OTHER INSPECTION FEES FIXED FEE TIME & MATERIAL DEPOSIT ADDITIONAL FEE OR DEPOSIT COMMENT Inspections Outside of Normal Business Hours $69.25 Per Hour (Minimum of 2 Hours) RE‐Inspection Fees Assessed Under Provisions of Section 305.8 $69.25 Per HourInspections for Which no Fee is Specifically Indicated $69.25 Per Hour Additional Plan Review Required by Changes, Additions & Revisions to Plans $78.50 Per Hour For Use Outside Consultants for Plan Checking & Inspections or Both Time and Materials Charge Energy Compliance Fees
25% of the Building Fee Applicable to all Structures with Heaters or any Conditioned Space
Access Compliance Fees
25% of the Building Fee Applicable on all Buildings Except Residential Use Buildings with Fewer Than four (4) Dwelling Units
ADDITIONAL FEE OR DEPOSIT COMMENT
The work listed in this supplement shall be valued based on the gross square footage of the work, or where noted, as a lump sum. Where actual costs are higher, those costs shall be used for the valuation.
Residential Addition $ 94.80 Sq. Ft.
Residential Remodel (to existing floor area) By ValueResidential Use Conversion from Garage By Value Sun room with 60% glazing, cabanas, other similar structures if conditioned space and Integrated with main Structure $18.65 Sq. Ft.Patio Cover By Value Deck $13.56 Sq.Ft.Deck ‐ With Cover By ValueRetaining Wall By Value Freestanding Fence By Value
Portable Doughboy Pools or Portable Spa (Electrical Only) $156.16 Includes Applicable City Fees Portable Doughboy Pools or Portable Spa With Gazebo or Decking By Value Remodel or Tenant Improvement Work in Commercial Buildings By Value Re‐Roofing‐Single Family or Duplex $178.80 Includes Applicable City Fees Commercial Building Re‐Roof By Value
Pre Fabricated Home on Permanent Foundation (Use minimum Electrical, Mechanical, and Plumbing Inspection Fees) By Value Moved Building By Value
$2,001.00 to $25,000.00 $69.25 for the first $2,000.00 plus $14.00 for each additional $1,000.00 or fraction thereof, to and including $25,000.000
SCHEDULE OF CONSTRUCTION PERMIT FEES
$1.00 to $2,000.00 $69.25
TOTAL VALUATION FEE
BUILDING FEES
$100,000.00 to $500,000.00 $993.75 for the first $100,000.00 plus $5.60 for each additional $1,000.00 or fraction thereof, to and including $500,000.00 $500,001.00 to $1,000,000.00 $3,233.75 for the first $500,000.00 plus $4.75 for each additional $1,000.00 or fraction thereof, to and including $1,000,000.00
BUILDING VALUATION DATA SUPPLEMENT
$25,001.00 to $50,000.00 $391.25 for the first $25,000.00 plus $10.10 for each additional $1,000.00 or fraction thereof, to and including $50,000.00 $50,001.00 to $100,000.00 $643.75 for the first $50,000.00 plus $7.00 for each additional $1,000.00 or fraction thereof, to and including $100,000.00 $1,000,001.00 and UP $5,608.75 for the first $1,000,000.00 plus $3.65 for each additional $1,000.00 or fraction thereof 169
ELECTRICAL INSPECTION FEES ADDITIONAL FEE OR DEPOSIT COMMENT New Dwelling 15% of the Building Permit Fee
Addition or Alteration to Dwelling Unit 20% of the Building Permit Fee, $69.25 minimum New Commercial Building 25% of the Building Permit Fee, $69.25 minimum Shell Building 25% of the Building Permit Fee, $69.25 minimum Commercial Alterations & Tenant Improvements 20% of the Building Permit Fee, $69.25 minimum Electrical Permit $69.25 minimum. See * note.
