City Council Agenda Report
September 2, 2025
TO: Honorable City Council
FROM: Jesus M. Gomez, City Manager
BY: Glen W.C. Kau, P.E., Director of Public Services/City Engineer Damian Rosales, Public Services Superintendent
SUBJECT: PROJECT NO. 3302-2425 - ACCEPT WORK FOR CITYWIDE SIDEWALK/CONCRETE REPAIR AND REPLACEMENT – ENGINEER’S
REPORT 25-21
Background:

On October 15, 2024, City Council awarded a contract to CJ Concrete Construction, Inc. ($499,600) for Citywide Sidewalk/Concrete Repair and Replacement. The work scope included improvements to sidewalks; removal/replacement of curbs-gutters and included adjacent asphalt repairs as necessary; removal and replacement of driveway approaches; miscellaneous asphalt paving; upgrades to current Americans with Disabilities Act (ADA) standards for access curb ramps at intersection corners and installation of detectable warnings (truncated domes) for the access ramps.

Final project costs are $484,346 and the work was satisfactorily completed on June 27, 2025.

Contract Value Contingency Total Completed Work
Value
Balance
$499,600 $74,940 $574,540 $484,346 $90,194
Fiscal Impact:

The project was funded utilizing $328,346 of Measure R Local Return funds and $100,000 of Gas Tax Funds included in the Fiscal Year 2024/25 budget and Transportation Development Act (TDA) Article 3 funding in the amount of $56,000 for ADA curb ramp installations. No General Funds were used for the project. Unexpended funds are available for reprogramming.

City Council September 2, 2025
Accept Project No. 3302-2425
Citywide Sidewalk/Concrete Repair and Replacement
Page No. 2
1 5
0 1
Citizens Advised:

N/A
Strategic Plan 2023 Implementation:

The recommended action will further the City’s Strategic Plan Goal 2: Work in Partnership with Our Community to Achieve Safe and Livable Neighborhoods, Objective 1, Reinvest in existing and aging infrastructure.

Recommended Action:

Staff recommends City Council accept the work completed by CJ Concrete Construction, Inc. in the amount of $484,346 for Citywide Sidewalk/Concrete Repair and Replacement and curb ramp installations to comply with Americans with Disabilities Act (ADA) standards.