AGENCY PROJECT BID DATE INTERSECTION BID ITEM QTY. COST EA. TOTAL City of OrangeOp/com GPS Project Led by the Fire Dept. 1/5/22 Wanda & Collins GTT 764 Op/com Phase Selector 3 $2,995.00 $8,985.00 Chapman & Manchester GTT GPS 3100 Intersec/on Antenna 3 $2,860.00 $8,580.00 Compton & Manchester 760 Op/com Card Rack 3 $395.00 $1,185.00 Op/com GPS Cable (500’) 3 $730.00 $2,190.00
AB-0155 Pelco Clamp 3 $75.00 $225.00
768 Aux. Harness 3 $560.00 $1,680.00
Installa/on of GPS Antenna per intersec/on 3 $1,100.00 $3,300.00 Tech Support Op/com per intersec/on 3 $800.00 $2,400.00 D- Connectors not needed 0 $0.00 $0.00
Op6com Total $28,545.00
TOTAL: $28,545.00
Rosalie Harvey Sales Tax (7.75%): $1,770.49
626-226-8844 Cell TOTAL COST: $30,315.49
909-614-7255 (fax)
rosalie@ddltraffic.com
www.ddltraffic.com *Quote Good For 90 Days
1
DDL Traffic, Inc. Quote
Orange City Council
February 8, 2022
- Document
- DDL Traffic, Inc. Quote
- Meeting
- February 8, 2022
- Body
- Orange City Council
- Original file
- 116 KB
Text extracted from the city's file for reading and search. Open the original on cityoforange.legistar1.com. That file is the official record.