MECHANICAL INSPECTION FEES ADDITIONAL FEE OR DEPOSIT COMMENT New Dwelling 10% of the Building Permit Fee
Addition or Alteration to Dwelling Unit 15% of the Building Permit Fee, $69.25 minimum New Commercial Building 15% of the Building Permit Fee, $69.25 minimum Shell Building 15% of the Building Permit Fee, $69.25 minimum Commercial Alterations & Tenant Improvements 10% of the Building Permit Fee, $69.25 minimum Mechanical Permit $69 25 minimum. See * note below
PLUMBING INSPECTION FEES ADDITIONAL FEE OR DEPOSIT COMMENT New Dwelling 15% of the Building Permit Fee
Addition or Alteration to Dwelling Unit 20% of the Building Permit Fee, $69.25 minimum New Commercial Building 20% of the Building Permit Fee, $69.25 minimum Shell Building 20% of the Building Permit Fee, $69.25 minimum Commercial Alterations & Tenant Improvements 15% of the Building Permit Fee, $69.25 minimum Plumbing Permit $69 25 minimum. See * note below
MISCELLANEOUS FEES FIXED FEE ADDITIONAL FEE OR DEPOSIT COMMENT Re inspections (When return trips to the site by an inspector are necessary) $69.25 Per HourOwner‐requested inspection of an existing building $69.25/$207.75 Per Hour with a 1 Hour Minimum. If Overtime is required the rate shall be $207.75 per hour with a 1 Hour Minimum
Inspection for Change of Occupancy $80.00 Per Hour with a 1 Hour Minimum Investigation of work without permit. When a Stop Work Notice is issued for work being performed without permits or performed beyond the scope of existing permits, a special investigation and inspection shall be made before permits may be issued for such work.
An investigation fee shall be charged equal to two times the amount of all permits fees required by this ordinance, with a minimum of $125.00. The fee is additive to the permit fees. This provision shall not apply to emergency work when it can be proven to the satisfaction of Building Official that such work was urgently necessary, that it was not practical to obtain a permit before the work was commenced, and that a permit was applied for as soon as practical.
*An electrical permit is required for all electrical work regulated by the Electrical Code. Fees for work not included in items 1‐5 above shall be calculated using Building Fees and based on the contract amount of the electrical work. Where such electrical work is performed in conjunction with a building permit, the fee may be added to that permit, and a separate electrical permit is required. * A plumbing permit is required for all plumbing work regulated by the Plumbing Code. Fees for work not included in Items 1‐5 above shall be calculated using Building Fees and based on the contract amount of the plumbing work. Where such plumbing work is performed in conjunction a building permit, the fee may be added to that permit, and a separate plumbing permit is not required. *A mechanical permit is required for all mechanical work regulated by the Mechanical Code. Fees for work not included in Items 1‐5 above shall be calculated using Building Fees and based on the contract amount of the mechanical work. Where such mechanical work is performed in conjunction a building permit, the fee may be added to that permit, and a separate mechanical permit is not required. 170
PERMIT PROCESSING AND ISSUANCE PROGRAM FIXED FEE ADDITIONAL FEE OR DEPOSIT COMMENT Plan Review‐Applicable when plans are required beyond a plot or site plan. 65% of Building Permit Fee Permit Review and ProcessingApplicable when review for compliance can be determined through a plot or site plan, or references to a master plan previously reviewed and approved by the department.
25% of Building Permit Fee. (Subsequent houses also). $78.50 per hour minimum.
Additional ProcessingApplicable when additional plan review is required due to: 1) incomplete or unacceptable follow‐through by applicant on deficiencies found in the initial plan review; 2) significant revisions submitted after plan review is well underway; or 3) revisions submitted during construction to reflect field changes. $78.50 Per Hour Plan Scanning:
8 1/2 x 11 $0.13 Per Sheet
11 x 17 to 12 x 18 $0.25 Per Sheet17 x 22 to 18 x 24 $0.81 Per Sheet24 x 34 to 24 x 36 $1.62 Per Sheet36 x 44 to 36 x 48 $2.97 Per Sheet Large Format Scanning $0.27 Per Square Foot
CONSTRUCTION INSPECTION PROGRAM ADDITIONAL FEE OR DEPOSIT COMMENT Building Permit The Building Permit fee shall be as set forth in the Fee Schedule (Table No. 1‐A) Energy Compliance
25% of Building Permit or processing fees. Applicable on all structures with heated or air conditioned space.
