TO: Honorable City Council
FROM: Jesus M. Gomez, City Manager
BY: Albert Mendoza, P.E., Director of Public Services/City Engineer Mario Mera, Engineering Division Manager
Run Chen, P.E., Principal Civil Engineer
Isiah Corona, Senior Management Analyst
SUBJECT: PROJECT NO. 7941 - ACCEPT WORK FOR COMMUNITY DEVELOPMENT
BLOCK GRANT CONCRETE AMERICANS WITH DISABILITIES ACT
IMPROVEMENTS 2026, ENGINEER'S REPORT NO. 26-34
Background:
On February 3, 2026, City Council awarded a construction contract to Towo Enterprise, Inc. for Project No. 7941 – Community Development Block Grant (CDBG) Concrete Americans with Disabilities Act (ADA) Improvements 2026 (“Project”). The scope of work included removal and replacement of ADA curb ramps, installation of cast-in-place truncated domes, and incidental asphalt work.
The project started on March 11, 2026 and was completed satisfactorily on June 26, 2026. City staff has completed a final inspection of the project and determined that the work has been satisfactorily completed in accordance with the approved plans, specifications, and contract requirements. The inspection found no outstanding issues or deficiencies, and all work was determined to be acceptable and in conformance with the project requirements. Accordingly, staff recommend acceptance of the project as complete.
Fiscal Impact:
The project has an approved construction budget of $854,950, inclusive of a 40% contingency, and funded by Fiscal Year 2025/26 CDBG funds. The total construction cost was $848,215. No General Fund Monies were used for this project.
City Council August 4, 2026
Accept Project No. 7941 Page No. 2
1 4
6 3
Citizens Advised:
N/A
Strategic Plan 2023 Implementation:
The recommended action will further the City’s Strategic Plan Goal 2: Work in Partnership with Our Community to Achieve Safe and Livable Neighborhoods; Objective 1 – Re-invest in existing and aging infrastructure.
Recommended Action:
Staff recommend City Council accept the work of Towo Enterprise, Inc. in the amount of $848,215 for Project No. 7941 – Community Development Block Grant Concrete Americans with Disabilities Act Improvements 2026, and release the retention payment in the amount of $42,410.75 to Towo Enterprise, Inc., 35 days after the recordation of the Notice of Completion.
Attachments:
CDBG Map Locations