Enclosure #4 City of Norwalk
TABLE A - MAJOR PROJECT COMPONENTS Corps Section 219 Proposed Water System Improvement Program - Phase I FY23 - FY30
Phase FY23 FY24 FY25 FY26 FY27 FY28 FY29 FY30 Funding
Adjustment TOTALS
Funding adjustment from prior FY23 I 1,136,368 1,136,368 1 I 333,333 140,167 473,500
2 I 1,050,000 1,050,000
3 I 2,500,000 2,500,000
4 I 160,000 160,000
5 I 300,000 300,000
I 4,073,862 4,073,862
6 I 364,500 364,500
I 2,700,000 2,700,000
7 I 80,000 80,000
I 675,000 675,000
8 I 675,000 200,000 875,000
I 2,500,000 2,500,000
9 I 72,000 72,000
I 600,000 600,000
I 600,000 600,000
10 I 250,000 250,000
I 1,500,000 1,500,000
I 1,073,862 1,073,862
I 2,000,000 2,000,000
11 I 80,000 80,000
I 800,000 800,000
12 I 200,000 200,000
I 200,000 200,000
I 100,000 100,000
13 I 200,000 200,000
I 1,827,500 1,827,500
North Service Area Transmission Main - Construction I 559,166 559,166 Totals Phase I 333,333 1,680,167 2,455,000 5,548,862 6,738,362 5,472,000 2,427,500 1,159,166 1,136,368 26,950,758 Federal Cost Share - Section 219 - 75% 250,000 1,260,125 1,841,250 4,161,647 5,053,772 4,104,000 1,820,625 869,375 852,276 20,213,069 City Local Agency Cost Share - 25% 83,333 420,042 613,750 1,387,216 1,684,591 1,368,000 606,875 289,792 284,092 6,737,690 6/20/2024
Automatic Meter Reading Program - Construction
Automatic Meter Reading Program - Construction
Automatic Meter Reading Program - Construction
North Service Area Transmission Main - Design & NEPA Docs North Service Area Transmission Main - Construction
SCADA System Installation - Phase A
SCADA System Installation - Phase B
SCADA System Installation - Phase C
166th Street Transmission Main Pioneer Blvd to East City Limits - Design & NEPA Docs 166th Street Transmission Main Pioneer Blvd to East City Limits - Construction Nordesta - Imperial Groundwater Recovery Project - Predesign & NEPA Docs Nordesta - Imperial Groundwater Recovery Project - Construction Nordesta - Imperial Groundwater Recovery Project - Construction Distribution Main Replacement Program - Design & NEPA Docs SCADA System Installation - Design Finalization
Distribution Main Replacement Program - Construction
Distribution Main Replacement Program - Construction
Norwalk Park Reservoir & Pump Station - Design & NEPA Docs Norwalk Park Reservoir & Pump Station - Construction
Norwalk Blvd. Transmission Main, Well 9 to Norwalk Park Reservoir - Design & NEPA Docs Norwalk Blvd. Transmission Main, Well 9 to Norwalk Park Reservoir - Construction Nordesta - Imperial Groundwater Recovery Project - Predesign & NEPA Docs Water System Improvement Projects - Description
Corps Environmental Infrastructure Project Partnership Agreement NEPA Docs Well No. 9 Hermosillo Park - Design, NEPA Docs, Drilling & Construction Well No. 9 Hermosillo Park - Equipping & Transmission Mains - Design & Construction 2023 Water System Analysis
Attachment No. 3