City Council Agenda Report
June 4, 2024
TO: Honorable City Council
FROM: Jesus M. Gomez, City Manager
BY: Glen W.C. Kau, P.E., Director of Public Services/City Engineer Mario Mera, Engineering Division Manager
Run Chen, P.E., Principal Civil Engineer
Andrew Del Carpio, Assistant Engineer
SUBJECT: PROJECT NO. 7935 - AGREEMENT AMENDMENT NO. 2 FOR DESIGN SERVICES –– RESOLUTION NO. 24-32, BUDGET AMENDMENT - ZONE 21 AND 26 ALLEYWAY IMPROVEMENTS – ENGINEER’S REPORT NO. 24-07 Background:

Kimley-Horn (design consultant) is currently designing the local street rehabilitation plans for Zones 2, 9, and 29 which are part of Project No. 7935. The alleyways in Zones 21 and 26 are degraded due to age and use and are in need of repaving.

There are three alleyways in Zones 21 and 26 in need of rehabilitation to repair the degraded asphalt pavement. Area residents have expressed to the City a desire for concrete alleyways to replace the current asphalt pavement due to durability. For expediency and economy of scale, the design of the alleyway improvements is being added to the local street rehabilitation projects currently in design.

On April 3, 2024, staff requested a proposal from Kimley-Horn for Professional Design Services for Alleyway Improvements in Zones 21 & 26 to be added to Project No. 7935. On April 30, 2024, the City received a proposal from Kimley Horn. Staff reviewed the proposals evaluating project scope and cost. Staff recommends amending the original agreement with Kimley-Horn to add Professional Design Services for Alleyway Improvements for Zones 21 & 26 and add it to Project No. 7935.

City Council June 4, 2024
Agreement Amendment No. 2 - Zones 21 and 26 Alleyway
Improvements
Page No. 2
8 7
1 A budget resolution is needed to add funding to Project No. 7935 to provide for the project scope in the amount of $96,400 for Amendment 2, $3,750 for Amendment 1, and $2,146 for Staff Time.

Funding is requested to provide for Amendment No. 1, previously executed for professional services and utilities research. To date, $2,146 in staff time has been expended on this project and was not previously budgeted.

The following is an estimated cost breakdown of the total project costs:

Original Contract Amount: $ 986,590
Amendment 1 Amount: $ 3,750
Amendment 2 Amount: $ 96,400
Total Contract Amount: $ 1,086,740
Staff Time: $ 2,146
Budget Resolution Amount: $ 102,296
Fiscal Impact:

The project is budgeted under Street Renovation Fund.

Citizens Advised:

N/A
Strategic Plan 2023 Implementation:

The recommended action will further the City’s strategic Plan Goal 2: Work In Partnership With Our Communities to Achieve Safe and Livable Neighborhoods.; Objective 1 - Re-invest in existing and aging a infrastructure.

Recommended Action:

Staff recommends City Council:
a. adopt Resolution No. 24-32, A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF NORWALK AUTHORIZING THE AMENDMENT TO THE FISCAL YEAR 2023/24

ADOPTED BUDGET TO APPROPRIATE STREET RENOVATION FUNDS TO PROJECT NO. 7935 FOR DESIGN WORK FOR ZONES 21 AND 26 – ALLEYWAY IMPROVEMENTS, IN THE AMOUNT OF $102,296; and
b. approve Amendment No. 2 to the agreement with Kimley-Horn, in the amount of $96,400 for additional professional design services for Alleyway Improvements in Zones 21 and 26; and authorize the City Manager to execute the amendment on behalf of the City, in a form approved by the City Attorney.

City Council June 4, 2024
Agreement Amendment No. 2 - Zones 21 and 26 Alleyway
Improvements
Page No. 3
8 7
1 Attachments:

1. Resolution No. 24-32

2. Proposal for Zone 21 and Zone 26 Alleyway Improvements