Item #: 3.9. 1/11/2022 File #: 21-0692
TO: Honorable Mayor and Members of the City Council
THRU: Thomas R. Hatch, Interim City Manager
FROM: Christopher Cash, Public Works Director

1. SUBJECT
Approval of plans and specifications for Fire Station No. 5 Bathroom Remodel, and authorization to advertise for bids.

2. SUMMARY
Plans and specifications have been completed and the project is ready to advertise for bids. The total estimated construction cost, including 15% contingencies and construction management, is $140,000.

3. RECOMMENDED ACTION
Approve plans and specifications and authorize advertising for bids for Fire Station No. 5 Bathroom Remodel Project; Bid No. 21-22.24.

4. FISCAL IMPACT
The total expenditure for this project is $140,000 and will be funded in Fire Station Maintenance & Renovation (20334) through Fire Facility Fees (560).

5. STRATEGIC PLAN GOALS
Goal 1: Provide for a safe community
b: Provide and maintain infrastructure necessary to ensure the safety of the public.

Goal 4: Provide outstanding public service
b: Provide facilities and services to meet customer expectations.

6. DISCUSSION AND BACKGROUND
Fire Station No. 5 was built in 1968, along with other similar Fire Stations. Minimal improvements have been done to the locker room at this station since its construction. Due to aging infrastructure and partial plumbing failure, restrooms and showers have been impacted. It has been a challenge for Fire staff at this station due to the limited restroom capacity. This project will restore full functionality and accommodate for three gender-neutral restroom and shower stalls.

Construction is scheduled to begin in March 2022 and is expected to be completed in six weeks.

The proposed project is categorically exempt from the provisions of the California Quality Act (CEQA) under CEQA guidelines Section 15301 “Existing Facilities” Class 1(c). The Notice of exemption will City of Orange Printed on 1/5/2022Page 1 of 2
powered by Legistar™
Item #: 3.9. 1/11/2022 File #: 21-0692
be filed with the County Recorder’s Office upon Council’s approval of the plans and specifications.

Specifications and cost estimate are available for review through the Public Works Department.