City Council Agenda Report
July 15, 2025
TO: Honorable City Council
FROM: Jesus M. Gomez, City Manager
BY: Glen W.C. Kau, P.E., Director of Public Services/City Engineer Mario Mera, Engineering Division Manager
Run Chen, P.E., PMP, Principal Civil Engineer
Andrew Del Carpio, Assistant Engineer
Nathan Garcia, Assistant Engineer
SUBJECT: PROJECT NO. 7940 – ACCEPT WORK FOR COMMUNITY DEVELOPMENT
BLOCK GRANT CONCRETE AMERICANS WITH DISABILITIES ACT
IMPROVEMENTS 2025, ENGINEER’S REPORT NO. 25-13
Background:
On April 1, 2025, City Council awarded the construction contract to DT Stellar General Engineering in the amount of $499,950 for the Community Development Block Grant (CDBG) Concrete American with Disabilities Act (ADA) Improvements 2025 – Project No. 7940. A contingency in the amount of $41,050 was included for the subject project.
The project work scope involved removal and replacement of ADA curb ramps, installation of cast-in-place truncated domes, incidental asphalt work, and related traffic control. The final project cost was $536,610.
The project was completed satisfactorily on June 11, 2025.
Fiscal Impact:
The project was funded through Fiscal Year 2024/25 approved/available CDBG in the amount of $536,610, which is the total project cost. No General Fund Monies were used for this project.
Unexpended funds are available for reprogramming.
City Council July 15, 2025
Accept Project No. 7940 – CDBG
Concrete ADA Improvements 2025
Page No. 2
1 4
3 0
Citizens Advised:
N/A
Strategic Plan 2023 Implementation:
The recommended action will further the City’s Strategic Plan Goal 2: Work in Partnership with Our Community to Achieve Safe and Livable Neighborhoods; Objective 1 – Re-invest in existing and aging infrastructure.
Recommended Action:
Staff recommends City Council accept the work of DT Stellar General Engineering in the amount of $536,610 for CDBG Concrete ADA Improvements 2025.
Attachments:
N/A