Cities Index.
Staff Report Background Doc

Norwalk City Council
May 28, 2024

Document
Staff Report Background Doc
Meeting
May 28, 2024
Body
Norwalk City Council
Original file
145 KB
Text extracted from the city's file for reading and search. Open the original on norwalk.primegov.com. That file is the official record.

City Council Agenda Report
May 28, 2024
TO: Honorable City Council
FROM: Jesus M. Gomez, City Manager
BY: Glen W.C. Kau, P.E., Director of Public Services/City Engineer Gabriela Garcia, Senior Management Analyst
SUBJECT: ACCEPT WORK FOR RE-ROOF PROJECT - PROJECT NO. 7863, SPROUL MUSEUM AND PROJECT NO. 7377, HOLIFIELD PARK MAIN SNACK BAR Background:

On January 16, 2024, City Council awarded a contract to Associated Construction Services Group for $116,770 to provide labor and materials to replace roofs at the Sproul Museum and the Holifield Park Main Snack Bar.

The work was satisfactorily completed on April 12, 2024 for $133,475. There were two change orders in the amount of $16,705 that were approved from the contingency amount of $18,862 to address unforeseen issues that needed to be repaired during the project.

Fiscal Impact:

Funding for this project is available in the approved FY 2023/24 Capital Project Park Renovation Fund budget. Below is the final accounting for the subject project:

(1) Contract Value $ 116,770
(2) Contingency $ 18,862
(3) Subtotal $ 135,632
(4) Additional Work Needed $ 16,705
Final Project Costs (1) + (4): $ 133,475

City Council May 28, 2024
Accept Work – Sproul Museum and Holifield Snack Bar Re-Roof Page No. 2 8 5
8 Citizens Advised:

N/A
Strategic Plan 2023 Implementation:

The recommended action will further the City’s Strategic Plan Goal 2 - Work in partnership with our community to achieve safe and livable neighborhoods - Objective 1 - Re-invest in existing and aging infrastructure.

Recommended Action:

Staff recommends the City Council accept the work of Associated Construction Services Group in the amount of $133,475 for Project No. 7863, Sproul Museum and Project No. 7377, Holifield Park Main Snack Bar roof replacements.

Attachments:

N/A

← All documents from this meeting