Attachment A. 2023 Safe Oakland Streets (SOS) Initiative Annual Report Engineering Safety Improvement Projects
The following table includes projects where the primary purpose is to substantially enhance pedestrian and bicyclist safety and/or to implement safe routes to schools. This includes Capital Improvement projects that began construction in 2023 and Near-Term Improvement projects where a Work Order has been completed and improvements installed in 2023.
Capital Improvements are large-scale and longer-term, generally incorporating whole corridors and including substantial community engagement to inform a project's design.
Near-Term projects are much smaller in scope and scale, and generally include improvements delivered in-house such as signage, striping, and other temporary materials.
2023 OakDOT Capital Improvement Projects and Near-Term Improvement Projects Improvement
Type Subtype Project Description (if applicable) Street Project Location - Start Project Location - End
Construction Start/
Work Order Completed
City Council
District 2018 HIN
Equity Priority
Community
Designation
Capital Capital East Bay Greenway - Segment IISan Leandro Street Seminary Avenue 75th Avenue 2023 6, 7 N Highest Capital Capital International Pedestrian Lighting and
Sidewalk Repair Project International Boulevard 36th Avenue 107th Avenue 2023 5, 6, 7 Y High/Highest Capital Paving 8th Street West Oakland Traffic
Calming Project 8th Street Market Street Wood Street 2023 3 Y Highest Capital Paving High Street Paving Project High Street MacArthur BoulevardTompkins Avenue 2023 4, 5, 6 Y High Capital Paving
West Grand Avenue Repaving &
Pedestrian Safety Improvement
Project
W. Grand Avenue Campbell Street Market Street 2023 3 Y Low/High/Highest Capital Paving New Bike Boulevard 34th Avenue Foothill Boulevard Peralta Hacienda Park 2023 5 Y Highest
Capital Paving Redesigned Buffered Bike Lane Keith Avenue College Avenue Broadway 2023 1 N Lowest Capital Paving Upgraded Buffered Bike Lane Oakland Avenue Orange Street MacArthur Boulevard 2023 1, 3 N Low
Capital Bikeway Fruitvale Land Crossing Bay Trail
Project
Waterfront Trail,
west of Fruitvale Avenue Lancaster Street Alameda Avenue 2023 5 N High Capital Paving Install New Bike Boulevard Sheffield Avenue/E 29th Street/ 25th Avenue MacArthur Boulevard E. 27th Street 2023 4, 5 N High/Low Capital Paving Restripe Existing Bikeway Howe Street 40th Street Kaiser Hospital 2023 1 N Lowest Capital Paving Install New Buffered Bike Lane Bellevue Avenue Perkins Street Grand Avenue E 2023 3 N Lowest/Medium Capital Paving Install New Bike Boulevard 45th Street City Limit (Emeryville)Market Street 2023 1 N Medium Capital Paving Install New Bike Boulevard Gaskill Street 55th Street 53rd Street 2023 1 N Low Near-Term Council Earmark
MacArthur/Coolidge Sideshow
Prevention MacArthur Boulevard Coolidge Avenue -- 2023 4 N High/Low Near-Term Council Earmark New All Way Stop 53rd Street Gaskill Street -- 2023 1 N Low Near-Term Council Earmark
Traffic - Delineator Install Repair
Replace Shattuck Avenue Aileen Street -- 2023 1 Y Low
Near-Term Council Earmark
Traffic - Delineator Install Repair
Replace Shattuck Avenue 57th Street -- 2023 1 Y Low
Near-Term Council Earmark
Traffic - Delineator Install Repair
Replace Shattuck Avenue 58th Street -- 2023 1 Y Low
