City Council Agenda Report
August 20, 2024
TO: Honorable City Council
FROM: Jesus M. Gomez, City Manager
BY: Glen W.C. Kau, P.E., Director of Public Services/City Engineer Jana Stuard, Director of Finance/City Treasurer
Jacque Koontz, P.E., Senior Civil Engineer
SUBJECT: PROJECT NO. 7872 - RESOLUTION NO. 24-47 – BUDGET AMENDMENT – CHANGE ORDER NO.1 FOR - TRANSPORTATION CENTER AND SOCIAL SERVICES PARKING LOT RESURFACING – SPEED HUMPS INSTALL
Background:

On June 18, 2024, City Council awarded a contract in the amount of $395,021 to All American Asphalt for Project No. 7872, Transportation Center and Social Services Parking Lots Resurfacing. The project will rehabilitate parking lots at the City’s shared Transportation Center, the Social Services Center and Alondra Library. The work scope includes for pavement surface preparation, specific location pavement repairs, pavement resurfacing, and pavement markings restoration. The project’s budget ($452,000) includes for construction, contingency for unknowns, project management/inspection and City staff administration.

Cecilia Street is a shared right-of-way with the City of Downey (Downey). The common border between agencies is approximately along the street centerline. Downey recently resurfaced (slurry seal) its side of Cecilia Street (west bound lane). Cecilia Street has been plagued by above the “prima facie” speed vehicle limit of 25 miles per hour.

At its’ scheduled August 6, 2024 meeting, City Council approved installation of speed humps and associated equipment for Cecilia Street between Orr and Day Road and Fairford Avenue.

The installation of the speed humps is to increase safety, driver awareness and provide for safer driving experience.

To the facilitate a solution and implement City Council’s directive, staff recommends Change Order No.1, which consists of pavement resurfacing followed by the installation of speed humps

City Council August 20, 2024
Resolution No. 24-47 Budget Amendment and Approve Change Order No. 1 For Project No. 7872 – Speed Hump Install
Page No. 2
9 7
5 on Cecilia Street. Pavement resurface (slurry seal) is recommended prior to speed hump installation to provide for a consistent pavement surface for speed humps installation.

The estimated costs for the above-described work (materials, labor & inspection) are as follows:

Work Item Costs
Herbicide & crack seal $ 17,056
Slurry seal - Type II $ 35,200
Speed humps $ 76,947
subtotal: $ 129,203
contingency (8 %): $ 10,336
Total: $ 139,539
Request: $ 140,000
The speed humps have a 4–6-week delivery lead time from order placement. Slurry seal requires advance preparation work (herbicide spraying, crack sealing) prior to slurry seal application and then pavement markings reinstallation. This work would be coordinated in a manner such that the pavement surface would be ready for speed humps installation once delivered. Estimated time to complete the additional work is approximately three months from change order execution.

Fiscal Impact:

Approved FY 2024/25 Gas Tax funds are available for this project.

Citizens Advised:

N/A
Strategic Plan 2023 Implementation:

The recommended action will further the City’s Strategic Plan Goal 2: Work in Partnership with Our Community to Achieve Safe and Livable Neighborhoods; Objective 1: Re-invest in existing and aging infrastructure.

Recommended Action:

Staff recommends City Council:
a. adopt Resolution No. 24-47, A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF

NORWALK AUTHORIZING AN AMENDMENT TO THE FISCAL YEAR
2024/25 PROPOSED BUDGET TO APPROPRIATE AVAILABLE GAS TAX FUNDING TO PROJECT NO. 7872 – TRANSPORTATION CENTER AND SOCIAL SERVICES

PARKING LOT RESURFACING PROJECT FOR PAVEMENT RESURFACING ON CECILIA STREET IN CONJUNCTION WITH NEW SPEED HUMP INSTALLATIONS, in the amount of $140,000; and
City Council August 20, 2024
Resolution No. 24-47 Budget Amendment and Approve Change Order No. 1 For Project No. 7872 – Speed Hump Install
Page No. 3
9 7
5 b. approve Construction Change Order No. 1 to All American Asphalt for Project No. 7872, Transportation Center and Social Services Parking lot resurfacing, in the amount of $129,203 to include pavement resurfacing eastbound Cecilia Street between Orr & Day Road and Fairford Avenue; and authorize the City Manager to execute the amendment, on behalf of the City, in a form approved by the City Attorney.