Accessibility
25% of Building Permit or processing fees. Applicable on all building permits except residential use buildings with fewer than 4 dwelling units.
State of California Earthquake Assessment Fee
Residential: .10 per each $1,000 building Valuation
Commercial: .21 per each $1,000 building Valuation
ADMINISTRATION AND OVERHEAD COSTS; ACTUAL COSTS
Actual costs include the Cityʹs administrative and overhead costs.
Section 2: VALUATIONCity of Oakley administrative and overhead costs are equal to 27% of all Construction Permit Fees. The Cityʹs administrative and overhead costs shall be included in the total amount charged for all Building Inspection Department services in a manner prescribed by the Building Inspection Department.
The determination of value or valuation under any provisions of the City Building Code shall be made by the Building Official. The total valuation to be used with the Fee Schedule shall be determined using the Building Valuation Data contained in the Building Standards magazine, published by the International Conference of Building Officials, Whittier, California. The data in the March‐April issue of each year shall be used for the ensuing fiscal year. Work not listed in the Building Valuation Data shall be valued per the Building Valuation Data Supplement.
The valuation to be used in computing Construction Permit Fees shall be the total valuation of all construction work for which the permit is issued, as well as all finish work, painting, roofing, mechanical, electrical, plumbing, beating, air conditioning, elevators, fire extinguishing systems, and any other permanently installed equipment.For industrial facilities, the value of process equipment and heavy machinery supported by the structure or by its own foundation shall be included. Contractor overhead and profit shall be included.
The valuation of grading, retaining walls, paving and other site work, and any demolition work, shall be included unless such work was included in other permits issued by the Building Inspection Department.
The valuation data is used to establish consistent criteria for calculating permit fees, and the calculated total valuation does not necessarily reflect actual costs. The County Assessor does not rely on these costs, but performs independent assessments of the permitted work. 171
CODE ENFORCEMENT FIXED FEE ADDITIONAL FEE OR DEPOSIT COMMENT Annual Rental Registration & Inspection fee $108.00
Fee for property not inhabited by tenants or vacant and not listed for rent on January 1st of each calendar year will be prorated on a monthly basis Re‐Inspection Fee $112.00Non Compliance for Failure to Register & Pay Fee/Code Enforcement Violations:
First Citation $100.00
Second Citation $200.00
Third Citation $500.00
Administrative Penalty Citation for Building and Safety Codes First Citation $130.00Second Violation of the Same Ordinance Within One Year $700.00 Each Additional Violation of the Same Year Within One Year of First $1,300.00 Rental Property Owners failing to register and pay the annual fee by January 31st of the calendar year or within 30 days of renting the property will be issued an Administrative Citation.
Administrative Citations are in addition to the Rental Registration and Inspection Fee and any other citations issued for Building and/or Code Enforcement violations. 172
User Groups:
Group 1: Oakley Resident, Oakley Based Businesses and Oakley Based Non Profits Group 2: Non‐Resident and Non‐Oakley Based Non Profits
Group 3: Community PartnerGroup 4: Private Business, Group or Organizations FACILITIES GROUP 1 GROUP 2 GROUP 3 GROUP 4
Sports Area $7.00 per hour $17.00 per hour As Outlined in Individual Agreement $40.00 per hour Creekside and Nunn Wilson Park Group Picnic Areas (up to 100 people) $100.00 per day $125.00 per day As Outlined in Individual Agreement $200.00 per day Crockett and Summer Lake Park Group Picnic Areas (under 50 people) $75.00 per day $100.00 per day As Outlined in Individual Agreement $150.00 per day FACILITIES GROUP 1 GROUP 2 GROUP 3 GROUP 4
Oakley Recreation Building Studio 1 Only available for parties with 50 or less people Monday ‐Thursday
$55.00 per day $75.00 per day As Outlined in Individual Agreement $100.00 per day Recreation Center Great Room Add on Kitchen to full room rental or side A for $100
M‐Th $150.00 per day
F‐Su $225.00 per day
M‐TH $175.00 per day
F‐Su $250.00 per day
As Outlined in Individual Agreement
M‐TH $225.00 per day
F‐Su $300.00 per day
Recreation Center Side A or Side B Add on Kitchen to full room rentalor side A for $100 M‐Th $75.00 per day
F‐Su $115.00 per day
M‐TH $100.00 per day
F‐Su $135.00 per day
As Outlined in Individual Agreement
M‐TH $125.00 per day
F‐Su $150.00 per day
Kitchen Available Monday ‐ Friday $45 per hour $50 per hour As Outlined in Individual Agreement $50 per hour Temporary Use Permit $100 application fee + $500 depositSpecial Event/Road Closure Permit (if required) $50 application fee* Park Rental Fee $250 per day
*Additional fees may apply based on the nature of your event A $150 damage deposit is due at the time of application to reserve any park or sports area.
