Mr. Andrew Del Carpio
City of Norwalk
Public Services Department – Engineering Division
12700 Norwalk Boulevard
Norwalk, CA 90650

Subject: Budget Amendment Request No. 3 – Proposal for Construction Management and Inspection for Local Streets Rehabilitation, Zones 2, 9, & 29, City Project Number 7935

Dear Mr. Del Carpio,
Pursuant to our recent discussions, this letter is to request authorization to modify our original construction management services contract for the City’s Local Streets Rehabilitation Project – Zones 2, 9, & 29, City Project Number 7935.

Willdan’s revised budget of $253,921.00 included construction management, material testing, and public works inspection services to monitor the additional working days required to complete the Project.

The current budget request includes the unforeseen items listed below:
 Willdan’s revised budget amendment includes additional material testing services not included in the original proposal.

Willdan’s current budget requires an adjustment to cover additional material testing services needed to monitor the pavement and slurry seal installation activities that occurred beyond the original working days. Willdan’s budget modification request would add an additional $109,764.33 to our revised budget.

To support this contract request, attached are a detailed spreadsheet and Willdan’s subconsultant’s estimate for the requested additional material testing services.

In conclusion, Willdan Engineering’s revised budget of $253,921.00 would increase by $109,764.33, for a revised total of $363,685.33. A modification is necessary to include the requested material testing services for the project.

If you have any questions or need additional information, please contact me at (310) 502-6335.

Respectfully submitted,

WILLDAN ENGINEERING

Chris Baca, RCI, CESSWI
Director of Construction Management and Inspection Services

Enclosure
 Exhibit A – Original Budget
 Exhibit B - Budget Amendment No.3