Council
District Project Funding Program Status
Anticipated Construction
or Study Completion1
(as of 3/28/24)
2, 5, 6, 7 International Boulevard (14th Avenue - 107th Avenue) quick build project Violence Prevention Pilot Program Pending Construction 6/30/2024 4 Park Boulevard/Beaumont Avenue crosswalk lane reduction FY 21-23 School Capital Improvement Project Pending Construction 6/30/2024 6 Rapid Response: Seminary Avenue/Outlook Avenue Rapid Response Program2 Pending Construction 6/30/2024 1 Rapid Response: MacArthur Boulevard/Piedmont Avenue Rapid Response Program2 Pending Construction 6/30/2024 4 Rapid Response: Joaquin Miller Road/Skyline Boulevard Rapid Response Program2 Pending Construction 6/30/2024 3 Rapid Response: Telegraph Avenue/Thomas L Berkley Way Rapid Response Program2 Pending Construction 6/30/2024 6 Sideshow Prevention: International Boulevard/66th Avenue FY21-23 Sideshow Prevention Pilot Program3 Pending Design 6/30/2024 4 Rapid Response: High Street/Westbound I-580 Freeway On-Ramp Rapid Response Program2 Pending Construction 6/30/2024 6 Rapid Response: International Boulevard/58th Avenue Rapid Response Program2 Pending Design 9/30/2024 5 Courtland Court/Brookdale Avenue FY 21-23 Council Earmark Project Pending Construction 10/31/2024 3 Bay Place/Montecito Avenue temporary lane reduction FY 23-25 Council Discretionary Project Pending Design 12/31/2024 Citywide 2024 Speed Bump Installations: 44 Locations Approved FY 23-25 Neighborhood Traffic Safety Capital Improvement Project Pending Construction 12/31/2024
Citywide 15 MPH School Zones4: 23 locations Speed Limit Lowering Program Pending Design 3/31/2025 6 Ney Avenue traffic calming project FY 21-23 Neighborhood Traffic Safety Capital Improvement Project 95% Design 6/30/2025
2 Lakeshore Avenue/Prince Street pedestrian refuge island FY 21-23 Council Earmark Project 65% Design 6/30/2025 1 Hillegass Ave & Colby St traffic claming pilot FY 23-25 Council Discretionary Project Contractor Solicitation 6/30/2025 7 96th Avenue/Sunnyside Street traffic circle FY 21-23 Council Earmark Project 65% Design 6/30/2025 4 Suter Street/Liese Avenue sideshow prevention FY 21-23 Council Earmark Project 65% Design 6/30/2025 6 MacArthur Boulevard/Ritchie Street sideshow prevention FY 23-25 Council Discretionary Project Pending Design 6/30/2025 MINOR CAPITAL PROJECT LIST - MARCH 2024

TRAFFIC ENGINEERING SECTION

Page 1 ends

Attachment D
Council
District Project Funding Program Status
Anticipated Construction
or Study Completion1
(as of 3/28/24)
MINOR CAPITAL PROJECT LIST - MARCH 2024

TRAFFIC ENGINEERING SECTION
4 35th Avenue/Kansas Street lane reduction FY 21-23 Council Discretionary Project Pending Design and Outreach 6/30/2025 6 Maxwell Park traffic study FY 23-25 Council Discretionary Project Contractor Solicitation 6/30/2025 Citywide 2024 Business Activity Districts - Reduced Speeds: 20 locations Speed Limit Lowering Program Pending Design 6/30/2025 7 Sideshow Prevention: International Boulevard/98th Avenue FY21-23 Sideshow Prevention Pilot Program3 Pending Design 6/30/2025 2 Sideshow Prevention: International Boulevard/16th Avenue FY21-23 Sideshow Prevention Pilot Program3 Pending Design 6/30/2025 6 Sideshow Prevention: Coliseum Way/66th Avenue FY21-23 Sideshow Prevention Pilot Program3 Pending Design 6/30/2025 3, 4, 6, 7
School Capital Improvements, 5 Schools: Yu Ming Charter K-8; Lincoln Elementary; MLK Jr. Elementary; Westlake Middle; East Oakland Pride Elementary
FY 21-23 School Capital Improvement Project Pending Construction Contract 6/30/2025 7 Golf Links Road/Fontaine Street stop sign flasher FY 21-23 Council Earmark Project Pending Design 6/30/2025 1 Market Street/45th Street sideshow prevention FY 21-23 Council Discretionary Project Pending Design 6/30/2025 2 Rapid Response: Embarcadero Avenue/16th Avenue Rapid Response Program2 Pending Design & Paving Schedule 12/31/2025 3 Crosswalk flashers @ Oakland Avenue/Moss Street, 98th Avenue/C Street Grant funded project 95% Design 12/31/2025 Citywide 2025 Speed Bump5 Installations: 11 Locations Approved; 22 Locations Under Review
FY 23-25 Neighborhood Traffic Safety Capital
Improvement Project Pending Design 12/31/2025
2 E 12th Street/13th Avenue crosswalk flashers FY 21-23 Council Earmark Project Pending Design 12/31/2025 At Large E 18th Street corridor crosswalk daylighting FY 21-23 Council Discretionary Project Pending Design 12/31/2025 2 Foothill Boulevard/22nd Avenue signal upgrade Rapid Response Program (grant funded) Pending Design 12/31/2025 1 Adeline Street/61st Street traffic study FY 21-23 Council Discretionary Project Pending Investigation 12/31/2025 Citywide 2025 Business Activity Districts - Reduced Speeds: 25 locations Speed Limit Lowering Program Pending Design 6/30/2026 2 East 15th Street permanent traffic diverters for human trafficking Violence Prevention Pilot Program Pending Design 6/30/2026