RECREATION CENTER FEES
Recreation Center Deposit $250, insurance required on all rentals. *Large events and events serving alcohol will require $500 deposit and security
CIVIC CENTER PARK STAGE & AMPITHEATER
PICNIC AREA AND SPORTS FIELDS
PARKS & RECREATION
173
RESIDENTIAL CUSTOMERS MONTHLY FEE
32 Gallon Trash Service $49.64
64 Gallon Trash Service $69.42
96 Gallon Trash Service $78.76
32 Gallon Senior‐Low Income Trash Service $42.14Additional Recycling Container $15.59Additional Green Waste Container $15.59
RESIDENTIAL CUSTOMERS FEE COMMERCIAL CUSTOMERS FEE
Account reinstatement Fee $20.00 Account reinstatement Fee $75.00 Go‐Back Service Fee $35.00 Go‐Back Service Fee $35.00
Same Day Service Fee $55.00 Same Day Service Fee
Cart Service (per cart) $40.00
Bin Service (per bin) $115.00
Admin Fee (Payment w/live Rep) $2.00 Admin Fee (Payment w/live Rep) $2.00 Overloaded/Contaminated Container Overloaded/Contaminated Container 1) First offense ‐ Phone call ‐ 1) First offense ‐ Phone call ‐ 2) Second offense ‐ Phone call and warning letter ‐ 2) Second offense ‐ Phone call and warning letter ‐3) Third offense ‐ Letter and fee $50.00 3) Third offense ‐ Letter and fee ‐ a) Cart Fee $75.00b) Bin Fee $150.00
MT. DIABLO RESOURCE RECOVERY /SANITATION AND REFUSE FEES
MISCELLANEOUS FEES AND CHARGES
174
STAFF REPORT
City of Oakley | 3231 Main Street, Oakley, CA 94561
O (925) 625-7000 | F (925) 625-9859 | www.ci.oakley.ca.us DATE: September 26, 2023
TO: Joshua McMurray, City Manager
FROM: Kevin Rohani, P.E., Public Works Director/City Engineer SUBJECT: Review the results of the second online survey for the Oakley Regional Park and for City Council to provide recommendations on a preferred alternative to finalize the Master Plan for this park
Background and Analysis
The initial planning for the Oakley Regional Park began in 2006. The first Master Plan prepared for this park was completed in 2019. Since then, at the request of the City Council, staff is making a second effort to redefine the Master Plan for this park by exploring other amenities of this park with potential grant opportunities in mind to fund construction.
On March 29, 2023, the City held the first Community Open House to seek input from members of the community. The presentation included project background, current site information, previous efforts in 2019, and project goals and objectives. An online survey was conducted to seek input from members of the community on what the desired use was envisioned for this park. Based on the survey results, two alternatives were created and presented to the second Community Open House held on July 19, 2023. A second online survey was sent out to gauge which alternative was preferred by the community. Attached is a summary of the second online survey.
In this Work Session, staff seeks any further refinement and input from City Council, so staff can proceed with finalizing the Master Plan for this park.
