City Council Agenda Report
October 15, 2024
TO: Honorable City Council
FROM: Jesus M. Gomez, City Manager
BY: Glen W.C. Kau, P.E., Director of Public Services/City Engineer Mario Mera, Engineering Manager Consultant
Jay Kasondra, Engineering Technician
SUBJECT: PROJECT NO. 7242 - ACCEPT WORK FOR EXCELSIOR DRIVE AND

BLOOMFIELD AVENUE SPEED FEEDBACK SIGN IMPROVEMENTS
Background:

On December 5, 2023, City Council awarded a contract to Select Electric, Inc. in the amount of $64,720 for Excelsior Drive and Bloomfield Avenue Speed Feedback Sign Improvements. Work scope includes supply and installation of four speed feedback signs at the subject intersection.

Final project costs are $73,419.99 and the work was satisfactorily completed on July 22, 2024. Additional work for concrete replacements in the amount of $9,700 is within the contingency amount and was required to complete the project.

Contract Value Contingency Total Completed Work
Value
Balance
$64,720.00 $9,700.00 $74,420.00 $73,419.99 $1,000.01
Fiscal Impact:

Funding for this project is available through approved/available Fiscal Year 2023/24 Measure “M” Bond proceeds. No General Fund Monies are used for this project. Unexpended funds are available for reprogramming.

Citizens Advised:

N/A

City Council October 15, 2024
Project No. 7242 - Accept Work Page No. 2
1 0
0 4
Strategic Plan 2023 Implementation:

The recommended action will further the City’s Strategic Plan Goal 2: Work in Partnership with Our Community to Achieve Safe and Livable Neighborhoods, Objective 1, Reinvest in existing and aging infrastructure.

Recommended Action:

Staff recommends the City Council accept the work completed by Select Electric, Inc. in the amount of $73,419.99 for Excelsior Drive and Bloomfield Avenue Speed Feedback Sign Improvements.