Near-Term Oak311 (Public) Service RequestAC Transit Signage 14th Street Broadway -- 2023 3 Y Medium/High/Highest Near-Term Oak311 (Public) Service RequestBus Stop Removal Seminary Avenue MacArthur Boulevard-- 2023 6 N High Near-Term Oak311 (Public) Service RequestFrontage Road Truck Sign Frontage Road West Grand Avenue -- 2023 3 N Lowest Near-Term Oak311 (Public) Service RequestSafe Routes to School Thornhill Drive Mountain Boulevard-- 2023 4 N Lowest Near-Term Oak311 (Public) Service RequestStop Ahead Legends MacArthur Boulevard 76th Avenue 78th Avenue 2023 6 Y Low/Highest Near-Term Oak311 (Public) Service RequestStop Sign Improvement MacArthur Boulevard 100th Avenue 2023 7 N High Near-Term Oak311 (Public) Service RequestStriping removal 8th Street Madison Street -- 2023 2 Y Medium Near-Term Oak311 (Public) Service RequestTraffic - Crosswalk Striping 104th Avenue & Plymouth Street-- -- 2023 7 N Medium Near-Term Oak311 (Public) Service RequestTraffic - Crosswalk Striping Jackson Street & 17th Street -- -- 2023 3 Y Medium Near-Term Oak311 (Public) Service RequestTraffic - Crosswalk Striping Bay Place Montecito Avenue -- 2023 3 N Low Near-Term Oak311 (Public) Service Request
Traffic - Delineator Install Repair
Replace Coronado Avenue & Desmond Street-- -- 2023 1 N Lowest Near-Term Oak311 (Public) Service Request
Traffic - Delineator Install Repair
Replace 98th Avenue & Holly Street -- -- 2023 7 Y High
Near-Term Oak311 (Public) Service Request
Traffic - Delineator Install Repair
Replace Lake Park Avenue Lakeshore Avenue 2023 2 N Lowest Attachment A. 2023 Safe Oakland Streets (SOS) Initiative Annual Report 2023 OakDOT Capital Improvement Projects and Near-Term Improvement Projects Improvement
Type Subtype Project Description (if applicable) Street Project Location - Start Project Location - End
Construction Start/
Work Order Completed
City Council
District 2018 HIN
Equity Priority
Community
Designation
Near-Term Oak311 (Public) Service RequestTraffic - No Parking Signs Skyline Boulevard Grass Valley Road -- 2023 7 N Low Near-Term Oak311 (Public) Service Request
Traffic - Other Traffic Control Device
Install Repair Replace 3000 Revere Avenue -- -- 2023 7 N Low Near-Term Oak311 (Public) Service RequestTraffic - Paint Curb Red Joaquin Miller Road & Crane Way-- -- 2023 4 N Lowest Near-Term Oak311 (Public) Service RequestTraffic - Paint Curb Red Camden Street & Brann Street-- -- 2023 6 N High/Highest Near-Term Oak311 (Public) Service RequestTraffic - Paint Curb Red Courtland Avenue & High Street-- -- 2023 5 Y Medium Near-Term Oak311 (Public) Service RequestTraffic - Paint Curb Red Market Street & 40th Street -- -- 2023 1 N Medium Near-Term Oak311 (Public) Service RequestTraffic - Paint Curb Red Seminary Avenue & Mondadnock Way-- -- 2023 6 N Low/Medium Near-Term Oak311 (Public) Service RequestTraffic - Paint Curb Red Foothill Boulevard & 12th Avenue-- -- 2023 2 Y Medium Near-Term Oak311 (Public) Service RequestTraffic - Paint Curb Red Foothill Boulevard & 68th Avenue-- -- 2023 6 Y Highest Near-Term Oak311 (Public) Service RequestTraffic - Paint Red Curb Mountain Boulevard Fieldbrook Road 2023 4 N Low Near-Term Oak311 (Public) Service Request
Traffic - Paint Curb Red (Bus Stop)
High scoring SR (#1320034) 73rd Avenue International Boulevard -- 2023 6 Y Highest Near-Term Oak311 (Public) Service RequestTraffic - Paint Investigate Bond Street & 46th Avenue -- -- 2023 5 N Highest Near-Term Oak311 (Public) Service Request Traffic - Sign New Install39th Avenue & Wattling Street-- -- 2023 5 N High Near-Term Oak311 (Public) Service RequestTraffic - Sign New Install 7th Street & Harrison Street -- -- 2023 2 Y Highest Near-Term Oak311 (Public) Service RequestTraffic - Sign New Install Grass Valley Road Glen Manor Place Sklyine Boulevard 2023 7 N Low Near-Term Oak311 (Public) Service RequestTraffic - Sign New Install Broadway 26th Street 27th Street 2023 3 Y Medium Near-Term Oak311 (Public) Service Request