Consistency with the Oakley Strategic Plan 27+
This effort is consistent with the Oakley Strategic Plan 27+ under the Parks and Open Space and Community and Collaborative Partnerships goal. The Oakley Community Regional Park will be the largest park in our City and this effort is in line with the envisioning and developing of this 55-acre park. The online survey is in line with our community outreach and engagement objectives.
Approved and
Forwarded to the
City Council
175
STAFF REPORT
City of Oakley | 3231 Main Street, Oakley, CA 94561 2
O (925) 625-7000 | F (925) 625-9859 | www.CI.Oakley.CA.US Fiscal Impact
There is no fiscal impact related to the discussion of the online summary survey conducted and the City Council’s preferred alternative at this time. Staff are continuing to seek grant opportunities for construction of this park.
Staff Recommendation
Given the outcome of the survey results, staff is seeking for additional feedback from City Council of the preferred alternative before moving forward with the final Master Plan for this park.
Attachments
1. Community Meeting #2 Survey Data Summary
176
www.callanderassociates.com
BURLINGAME GOLD RIVER SAN JOSE
1633 Bayshore Highway, Suite 133 12150 Tributary Point Drive, Suite 140 2025 Gateway Place, Suite 285 Burlingame, CA 94010 Gold River, CA 95670 San Jose, CA 95110 650.375.1313 916.985.4366 408.275.0565
Recreate
Educate
Live+Work
Connect
Sustain
August 16, 2023
Community Meeting #2 Survey Data Summary
Oakley Regional Park Master Plan
Number of Attendees who were at Outreach Meeting #1
• 48 out of 162 had attended.
Number of participants who live in Oakley
• 143 out of 162 live in Oakley.
Preferred Alternative
o Alternative 1: 70 votes
o Alternative 2: 72 votes
o Both: 4 votes
o Neutral: 9 votes
Participants Reason for Preferring Alternative 1
• Programming and outdoor classroom
• Disc golf
• Variety of activities/sports for all ages
• Baseball fields
• Soccer fields
• Pickleball courts
• Ability to hold events
• Family oriented
• Amenities for kids
• Trails
• Fishing decks
• Community garden
Participants Reason for Preferring Alternative 2
• Swimming area
• Nature play area
• More nature oriented
• It’s overall uniqueness
• Fishing opportunities
• Has more open space
• The camping
• Family oriented
• Dog park
• Trail space/ nature walks
• Wine Tasting
• Sports fields
177
Outreach #1 Data Summary
Oakley Regional Park Master Plan
April 28, 2023
22048_SUM_Outreach2Data.docx
© copyrighted 2021 Callander Associates Landscape Architecture, Inc.
Improvement Recommendations for Alternative 1
• Skate park
• Smaller corp yard
• Add a kayak launch
• Have four baseball field flipped the other direction. • Add swimming area/lagoons.
• Add splash pad.
• More picnic and bbq areas.
• Add dog park.
• Add vineyard and wine tasting.
• Have pickleball courts over tennis courts.
• Have water access similar to alternative 2.
• Have two 90’ ball fields.
• Provide as many additional soccer field sizes as possible. • Include a badminton court.
• Additional restrooms.
• Shaded play structures.
• Indoor sports facilities.
• Fenced play area.
• Add full size basketball court.
• Add livestock arena.
Improvement Recommendations for Alternative 2
• To not have sports dual sports field. To have either soccer or baseball. • Add an observation deck to look out towards the delta. • More shade around play area.
• Add disc golf.
• Remove ball fields for different amenities for camping. • Science camp area.
• Swap motorized boar ramp to human powered craft launch only. • Have paved trails and walkways.
• Provide full hook-up within camp site.
• Additional fishing decks.
• Add fishing pier.
• Add a bike/skate park.
• Add pump track.
• More shade around swimming area.
• Add water theme activities.
• Add a kayak launch.
• Add splash pad.
• Provide a convenience store within campsite.
• More open space.
• Provide regular programming and events.
• Add community garden.