Page 2 ends

Attachment D
Council
District Project Funding Program Status
Anticipated Construction
or Study Completion1
(as of 3/28/24)
MINOR CAPITAL PROJECT LIST - MARCH 2024

TRAFFIC ENGINEERING SECTION
4 38th Avenue/Penniman Avenue traffic circle FY 21-23 Council Earmark Project 35% Design 12/31/2026 Citywide
School Capital Improvements, 17 Schools: Yu Ming Charter Upper School; Sankofa Elementary; KIPP Bridge Academy; Oakland School for the Arts; Dewey Academy/La Escuelita Elementary; Manzanita Community; St. Anthony's; Community School for Creative Education; Sequoia Elementary; Redwood Heights Elementary; Skyline High; Oakland Charter Academy; Bridges Academy; Lockwood Steam Academy; Rusdale Continuation School; Elmhurst Middle; Esperanza Elementary
FY 23-25 School Capital Improvement Project Pending Design 12/31/2026 Citywide Sideshow Prevention: Locations TBD FY 23-25 Sideshow Prevention Pilot4 Pending Location Referrals TBD 7 Toler Avenue/Thermal Street Speed Bumps FY 21-23 Council Earmark Project Awaiting Resident Petition TBD 6 MacArthur Boulevard Stop Sign Analysis - 65th, 66th, & 69th Avenues FY 21-23 Council Earmark Project Pending Investigation TBD 4 Dimond District crosswalk flashers FY 21-23 Council Earmark Pending Investigation TBD 4 Laurel District crosswalk flashers FY 23-25 Council Discretionary Project Pending Investgiation TBD 1 Idora Park traffic calming project FY 21-23 Council Earmark Pending Design TBD Notes

2. Additional Rapid Response investigations are added on an ongoing basis. The Rapid Response Program is activated following fatal traffic collisions involving vulnerable populations, including but not limited to children, seniors, people with disabilities, pedestrians, and bicyclists. The Program involves an engineering assessment that is separate and informed by police investigation of the crash, focused on the prevention of future loss of life. Identified improvements are delivered through the Rapid Response Program (via a maintenance treatment or quick-build improvement) or through other existing programs, such as the paving program or capital improvements when there are existing plans for improvements as part of a larger project. In some cases, the engineering investigation may determine that the crash and resulting fatality was not preventable through engineering treatments, and no engineering action is identified for these cases.

Numerous Rapid Response investigations over the last year were related to fatalities on International Boulevard. Improvements developed from these investigations were folded into the International Boulevard Quick Build Project.

1. Anticipated construction completion reflects a snapshot in time of current conditions. Many factors outside of OakDOT's control that may impact delivery timelines include the City's contracting and procurement process, contractor availability, and severe and inclement weather. For traffic studies, this column reflects the anticipated completion date of the and NOT the construction completion date.

Page 3 ends

Attachment D
Council
District Project Funding Program Status
Anticipated Construction
or Study Completion1
(as of 3/28/24)
MINOR CAPITAL PROJECT LIST - MARCH 2024

TRAFFIC ENGINEERING SECTION

6. One additional FY 21-23 Council Earmark is not captured on this list (Sidewalk Cut-outs) because it will not be delivered through the Traffic Engineering Section.

7. In addition to the minor capital projects on this table, the Traffic Engineering Section manages investigation and any resulting implementation related to general traffic safety requests and traffic safety requests from school officials, as well as citywide speed limit management.

5. The Speed Bump program is a resident-led petition process. Because OakDOT receives applcations on an ongoing basis, the number of locations under review and/or approved for installations will change throughout the course of the year.

3. OakDOT plays a supportive role in the City's Sideshow Prevention Pilot program and relies on the City Administrator's Office and Oakland Police Department to identify and prioritize locations of the most dangerous and persistent sideshows in the City where enforcement efforts may benefit from engineering strategies. OPD then refers these locations to OakDOT for installation of hardened center lines. Please note OakDOT no longer installs Botts' Dots as part of the Sideshow Prevention Pilot based on their lack of demonstrated effectiveness and durability; slipping concerns from people bicycling and motorcycling; and their high maintenance burden.

4. School zone speed limit lowering also includes bringing existing school signage and markings up to current day standards. The specific upgrades will vary depending on site conditions at each school location and may include replacement of signage with high-visibility/fluorescent signage, relocation of signage that may be obscured, remarking faded crosswalks, remarking faded curbs, etc.

Page 4 ends