City Council Agenda Report
November 4, 2025
TO: Honorable City Council
FROM: Jesus M. Gomez, City Manager
BY: Ozzie Ramos, Deputy City Manager
Mario Mera, Engineering Division Manager
Run Chen, P.E., PMP, Principal Civil Engineer
Andrew Del Carpio, Assistant Engineer
Nathan Garcia, Assistant Engineer
SUBJECT: PROJECT NO. 7934 - ACCEPT WORK FOR LOCAL STREETS REHABILITATION PROGRAM ZONE 7 ASPHALT IMPROVEMENTS,
ENGINEER'S REPORT NO. 25-25
Background:

On February 18, 2025, City Council awarded the construction contract to Manhole Adjusting, Inc. in the amount of $968,669.90 for the Local Streets Rehabilitation Program (LSRP) Zone 7 Asphalt Improvements – Project No. 7934. A contingency in the amount of $145,300.49 was included for the subject project.

The project work scope involved application of Cape Seal, Slurry Seal to the streets, grinding of existing pavement, removal and replacement of asphalt at localized repairs, removal and replacement of curb and gutter, and restoration of traffic striping, legends, and crosswalks. The final project cost was $1,061,657.42.

The project was completed satisfactorily on October 2, 2025.

Fiscal Impact:

The project was funded through Fiscal Year 2024/25 approved/available Measure M, Measure R, Proposition C, and Street Renovation Fund in the amount of $1,061,657.42, which is the total project cost. No General Fund Monies were used for this project. Unexpended funds are available for reprogramming.

City Council November 4, 2025
Accept Project No. 7934 – LSRP Zone 7
Asphalt Improvements
Page No. 2
1 5
7 6
Citizens Advised:

N/A.

Strategic Plan 2023 Implementation:

The recommended action will further the City’s Strategic Plan Goal 2: Work in Partnership with Our Community to Achieve Safe and Livable Neighborhoods; Objective 1 – Re-invest in existing and aging infrastructure.

Recommended Action:

Staff recommends City Council accept the work of Manhole Adjusting, Inc. in the amount of $1,061,657.42 for Local Streets Rehabilitation Program Zone 7 Asphalt Improvements.