Traffic - Sign Replacement
High Scoring SR (#1279325) 14th Street Webster Street -- 2023 3 Y Highest Near-Term Oak311 (Public) Service RequestTraffic - Striping (not crosswalks)Joaquin Miller Road & Crockett Place-- -- 2023 4 N Lowest Near-Term Oak311 (Public) Service RequestTraffic - Striping (not crosswalks)Jefferson Street & 11th Street-- -- 2023 3 Y Medium Near-Term Rapid Response n/a Foothill Boulevard Austin Street -- 2023 5 Y Highest Near-Term Rapid Response n/a Lakeshore Avenue Hanover Avenue -- 2023 2 N Low Near-Term Rapid Response n/a Foothill Boulevard Vicksburg Avenue -- 2023 5, 6 Y High Near-Term Rapid Response n/a 90th Avenue Plymouth Street -- 2023 7 N High Near-Term Rapid Response n/a 35th Avenue E. 16th Street -- 2023 5 Y High Near-Term Safe Routes to School
Allendale Elementary School -
Traffic Safety Request Penniman Avenue 35th Avenue 38th Avenue 2023 4 Y High Near-Term Safe Routes to School
Aspire Berkley Maynard Academy -
15 MPH School Zone 63rd Street San Pablo Avenue -- 2023 1 Y Low Near-Term Safe Routes to School
Bella Vista Elementary School - 15
MPH School Zone 10th Avenue & 11th Avenue E. 28th Street -- 2023 2 N Low Near-Term Safe Routes to School
Bentley School - Traffic Safety
Request S. Hill Court Hiller Dr -- 2023 4 N Lowest
Near-Term Safe Routes to School
Bridges Academy at Melrose- 15
MPH School Zone 52nd Avenue and 53rd Avenue International Boulevard E. 12th Street 2023 5 N Medium Near-Term Safe Routes to School
Brookfield Elementary School - 15
MPH School Zone Jones Avenue Ashton Avenue -- 2023 7 N High Near-Term Safe Routes to School
Burckhalter Elementary School -15
MPH School Zone
Burckhalter Avenue and
Edwards Avenue Sunkist Drive Sunnymere Avenue 2023 6 N Low Near-Term Safe Routes to School
Cleveland Elementary School - 15
MPH School Zone Cleveland Avenue Montclair Avenue -- 2023 2 N Low Near-Term Safe Routes to School
Franklin Elementary School - 15 MPH
School Zone E. 15th Street 8th Avenue 11th Avenue 2023 2 N Medium Near-Term Safe Routes to School
Fruitvale Elementary School - 15
MPH School Zone Boston Avenue School Street Coolidge Avenue 2023 5 N High Near-Term Safe Routes to School
Global Family Elementary - Traffic
Safety Request 40th Avenue Carrington Street -- 2023 5 N Medium Near-Term Safe Routes to School
Greenleaf Elementary School -
Traffic Safety Request 62nd Avenue E. 17th Street -- 2023 6 N High Attachment A. 2023 Safe Oakland Streets (SOS) Initiative Annual Report 2023 OakDOT Capital Improvement Projects and Near-Term Improvement Projects Improvement
Type Subtype Project Description (if applicable) Street Project Location - Start Project Location - End
Construction Start/
Work Order Completed
City Council
District 2018 HIN
Equity Priority
Community
Designation
Near-Term Safe Routes to School
Highland Community School - Traffic
Safety Request 86th Avenue B Street A Street 2023 7 N Highest Near-Term Safe Routes to School
Hoover Elementary School - Traffic
Safety Request 33rd Street West Street -- 2023 3 N High Near-Term Safe Routes to School
Horage Mann Elementary School -
15 MPH School Zone
Foothill Boulevard and
Ygnacio Avenue Vicksburg Avenue Congress Avenue 2023 5 Y High Near-Term Safe Routes to School
La Escuelita Elementary School - 15
MPH School Zone E. 10th Street 2nd Avenue 4th Avenue 2023 2 N Medium Near-Term Safe Routes to School
La Escuelita Elementary School -
