Attachment B: Bid Summary
PROJECT NO:
PROJECT NAME:
BID DATE:
ENGINEER'S ESTIMATE: $31,194,159.00
BASIS OF AWARD: lowest base bid
NUMBER OF ADDENDA: 9
LOW BIDDER:
BID SUMMARY ISSUED:
BIDDERS:
Base Bid Total
Bid Form and
Schedule
Addendum
Acknowledgement License Type
% Over/Under
Engineer's Estimate
BHM Construction LLC $25,863,000.00 Y Y A, B -17.09%
Lathrop Construction Associates, Inc. $26,829,400.00 Y Y A, B -13.99% SJ Amoroso Construction Co LLC $28,437,000.00 Y Y A, B -8.84% Zovich & Sons, Inc. $28,999,000.00 Y Y A, B, C-8 -7.04% EF Brett & Company, Inc. $28,700,000.00 Y Y A, B -8.00% Monday, August 4, 2025
CITY OF OAKLAND BID SUMMARY
Public Works Department - Capital Contracts Division
1004857 (Federal Project No. B-23-CP-CA-
0067)Lincoln Recreation Center Project
Thursday, July 31, 2025
BHM Construction LLC
Bid Summary Issued 8/4/2025