Cities Index.
Staff Report Background Doc

Norwalk City Council
December 16, 2025

Document
Staff Report Background Doc
Meeting
December 16, 2025
Body
Norwalk City Council
Original file
77 KB
Text extracted from the city's file for reading and search. Open the original on norwalk.primegov.com. That file is the official record.

City Council Agenda Report
December 16, 2025
TO: Honorable City Council
FROM: Jesus M. Gomez, City Manager
BY: Albert Mendoza, P.E., Director of Public Services/City Engineer Mario Mera, Engineering Division Manager
Run Chen, P.E., Principal Civil Engineer
Nathan Garcia, Assistant Engineer
SUBJECT: PROJECT NO. 7232 – ACCEPT WORK FOR ALONDRA BOULEVARD

TRAFFIC SIGNAL IMPROVEMENTS FROM HOME DEPOT SIGNAL TO
SHOEMAKER AVENUE [FEDERAL-AID PROJECT NO. HSIPL-5347 (042)], ENGINEER'S REPORT NO. 25-26
Background:

On December 6, 2022, City Council awarded a construction contract to Select Electric, Inc., in the amount of $1,595,850 for the Alondra Boulevard Traffic Signal Improvements from the Home Depot Signal to Shoemaker Avenue. A contingency in the amount of $398,963 was authorized for this project.

The project work scope included upgrading signal hardware, installing new pedestrian countdown signal heads, installing American with Disabilities Act compliant curb ramps, and updating the signal timing coordination at specific locations along the entire project corridor. The amount of $610,904 was required due to City approved change orders, unforeseen conditions, and design discrepancies. The final construction project cost was $2,206,755.

The construction work was completed satisfactorily on December 6, 2024. Final acceptance was withheld until issues regarding labor compliance were resolved, resulting in acceptance at this time.

City Council December 16, 2025
Accept Project No. 7232 – Alondra Boulevard Traffic
Signal Improvements
Page No. 2
1 6
5 7
Fiscal Impact:

The project was funded through Fiscal Year 2025/26 approved/available Measure M and Highway Safety Improvements Program (HSIP) funds. No General Fund monies were used for this project.

Citizens Advised:

N/A
Strategic Plan 2023 Implementation:

The recommended action will further the City’s Strategic Plan Goal 2: Work in Partnership with Our Community to Achieve Safe and Livable Neighborhoods; Objective 1 – Re-invest in existing and aging infrastructure.

Recommended Action:

Staff recommend City Council accept the work of Select Electric, Inc., in the amount of $2,206,755 for Project No. 7232 – Alondra Boulevard Traffic Signal Improvements from the Home Depot Signal to Shoemaker Avenue, and release the retention payment in the amount of $110,338 to Select Electric, Inc., thirty-five (35) days after the recordation of the Notice of Completion.

Attachments:

N/A

← All documents from this meeting