Traffic Safety Request 2nd Avenue E. 10th Street E. 11th Street 2023 2 N Medium Near-Term Safe Routes to School
Lodestar School- 15 MPH School
Zone 105th Avenue Acalanes Drive Pearmain Street 2023 7 N High/Highest Near-Term Safe Routes to School
Montclair Elementary School - 15
MPH School Zone Mountain Boulevard Colton Boulevard -- 2023 4 N Lowest Near-Term Safe Routes to School
Oakland High School- Traffic Safety
Request MacArthur Boulevard Park Boulevard -- 2023 2 N Low Near-Term Safe Routes to School
Oakland Technical High School -
Traffic Safety Request 45th Street Manila Avenue Broadway 2023 1 N Lowest Near-Term Safe Routes to School
Prescott Elementary School - Traffic
Safety Request 12th Street Campbell Street -- 2023 3 N High Near-Term Safe Routes to School
Saint Paul's Episcopal School -
Traffic Safety Request Montecito Avenue Bay Place -- 2023 3 N Low Near-Term Safe Routes to School Speed Limit Signs Foothill Boulevard 106th Avenue Durant Avenue 2023 7 N High Near-Term Safe Routes to School
Thornhill Elementary School - 15
MPH School Zone Thornhill Drive Grisborne Avenue -- 2023 4 N Low Near-Term Safe Routes to School Traffic - Crosswalk Striping 18th Street & West Street -- -- 2023 3 Y Medium Near-Term Safe Routes to School Traffic - Crosswalk Striping 42nd Avenue & Foothill Boulevard-- -- 2023 5 Y Medium/Highest Near-Term Safe Routes to School
Traffic - Delineator Install Repair
Replace 11th Street 2nd Avenue 4th Avenue 2023 2 N Medium Near-Term Safe Routes to School Traffic - Paint Curb Red Lincoln Avenue & Hearst Avenue-- -- 2023 4 N Low Near-Term Safe Routes to School Traffic - Sign New Install 28th Avenue E. 16th Street Foothill Boulevard 2023 5 N Highest Near-Term Safe Routes to School
United Nation CDC- Traffic Safety
Request 4th Avenue E. 10th Street -- 2023 2 N High
Near-Term Safe Routes to School
Yu Ming Upper School - Traffic
Safety Request Martin Luther King Jr. Way 40th Street 41st Street 2023 1 Y High Near-Term Speed Limit Reduction Business Activity District MacArthur Boulevard 89th Avenue 90th Avenue 2023 6, 7 Y Medium/Highest Near-Term Speed Limit Reduction Business Activity District San Pablo Avenue Wiliam Street 16th Street 2023 3 Y High Near-Term Speed Limit Reduction Business Activity District Fruitvale Avenue E. 15th Street E. 10th Street 2023 5 Y High/Highest Near-Term Speed Limit Reduction Business Activity District Fruitvale Avenue E. 22nd Street E. 19th Street 2023 5 Y High/Highest Near-Term Speed Limit Reduction Business Activity District Fruitvale Avenue Lynde Street Blossom Street 2023 5 Y High/Highest Near-Term Speed Limit Reduction Business Activity District Foothill Boulevard Rutherford Street High Street 2023 5 Y Medium/High/Highest Near-Term Speed Limit Reduction Business Activity District 11th Street Broadway Harrison Street 2023 2 Y Highest Near-Term Speed Limit Reduction Business Activity District 12th Street Broadway Alice Street 2023 2 Y Highest Near-Term Speed Limit Reduction Business Activity District 23rd Avenue Foothill Boulevard International
Boulevard 2023 2 Y Highest
Near-Term Speed Limit Reduction Business Activity District Foothill Boulevard Congress Avenue Cole Street 2023 5, 6 Y Medium/High/Highest Near-Term Speed Limit Reduction Business Activity District 14th Street Broadway Oak Street 2023 3 Y Medium/Highest Near-Term Violence Prevention Pilot
Diagonal Diverters to Deter Human
Trafficking E. 15th Street 16th Avenue 20th Avenue 2023 2 N Highest Attachment A. 2023 Safe Oakland Streets (SOS) Initiative Annual Report