174007000
$170007000
$376357000
$3507000
WF
GF
GF
GF, SB1,
M2
GF
STREETS & DRAINAGE CONTINUED...

GF - General Fund S81 - S81 RMRA M2 - OCTA Measure M WF — Water Fund

STREETS & DRAINAGE [New proposed funding]
➢ Pavement Management Plan Update $307000 GF
➢ Rubberized Asphalt Pavement Overlay Program $2507000 CF ➢ San Miguel Drive Pavement Rehab $6207000 SB1
(Newport Center Drive to MacArthur Blvd.)
Rebudgeting - $8, 000 for a total of $628, 000
➢ Slurry Seal Program (Dover/Mariners) $176807000 GT
➢ Street Pavement Repair Program $8507000 GT
STREETS & DRAINAGE CONTINUED...

GF - General Fund S81 - S81 RMRA GT - Gas Tax CF - Contributions & Grants

STREETS & DRAINAGE [New proposed funding]
➢ Streetlight Rehabilitation Program
Rebudgeting - $350, 000 for a total of $850, 000
➢ Superior Avenue Pavement Rehabilitation
(Coast Hwy to Placentia Ave. )
➢ MacArthur Blvd Pavement Rehabilitation (Design)
(Jamboree Rd to Campus)
➢ Old Newport Curb Improvements
(15t" Street to Orange Street)
➢ Via Lido/Via Porto Intersection Ped. Improvements
➢ Irvine Blvd at Bristol — Fair Share Pvmt Rehab w/ OC
$500,000 GF
$1,420,000 GF,
SB1, GT
$350, 000 GF
$2507000 GF
$2507000 GF
$200, 000 GF
TOTAL STREETS & DRAINAGE (News) $12,505,000
GF - General Fund S81 - S81 RMRA GT - Gas Tax

TRANSPORTATION [New proposed funding]
➢ Traffic Signage, Striping and Marking Program
Rebudgeting - $26, 000 for a total of $950, 000
➢ Traffic Signal Rehabilitation Program
(Signals in Airport Area)
Rebudgeting - $682, 000 for a total of $1, 682, 000
TOTAL TRANSPORTATION (News)
$757000 GF
$170007000 GF
$1,075,000
GF - General Fund

WATER QUALITY & ENVIRONMENTAL
[New proposed funding]
➢ Newport Bay Trash Wheel
Rebudgeting - $1, 877, 000 for a total of $3,177, 000
➢ TMDL Compliance/Water Quality Improvements
Rebudgeting - $100, 000 for a total of $200, 000
➢ Peninsula Point Restoration — Monitor & Maint.

TOTAL WATER QUALITY & ENVIRONMENTAL (New $)
$173007000 TBD
$1007000 TL
$1507000 OEF
$135503000
OEF — Oceanfront Encroachment Fund TL — Tidelands TBD — To Be Determined

PARKS, HARBORS & BEACHES
0 0
[New proposed funding]
Playground Refurbishment Program
Park Maintenance Master Plan (PMMP)
SUBTOTAL PARKS (New $)
$3007000
$170007000
$133003000
BET— Building Excise Tax PMMP— Park Maintenance Master Plan BET
PMMP

PARKS, HARBORS & BEACHES
[New proposed funding]
➢ Balboa Yacht Basin Docks (Design)
Rebudgeting - $200, 000 for a total of $1, 000, 000
➢ Beach and Bay Sand Management
Rebudgeting - $100, 000 for a total of $600, 000
➢ Harbor & Ocean Bulkheads/Seawalls/Structure
Repairs
Rebudgeting - $489, 000 for a total of $889, 000
➢ Harbor & Ocean Maintenance/Minor Repairs
Rebudgeting - $100, 000 for a total of $250, 000
$5005000
$400, 000
$150, 000
HARBORS & BEACHES CONTINUED...

TL
TL
TL
TL
TL - Tidelands

PARKS, HARBORS & BEACHES
[New proposed funding]
➢ Harbor Piers Rehabilitation
Rebudgeting - $900, 000 for a total of $1, 300, 000
➢ Harborwide Dredging
➢ Balboa Island Seawall - Ferry Landing (Design)
SUBTOTAL HARBORS & BEACHES (New $)
$400 5 000
$5005000
$500,000
$352505000
TOTAL PARKS, HARBORS & BEACHES (News) $4,550,000
TL
TL
TL
TL - Tidelands

WATER [New proposed funding]
➢ Balboa Island Water Main Replacement - Phase 3 $179247000 WF ➢ Grade Adjustments — Water Valve $807000 WF
Rebudgeting - $50, 000 for a total of $130, 000
➢ Water System Rehabilitation $3907000 WF
➢ Cathodic Protection Program $3967000 WF
➢ Distribution Valve Replacement Program $1107000 WF
WATER CONTINUED...

WF - Water Fund

WATER [New proposed funding]
➢ Dover Dr / Coast Hwy PRS Replacement
➢ New Wells & Pipeline in Fountain Valley (study)
➢ Water Well Rehabilitation
➢ Shorecliff Water Main Replacement
TOTAL WATER (News)
$1547000
$2507000
$9007000
$170007000
$5,213,000
► TIa
WF
WF
WF
WF - Water Fund

WASTEWATER [New proposed funding]
➢ Grade Adjustments — Sewer Manhole Covers $1009000
Rebudgeting - $50, 000 for a total of $150, 000
➢ Sewer Main Lining and Repairs $5009000
TOTAL WASTEWATER (News) $600,000
SF - Sewer Fund
SF
SF

MISCELLANEOUS [New proposed funding]
➢ Fleet Electrification Program (study)
TOTAL MISCELLANEOUS (News)
$2007000
$2009000
AQMD
AQMD — AQMD Subvention Funds

Proposed Fiscal Year 2023/24
Summary of New Funding by Type
0 Funding Type
Proposed New Funding
General Fund
$6,0001000
Roadway Funding (SB1, GT, M2)
$6,930,000
Water/Wastewater
$6,213,000

FFP/FMMP/PMMP (GF)
$4,350,000
Tidelands / Oceanfront Encroachment
$3,500,000
Grants & Contributions
$250,000
Building Excise Tax / AQMD Funds
$500,000
To Be Determined
$11300,000
TOTAL
$29,043,000

5-Year Look Ahead - Significant Projects
Estimated Construction Start Dates
➢ FY 24-25
Balboa Island Drainage Project (Collins Bridge & Pump Station) Balboa Library/Fire Station No. 1
Bonita Creek Field Turf Replacement
MacArthur Pavement Rehab (Jamboree to Campus)
Reconstruct & Dredge Balboa Yacht Basin
➢ FY 25-26
Balboa Island Drainage Project (West Side Piping)
Bay/Channel Water Main Crossings Replacements
Bristol Street North and South Pavement Rehabilitation
Lower Castaways Bulkhead Replacement
Santa Ana Ave/San Bernardino Ave Pavement Reconstruction

5-Year Look Ahead - Significant Projects
➢ FY 26-27
Balboa Island Drainage Project (East Side Piping)
Birch Street Pavement Rehabilitation
Newport Pier/McFadden Square Rehabilitation/Replacement San Joaquin Hills Road Pavement Rehab (MacArthur to Marguerite Ave) ➢ FY 27-28
Balboa Island Seawall — Phase 1
Jamboree Pavement Rehab (Campus to University)
Newport Center Drive Pavement Rehab
West Coast Hwy/Superior Ave Intersection Improvements & Ped. Bridge ➢ FY 28-29
East Irvine Terrace Water Main Replacement
San Joaquin Hills Road Pavement Rehab (Spyglass Hill to Newport Coast Dr.) Villa Balboa Concrete Trail and Fire Access Concrete Replacement

Comments / Questions
NEWPORTBEACHCA.GOV/PUBLICWORKS

← All documents from this meeting